Overview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations

Similar documents
Fall 2018 Engineer Trainee Recruitment Preference Sheet

Project Delivery. Rodger Rochelle, PE Technical Services Administrator. Mike Holder, PE Chief Engineer

Statewide Acceleration Transformation (SWAT)

Presented By: Debbie Hunt Florida Department of Transportation District Seven Director of Transportation Development October 16, 2013

Research Initiatives at TxDOT Related to Utilities and Right of Way

Project Planning and Development Process

Any discussions or marketing activities related to this specific project.

DESIGN BUILD LA 318 INTERCHANGE FUTURE I-49 SOUTH

Design-Build Overview Alternate Project Delivery Office. Jeff Roby, P.E., DBIA Design-Build Program Manager Alternate Project Delivery Office

DRAFT SCOPE 1.0 General Requirements

DESIGN BUILD LA 318 INTERCHANGE FUTURE I-49 SOUTH

Florida Department of Transportation District-Wide DESIGN-BUILD TOPICS PUSH BUTTON Contract

Design -- geometric and structural design of roadways and bridges, and preparation of detailed plans and specifications for individual projects;

FDOT PROJECT INFORMATION APPLICATION FORM

NC General Statutes - Chapter 136 Article 3A 1

content chapter NEPA and Right-of-Way 28.1 Balancing Right-of-Way Detail in NEPA Documentation

Design-Build and Design-Bid-Build

NCDOT Overview. Nick Tennyson, Chief Deputy Secretary March 4, 2015

Table of Contents Local Agency Guidelines Section B August 2011

Please note the following policy concerning communication between Consultants and Pike County Engineer during the announcement and selection process:

Accelerated Construction: A Path Forward by Texas Department of Transportation 512/ All Rights Reserved

Transportation Project Delivery Process & Mitigation

Please note the following policy concerning communication between Consultants and Pike County Engineer during the announcement and selection process:

Project Delivery Process. Bruce Johnson, P.E. State Bridge Engineer Oregon Department of Transportation

Route 7 Corridor Improvements Project Reston Avenue to Jarrett Valley Drive Public Hearing

SH 34 Corridor Study & Environmental Assessment:

Attachment A FTA DCE Worksheet Section II, NEPA Class of Action

Selecting Projects for Accelerated Bridge Construction

Design-Build. Authorization. Criteria Selection/Award Process. Design-Build Construction Engineering and Inspection

EXHIBIT A SCOPE OF SERVICES FOR FINANCIAL PROJECT ID TRANSPORTATION SYSTEM MANAGEMENT & OPERATIONS (TSM&O) GENERAL CONSULTANT SERVICES

SCOPE 1.0 General Requirements

OFFICE OF INSPECTOR GENERAL. OIG Risk Assessment and Proposed Work Plan

The purpose of this addendum is to respond to RFI s submitted to the County and issue a revised SECTION BID FORM.

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

TRANSPORTATION SYSTEM JURISDICTION AND NUMBERING

New Jersey Department of Transportation. Local Freight Impact Fund Handbook. Procedures and Criteria for Local Freight Impact Fund Grant Program

STATE AID GUIDE FOR: Updated: December 16, 2005

ALTERNATIVE PROJECT DELIVERY DIVISION

Chapter 18. Quality Assurance and Quality Control

I-95/Route 630 Reconstruction and Widening Initial Financial Plan

Integrating Utility and Environmental Processes. Cesar Quiroga Texas Transportation Institute Texas A&M University System

EXHIBIT A SCOPE OF SERVICES FOR. FINANCIAL PROJECT ID(S). Various Projects DISTRICT 2 VARIOUS COUNTIES

448 INNOVATIVE BIDDING TOOLKIT

RAPID INCIDENT SCENE CLEARANCE (RISC)

Construction Project Guidelines Locally Let, State Funded Projects

APPENDIX F: CALTRANS COST ESTIMATE TEMPLATE (included in Appendix AA of the CALTRANS Project Development Procedures Manual)

The Essential Elements of a SMARTZONE Contract

Quarterly Transportation Report 1 st Quarter 2015 March 10, Thomas Blaser Director Department of Transportation

Project Location. Pensacola Bay Bridge Replacement Design Build 03/02/16. Kerrie Harrell, P.E. District 3 Consultant Project Management Engineer

CONTRACTOR'S ESTIMATE PACKAGE

Cost Estimating Guideline February, 2017

Town of Brandon, Vermont Brandon Union St. Sidewalk STP EH 05 (4) Request for Qualifications Construction Inspection and Testing Services

Materials and Surfacing - Organization and Functions

Capacity Building Workshop NCHRP Report 574 and Beyond: Where were We, Where are We, and Where are We Going?

PROGRAMMATIC AGREEMENT

PUBLIC CONTRACT CODE SECTION

CONTRACT PROPOSAL/CONTRACT ACCEPTANCE HIGDON LOOP ROAD BRIDGE

TAMPA BAY NEXT MAJOR PROJECTS UPDATE

Strategic Intermodal System (SIS) and Shared Use Non Motorized (SUN) Trail Program Update

INNOVATIVE CONTRACTING GUIDELINES

PREPARATION OF THE AUTHORIZATION / OFFICIAL CONSTRUCTION COST ESTIMATE AND CONTRACT BID REVIEW PACKAGE

TxDOT Internal Audit ROWAPS Follow-up Audit Report (1104-1F)

Enterprise Parkway Improvement Project, CIP# E364

CITY OF SAFETY HARBOR ENGINEERING

ADMINISTRATIVE DIRECTIVE #CS-04

I-49 North Shreveport (I-220) To Arkansas State Line

Data Knowledge and Knowing What To Do Next. 11th National Conference on Transportation Asset Management

Highway / Utility Guide

Asphalt Pavement Association of West Virginia 2018 Fall Conference

Strategic Intermodal System (SIS) and Shared Use Non Motorized (SUN) Trail Program Update

FLORIDA DEPARTMENT OF TRANSPORTATION PROCEDURE DEVELOPMENT OF THE

Re: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy

SECTION BID FORM (REVISED ) ADDENDUM No. 1

Town of Moraga Canyon Road Bridge Replacement Project October 10, 2018 Town Council Presentation

PUBLIC NOTICE MEDINA COUNTY HIGHWAY ENGINEER SHAW ROAD BRIDGE REPLACEMENT - DESIGN REQUEST FOR STATEMENT OF QUALIFICATIONS (RFQ)

Town of Brandon, Vermont US Route 7 (Center Street) Bridge 114 Improvements

Advanced Construction Techniques

Mike Wawszkiewicz, P.E.

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION. Project Commitment. Public Yes Design/ Permitting (Prior to Construction Beginning)

Town of Bennington, Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11)

Engineering & Capital Improvements. Shore Acres Civic Association August 21 st, 2017

Managing a Design-Build vs. Bid-Build Project

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

Reconstruction Project Update

Florida Department of Transportation

ENGINEERING SERVICES Phase III Construction Engineering Services for the Benedictine Parkway Improvement Project

CENTRAL FLORIDA EXPRESSWAY AUTHORITY. SR 408 Eastern Extension PD&E Study

KURTS 2.0 Mobilizing and Sharing Price, Conflict, and Inspection Data

ADDITIONAL TYPES OF WORK REQUIRING PRE-QUALIFICATION:

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

BUTLER COUNTY ENGINEER S OFFICE Butler County, Ohio. * Request For Qualifications *

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions

Nation Environmental Policy Act (NEPA)

STATE OF NEVADA DEPARTMENT OF TRANSPORTATION TRAFFIC AND CONSTRUCTION NOISE ANALYSIS AND ABATEMENT POLICY

FTBA 2018 Construction Conference Major Projects Update

BUY AMERICA Federal Law and FHWA Policy

Review of Construction Costs and Time Schedules for Virginia Highway Projects

State of Ohio. Department of Transportation ~ Innovative Contracting Manual

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY

Transcription:

Overview of the Project Development Process Brian Blanchard, PE Assistant Secretary for Engineering and Operations

Overall Project Development Process The time it takes to produce a project varies significantly depending on the scope of the project and issues involved. Issues affecting the time include: Environmental issues >>>> ETDM Multiple permitting agency requirements and mitigation Local government coordination Community impacts assessment Inclusion of significant design features such as major bridge structures Range of alternatives that need to be studied Right of Way process 2

Project Development Process The basic activities are: Determine project scope & resource needs Conduct Project Development and Environmental (PD&E) study Prepare Design & Right-of-Way Documents Acquire Right-of-Way Obtain Necessary Permits Advertise Contract 3

PD&E Study Process Controlled by federal law (NEPA), regulations, and state law Key Processes: Develop Feasible Project Alternatives Develop Project Scope based on input from ETDM and select environmental class of action (EIS, EA, Type 2 CE, SEIR) Complete Environmental Analysis and Studies Perform Public Involvement and Interagency Coordination Select Preferred Alternative and Document Impacts and Project Location, Design and Commitments Reevaluation of environmental impact as project advances After the environmental document is approved, the project is ready for its design and right of way acquisition. 4

PD&E Study Process Project Scoping 1-2 mo. Develop Alternatives Environmental Studies 6-8 months 6-12 months Public Involvement continuous Select Preferred Alternative Reevaluation(s) Schedule for Type 2 CE with ETDM Input 3-4 mo. To Design Development 1-2 mo. 2 4 6 8 10 12 14 16 18 20 22 MONTHS PD&E Study: 1½ to 5 years depending on magnitude of project and environmental class of action: Type 2 CE to EIS 5

Design Development Process Controlled by the FDOT s Office of Design Key Processes: Preliminary Engineering (Plans & Maps developed to initiate ROW acquisition process) Final Engineering (Plans and Specifications developed into Construction/Contract Documents) Key Documents: Plans Preparation Manual Other Design Manuals (Structures, Drainage, Pavement, Utilities) Design Standards Computer Programs After the Contract Documents are produced, the project is ready for Contract Letting which immediately precedes Construction. 6

Preliminary Design Compile Data/Criteria Develop Alignment & Initial Design Complete Preliminary Design Design Development Process (Traditional) 4-6 mo. 2-8 months 2-6 mo. To ROW Final Design Final Plans & Maps Specifications 3-12 months 1-3 mo. Cost Estimates Assemble Documents 1-3 mo. 1-2 mo. To Construction 4 8 12 16 20 24 28 32 36 40 44 MONTHS Design Development: 1½ to 3½ years depending on project complexity 7

Right-of-Way Acquisition Process Controlled by federal law, regulations, and state law Key Processes: Appraisal-value established Negotiation - good faith offer Eminent Domain - court action to acquire title Order of Taking (OT) - clear title passed to DOT Relocation/replacement options determined and offered Property Management - clear R/W Once OT has occurred, the project is ready for construction to begin. 8

Right-of-Way Acquisition Process Appraisal 6-10 months Negotiation/Closing 6-8 months Relocation Eminent Domain (if necessary) 0-9 months 0-2+ years Order of Taking (Title) Property Management (Demolition) 3-4 mo. 1-4 months To Construction 2 4 6 8 10 12 14 16 18 20 22 Months Maps and Documents to R/W Certification: 1½ to 2 years 9

Construction Contract Administration Process Controlled federal law/regulations and state law Key Processes: Prequalify Contractors Train Personnel (CTQP) Contractor s Quality Control Inspection & Verification Public & Worker Safety Payment Processing Warranties 10

Construction Contract Administration Process Key Documents (FDOT): Standard Specification Design Standards Manual of Uniform Traffic Control Devices Construction Procedures Manual Final Estimates Manual Once Construction is complete, the project is turned over to the Maintaining Authority. 11

Contract Letting through Construction Process Contract Letting 20 days Contract Award 10days. Contract Execution 25 days Notice to Proceed 16 days Construction 6-36 months 6 8 10 12 14 16 18 20 22 MONTHS Construction Process: 6 mo. to 3 years depending on project complexities. 12

Use of Alternative Contracting The Department uses the following Alternative Contracting methods to reduce contract time or overall contract costs. Reduced project time generates savings in contract costs and reduces impacts to motorists, businesses and residences created by work zones. Lane Rental A+B Bidding No Excuse Bonus Liquidated Savings Design Build Lump Sum Incentive/Disincentive Warranties 13

Dollars (Billions) 5.0 4.5 4.0 3.5 3.0 2.5 2.0 1.5 1.0 0.5 0.0 STATEWIDE LETTINGS - HISTORY/PLANNED 3.2 0.4 2.8 2.7 2.7 0.1 2.3 2.3 0.3 2.1 2.2 2.3 1.3 1.9 0.2 2.0 1.2 0.1 0.4 0.7 1.0 1.5 1.0 2.8 2.4 2.1 1.8 1.7 1.5 1.4 1.5 1.3 1.0 0.8 07 08 09 10 11 12 13 14 15 16 17 FISCAL YEARS 07 THRU 11 ARE ACTUAL LETTINGS, FISCAL YEAR 12 IS ADOPTED 7-1-2011 and FISCAL YEARS 13 THRU 17 ARE AS OF 1-11-2012 SNAPSHOT. The above Lettings include only Highway & Bridge construction contracts for Roadway, Resurfacing, Bridge, Safety and Traffic Ops. They are contract class 1 (Central Office), 7 (District Let) and 9 (Design Build). Projects such as Public Transportation (seaports, rail, aviation, etc.) and Local Agency Program contracts, are not included. Actual Lettings Planned Lettings (As of Work Program Snapshot 1-11-12) Contractor Financed Projects Planned Potential Project Funding P3 Projects Stimulus Projects (Includes P3 with ARRA Funds and Other Funds)

Questions?