TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

Similar documents
TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

Environmental and Social Impact Assessment [ESIA] for Proposed Liquefied Natural Gas (LNG) Project at Tema in the Greater Accra Region of Ghana

STAKEHOLDER ENGAGEMENT STRATEGY

CHAPTER 7 STAKEHOLDER ENGAGEMENT

TABLE OF CONTENTS 1 INTRODUCTION... I 1.1 PROJECT OVERVIEW... I 2 PROJECT DESCRIPTION... II 2.1 PROJECT LOCATION... II 2.2 PROJECT COMPONENTS...

1 PROJECT OVERVIEW. Quantum Power Ghana Gas Limited 1 Knight Piésold Consulting GMF

CHAPTER 13 ASSESSMENT OF SOCIO-ECONOMIC IMPACTS AND MITIGATION

On Board Regasification for LNG Ships. 22 nd World Gas Conference WS 3-2 Tokyo 2003 Wayne Perry

February 2012 Tweneboa, Enyenra, Ntomme T.E.N. Development Project Environmental Impact Assessment Scoping Report and Terms of Reference (ToR)

Amended Background Information Document

Convention in International Trade of Endangered Species

Contents. Non-Technical Summary. 1. Introduction. 2. Policy, Regulatory and Administrative Framework. 3. Impact Assessment Methodology

About WCC LNG Project Ltd.

Background Information Document

URS- EIA- REP Date of Issue 19th November 2012

Background Information Document

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT SUMMARY

GLOSSARY. Quantum Power Ghana Gas Limited ix Knight Piésold Consulting Environmental and Social Impact Assessment

Jubilee field. development - the story so far. June 2010

THE CURRENT CLIMATE FOR A SUSTAINABLE BLUE ECONOMY

LNG Business In India

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

Aquaculture in Offshore Wind Farms: Multi-use Concepts to Reduce Spatial Conflicts in the Marine Realm

Introduction. FLNG: Costs and Cost Drivers. What is FLNG (and what isn t) FLNG Project Costs

member of the TSAKOS GROUP of companies

The Project will be undertaken in line with a number of national laws and standards. Key local laws relating to ESIA include:

T.E.N. EIA COMMUNITY CONSULTATION: POTENTIAL STAKEHOLDER QUESTIONS (QUESTIONS AND ANSWERS SHEET)

FUGRO GROUP LNG FIELD DEVELOPMENT AND FACILITIES. TACKLING your complex challenges. UNDERSTANDING your operational objectives

LNG Import Facility Infrastructure Options

BACKGROUND INFORMATION DOCUMENT

The overall objectives of the monitoring activities are to:

Gorgon Project Update: Selected Images

Appendix A: Project Characteristics

Takoradi LNG Floating Storage Regasification Unit

SEAHORSE MARINE. Company Profile. Seahorsemarine services Ltd. P.O.Box CS 9132, Tema, Ghana. Mob: / /

Draft Structure of the Environmental Report for the Spatial Offshore Grid Plan of the German Exclusive Economic Zone (EEZ) in the Baltic Sea 2013

The Halifax Harbour Solutions Project Provision of Sewage Treatment

PERP Program LNG Receiving Terminals New Report Alert

Background Information Document

FRAMEWORK FOR AQUACULTURE DEVELOPMENT ON THE VOLTA LAKE. Implementation Guidelines Document

8 IDENTIFICATION OF KEY ENVIRONMENTAL AND SOCIAL ISSUES

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project

Mangaluru Integrated Gas Project

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT

Berth 9 Quay Extension Environmental Statement Non-Technical Summary

7 MONITORING PLAN 7.1 INTRODUCTION

LNG IMPORT OPTIONS STUDY REPORT

North American LNG 2006

6 IDENTIFICATION AND PREDICTION OF IMPACTS

Abeokuta, Nigeria Greenfield Power Generation Plant Environmental Impact Assessment (EIA) Background Information Document (BID) January 2015

Combined Cycle Gas Turbine Power Plant Project at Fort George, Mauritius

ENVIRONMENTAL SCOPING PLAN

Liquefied Natural Gas Terminals Services and solutions

Environmental and Social Impact Assessment (ESIA) for Oil & Gas Projects, a Myanmar Context

8. Risk Assessment Process

Update on the implementation of EU nature, marine and fisheries policies relevant for ASCOBANS activities

Environmental Impact Assessment (EIA) for Oil & Gas and Power Projects

Welcome. About the Proponent. About the Proposed Project. The Proposed Project is now in the Regulatory Review period of the schedule.

Conversion of Kurnell refinery to a fuel import terminal

MARINE POLLUTION DEGRADATION MITIGATION MANAGEMENT IS ESSENTIAL FOR IMPROVING MARINE ENVIRONMENT

Handling and Transportation of LNG

Project Overview. Northwest Innovation Works LLC and the Port of Kalama propose to develop and operate

LNG in the United States

Marine Asset Protection using AIS Data

Known and potential impacts of deep sea mining and oil and gas exploration

FORM B: SWING MOORINGS

Arindom Goswami Technical Professional Leader M.W.Kellogg Ltd Greenford, UB6 0JA, U.K.

Member of DP World Group

Barossa Gas Export Pipeline Installation

Energy from Offshore Kelp Farms: Technologies and Production of Laminarian Species

Marine Facilities for LNG Carrier Transfer Alternatives

Greater Amman Municipality

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI

Indirect and Cumulative Effects

PENDER HARBOUR DOCK MANAGEMENT PLAN

Background Information Document

SHAPING THE NATURAL GAS MARKET OF CYPRUS

CAO Audit of IFC Investment in Coastal Gujarat Power Limited, India August 22, 2013 (Published on October 23, 2013)

Integrated Actions to Mitigate Environmental Risks in the Mediterranean Sea

ECO-FRIENDLY LNG SRV: COMPLETION OF THE REGAS TRIAL

5.4 Initial Environmental Examination

Significant prevention measures in place for each LNG carrier *

Experience from the UK: Monitoring, Modelling and Uncertainty

6 Risk assessment methodology

Onshore terminal plants

Design of onshore LNG regasification plant

STUDY ON THE PROJECT FOR DEVELOPMENT OF NATIONAL STRATEGIC OIL STOCKPILING MEGA-FLOATING SYSTEM IN VIET NAM SUMMARY. February 2012.

Elastopor Sustainable solution for cryogenic insulation

THE TRANSFER OF LNG IN OFFSHORE CONDITIONS. SAME SONG NEW SOUND

Operative Part VI Annexes 26 February Annex 1: Resource Management (Marine Pollution) Regulations 1998

Environmental and Social Action Plan. Draft Report. The business of sustainability

NZCPS 2010 Guidance note Policy 9: Ports

PIPED-GAS REGULATION FEBRUARY 2017

Submission on the draft terms of reference for Balaclava Island Coal Export Terminal project

APPENDIX 8-A. Valued Component Selection Rationale

1. SCOPE OF WORKS. 1.1 Background of Preparation of ESHIA rev. A- 01

Factor Potential Effects Mitigation Measures

TRANSBOUNDARY ENVIRONMENTAL IMPACT ASSESSMENT

Integrated water resources management plan for Densu River Basin, Ghana

Chapter 14 Overall Project Assessment

Transcription:

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT Final Scoping Report - Non-Technical Summary Presentation

Structure of the Presentation Introduction to the Tema LNG Project Introduction to the ESIA Process The Public Participation Process Potential Issues Identified During the Scoping Phase Next Steps Questions and Answers 2

Introduction to the Tema Liquefied Natural Gas Project

Quantum Power Ghana Gas Limited (Quantum Power) propose to develop the Tema Liquefied Natural Gas (LNG) Project, which will include all the necessary infrastructure to import, store, re-gasify and deliver re-gasified LNG to off-takers in the Greater Accra Area. The proposed Project will include infrastructure in the sea (Marine) and on land (Terrestrial) and will cross two administrative districts in the Greater Accra Area, namely Tema (West and East) and Kpone Katamanso. The proposed Project will be located almost exclusively in a Right of Way Servitude and Marine Exclusion Zones. The proposed Project will provide LNG to Independent Power Producers in order to provide much needed electricity. 4

5

What is LNG and what will the Project entail? LNG is produced by cooling natural gas to a very low (cryogenic) temperature until the gas becomes a liquid. The process reduces the volume of the natural gas to 1/600th of its un-liquefied volume. This much smaller volume allows large amounts of natural gas to be transported economically over long distances by special ships called LNG carriers. When the LNG is offloaded at its destination (the Tema LNG Project location), it is then re-gasified by heating it, which allows it to return to its gaseous state. The resultant natural gas is then distributed to customers via natural gas pipelines which transport the gas to power stations which provide electricity to domestic and industrial users. 6

PROCESS THAT TAKES PLACE OVER SEAS Raw Gas from Gas Fields Co 2, water and other Impurities Removed Stages of refrigeration to cool the gas turning it into liquid (Liquefied Natural Gas or LNG). This makes it easier to transport as it takes up less space LNG will be transported in LNG Carrier Ships to Tema where they will berth at the Floating Storage and Regasification Unit (FSRU) and Mooring Jetty located approximately 12km offshore The FSRU and Jetty will rest on piles or be anchored on the seabed and will be able to re-heat the LNG and return it to a gaseous state THE TEMA LNG PROJECT The gas will then be transported via a subsea gas pipeline to an onshore Landing Facility/ Metering Station before it is distributed via a pipeline (in an existing servitude) to Power Stations who supply electricity to domestic and industrial users

What infrastructure will be needed? Floating Storage and Regasification Unit (FSRU), Offshore Mooring and Supply Vessels - The FSRU will berth at the offshore mooring jetty, located approximately 12 km off the coastline of Tema. It will have an overall length of 295m, a width of 44m and will be able to store approximately 170,000 m 3 of LNG. The Floating Units will be permanently held in position by a mooring jetty, which will be connected to a subsea pipeline via a flexible riser. The mooring system will rest on permanent piles in the seabed and support a permanently moored storage and re-gasification vessel, an LNG trading vessel and a riser from the subsea pipeline. Subsea Gas Pipeline the subsea pipeline will be made from 18 inch carbon steel seabed pipe which will be laid on the seafloor in order to transport the gas from the FSRU to the onshore metering station. The pipeline will be designed to comply with international standards and will have concrete ballasts to prevent it from floating to the surface. 8

Landing Facilities and Distribution Pipelines to Power Stations in the Greater Accra Region - The subsea pipeline will run from the FSRU under the sea to a landing facility and a metering station. The subsea pipeline will be located in an existing exclusion zone where the West African Gas Pipeline (WAGP) is located. The metering station will also be located within close proximity to the WAGP metering station. The metering station will be able to monitor the amount of gas being distributed to the six planned Independent Power Producers, who will then provide electricity to other parts of Ghana. The metering station will also be able to monitor the pressure of the gas in the pipeline to detect any possible leaks. The gas will be distributed using underground pipelines that will be located in the existing Volta River Authority (VRA) Right of Way Servitude. 9

What is the project lifecycle Feasibility: This phase involves planning for the proposed Project, preliminary designs and the ESIA study. The Project is at this Stage Pre-construction: This phase involves planning for construction, putting in place mitigation measures and resettlement (if necessary). Construction: This phase involves construction activities to construct the Project and other required infrastructure. This phase also includes monitoring activities to make sure what is in the ESIA is implemented. Operational: This phase involves importing and distributing LNG within Ghana. Closure: This phase involves closing the Project, retrenching workers and rehabilitating the area. 10

The Environmental and Social Impact Assessment Process

What is the ESIA Process? Before the Project can start, a study called an Environmental and Social Impact Assessment (ESIA) needs to be done. An ESIA is a study to understand how the proposed Project will change the environment and affect the people living and working there. It also identifies ways to manage any changes that may happen (mitigation). 12

Why do an ESIA? The aim of this study is to advise the Ghanaian Government and international banks that may lend money to the proposed Project on the impact of the project and whether the Project should be allowed to be developed and under what conditions. The ESIA also identifies the expected impacts of the proposed Project and suggests how these effects can be managed. 13

What is the Process? Screening defines what environmental and social issues the study will focus on. The report will be submitted to the Government of Ghana who will then issue a Record of Decision. Scoping identifies the likely changes (impacts) that will happen because of the proposed Project. This phase includes a scoping report which is made available to the public and the Government of Ghana for comment. Scoping plans what areas need further investigation. The Impact Assessment understands how significant the changes are likely to be, and identify ways to manage these changes. This ESIA is at this stage. Specialist Studies collect information to understand what the environment and people in the area are like and how the proposed Project is likely to effect them. 14

The Public Participation Process

Objectives of Engagement Objectives of Engagement: To provide information to all potentially affected and interested people; To give all stakeholders a chance to comment on the ESIA team s work, including what impacts they have identified, how important they thought these impacts were and how they think the impacts can be managed; To manage expectations; and To meet the national and align with international requirements for impact assessments. 16

National Stakeholders: Who are our Stakeholders? Environmental Protection Agency (Accra and Tema) Ghana Maritime Authority Ghana Ports and Harbours Authority (GHAPOHA) Volta River Authority (VRA) Ministry of Energy (MoEn) Energy Commission (EC) Ministry of Fisheries and Aquaculture Development-Fisheries Commission Independent Power Producers Ghana Highway Authority Electricity Company Ghana Ghana Water Company 17

Regional and District Stakeholders: Tema Metropolitan Assembly (TMA) Kpone Katamanso District Assembly Ningo Prampram District Assembly Tema Development Corporation (TDC) The Tema Ashaiman Golf Club Local Stakeholders: Wonsom Fishing Association National Fisheries Association of Ghana (NAFAG) Ghana Canoe Fisheries Association Ghana Inshore Fishery Association-Tema Ghana Industrial Trawlers Association Dzigbordi Fish Mongers Association Enufa Enufa Canoe Association Directly Affected Parties The General Public: Communities living in close proximity to the servitude 18

How will stakeholders be involved? Some engagement has already taken place. There are four more opportunities for stakeholders to be involved: 1. Scoping Disclosure: Meetings and workshops with national, regional and local stakeholders on the findings of the scoping phase in February 2015 THIS MEETING. The Final Scoping Report is also available online and in a Non-Technical Summary (NTS). Stakeholders may comment at this meeting or in writing. 2. Data Gathering Activities: Some stakeholders have been and will still be engaged directly by the ESIA team to obtain certain information to feed into the ESIA. Some of these activities have taken place already but the ESIA team is still collecting information as they write up the baseline reports and undertake the impact assessment. 3. Draft ESIA Report Disclosure: Meetings to disclosure the findings of the Draft ESIA. Again a NTS will be available. Stakeholders will be provided with an opportunity to comment on the predicted impacts and the acceptability of the mitigation measures. 4. Final ESIA Report Disclosure: Last round of meetings with local communities and local authorities on the Final ESIA. The aim of this round is to understand the communities positions on the proposed Project so these can be communicated to Quantum Power and the national authorities. 19

20

Potential Issues Identified at the Scoping Phase

Summary of Potential Impacts Identified During the Scoping Phase Summary of Potential Positive Impacts: Direct Impacts Increased Income Generation Opportunities from Direct and Indirect Job Creation Supporting community development Indirect Impacts Much Needed Electricity Supply (Indirect Impact) Summary of Potential Negative Impacts: Direct Impacts Marine Environment The FSRU, associated infrastructure and activities may effect seawater quality, fish and other sea life. Restriction of ships and fishing boats. Terrestrial Environment The pipeline, roads and metering station may effect plants and animals, surface water quality, traffic, air quality and noise in the Project area. Socio-Economic Environment - people living or undertaking activities in the servitude or close to the proposed Project may be effected. Possible physical and economic displacement (to be confirmed). Views for locals 22

Terms of Reference for the Next Phase Based on the Scoping Phase findings, the following specialist studies have been commissioned: Marine Environment Oceanography Marine Water Quality Benthic Planktonic Estuaries and Lagoons Fish and Fisheries Marine Mammals and Reptiles Offshore Air Quality Offshore Noise Terrestrial Environment Hydrology Aquatic Ecology Terrestrial Ecology - Flora and Fauna Traffic Air Quality Noise Socio-economic Environment Governance and Administration Demographic Profile Social Infrastructure, Resources and Services Education Health Cultural Heritage Landscape and Visual Livelihoods and Socio-Economics Human Rights and Vulnerability Stakeholder Perceptions and Attitudes. 23

Next Steps The Scoping Report has been approved by the Ghana Environmental Protection Agency. Knight Piésold is now reaching completion with baseline studies based on the Terms of Reference identified in the Scoping Report. These studies are being undertaken by specialists in their fields. Knight Piésold are in the process of assessing the impacts and proposing mitigation measures. Knight Piésold will then engage with stakeholders again at the national, regional/district and local level. The aim of engagement will be to present the draft ESIA report to stakeholders for comment. This will be undertaken in March. Based on stakeholders comments, the final ESIA will be amended and submitted to the Ghana Authorities for their consideration. 24

What should I do now? Give your comments in this meeting. Review the scoping report or the Non-Technical Summary (NTS) pamphlet also available at http://www.knightpiesold.com/temalngesia. Contact George Lartey Young of Knight Piésold Consulting for more information if you would like. Come to the next meeting which will discuss the Draft ESIA Report 25

Questions and Answers

Thank You Knight Piésold Ghana Limited Physical Address: No. 20, 2 nd Close Airport Residential Area Post: P.O. Box CT 4122, Cantonments, Accra Phone: +233 30 7021155 l Email: TemaLNG@knightpiesold.com 27