SUNSHINE SKYWAY BRIDGE

Similar documents
Florida DOT efforts toward improving Post Tension Durability

Special Considerations for Maintenance of the Sunshine Skyway Bridge

Corrosion Evaluation of Post-Tensioned Tendons on Mid-Bay Bridge

Bonner Bridge Replacement Update:

TECHNICAL SESSION 3. Strengthening, Repair & Rehabilitation

NDT in Grouted PT Inspection for Bridges

US-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Ironton Russell Bridge Project

INSPECTION AND LOAD RATING OF P-T SEGMENTAL BRIDGES. Elias Ajami, PE Illinois Tollway Brett Sauter, PE, SE Ciorba Group

Pushing the Envelope For 100 Years

EVALUATION & REPAIR OF CORROSION DAMAGED ROOF LIFT SLAB WITH WIRE POST-TENSIONING SYSTEM (BUTTON HEADS)

I-74 over the Mississippi River

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

Construction of Long Key Bridge

Foundation Strengthening Of Bascule Piers At The Bridge Of Lions

The Hashemite University Department of Civil Engineering. Dr. Hazim Dwairi. Dr. Hazim Dwairi 1

Bridge Construction. Nick Haltvick North Region Bridge Construction Engineer May 17, Bridge Office mndot.gov/bridge/construction.


City of Mesquite General Design Standards Revision Date:

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E.

JULY 2014 LRFD BRIDGE DESIGN 5-1

John James Audubon Bridge

STRUCTURE AND BRIDGE DIVISION

Chapter 2 Notation and Terminology

Design & Seismic Detailing of Nonstandard Deep Precast Concrete Box Girders For Long Span Railroad Bridges By:

For Two Steel Bridges

Lecture 13: Practical Design, The Future of Prestressed Concrete, and Concluding Thoughts...

Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions

Ironton Russell Bridge Project

CONCRETE SPLICED GIRDERS IN TEXAS. Nicholas Nemec, P.E. TxDOT-BRG

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

FEBRUARY 2019 LRFD BRIDGE DESIGN 5-1

LRFD Bridge Design Manual Changes

Accelerated Bridge Construction in USA

2016 ACEC/PA ANNUAL MEETING

Ironton Russell Bridge Project

STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION LOAD RATING REPORT GENERAL SULLIVAN BRIDGE - DOVER 200/023 OVER THE LITTLE BAY

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

PRECAST CONCRETE CONNECTIONS - US PRACTICE

John James Audubon Bridge. Introduction

Critical Structures Construction Issues

INSPECTION AND REPAIR OF THE DETERIORATED RT.72 MANAHAWKIN BAY BRIDGE

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

Title. Author(s)KIM, D. W.; SHIM, C. S. Issue Date Doc URL. Type. Note. File Information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit

SUMMARY SHEETS OF HYBRID CONNECTIONS

B R I D G E O F F I C E

B R I D G E O F F I C E

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

A precast Concrete Bridge Bent for Seismic Regions: Achieving both Performance and Constructability

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

Bijan Khaleghi, Ph, D. P.E., S.E.

Structural Technical Report 1 Structural Concepts / Existing Conditions

IMUA ANNUAL PRESENTATION 2013

Chapter 1. General Design Information. Section 1.03 Loads and Load Factors. Introduction. Load Modifying Factors

S T R U C T U R. One-of-a-Kind Design The New San Francisco-Oakland Bay Bridge Self-Anchored Suspension Span. magazine. Copyright

Don Theobald, V.P., Gulf Coast Pre-Stress. Standardizing Existing Spliced Girder Systems

Temecula Medical Center Temecula, CA

Ironton Russell Bridge Project

PUBLIC INFORMATION MEETING June 24, 2015

Red Wing Bridge Alternates

DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari

Rehabilitation of Masonry Piers at Nipigon, Ontario

103rd Annual T.H.E. Conference February 28 & March 1, 2017 University of Illinois at Urbana-Champaign. Planning and Design. of IL-104 BRIDGE OVER

Executive Summary. Champlain Bridge Approach Spans Edge Girder Condition Assessment and Rehabilitation Requirements.

AASHTOWare BrD 6.8 Substructure Tutorial Pier Drilled Shaft Example

Long Key Bridge, a spectacular example. Design Features and Prestressing Aspects of Long Key Bridge

Connections between precast girders and cap beam

CONTINUITY OF PRECAST BRIDGE U-GIRDERS CONNECTED TO A CAST-IN-PLACE SUBSTRUCTURE SUBJECTED TO SEISMIC LOADS

East Lyme Middle School EAST LYME MIDDLE SCHOOL

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES

SOUTHEAST TEXAS CONTINUING EDUCATION BRIDGE INSPECTION, MAINTENANCE AND REPAIR

SUMMARY SHEETS OF INTEGRAL CONNECTIONS

Chapter 13 Bridge Load Rating

AASHTOWare BrD 6.8. BrR and BrD Tutorial. PS7-3 Stem PS Bridge Example

Table of Contents 2. Structural Systems.4 Foundations.4 Floor System...4 Columns..5 Lateral System...5

Crossroads at Westfields Building II

Appendix A Proposed LRFD Specifications and Commentary

NEWINGTON-DOVER WELCOME

Statement of Special Inspections

Replacing the Aging US 52 Mississippi River Bridge

Bridge PBEE Overview & Pilot Next Generation Bridge Studies

Structural Technical Report 1 Structural Concepts / Structural Existing Conditions Report

Blaxland's Crossing Bridge, Wallacia NSW Bearing Replacement

LRFD SEISMIC BRIDGE DESIGN, CALIFORNIA EXAMPLE. Mark S. Mahan 1

Seismic performance of precast concrete segmental bridges: Summary of experimental research on segmentto-segment

Modeling and Design of Bridge Super Structure and Sub Structure

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

New Development in Accelerated Bridge Design and Construction in WA

Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding)

THE FORENSIC MEDICAL CENTER

Basarab Cable Stayed Bridge in Bucharest

Structural Technical Report 1 Structural Concepts/ Structural Existing Conditions Report

2014 HDR, all rights reserved.

Safety was in everyone's mind when a. Sunshine Skyway Bridge Ship Impact Design of Low Level Approaches

Transcription:

SUNSHINE SKYWAY BRIDGE Retrofit of the Post-Tensioned Precast Transition Pier Columns on the Sunshine Skyway Bridge Presented by: Antonio Ledesma, P.E. May 7, 2012

SUNSHINE SKYWAY BRIDGE, FLORIDA

Presentation Outline 1. INTRODUCTION 2. SKYWAY STRUCTURAL SYSTEM 3. SKYWAY CONSTRUCTION METHODS 4. PREVIOUS REHABILITATION OF HIGH-LEVEL APPROACH COLUMNS 5. PRECAST SEGMENTAL TRANSITION PIERS 6. REPAIR OPTIONS 7. CONSTRUCTION

Introduction The Sunshine Skyway Bridge is located on the west central coast of Florida. Part of I-275 linking Tampa/St. Petersburg to Bradenton/Sarasota across Tampa Bay. In May 1980, a major ship impact caused the collapse of the southbound main span. Sunshine Skyway Bridge St. Petersburg

Sunshine Skyway Bridge NORTH LOW LEVEL TRESTLE SPANS (4283 ) NORTH HIGH LEVEL APPROACH (2430 ) MAIN SPAN (4000 ) SOUTH HIGH LEVEL APPROACH (2430 ) SOUTH LOW LEVEL TRESTLE SPANS (8738 ) Total Bridge length: 4.14 miles

High Level Approaches and Main Span Unit

Structural System High Level Approaches HIGH LEVEL APPROACH HIGH LEVEL APPROACH Total length: 4,860 ft Post-Tensioned Precast Segmental Box Girders (Span-by-Span) Post-Tensioned Precast Segmental Columns

Structural System Main Span Unit MAIN SPAN UNIT Total length: 4,000 ft Post-Tensioned Precast Segmental Box (Balanced Cantilever)

Precast Segmental Substructure Bearing pad PT anchorage Column cap Transition point External Tendon Segment joint (typ) Internal tendon Precast footing shell Grout pad Cast-in-place concrete Precast concrete strut Tremie seal concrete

Previous Rehabilitation of Approach Piers PE Duct Couplers Poor detail of vertical tendon couplers

Column 133 NB SE Tendon September 2000 Corroded strands in the zone of 2 ft below the column cap (11 out of 17 0.5 strands were failed)

Failed strands as a result of severe corrosion

Previous Rehabilitation of Approach Piers

Previous Rehabilitation of Approach Piers

Previous Rehabilitation of Approach Piers Core holes in footing and grout PT bars in place Top of Footing Place reinforcing

Previous Rehabilitation of Approach Piers Concrete pumped from top of deck Placing concrete inside column

Transition Piers Between HLA and Main Unit

Transition Piers 106 (6 S) and 117 (6 N)

Expansion Joint Segment at Transition Pier

As-Built Transition Columns Tie-Down Tendons Hollow Columns Filled with Concrete for Vessel Impact

Transition Pier Analysis Do we need to repair the transition pier columns? How to repair columns with concrete already placed inside segments? What is the purpose of the tie-down tendons Vessel Impact Load Case Hurricane Wind Load Case Impact of vessel impact risk analysis Repair options

Transition Column Inspection Column 117 SB Top view of interior column

Transition Column Inspection Column 106 SB Poorly done duct couplers

Transition Column Inspection Column 117 SB

Transition Column Inspection Column 117 NB Tendon T4 E (spiral cracked duct)

Transition Column Inspection Column 106 SB Cracked PE duct in 6 gap beween top of pier cap and transition segment

Transition Column Inspection Column 117 SB View at column transition point

Transition Column Inspection Column 117 SB Void

Transition Column Inspection Column 117 SB View of T1 W (cracked duct and void)

Purpose of Tie-Down Tendons 4 looped tendons (8 vertical tendons) 2-17x0.5 Tendons extend into superstructure EOR used tie-down tendons for vessel impact and hurricane wind analysis 2 4 2 Tie-Down Tendons

EOR Original Design Scenario 2100 k 1900 k Vessel Impact Load - 4000k Design Load Pier cannot withstand full force; inelastic scenario was used to satisfy requirement

Vessel Impact Risk Analysis 3*LOA = 2310 ft CL Channel Limit analysis to 3*LOA limit as specified in AASHTO (piers outside of limit are designed for minimum vessel impact) 8 piers on either side of the channel

Aerial View of Sunshine Skyway Bridge First two piers are very well protected, eliminate from risk analysis Conservatively ignore protection of remaining piers

Vessel Impact Risk Analysis 1350 k 2000 k Transition Pier 4000 k Protected

Wind Load on Bridge Wind Pressure Service Level Ultimate Strength 80 psf 177 mph 250 mph 60 psf 153 mph 217 mph

Check Uplift at Bearings Service Level Wind (153 mph) No Uplift at Bearings Tie-Down Tendons Not Required M top Wind Ultimate Wind defined as 1.6 x Wind @ 80% of Ultimate Strength M u = 1.6 x Moment / 0.8 M top = 7725 kip-ft M base = 15125 kip-ft M base

Analysis Summary Proposed Vessel Collision Load = 2000 k Actual Column and Foundation Capacity = 2250 k Collapsed Column Scenario would not be required Tie-down tendons not required for vessel collision or hurricane wind load cases

Transition Pier Repair Potential Options for Lower Column Repair Option 1: Repair the columns from the inside (coring 55 deep concrete) Option 2: Repair the columns from the outside (using a cofferdam)

How do you repair the columns? Hollow Columns Filled with Concrete for Vessel Impact

Repair Option 1: Core Holes Inside Column Lower Column Repair: Core 5 φ holes through filled column and footing 28-1 ¾ φ unstressed PT bars Grout bars in place

Repair Option 2: Core Holes Outside Column 1 Concrete Shell 1 Concrete Shell Cofferdam

Repair Option 2: Core Holes Outside Column Steel Cofferdam (need split form for repair) Precast Dumb-Bell Precast Concrete Strut Precast Dumb-Bell And Steel Cofferdam During Construction

Repair Option 1 Chosen: Core Holes Inside Column Column Buttresses Upper Column: 24-1 ¾ φ Bars 5 φ Cored Holes Lower Column: 28-1 ¾ φ Bars

Upper Column Repair: Reinforced Column Buttresses Upper Column Repair: Core 5 φ holes through 2 thick lower segments and pier cap 4 column buttresses 24-1 ¾ φ unstressed PT bars

Upper Column Repair: Remove External Tendons Upper Column Repair: After column buttresses in place, strip external ducst, add anchorage plates to tendons and encapsulate in concrete to form an anchorage block Cut and remove external tendons Lower tendons to remain and will provide redundancy to lower column repair PT bars connecting pier cap to transition segment added at Department s request

Cost Estimate Option 1: Repair from inside (coring concrete) Estimated Total: $ 3 million Option 2: Repair from outside (w/ cofferdam) Estimated Total: $ 4 million Construction Time : 9 months to 12 months. Original Contract Amount: $2.2 million Original Construction Time: 1 year Unforseen conditions will increase total dollar amount and contract time.

Construction Photos Core Drill 5 diameter, 5 long steel tubing

Construction Photos Cleaning out core holes for lower column repair Core holes in thickened section For upper column buttress bars

Construction Photos Preparing and finishing column buttresses

Construction Photos Removal of external tendon ducts and addition of anchorage clamps

Removal of external PT tendon tie-down and installation of PT bar tiedown Construction Photos

Current Project Status 2 columns completed, 2 ongoing Estimated completion: Summer, 2012

Thank you. Contact: Antonio Ledesma, P.E. ledesma@pbworld.com