TESTING PTE EARTHING

Similar documents
CS-21 STREET STRUCTURES TABLE OF CONTENTS

STANDARD TECHNIQUE: OH4K/1

ERECTION OF POLES INTO LIVE HV (11kV and below) AND LV OVERHEAD LINES

CHAPTER 14 STEELWORK

OVERHEAD SERVICES - SECONDARY

Temporary Wiring. Low-Voltage Electrical Safety Orders

Earthing in electrical network purpose, methods and measurement

These Electricity Safety Rules and associated National Safety Instructions are written to safeguard personnel working for or on behalf of National

ENGINEERING SPECIFICATION EE SPEC

INFORMATION PROVIDED TO ASSIST THE TENDERER FOR THE SUPPLY OF:

Ensure no person makes contact with the steel pole streetlight or temporary earth electrode while the testing procedures are being undertaken.

Northern Powergrid Appendix B for ENA Engineering Recommendation G81 Part 4: Design and Planning

Rehabilitation of Electricity Power Distribution Network in three areas in the Gaza strip (GS) PAL Bill of Quantity : Package2 - Lot 3

Part 4 High Voltage Overhead DISTRIBUTION CONSTRUCTION STANDARDS HANDBOOK

A. All materials shall be tested and listed by an OSHA approved Nationally Recognized Testing Laboratory (NRTL).

HAS/042/001 Code of Practice for Work on Street Lighting and Street Furniture including Installation, Repairs and Maintenance

C&G 2382 BS7671: th Edition IEE Wiring Regulations. 25 Questions

Route to Authorisation

Approved Tasks for the Application of Safe Approach Distance Special

These Electricity Safety Rules and associated National Safety Instructions are written to safeguard personnel working for or on behalf of National

STANDARD TECHNIQUE : OH4L/1

Title Transmission Line Maintenance Standards. Reference Number PMP 17 - (RIC Standard: EP SP)

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

Part 4 High Voltage Overhead DISTRIBUTION CONSTRUCTION STANDARDS HANDBOOK

SECTION 7.3 TECHNICAL SPECIFICATION OF POWER CABLES & CONDUCTOR

Duke Energy Carolinas Distribution Construction Standards Reference Guide

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL

Same as Client Address. 40, Havelock Close. India Way. London. Postcode: W12 7NQ

Same As Client Address SPECIMEN. operational limitations. of the inspection and. agreed with):

ECP SECONDARY COMMISSIONING REQUIREMENTS

PARTICULAR SPECIFICATION E11: GENERAL ELECTRICAL EARTHING AND LIGHTNING PROTECTION

Installation Address. Postcode. Purpose of the report This form to be used only for reporting on the condition of an existing installation.

NPS/001/024 Technical Specification for Low Voltage Aerial Bundled Conductor Fittings

30-SDMS-01 SPECIFICATIONS FOR LOAD BREAK SWITCH

RESIDENTIAL QUICK REFERENCE

4. POINTS ON SWITCH AND CIRCUIT BREAKER PLATFORM GROUNDING.

FREQUENTLY ASKED QUESTIONS

INDEX. Page SECTION 1.0: SCOPE Toronto Hydro Requirements Ontario Electrical Safety Code 1 SECTION 2.0: PURPOSE 1

Cignal-owned Tower Sites Tower Operations & Rigging Policy

GENERAL NOTES PEDERNALES ELECTRIC COOPERATIVE, INC. RESIDENTIAL AND COMMERCIAL AMP METER LOOP SPECIFICATIONS

2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING

Transmission Line General Requirements Including Typical Overhead Line Structures. Document Number: 1-03-FR-09

NPS/002/020 Technical Specification for 11 & 20kV Power Cables

CHAPTER 13 GROUNDING AND BONDING

RESIN FILLING TYPE JOINTING KITS FOR LOW VOLTAGE UNDERGROUND CABLES

NPS/002/023 Technical Specification for 132kV Power Cables.

CONTENTS INSTRUCTIONS. UK POWER NETWORKS LV JOINTING MANUAL I Version Section Index I Page 1

FREQUENTLY ASKED QUESTIONS

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

33-SDMS-02 SPECIFICATIONS FOR

Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11

Specification for UDC Electrical Testing

New Whole-Current-Metered Connections up to 60kVA

UNITED COOPERATIVE SERVICES. SPECIFICATIONS FOR SELF-CONTAINED METER INSTALLATIONS August 2014

SECTION EARTHING AND EARTH FAULT PROTECTION

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

SECTION SECONDARY UNIT SUBSTATIONS

GN7 Amendment 3-5 Agricultural and horticultural premises

0.6/1 kv LOW VOLTAGE CONTROL CABLES. Conductors. Insulation. Assembly. Standard Colour Code. Armour (Optional) Screening (Optional) Outer Sheath

DOMESTIC ELECTRICAL INSTALLATION PERIODIC INSPECTION REPORT (FOR A SINGLE DWELLING) B ADDRESS AND DETAILS OF THE INSTALLATION Address: SPECIMEN


Technical Specification for LV ABC Fuse Switch Disconnectors

Grounding & Bounding. 1. Bonded Connected to establish electrical continuity and conductivity.

ELECTRICAL INSPECTION BULLETIN B Installation and Inspection Requirements for Street and Roadway Lighting Systems. (Effective 2015/11/15 )

Municipality For the purpose of this bulletin, municipality means: a town, village, county, district or a regional municipality.

Effective June, Eaton-Durham Model # UTRS223ACH. Siemens, Model # SUAS877-PG. (or Landis & Gyr # UAS877-PG) Milbank. Model # U1980-O.

Distribution Tradesperson (Jobsplus Permit No. 706/2017)

S. C. Electric Cooperative s Specification for a Single-Phase, Two Bushing Overhead Distribution Transformer (Revised 10/2013)

ELECTRICAL SAFETY INSPECTION REPORT

(Condensed from National Electric Code)

LIGHTNING PROTECTION SYSTEM EARTHING SYSTEM ELECTRICAL ACCESSORIES

VOLUME-2 (PRICE BID) FOR TENDER NO. NABI/7(171)/2019-WORKS

ELECTRIC METERING GENERAL

Ground Fault Circuit Interrupters (GFCI) & Assured Grounding Program

660 Volts 630 & 800AMP

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS SINGLE-PHASE PADMOUNTED TRANSFORMERS

ELECTRICAL SAFETY INSPECTION REPORT

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT

NPS/002/018 Technical Specification for Pilot, Control and Telephone Cables

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

Engineering Recommendation G81- Part 2: Materials Specification

overhead and underground power equipment ISSUE 28 AUGUST / SEPTEMBER 2013 / OHUG.COM OHUG WINS BEST TRADE STAND AT EEA FOR THE SECOND YEAR IN A ROW!

Sarawak Plantation Property Holding Sdn. Bhd. ( T)

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

PART 7 Technical Specification for Overhead and Underground Service Connection works for the Year

ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS

NORTHEASTERN REMC ELECTRIC STANDARDS MANUAL

Two-Way and Four-Way Underground Link Boxes

CONSTRUCTION SPECIFICATION FOR CABLE INSTALLATION

WESTERN CONNECTICUT STATE UNIVERSITY ELECTRICAL SAFETY PROCEDURE S-109

Sections through of Chapter 5 of the Victoria City Code are amended to read as follows: ARTICLE IX. NATIONAL ELECTRICAL CODE

Title Cables for Railway Signalling Applications - Traction Return Bonding and Track Connection Cables

SECTION GROUNDING AND BONDING

NAPIT Periodic Report on an existing Electrical Installation Requirements for Electrical Installations BS 7671 [IEE Wiring Regulations 17th Edition]

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

GUIDANCE FOR CUT OUT WORKS

Huntsville Utilities Underground Residential Service Requirements

SECTION GROUNDING

Transcription:

1 SCOPE This section of the Power Systems Live Working Manual details the procedures to be followed to achieve Safety from the System when carrying out examination, testing and remedial work on PTE (Pole Transformer Equipment) HV and LV Earthing, where the PTE is connected to the System and is Live at normal System voltage. 2 ISSUE RECORD This is a controlled / maintained document All copies printed via the Intranet or photocopied will be deemed uncontrolled. Issue Date Issue No Author Amendment Details May 2001 1 D McKay Initial Issue New Format 14 Page Document June 2004 2 Jack Neilson Document reviewed. No changes required. 3 ISSUE AUTHORITY Author Owner Issue Authority Jack Neilson Operational Compliance Manager Jack Neilson Operational Compliance Manager William Cuthbert Business Risk and Safety Manager SP Power Systems Limited Page 1 of 14 PSLWM 5.8

4 CONTENTS 1. SCOPE 2. ISSUE RECORD 3. ISSUE AUTHORITY 4. CONTENTS 5. DANGERS 6. DEFINITIONS 7 GENERAL REQUIREMENTS 8 EARTHING LEADS AND CONNECTIONS 9 TESTING PROCEDURE WL-1.28 10 CORRECTIVE ACTION 11 APPENDIX 1 PTE EARTHING CHECK SHEET 5 DANGERS The main Dangers to personnel carrying out examination testing and remedial work on PTE Earthing are electric shock and burns arising from: (i) (ii) (iii) (iv) Infringing Safety Distances. Incorrect application of equipment. Inadequate connections to permanent System Earths or Temporary Earths. Failure to make proper use of appropriate PPE. 6 DEFINITIONS Terms printed in bold type are as defined in the ScottishPower Safety Rules (Electrical and Mechanical) 4 th Edition SP Power Systems Limited Page 2 of 14 PSLWM 5.8

7 GENERAL REQUIREMENTS This Section lays down the general requirements for the Examination of the Earthing arrangements at pole transformer equipments (PTE s) and shall include testing the Earth resistance values of both the HV steelwork and the LV neutral Earths. The acceptable conditions allowed in this Section of the Manual must not be taken as being acceptable for new lines, which must be to the standards laid down in the Distribution Construction Manual. This Section also provides guidance on the action to be taken to correct situations where the Earthing arrangements are not acceptable. All work associated with the Examination must be carried out in accordance with the Safety Rules and Safety Instructions when testing Earth values with the transformer Live, strictly in accordance with the Procedure WL-1.28 laid down in this Section of the Manual. The Examination requirements are summarised in Maintenance Procedure Check Sheet No. D4.4/A which also serves as an Examination Report Sheet. See Appendix 1. 8 EARTHING LEADS AND CONNECTIONS 8.1 General Unless the combined resistance of the HV steelwork and LV neutral Earth Systems is one ohm or less, the electrode Systems must be separate. Such a figure will not normally be obtainable on overhead line Systems, therefore unless information is available to the contrary it can be assumed that the electrode Systems will be separate. Where it is practical to do so, the LV neutral Earth electrode should be installed at the first LV pole out from the transformer, and will in any case have a minimum separation of 8metres (Scotland), 10metres (Manweb) from any other System Earth. Where the neutral Earth is installed on the transformer support, check to ensure that the HV steelwork and LV neutral Earth Systems are separate. Where the Earth conductors are bare, there should be at least 150mm separation across a wood pole surface and 50mm in air. Check to ensure that any anti-climbing device, wire or bracket on the pole does not come into contact with a bare Earthing lead. It is particularly important that metallic objects do not form a short circuit between the HV and LV Earthing leads. SP Power Systems Limited Page 3 of 14 PSLWM 5.8

Note: Unless insulation is a minimum of 0.8mm thick PVC, Earthing leads should be considered as bare and where bare Earth leads are found, arrangements shall be made to replace them with insulated leads at the earliest opportunity. Check to ensure that the bottom section of any Earthing lead on a wood pole is protected by a non-metallic guard. Check to ensure that aluminium Earthing leads do not go into the ground and that any bi-metallic joints are adequately taped and sealed against ingress of moisture. Only copper is acceptable for Earthing leads and conductors below the ground. 8.2 HV Earthing Leads and Bonding Check all Earthing leads and bonding above ground to ensure that they are undamaged, corrosion free and adequately fixed and that they are of the correct size for the line specification. Check that steelwork is bonded correctly. Guidance on Earthing and bonding lead sizes and the Plant and Apparatus to be bonded is given below. 8.2.1 HV Earthing and Bonding Leads Type of Line Specification Minimum Cross Section Area (Copper Equivalent) Light Lines (e.g. L10 or similar; 32mm 2 copper equiv. conductor and below) Heavy Lines (all above 32mm 2 copper equivalent conductor) 16mm 2 (0.025in 2 ) 70mm 2 (0.1in 2 ) Present Standard 35mm 2 copper green/yellow PVC Insulated 70mm 2 copper green/yellow PVC Insulated 8.2.2 Plant and Apparatus to be bonded to the HV Steelwork Earth at Transformer Poles, HV Cable Box Poles and Air Break Switch Poles. (i) (ii) (iii) (iv) Transformer tank and supporting steelwork Pole mounted auto reclosers and other pole mounted switchgear and supporting steelwork HV cable box HV cable sheath SP Power Systems Limited Page 4 of 14 PSLWM 5.8

(v) (vi) (vii) (viii) HV fusegear steelwork and mountings Steel crossarms Pilot insulator pins and brackets HV stay tops Note: (a) (b) (c) An air-break switch disconnector handle shall be bonded to an Earth mat which must be kept separate from other Earth electrodes. Anti-climbing devices shall not be connected with Earth. Metallic cable guards (on HV or LV cables) shall not be connected with Earth 8.3 LV Neutral Earthing Conductors and Bonding 8.3.1 Guidance on Plant and Apparatus to be bonded to the LV neutral Earth is as follows: (i) LV metallic cable box (ii) LV metallic cable sheath (iii) LV fusegear metallic mountings (iv) LV insulator brackets ('D' irons) (v) LV stay tops 8.4 Stays 8.4.1 Check to ensure that the top portions of all HV stays are bonded to the HV steelwork Earth and report where there is not an insulator in the stay. Where an insulator is fitted, check to ensure that the insulator is so placed that if the stay broke, that part of the stay below the insulator would not come into contact with Live conductors. Also check that stay insulators are at a minimum height of 3m above ground level. SP Power Systems Limited Page 5 of 14 PSLWM 5.8

8.4.2 Check to ensure that all LV stays have an insulator fitted and that the top of the stay above the insulator is bonded to the LV neutral Earth. Check to ensure that the insulator is so placed that if the stay broke, that part of the stay below the insulator would not come into contact with Live conductors. 8.4.3 Where there are HV and LV conductors on a pole, stays associated with the HV conductors require 2 insulators. SP Power Systems Limited Page 6 of 14 PSLWM 5.8

9 PROCEDURE WL-1.28 TESTING PTE EARTHING 9.1 Scope This procedure describes the methods and precautions to be followed when testing HV steelwork and LV neutral Earths of PTE s with the System Live, in order to determine their respective resistance values. The maximum acceptable values are given in the table below. Where practicable, action should be taken immediately to correct unacceptable values at the time of the test, particularly if Danger exists. Table Maximum Earth Resistance Values Earth Electrode Scotland Max. Value (OHMS) Where protected by 25A Slow Blow Fuse Manweb All other locations HVSteelwork 40 11Kv, 40. 6.6 Kv, 20 11Kv, 20. 6.6Kv,10 LV Neutral - Direct Earthed 1 1 - Continuous Earth Wire 40 20 - PNB (Protective Neutral Bonding, single customer) - PME single electrode - PME combined electrodes 40 20 40 20 40 20 9.2 HV Steelwork Earth Test (a) (b) Set up the Earth test instrument with its auxiliary electrodes 23 and 46 metres from the instrument. Establish a temporary reference Earth at least 5 metres from the base of the pole and check with the Earth tester that it has a resistance at or below the maximum permitted value. If it proves impossible to obtain a temporary Earth with a resistance at or below the maximum permitted value, arrangements must be made to conduct the test with the line and pole transformer dead. SP Power Systems Limited Page 7 of 14 PSLWM 5.8

(c) (d) (e) With the temporary reference Earth established, using an Approved tester check that there is no detectable voltage between the Earth lead on the pole and the temporary reference Earth. If no voltage is detectable on the high voltage indicator, then take a second measurement using an Approved multimeter. If there is an indication of voltage from either of these tests then the test procedure shall stop and arrangements made to conduct the test with the line and pole transformer dead. If zero volts is detected, connect an insulated lead first to the test instrument and then to the Earth conductor on the support. The most convenient point will usually be immediately above the protective capping. It is not necessary to disconnect the Earth from the pole where there is no HV aerial Earth wire on the System. If the Earth resistance measurement is higher than the maximum permitted value, make a secure connection between the temporary reference electrode and the Earth conductor on the support to provide a safe by-pass to the permanent Earth. It will then be safe to investigate the underground part of the Earth system with a view to ascertaining the cause of the high reading. Any necessary repairs may then be made or additional rods installed with a view to reducing the Earth resistance to an acceptable value. The Earth resistance should then be re-measured having first removed the temporary connection to the reference Earth. 9.3 LV Neutral Earth Test (a) (b) Set up the test instrument with its auxiliary electrodes at 23 and 46 metres from the instrument. Establish a temporary Earth not less than 5 metres from the pole and check with the test instrument that it has a resistance not exceeding the maximum permitted value. Note: In situations where the neutral is Earthed at the transformer pole the temporary reference Earth already set up for measuring the HV steelwork Earth will also suffice for this test. (c) With the aid of an Approved multimeter and a low range clip on ammeter, check for voltage between the temporary Earth and the permanent Earth and for current in the permanent Earth conductor. If there is an indication of more than 10 volts or 1 amp then do not proceed until the cause of the leakage has been ascertained. SP Power Systems Limited Page 8 of 14 PSLWM 5.8

(d) If the above tests are satisfactory, then securely connect an insulated lead (minimum size 70 mm 2 Cu.) from the temporary Earth to a point immediately above the test point, or above the position where a test point should be. Note: Where no disconnectable test point exists, then one shall be introduced using the following procedure: First connect a bridging conductor across the points where the test point is be formed so as to maintain the continuity of the Earth System, then cut the Earth wire and crimp two double hole lugs to the ends so that they can bolted together, thus forming a disconnecting link for future use. Remove the bridging conductor on completion of the disconnecting link. (e) (f) Open the disconnecting link to leave the neutral connected to the temporary Earth. Measure the resistance of the LV Earth electrode as quickly as practicable then reconnect the link immediately, so that the System will not be dependent on the temporary Earth for longer than necessary. If the resistance value obtained is higher than the maximum permitted value as defined in the table above, the existing installation must be examined to determine: (i) (ii) (iii) If the installation requires repair (e.g. corroded connections), or If the installation of a reasonable number of additional rods will achieve the desired level, or If one of the alternative methods of Earthing detailed in 10.2 below would be more practicable. Note: The temporary Earth must be connected in parallel as a precautionary measure before the established Earth electrode is disturbed. SP Power Systems Limited Page 9 of 14 PSLWM 5.8

10 CORRECTIVE ACTION 10.1 HV Steelwork Where the HV steelwork Earth value is above the maximum permitted value, steps shall be taken to investigate the reason and where necessary carry out appropriate repairs or install additional Earth rods. 10.2 LV Neutral Earth Where the LV neutral Earth value is above that given in the Table in this Section of the Manual, the corrective action to be taken shall be in accordance with the following guidelines. 10.2.1 If the existing System Earthing is CEW (Continuous Earthwire) PME or PNB, no change should be made to the method of Earthing. The installation must be examined for any corroded connections or other defects and corrective action taken to meet the maximum permitted value. 10.2.2 If the existing method of Earthing is direct Earthing, consideration can be given to an alternative method of Earthing after the installation has been examined for any corroded connections or defects, and the corrective action required to achieve the maximum permitted value of direct Earthing is considered excessive. It is recognised that the one ohm maximum value of direct Earthing installations will be difficult to achieve in the majority of existing installations. The preferred alternative Earthing arrangement should include a continuous metallic return for customers Earth fault current from an Earth terminal provided and connected by the Company at the customers supply point to the LV System neutral Earth. This principle is embodied in PME and CEW arrangements. Although PME can readily be adopted for the overhead lines of most LV Systems, its application for existing services depends on the condition of the customers installation. Work on the customers installation could be as expensive as the measures to meet the one ohm criteria, and in these cases PME is not an acceptable economic solution. SP Power Systems Limited Page 10 of 14 PSLWM 5.8

APPENDIX 1 PTE Earthing Check Sheet PTE Name Ref No.. Examination Frequency 8years Page 1 of 4 Maintenance Checks / Actions (Ref Section R 4 of Maintenance Manual) General : 1. HV and LV neutral earths at same pole, check to ensure that sufficient separation exists between uninsulated leads 2. Anti-climbing device; check clear of HV and LV earths 3. Protective capping; Condition Correct Incorrect Remedial work date Acceptable Conditions One or both uninsulated separation 50mm in air; 150mm across wood surface Must not be bonded to earths Covers earth leads to a height 2.5m (min) from ground level 3. Aluminium earth wires; check that they do not enter ground HV Earth Wires and Bonding 1. Check leads and connections for signs of corrosion or damage 2. Check conductor size; - Light Lines, BS 1320; 32mm Cu or less Minimum 16mm (0.25) Cu equivalent - Heavy Lines, above 32mm Cu Minimum 70mm (0.1) Cu equivalent SP Power Systems Limited Page 11 of 14 PSLWM 5.8

APPENDIX 1 Page 2 of 4 Check Items Bonded to HV Steelwork Earth Condition Remedial Correct Incorrect work date Acceptable Conditions 1. Transformer tank At earth stud or bolt between tank and support steelwork 2. Transformer support steelwork 3. HV Cable boxes (Metallic) Box bonded to support steelwork 4. HV Cable sheath Sheath plumbed to box gland or Flexible lead bonded to support steelwork 5. HV fusegear mountings and support steelwork 6. Steel crossarms and tie straps Sufficient to have tie straps bonded 7. Pilot insulator pins and brackets 8. Stay tops One strand of stay wire to tie strap / crossarm bolt 9. HV Air-break switch mountings and support steelwork Items above operating rod insulator only 10. HV Air break switch operating handle and mounting Bonded to separate earth mat below operating position SP Power Systems Limited Page 12 of 14 PSLWM 5.8

LV Neutral Earth Wires and Bonding: Above ground, check leads and connections for corrosion, damage, fixings, etc. Check size of earth wire Check Items Bonded to LV Neutral 1. LV cable boxes (Metallic) 2. LV Cable sheath Condition Correct Incorrect Remedial work date APPENDIX 1 Page 3 of 4 Acceptable conditions Min 32mm 3. LV Fusegear (Metallic mounts) For all insulated, do not bond coach bolts 4. LV Insulator Brackets ( D Irons) 5. LV Stay Tops 6. Check HV Stay Insulator(s) and position of same if applicable Insulators in stays must be positioned such that if stay broke, part below insulator would not contact live conductors. 7. Check LV Stay Insulator(s) and position of same if applicable As for HV stays SP Power Systems Limited Page 13 of 14 PSLWM 5.8

APPENDIX 1 Page 4 of 4 Condition Remedial Max. Value (Ohms) Measure Earth Resistance Values Correct Incorrect work date Scotland Manweb At All Locations 25A Fuse Protection All Other Locations HV Steelwork Earth (Correct if necessary) 40 11Kv, 40 6.6Kv, 20 11Kv, 20 6.6Kv, 10 LV Neutral Earth (Correct if necessary ) 1. Direct Earthed 1 1 1 2. CEW (Continuous Earth Wire) 40 20 20 3. PNB (Protective Neutral Bonding, single customer) 40 20 20 4. PME Single Electrode 40 40 40 PME Combined Electrodes 20 20 20 SP Power Systems Limited Page 14 of 14 PSLWM 5.8