A Building Information Modelling-Based Tool for Heuristically Assessing Façade Manufacturability

Similar documents
IDES-EDU. WP2 Workshop. Building Information Modelling and Interoperability. Anna Osello & Carlo Caldera 4/17/2013. About BIM

UNIVERSITY COLLEGE CORK

Optimizing Construction Planning and Scheduling through Combined Virtual Prototyping Technology and Building Information Models

Technion Graduate BIM Course

PRODUCT MODELS AND LIFE CYCLE DATA MANAGEMENT IN REAL PROJECTS

Automated Cost Analysis of Concept Design BIM Models

A BIM ASSISTED RULE BASED APPROACH FOR CHECKING OF GREEN BUILDING DESIGN 1

B/555 Roadmap (June 2013 Update)

GA2016 XIX Generative Art Conference

BIM In Infrastructure - Challenges & Solutions. Robert Ryan

STUDY ON BIM-BASED STRUCTURAL WORKING DRAWING DESIGN SYSTEM

Experiencing Interoperability of BIM in a Stadium Project in China

10 REASONS WHY IFC IS THE CENTRAL KEY TO SUCCESSFUL BIM PLANNING

BIM In Infrastructure - Challenges & Solutions

Parametric engineering: twisted logic or common sense?

This is the submitted version of a paper presented at CIB World Building Congress Construction and Society, Brisbane 5-9 May 2013.

Bentley Building.

O10 BIM for specialist sub-contractors and trades BIM IN PRACTICE

Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study

THE INTERLINK APPROACH - USING OPEN STANDARDS FOR ROAD ASSET INFORMATION MANAGEMENT. bsi Tokyo 2018 Bart Luiten -

BIM Event. Martin Huggins Senior R&D Consultant University of Wolverhampton. Black Country Constructing Excellence Club

NBS National BIM Survey 2011

A Framework for Collaboration Management of BIM Model Creation in Architectural Projects

Development of a sub building information model for 4D structural safety analysis during construction

Energy and Thermal Performance Management Through Utilisation of Building Information Models

Better digital collaboration through buildingsmart

What is Simulation. Merriam-Webster Dictionary On-line. Computer Simulation. Intent/purpose of simulation

Rapid Design Development and Integrated Collaboration

Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs

THE FUTURE OFFSITE CONSTRUCTION & DIGITAL ENGINEERING MATHEW RILEY MANAGING DIRECTOR, RAMBOLL UK

BIM MODELLING GUIDELINES ARCHI-CAD BIM MODELLING GUIDELINES ARCHI-CAD

Research on the Application of BIM in Sewage Treatment Project

Open Research Online The Open University s repository of research publications and other research outputs

Automated Clash Resolution of Steel Rebar in RC Beam Column Joints using BIM and GA

Capturing the Stakeholder Values of a Construction Project

TEACHING BUILDING INFORMATION MODELLING IN AN ARCHITECTURAL SCHOOL

A Building Products Procurement Platform for Environmental Evaluation of Design Alternatives

BIM for FM Opportunities: Overcoming Challenges and Sharing Lessons Learned

Virtual Prototyping for Engineering Design

Construction management supported in a BIM model: Practical case study applied to an energy recovery center from solid waste

BIM guide for members of the Institution of Mechanical Engineers

3drepo.io. The Digital Construction Platform. Collaboration Simplified

A BIM STORY. Andreas Wecker BIM Management / Losinger Marazzi. Thibaut Lecoutere BIM Site Coordinator / Losinger Marazzi

Modelling to Drive Design

IFC-Based Sustainable Construction: BIM and Green Building Integration

Strategic Plan to Develop BIM Interoperability in Structural Concrete

Challenges and Obstacles of Adoption BIM Technology in the Construction Industry in Iraq

BIM Are you BIM Level 2 Ready?

The Digital Twin in the water business in context with ISA 95

Information Delivery Manual (IDM) for Quantity Takeoff for Cost Estimating

A New Approach for Construction Engineering Design Management Research Based on BIM LIU Qing 1, a

Field BIM and Supply Chain Management in Construction: an On-going Monitoring System

Cold-Bent Single Curved Glass; Opportunities and Challenges in Freeform Facades

SIMULATE CONSTRUCTION SCHEDULES USING BIM 4D APPLICATION TO TRACK PROGRESS

Application of Building Information Modelling (BIM) in Construction Planning Process

Software Interoperability and Information Networking in the Construction Industry. Arto Kiviniemi

Towards a BIM Approach for a High Performance Renovation of Apartment Buildings

Robotic Process Automation. Reducing process costs, increasing speed and improving accuracy Process automation with a virtual workforce

OPTIONEER AN INNOVATIVE APPROACH TO CONCEPT DESIGN AND REWORK AVOIDANCE FOR THE WATER INDUSTRY

The Research of Integration Design Method of Prefab Aluminum Architecture

75% of the sample reported an increase in demand for BIM in Ireland. What is your role with the company?

Generic AEC/FM BIM View Specification Architectural Design to Spatial Program Validation

Available online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)

Information Delivery Manual Work within HESMOS A descriptive approach to defining Information Delivery Manuals

BIM AND THE CHALLENGE FACING MANUFACTURERS

Project Streamer - Introduction

Chapter 16 Software Reuse. Chapter 16 Software reuse

Applications of Building Information Modeling (BIM) in Knowledge Sharing and Management in Construction

CHAPTER 7 Building Information Modeling

BIM Uncovered. Collaborate Effectively and Deliver Better Design, Construction and Operational Models

Asta Powerproject NEW FEATURES IN VERSION elecosoft.com. Asta Powerproject: The power behind successful projects

BIM and the Consultant / Client s Quantity Surveyor

- DATA REQUIREMENTS BIM

Implementation of the Timetable Planning System STRAX/TPS in Denmark

ENERGY PERFORMANCE OF DIFFERENT TYPES OF DOUBLE SKIN FACADES IN VARIOUS CLIMATES

Rule based building components for modular coordination

PRSM Association. BIM in the Retail Capital Facility Industry: Benefits, Challenges and Adoption

Global Building Information Modeling (BIM) Market: Size, Trends & Forecasts ( ) May 2016

A METHODOLOGY OF MAPPING INTERFACE FOR ENERGY PERFORMANCE ASSESSMENT BASED ON OPEN BIM

MILLENNIUM SCIENCE COMPLEX AE SENIOR THESIS: IPD/BIM ( )

T Software Testing and Quality Assurance Test Planning

Tekla Software in practice BIM and precast concrete fabrication. Loe Betongelementer, norway. Copyright: LPO Architects

Parametric Library Components for BIM-based Curtain Wall Design Automation Module

5D BIM: Creating Cost Certainty and Better Buildings

Implementing building information modelling: a case study of the Barts and the London hospitals

Balancing Design and Performance in Building Retrofitting A Case Study Based on Parametric Modeling

PROCUREMENT UPDATE BIM - BUILDING INFORMATION MODELS

PLANON CONNECT FOR BIM. For the successful use of BIM data in Facility and Property Management

Cloud Engineering Services

BIM+GIS Integration methods for an Infrastructure Project in Amsterdam. GeoDesign+BIM 2018, , Amsterdam

AECOsim Building Designer Quick Start Guide

BUILDING INDUSTRY CHALLENGES AND BIM WEEK #2

USERS BENEFITS IN USING BIM (BUILDING INFORMATION MODELING) Nilforoushan, Massih. Saint John International University, Turin, Italy

HARMONIZATION OF STANDARDS FOR ENTERPRISE INTEGRATION AN URGENT NEED. Martin Zelm

Effective Implementation of DFM

Enabling Siemens PLM Software for the AEC Industry. Lake Constance 5D-Conference 2013 Constance, 28th-29th of October

BIM and sustainability concepts in construction projects: A Case Study

A PERFORMANCE STUDY OF PROJECT SUSTAINABILITY: REDUCING CONSTRUCTION WASTE THROUGH BIM

Capability Statement. For more information please contact: Capability Statement

Anaheim Regional Transportation Intermodal Center (ARTIC) 2014 AIA TAP / BIM Awards

Transcription:

A Building Information Modelling-Based Tool for Heuristically Assessing Façade Manufacturability Eleanor VOSS 1, Mauro OVEREND 2, and Will STEVENS 3 1 Glass and Façade Technology Research Group, Department of Engineering, University of Cambridge, UK, ev236@cam.ac.uk 2 Glass and Façade Technology Research Group, Department of Engineering, University of Cambridge, UK 3 Façade Engineering Team, Ramboll, UK Summary Reviews of real-world façade project processes have shown that understanding and incorporating manufacturing constraints at early stage design can lead to improved design development. The paper presents a tool to assist façade engineers in the development of panelisation schemes to facilitate manufacture. The tool uses the data stored in project Building Information Modelling (BIM) databases to evaluate the proposed designs against manufacturing constraints. It has been implemented in two ways, the first using a proprietary BIM application and the second using open source International Foundation Classes (IFC) BIM technology and the TNO IFC Engine toolbox. The paper includes a case study of the tool s application to a real world façade project. The principal finding is that implementation through open source technology is preferable due to significantly reduced analysis times arising from accessibility of required design data. Keywords: Façade; BIM; design; manufacture; IFC; Design Research Methodology (DRM) 1. Introduction Façade engineering suffers from many problems common to the broader construction industry, such as poor communication and fragmented working methods. These can in part be addressed Building Information Modelling (BIM), whose primary benefits include efficient storage, access and transfer of design information, and increased collaborative working [1]. The construction industry as a whole has recently increased its use of BIM. However, the discipline also faces specific challenges, since building envelopes are constructed from a wide range of materials with a variety of possible treatments. This increases the difficulty in managing manufacturing and installation design constraints. Furthermore, since façade consultants are appointed to provide specialist advice to design teams, the projects in a façade consultant s portfolio tend to be particularly complex in terms of geometry, materials or performance. This leads to design issues such as manufacturability, constructability and maintenance and it is the façade engineer s responsibility to advise the design team on these issues and to assist with design and development of the façade. 1.1 Building Information Modelling BIM technology is primarily deployed in industry through proprietary applications such as Digital Project, Revit and Microstation. This poses problems such as the introduction of errors and omissions resulting from the transfer of design information between different applications used by different members of the design and construction team. A possible solution to this problem is to standardise on neutral digital information storage formats.

The IFC data model schema is an international open specification designed for the exchange of building information in the construction industry. BuildingSMART, previously the International Alliance for Interoperability (IAI), coordinates the schema development. The schema provides an object model based description of spatial elements, building elements, MEP elements and other building components [2]. The flexibility of the schema is increased by the IFC Property Set attribute, which allows users to include data not currently specified by the schema. Karhu [3] noted that the IFC data model schema (which was in its early stage development at the time of writing, 1997) offers an industry standard product model that could be applied in this sector. Since then, many projects have used the IFC schema to store and exchange design information, including Sacks et al. [4], Sanguinetti et al. [5], Mitchell et al. [6], Laine et al. [7], and Fazio et al. [8]. A common finding is that although the IFC data model schema supports the exchange of design information, the schema is underdeveloped. Alongside the development of the schema, others such as the Building and Construction Research Group of the Netherlands Organisation for Applied Scientific Research (Nederlandse Organisatie voor Toegepast Natuurwetenschappelijk Onderzoek, TNO) [9] have developed tools to facilitate the use of the IFC schema. TNO s IFC Engine toolbox includes a DLL file, making available a selection of C++ methods that can be used to interrogate and modify a BIM IFC file. 1.2 Design Research Methodology (DRM) The Design Research Methodology developed by Blessing et al. [10] is a structured approach to design research projects. Through mapping the influences on design project outcomes, it is possible to identify areas of the design process that could be targeted by the research project. In response, support tools can be developed and tested. This methodology has been employed in the initial phase of the research project to identify the scope of the design support tool. 1.3 Outline of Content to Follow The following section describes the process used to identify the area of the façade design process that the BIM-based support tool is to target. Section 3 describes the two implementation methods and provides a comparison. Section 4 uses a case study to demonstrate the tool s use on a realworld project. Finally conclusions are drawn and further work outlined. 2. Design Influence Map The DRM design influence map has been employed in this research project. It is used to identify the part of the design process undertaken by the façade engineer that, if addressed by a support tool, would have a positive impact on the outcome of façade design projects. 2.1 Design Influence Map Production The maps have been developed through an iterative process, drawing on the experience of façade engineers currently working in the façade sector. First an outline map was developed by the research team after a series of interviews with industry members. This was then reviewed through an interview with a façade engineering team director whose comments and modifications were incorporated into the map. The final iteration consisted of a workshop to elicit knowledge from a team of façade engineers and produce the final map.

2.2 Design Influence Map An enlarged section of the whole map is shown in Figure 1. Each bubble in the map describes either a design influence or a project outcome. For example, the quality of the scheme review comments passed to the design team influences the quality of the design development undertaken by the design team. Figure 1: An expanded extract of the Façade Engineering Design Influence Map By using the DRM it was possible to identify which factors influence the overall construction cost, and the extent to which the final design conforms with the architect s and client s original design intent. Chief among these was the façade consultant s access to and understanding of manufacturing constraints and the impact of these constraints on the design at pre-tender design stages. As a result, this is the aspect of the façade engineer s design work that is addressed through the development of a BIM-based support tool described in the following section. 3. BIM-Based Façade Design Support Tool The tool has been developed to improve the façade consultant s understanding, at pre-tender design stages, of the impact of panel manufacturing constraints on a façade panelisation scheme. It provides the consultant with a heuristic analysis of the manufacturability of the proposed panelisation scheme using design data available from the project BIM database. The constraints on the panel geometry due to manufacturing processes are stored in a knowledge database, detail on capture and access to this heuristic knowledge will not be provided here for brevity. This section focuses on accessing the required design data and analysis of this data.

3.1 Implementation The tool has been implemented in two configurations. The first uses a proprietary BIM application, which is the main method of deployment of BIM technology in industry. The second uses open source BIM technology which is proposed as a solution to data translation or interoperability problems experienced by industry due to the range of proprietary BIM applications available. Currently, analyses have been implemented to evaluate three characteristics of panel manufacturability. Analysis of panel curvature is used to predict the ability of the manufacturers to bend the panel to the correct shape. For example, glass with low curvatures can be cold bent into shape, while, above certain curvatures this is not possible and the glass must be sag bent thereby increasing the cost of manufacture significantly. Through discussions with the research project industrial partner, a heuristic curvature measurement was selected. It uses the ratio of the distance from the corner of the panel to a plane defined by three other corners (H), to the distance from the corner to the corner diagonally opposite (L) (Figure 2). The heuristic curvature is the smallest value of H/L found by considering each corner in turn. Figure 2: Heuristic curvature measurement The second analysis implemented finds the value of the minimum corner angle in the plane of the panel. This is a good practice consideration as highly acute angles are easily damaged on site. The final analysis is that of the overall panel dimensions. This is a consideration for a variety of reasons, for example, glass requiring heat treatment in an oven is restricted in size by the dimensions of the oven. 3.1.1 Implementation using Proprietary BIM Application Since Digital Project (DP) is used by the research project industrial partner as their main BIM application, it was selected for this system configuration. The building information is stored within the application and is solely accessed through Digital Project. The heuristic geometric analysis is pre-scripted through the Digital Project Visual Basic Application (DP-VBA) scripting interface. The results of the analysis are stored in the main DP design database as an additional element attribute. For ease of deployment to industry, access to the support tool is through the addition of a toolbar available in the main application interface. The user must input the geometrical constraint against which the panels will be assessed.

Figure 3: Tool configuration using proprietary application A key factor in the scripting of the analysis was access to the required design data. The analyses require the coordinates of the vertices of the panels, but, this data is not necessarily made explicit in the model. For example a model imported from elsewhere may only make available a surface representing a panel and not the underlying data (the vertices) used to construct the surface. To extract the required data from the model, various elements of construction geometry have to be generated by the script, increasing the analysis time significantly. 3.1.2 Implementation using Open Source BIM Technology The second implementation of the system uses open source BIM technology. The building information is stored in IFC format. The IFC file is generated by any proprietary BIM application with IFC export capabilities and the façade panels are made recognisable by defining them as IFC- CurtainWall building elements. Figure 4: Tool configuration using open source BIM technology

A specially constructed C++ application performs the manufacturability analysis. The application uses the user interface of the TNO IFC Engine example project. The manufacturability algorithm and data extraction uses C++ methods available through the IFC Engine DLL, but has been programmed specifically for this project. The application extracts the required data the coordinates of the panel vertices from the IFC file. The required design data is accessible in the IFC file directly, i.e. the coordinate vertices are made explicit and are available through the IFC Engine DLL. The application places the result of the analysis of each panel back in the original IFC file as a bespoke attribute using IFC Property Set class. The application is executable as a stand-alone program. It requires the user to specify the file name of the IFC file containing the building information model and the IFC schema revision to use. The results can be visualised by importing the analysed IFC file into any BIM application with visualisation functions or attribute interrogation functions. For example, a colour by attribute function allows the user to colour the panels according to the results, highlighting those for which analysis results exceed a constraint. 3.2 Comparison of Implementation Methods The key difference between the two implementation methods is the accessibility of the required design information from this BIM database. Access to the underlying construction geometry is restricted in the proprietary application, but easily accessible through the IFC technology. This made a significant difference in the analysis times for the two system configurations, as discussed in the case study in the next section. 4. Case Study: Astana, Presidential Library The Presidential Library building in Astana, Kazakhstan is a geometrically complex building, based on a Möbius Strip. The project is from the portfolio of the research project industrial partner, who in the real world project provided advice to the design team and assisted in generating the panelisation scheme. In this case study the BIM-Base support tool described in the previous section is was used to evaluate the manufacturability of the façade and to assist the façade engineer in the iterative development of the panelisation scheme by proving fast feedback on different options Figure 5: Architect s representation of the Presidential Library Image produced by BIG Architects Both tool system configurations were tested on this project using the same personal computer with 4GB of RAM, operating a Windows 7 32-bit operating system. The tool was used to assess the extent to which the problem of highly acute panel corner angles occurred in the triangular panels. The building was particularly large, with over 40,000 panels. To run the analysis successfully using the proprietary application the model had to be segmented into 20 sections that where analysed individually and then recombined to visualise the results. This process took a full working day. Using the IFC- based system configuration, it was possible to perform the whole analysis in 20 minutes. However, the process was limited by the speed of exporting the IFC file from the proprietary application used to construct the building information model.

Figure 6: Visualisation of the result of the analysis The visualisation of the results clearly shows an area of the building where the smallest angle of the panel is less than that recommended by façade engineers (12.5 ) [11]. Since the model is constructed parametrically, the parameters can be adjusted and the model re-analysed to rapidly develop the design. In addition, the visualisation and BIM can be used to communicate this design issue to the rest of the design team. 5. Conclusions The Design Research Methodology has been used successfully, through consultation with industry, to identify areas of the design process to be addressed by the BIM-based support tool. The implementation of the tool using a proprietary BIM application, Digital Project, highlighted the difficulty in accessing non-explicit design information through the proprietary application s scripting interface. This increases the difficulty in performing non-pre-programmed design analyses and evaluations. The implementation using open source technology, the IFC file to store design information and the TNO IFC Engine Toolbox, produced a far more rapid analysis. This relied on a small amount of C++ programming which may not be frequently available to members of the construction industry. However, the IFC Engine toolboxes are very useful in this regard, reducing the required programming considerably. The IFC schema was found to be sufficiently defined for this project as the IFC Property Set Class allowed user defined attributes to be included. The tool has been successfully used to assess the panelisation scheme of a large and geometrically complex real-world project. 6. Further Work A key area for further work will be to automate the constraint selection by incorporating an additional module in the tool. The constraint selection will be based on building information input by designer describing the material and finish specification of the façade panel. In addition, the incorporation of an optimisation module into the tool will partly automate the design modification phases of design development, and may allow a greater design space to be explored. Finally, but outside the scope of the broader research project, the tool could be employed to perform analysis for design issues other than manufacturability and constructability, for example, sustainability.

7. Acknowledgements Thanks are due to the Façade Team at Ramboll for their input. We would also like to acknowledge Ramboll and EPSRC for funding this research project. References [1] C. Eastman, P. Teicholz, R. Sacks, and K. Liston, BIM Handbook. John Wiley & Sons, Inc. Hoboken, New Jersey, 2008. [2] BuildingSMART. [Online]. Available: www.buildingsmart.com. [Accessed: 2011]. [3] V. Karhu, Product Model Based Design of Precast Facades, ITcon, vol. 2, 1997. [4] R. Sacks, I. Kaner, C. M. Eastman, and Y.-S. Jeong, The Rosewood experiment Building information modeling and interoperability for architectural precast facades, Automation in Construction, vol. 19, no. 4, pp. 419-432, Jul. 2010. [5] P. Sanguinetti, C. Eastman, and G. Augenbroe, Courthouse Energy Evaluation: BIM and Simulation Model Interoperability in Concept Design, in Building Simulation, 2009, pp. 1922-1929. [6] J. Mitchell, J. Wong, and J. I. M. Plume, Design Collaboration Using IFC, in CAAD Futures, 2007, pp. 317-329. [7] T. Laine, R. Hänninen, and A. Karola, Benifits of BIM in the Thermal Performance Management, in Building Simulation, 2007, pp. 1455-1461. [8] P. Fazio, H. S. He, a Hammad, and M. Horvat, IFC-Based Framework for Evaluating Total Performance of Building Envelopes, Journal of Architectural Engineering, vol. 13, no. 1, p. 44, 2007. [9] TNO, IFC Engine. [Online]. Available: http://www.ifcbrowser.com/. [Accessed: 2011]. [10] L. T. M. Blessing and A. Chakrabarti, DRM, a Design Research Methodology, no. 30. Springer, 2009, pp. 28-31. [11] J. Wurm, Glass structures: design and construction of self-supporting skins. Springer, 2007.