CROWN PILLAR ON VENTILATION DRIFT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA

Similar documents
DRAW POINT CONSTRUCTION IMPROVEMENT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA USING THE SIX SIGMA METHOD

Design of Steel-Concrete Composite Bridges

Analysis of Buried Arch Structures; Performance Versus Prediction

Effect of dip on pillar strength

Grasberg Block Cave mine: cave planning and undercut sequencing

M.C. Christianson Itasca Consulting Group, Inc., Minneapolis, Minnesota, USA

The Aizhai Suspension Bridge is

Long-Hole Stope Evaluation. Operating procedures. Introduction. 1. Approach of the model. 2. Notification. 3. Worksheets

EFFECT OF DEEP EXCAVATION SUPPORTED BY CONCRETE SOLIDER PILE WITH STEEL SHEET PILE LAGGING WALL ON ADJACENT EXISTING BUILDINGS

Crack detection in composite bridges with relative displacement sensors

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY

NON-LINEAR ANALYSIS OF BURIED ARCH STRUCTURES

Odin s Bridge Northern Europe s Longest Twin Swing Bridge.

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.

Comparison of geotechnic softwares - Geo FEM, Plaxis, Z-Soil

Ductility of Welded Steel Column to Cap Beam Connections Phase 2

APPENDIX B ABC STRUCTURES DESIGN GUIDE

Council on Tall Buildings. and Urban Habitat BACKGROUND SECTION STEEL REINFORCED CONCRETE SHEAR WALL STEEL PLATE COMPOSITE SHEAR WALL

Field Load Testing of the First Vehicular Timber Bridge in Korea

Route 360 Inverted T-beams. Carin Roberts-Wollmann Virginia Tech Tommy Cousins Clemson University Fatmir Menkulasi Louisiana Tech

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil

PRESTRESSED CONCRETE STRUCTURES. Amlan K. Sengupta, PhD PE Department of Civil Engineering Indian Institute of Technology Madras

Load capacity rating of an existing curved steel box girder bridge through field test

BS EN :2004 EN :2004 (E)

Full-Ring Experimental Study of the Lining Structure of Shanghai Changjiang Tunnel

TEST AND ANALYSIS OF A SHORT-SPAN RAILWAY BRIDGE

FULL-RING EXPERIMENTAL STUDY OF THE LINING STRUCTURE OF SHANGHAI CHANGJIANG TUNNEL

In-plane testing of precast concrete wall panels with grouted sleeve

Numerical Analysis of Lining Hinge in Tunnels

Types of Structures and Loads

EVALUATION OF SEISMIC BEHAVIOR OF IRREGULAR STEEL STRUCTURES IN PLAN WITH BRB AND EBF BRACES UNDER NEAR-FAULT EARTHQUAKE

ST7008 PRESTRESSED CONCRETE

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

Stress-Laminated / Steel T-Beam Bridge System

CYCLIC BEHAVIOR OF AN INNOVATIVE STEEL SHEAR WALL SYSTEM

Numerical Modeling of Soil Improvement for Construction of Tunnels Using Forepole Presupport

Cut and fill productivity. Operating procedures. Introduction. 1. Approach of the model

MODELLING OF SHEAR WALLS FOR NON-LINEAR AND PUSH OVER ANALYSIS OF TALL BUILDINGS

Interpretation of Danish Chalk Parameters Applicable to Foundation Design

Numerical Analysis of a Novel Piling Framed Retaining Wall System

Prepared by Elie F. Issa, Eng. D.E.C. August 2016

Appendix D.2. Redundancy Analysis of Prestressed Box Girder Superstructures under Vertical Loads

Sabah Shawkat Cabinet of Structural Engineering 2017

ANALYSIS AND ASSESSMENT OF ARTICULATED SKEW HOLLOW SLAB BEAM BRIDGE

Damage states of cut-and-cover tunnels under seismic excitation

Design and Rating of Steel Bridges

HANDLING OF BRIDGE BEAMS ON SITE

MINING ENGINEERING. Subject Code: MN. Course Structure. Engineering Mathematics. Vector Calculus. Differential Equations. Probability and Statistics

Three-dimensional computer simulation of soil nailing support in deep foundation pit

SEISMIC BEHAVIOR AND DESIGN OF STEEL SHEAR CONNECTIONS WITH FLOOR SLABS

CYCLIC BEHAVIOR OF TRADITIONAL AND INNOVATIVE COMPOSITE SHEAR WALLS

Possible solution to past CM exam question. Question 2 July New city centre office block. by Rajavel Inbarajan

Sabah Shawkat Cabinet of Structural Engineering 2017

Response Analysis of an RC Cooling Tower Under Seismic and Windstorm Effects D. Makovička

Figure 1 Swing Span Supported by Center Pivot Pier and Two Rest Piers

Comparison of Seismic Behavior of Multi-Storey R/C Buildings With and Without Internal Beams

Roofex Results of Laboratory Testing of a New Concept of Yieldable Tendon

Relationship between twin tunnels distance and surface subsidence in soft ground of Tabriz Metro - Iran

Field and Laboratory Performance of FRP Bridge Panels

by Dr. Evert Hoek prepared for RocNews - Spring 2011

Theories and techniques of coal bed methane control in China

USE OF SALE CHARTS IN DETERMINING MOMENT AND SHEAR

Investigation of the behavior of stiffened steel plate shear walls with Finite element method

xiii Preface to the Fifth Edition Preface to the Second Edition Factors for Conversion to SI Units of

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables

Stage analysdeckis for deck erection of single-pylon suspension bridge

twenty two concrete construction: flat spanning systems, columns & frames Reinforced Concrete Design Reinforced Concrete Design

NEW COMPOSITE CONSTRUCTION OF HYBRID BEAMS COMBINING STEEL INVERTED T-SECTION AND RC FLANGE

AASHTOWare BrDR 6.8 Steel Tutorial STL6 Two Span Plate Girder Example

Investigation of Structural Steel Webs for Punching Shear

Characterization of Cement Treated Crushed Rock for Western Australia Roads

TESTING AND NUMERICAL MODELING - STEEL TRUSS OF THE SPORTS HALL

DIAPHRAGM BEHAVIOR OF DECONSTRUCTABLE COMPOSITE FLOOR SYSTEMS

Steel concrete composite construction is re-emerging. Development and Testing of a New Shear Connector for Steel Concrete Composite Bridges

CODE PROVISIONS RELATED TO SOILS AND FOUNDATIONS

Final Report. Non-Destructive Bridge Testing With Advanced Micro-II Digital AE system

Computer-aided design and analysis of multiple Tee-beam bridges

GEO-SLOPE International Ltd, Calgary, Alberta, Canada Tie-back Wall

Simulating Intact Rock Behaviour Using Bonded Particle and Bonded Block Models

CIVIL BREADTH Exam Specifications

This material may be downloaded for personal use only. Any other use requires prior permission of the American Society of Civil Engineers.

Combination of undrained and drained analysis to design the temporary supports of a large diameter tunnel

Ventilation and fire door coverage solution at the Chuquicamata underground mine project

UNDERPINNING A CRANE FOUNDATION

1. background: design & construction options

3.5 What guidance is there?

DIN EN : (E)

Long-term Experiments of Composite Steel-Concrete Beams

Comparative Study on Post - Tensioned and Reinforced Concrete flat Slab Systems for a Multistory Building

EXPERIMENTAL INVESTIGATION ON THE INTERACTION OF REINFORCED CONCRETE FRAMES WITH PRECAST-PRESTRESSED CONCRETE FLOOR SYSTEMS

BIN-WALL BRIDGE ABUTMENTS PRODUCT GUIDE

The HKIE Structural Examination Written Examination

Upgrading ductility of RC beam-column connection with high performance FRP laminates

6 Preliminary Assessment of Construction Method and Constructability Issues

Xyston Inn. NY. Proposal. Xiaodong Jiang. Structure Option. Advisor: Dr. Linda Hanagan

Surface Subsidence Analysis Due to Longwall Underground Coal Mining Method in PT. Gerbang Daya Mandiri, Tenggarong, East Kalimantan

Coupled Stress-Seepage Numerical Design of Pressure Tunnels

Transcription:

CROWN PILLAR ON VENTILATION DRIFT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA Rian Nugroho, PT Freeport Indonesia, DMLZ Engineering, Papua, Indonesia Andrew Parhusip, PT Freeport Indonesia, DMLZ Construction, Papua, Indonesia William Teweng, PT Freeport Indonesia, DMLZ Geotechnical, Papua, Indonesia Abstract Crown pillar is a situation which two different levels of development tunnel overlaying with adjacent distance. This situation results small pillar between these two drift/tunnels. Many cases crown pillar cannot be avoided due to designated ore body position and existing facility drift such as ventilation drift, haulage drift. Crown pillar also been a case on Deep Mill Level Zone (DMLZ) PT Freeport Indonesia. This paper will discussed a geotechnical decision to state a crown pillar status on DMLZ, Consequence assessment start from Development phase, pre-production/ground support phase and steel set construction to fix Crown pillar issue on DMLZ, a calculation on economic/actual cost of all of these phases revealed on this paper. The DMLZ Mine is the fourth vertical lift in the East Ertsberg Skarn system (EESS) deposit (figure 1) which is located between the 2905 and 2605m elevations, hosted in diorite (vein-style mineralization) and in skarn (disseminated and vein style mineralization). The DMLZ mine initiated caving produce in September 2015 and is continuing with production ramp-up activities. A significant amount of development and preproduction work was required to get the DMLZ to its current state and to initiate the cave, where the operations require adequate ventilation system. It takes intake drift and exhaust drift, which is will be used access to develop the other level such as extraction drift, and haulage drift. Introduction PT. Freeport Indonesia (PTFI) is the one of mining companies operating in Indonesia and start production in 1972, currently Freeport Indonesia implementing two methods of mining, there is open pit mine at Grasberg and underground mine at Deep Ore Zone (DOZ) with block cave mine method and Big Gossan with open stope method. The Deep Mill Level Zone (DMLZ) is the part of underground expansion project that will be prepared with underground block cave mine and will replace the production from the DOZ Mine. Figure 2 Design of DMLZ Mine Layout (source: Vulcan Maps) Crown Pillar The DMLZ Mine have design of intake level will be used as main access for development haulage access, and it will have thin pillar with exhaust level. It with a distance of countless pillar from back of exhaust drift to floor of intake drift. It have 4.3 meter between both levels, more precisely the location of pillar at DMLZ Intake 1 Lateral 2 Drift and DMLZ Exhaust 4 Drift (figure 3). Figure 1 Future Underground Mine Layout at PTFI 1

Table 1 DMLZ Mine Crown Pillar Calculation Figure 3 DMLZ Mine Crown Pillar Location, Vulcan Maps The dimension of intake drift is 7 meter width by 7 meter height as same as at the exhaust drift. It means the pillar have block of probable failure and have not good safety factor from the geotechnical consideration, it shown in figure 4 and 5 with calculation on table 1. One of the challenges involved in this case study is cut the pillar or build the raise between these two drift with blasting sequence properly to maintain the stability of the pillar around. Blasting Pattern According to the cut the pillar needs, and with regard to the actual drift, the blasting pattern to cut the pillar has two sequences with calculation blasting controllable variables. The blasting pattern sequences are with staggered pattern, diameter of charge holes is 102 millimeter with 1 meter of burden and 1 meter of spacing, it shown in figure 6. Figure 4 DMLZ Mine Crown Pillar 3D Representation Figure 6 DMLZ Mine Crown Pillar Blasting Pattern GEOTECHNICAL The Map3D numerical model using for analysis the condition of pillar, following the development sequences. In the early stages of sequence the rock behaves more or less elastically. This means that deformations occur without causing any damage to the rock. At some point the loads get high enough that the rock begins to crack and the deformation are no longer entirely elastic. Due to damage to the internal structure, only part of the deformation is recoverable upon unloading. Figure 5 DMLZ Mine Crown Pillar 2

Figure 9 Strength envelope graph use linear distribution Figure 7 Sigma-1 response when the drift close and past the pillar (source: Map3d model) In elastic modelling, the proceed along a linear projection above the non-linear part of the stress-strain response, various levels of over stressing corresponding to levels of damage or non-linear strain. The borehole camera observation would like to define various criteria to represent different ground conditions and calibrate the strength envelope. From the model, the spalling indicated is in 4m before past the pillar and the damages would expect when the exhaust drift past the pillar. Figure 8 Damage prediction on the core pillar (Source: Map3D model) Average pillar stress compare to strength envelope Back-analysis of observed in situ response conducted to determine a representative rock mass strength envelope and corresponding coefficient of variation. This need not be restricted only to stress driven failure events such as pillar failures. Strength envelopes corresponding to a variety of stress induced responses the strength envelope graph was created from the borehole camera observation on several areas at DMLZ mine. Figure 10 Strength envelope graph use linear distribution 3

Refer to another damage criteria created from damage model DMLZ for the baseline of calibrations (Source: Bewick.R & Teweng.W, 2015). The average pillar stress was increase during the development sequences, indicated by the σ1 σ3 above the spalling initiation line. stable, the second option is break through the pillar and build the bridge for the option. Construction as a solution To answer this problem, raise between these two drift must be connected by some structure. As the Intake will be used as main access for development haulage access, future structure required to meet the determined load. Biggest equipment with full capacity of load is aimed as the determined load. Articulated Dump Truck Series AD 60 is chosen as the designated load with full muck capacity assumption. From table 2 and Figure 13 below indicated that structure has to bear more than 110 ton moving load. Open raise condition left two options for this situation. Steel sets or to build a structure as bridge. These options required to be taken to connect Intake drift above. Steel Sets options will be constructed on below level or Exhaust Level, otherwise Bridge option will be constructed to connect intake level. Absolutely these two options will bear designated load as mentioned before. Figure 11 Damage calibration graph (Source: Bewick.R & Teweng.W, 2015) Figure 13 AD60 Truck full load distribution Table 2 Weight specification on Haulage Equipment (Caterpillar Handbook) Figure 12 Average Pillar stress on damage calibration graph (Source: Bewick.R & Teweng.W, 2015) The damage or strength criteria graphs shown the pillar will be have damages when the drift pass on the below of pillar. The pillar have a potential failure or major damage on the future. Base on the geotechnical analysis, first option is if the drift will be use for the main access on life of mine, steel beam is required for keep the pillar 4

Structural Loadings Commonly structural loads is defined as several types; Permanent load, traffic load caused by heavy equipment s and others. Permanent loads consist of Self weight of the structures and other non-structural element. Meanwhile Traffic load for bridge design consist of D lane load and T truck load. The D lane loading is applied across the full width of the bridge roadway and produces effects in the bridge equivalent to a queue of real of vehicles. The total amount of D lane loading applied depends upon the width of the bridge roadway. The T truck loading is single heavy vehicle with three axels which are intended to simulate the effects of the wheels of heavy vehicles. Only one T truck may be applied per design traffic lane. D Lane Load Uniform Distribution Load (UDL) with intensity q kpa, q depends on the bridge loaded length: L < 30m; q = 8.0 kpa L > 30m; q = 8 * (5 + 15/L) kpa UDL may be places in discontinue length to get the maximum influence. In this case L is amount from discontinue length of each D Lane load. D Lane load place vertical to traffic direction. T Truck Load Only one truck has to be placed in every traffic lane. T truck has to be placed in the middle of traffic lane. The load is applied on the structure as point moving load which produces the maximum effect on moment Steel set is designed with steel beam combinations with addition on connector between each set, proposed gap between each set is 1.2 meter. Seen figure 15 below, maximum bending moment will happen on the center of the cross beam. Additional stiffener between cross beam and the column reduce maximum moment significantly. Figure 15 Steel set 3D design Using steel set answer the solution for this crown pillar problem, proven can handle designated loads. With some recommendation like all supports for the frame of steel sets are fixed, steel set spacing must be lower than 1200 mm. Figure 16 shows bending moment in each frame caused by the loads. Steel Sets Option Figure 14 shows steel set design as a structure to bear maximum load. As illustrated on below Figure. Intake level and exhaust level separated by concrete fill. Steel sets hold concrete load and moving load generated by AD 60. Figure 16 Bending Moment on steel set design arrangement Figure 14 Steel Set arrangement design Steel bridge Option Figure 17 shows steel frame fabricated as bridge to connect Intake level. Using profile Welded beam 900 as main girder and Universal beam 410 as connector, bridge designated to hold and connect intake level as 5

well as steel set option. Bridge will be constructed on Intake level, while this option will consume less concrete and less steel consumption rather than steel sets. Applied loads on bridge will be same as applied on steel set. stress, UB 410 as connector beam reduced this stress significantly. Figure 19 Bending Moment Distribution on Steel bridge design ACKNOWLEDGEMENT Figure 17 Steel Bridge 3D design Figure 18 show Plot Bridge unto actual drift on intake level. This bridge designated to serve heavy equipment access on underground. Figure 18 Bridge design plotted on actual drift on plan view Table 3 Comparison of material consumption based on two proposed design The authors would like to thank to management teams of PTFI for permission to prepare and publish this paper, also thank to Mr. Timothy Casten for final Review and Underground DMLZ Construction team for support and sharing knowledge. REFERENCES 1. AISC-ASD (American Standard for Steel Design), (2010). 2. Nurdi, Herry. Various Design, DMLZ. 2015 3. Martin CD, Kaiser PK, McCreath DR. Hoek-Brown parameters for predicting the depth of brittle failure around tunnels. Can Geotech J 1999 4. C.D. Martina,W.G. MaybeebThe strength of hard-rock pillars ; International Journal of Rock Mechanics & Mining Sciences 37 (2000) 1239±1246 5. W. G. Maybee ;Pillar Design In Hard Rock, 2000 6. Hoek, E., Kaiser P.K. and Bawden W.F. 1995. Support of underground excavations in hard rock 7. Hoek, E. 1990. Estimating Mohr-Coulomb friction and cohesion values from the Hoek-Brown failure criterion. Intnl. J. Rock Mech. & Mining Sci. & Geomechanics Abstracts. 12 (3), 227-229 8. Kaiser and Kim (2008), Rock Mechanics Challenges in Underground Construction and Mining 9. P. K. Kaiser1 M.S. Diederichs2, C. D. Martin3, J. Sharp4, and W. Steiner5, UNDERGROUND WORKS IN HARD ROCK TUNNELLING AND MINING The comparison of material consumption briefly showed on table 3. Steel bridge could be alternative solution to face crown pillar. Structural analysis showed on Figure 19 indicated biggest moment happen on the center girder and on the abutment, further analysis on concrete abutment is required to ensure the foundation strong enough. Bridge structure also receive torsion and shear 6