PowrSym4. A Presentation by. Operation Simulation Associates, Inc. February, 2012

Similar documents
3. DATA INPUT PREPARATION...

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool

Latest Computational and Mathematical Tools for Transmission Expansion

RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES

Background: ERCOT studies in 80 s and 90 s using NARP (N Area Reliability Program): o Small model in which each node represented a major load center

FAST Tool and Exercise

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

CARIS Procedure Development and Simulation Model Evaluation

Simulatie van het EU-wijde elektriciteitsysteem. Modellering van de elektriciteitsmarkt en de hierin gebruikte elektriciteitsinfrastructuur

Optimizing the Generation Capacity Expansion. Cost in the German Electricity Market

Situational Awareness Workshop for Management of Wind and Solar Power

ENTSO-E scenarios- general overview. Daniel Huertas Hernando ENTSO-E System Planning Adviser

ENERGY PORTFOLIO MAN AGEMENT. Hydro and pump storage modelling in ABB Ability PROMOD Benchmark report

Dispatch Signal & Locational Marginal Pricing (LMP)

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

Reliability Analysis using PLEXOS

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process

Integrating High Levels of Variable Renewable Energy Sources

Methodology to Perform Long Term Assessments

APPENDIX I PLANNING RESERVE MARGIN STUDY

Dynamic reserve requirement in real time operation

Principles of Flowbased Market Coupling

A study for an optimization of a hybrid renewable energy system as a part of decentralized power supply

THERMAL ENERGY STORAGE AS AN ENABLING TECHNOLOGY FOR RENEWABLE ENERGY

MISO LOLE Modeling of Wind and Demand Response. Item-9b LOLE Best Practices Working Group July 26-27, 2012

A Dynamic Framework for Real time and Regulation Markets for Smart Grids

2010 Loss of Load Expectation Report PUBLISHED: 10/01/2010 LATEST REVISION: 10/08/2010

Reliability and the Future of the Electricity Grid: A North American Bulk Power System Perspective

Using PLEXOS to Validate TIMES

Eastern Wind Integration and Transmission Study

4 Calculation of Demand Curve Parameters

SOVN - NEW MARKET MODEL EXPERIENCE AND RESULTS

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY

Alberta Capacity Market

Effective Integration of Theory and Practice

Emerging issues relating to RE grid integration beyond F&S regulations

Locational Marginal Pricing (LMP): Basics of Nodal Price Calculation

Assessment of Marginal and Long-term Surplus Power in Orissa A Case Study

Can we achieve 100% renewables? Flexibility options in the electricity system

Valuing Distressed Generation Assets

TRANSITION OF THE DANISH POWER SYSTEM

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

APPENDIX 9.2 Description of SPLASH Model

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

Generation Technology Assessment & Production Cost Analysis

A Revised Resource Adequacy Standard for the Pacific Northwest. NERC LOLE Work Group November 7-8, 2011 Austin, TX

Optimal replacement strategy for residential solar panels using monte carlo simulations and nonlinear optimization methods

Integrated Assessment Tools for Network Investments in volatile Market Environments

Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008

Reduced Network Modeling of WECC as a Market Design Prototype

Grid Integration Studies for Identifying Flexibility Solutions

Mobilizing Grid Flexibility for Renewables Integration through Topology Control and Dynamic Thermal Ratings

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY. Prof. Michael W. Golay Nuclear Engineering Dept.

Impact of capacity value of renewable energy resources on RAPS system energy management

Available online at ScienceDirect. Energy Procedia 87 (2016 ) 45 52

Flexibility in the Swiss Electricity Markets. Jan Abrell Energieforschungsgespräche Disentis 2019,

Flexibility from the Demand Side

The Role of Energy Storage with Renewable Electricity Generation

Ancillary Services Matrix

What s That. Using AURORAxmp to Evaluate Transmission i Expansion. September 10, Electric Market Forecasting Conference Stevenson, WA

Overview of Renewables in the ERCOT System. Julia Matevosyan Lead Planning Engineer, Resource Adequacy

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Grid-Interactive Electric Thermal Storage (GETS) Space and Water Heating

The Evolution of the PJM Market in the United States: Looking Back to Look Forward

Intermittent Renewable Energy Sources and Wholesale Electricity Prices

Alberta Capacity Market

PJM Markets. Energy and Ancillary Services. PJM State & Member Training Dept. PJM /29/2014

Integration of Renewable Generation in ERCOT

The South African Grid Code

The Influence of Distributed Energy Resources on the Hourly Clearing Price of Electricity in a Restructured Market

Capacity reserves until 2025: declining, but sufficient

Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis

Solutions for Power Generation

2011 Probabilistic Assessment. 11JAN12 Interregional Coordination

ESD.934, Engineering, Economics and Regulation of the Electric Power Sector. Ignacio J. Pérez-Arriaga

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Innovative grid-impacting technologies for pan-european system analyses: key GridTech results on Demand Response application

Keeyask Generation Project. Public Involvement. Supporting Volume. Environmental Impact Statement

New Grid Controls to Enable Renewable Generation

2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Planning Criteria February 22/23, 2005

Applying Robust Optimization to MISO Look-ahead Unit Commitment

Integration of large-scale wind power and use of energy storage in the Netherlands electricity supply B.C. Ummels 1 E. Pelgrum 2 W.L.

Reliability Assessment of a Power Grid with Customer Operated Chp Systems Using Monte Carlo Simulation

Dispatch Signal & Locational Marginal Pricing (LMP)

4»IEEE POWER SYSTEMS .*ISK ASSESSMENT OF. Models, Methods, and Applications. Wiley. Ph.D., Fellow, IfE, CAE, EIC SECOND EDITION

Development of simultaneous energy and reserve dispatch model and corresponding pricing mechanism. Stefanos Delikaraoglou and Yi Ding

6.1.9 IFM Initial Conditions

Regional Impact of Renewables: ERCOT

Grid-Interactive Electric Thermal Storage (GETS) Space & Water Heating

Integration of renewable energy in China lessons learnt from Europe. Kaare Sandholt Chief expert China National Renewable Energy Centre

Overview of Congestion Revenue Rights In the New California Energy Market

BROCHURE. e7 PROMOD Generation and transmission modeling system with nodal and zonal price forecasting

PJM Fixed Transmission Rights (FTRs)

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

California Independent System Operator (CAISO) Challenges and Solutions

ENERGY PORTFOLIO MANAGEMENT. ABB Ability PROMOD Generation and transmission modeling system with nodal and zonal price forecasting

Transcription:

PowrSym4 A Presentation by Operation Simulation Associates, Inc. February, 2012 1

Presentation Contents History of PowrSym Introduction to OSA The PowrSym3 Model PowrSym4 Enhancements 2

PowrSym Background PowrSym1 developed for TVA in 1970 s Placed in public domain Foundation for PowrSym Plus (also called P+) PowrSym2 developed by OSA in 1980 s Foundation for PROSYM PowrSym3 developed by OSA mid 1990 s Enhancement has been on-going Addition of NTC multi-area flow logic Unique features for modeling wind power, cogeneration and energy storage PowrSym4 Nodal released in 2010 PTDF multi-area flow logic (Zonal or Nodal by Bus) Interface to transmission models Enhancements for multi-area adequacy studies using Monte Carlo uncertainty algorithm. 3

PowrSym General Overview Chronological Simulation Energy Storage Unit Commitment (Dynamic, Multi-state) Monte Carlo Uncertainty, Probabilistic Combined Heat & Power Blast Furnace & Steel Converter Gasses Multi-Area (LTC or PTDF) Zonal LMP (Locational Marginal Pricing) 4

PowrSym Overview Continued Wind & Solar Energy Maintenance Scheduling Fuel Contracts Load Flow Interface by TenneT & T.U. Delft Zonal & Nodal LMP with PTDF Flow Scheduling Computation time in range of seconds for detailed week simulation to a couple of hours for an annual simulation of a multi-region grid. 5

PowrSym3 - Features Input & Output are Keyword driven records Easy to manipulate by database or Excel Multiple Areas Simulation Chronological, by hours or minutes (time step user definable) Combination of heuristic & dynamic commit Equal incremental cost dispatch Combined heat and power optimization (not as constrained units) Hydro, Pumped Hydro, Wind Power Fuel Contracts and Limitations 6

Marginal Costs Hourly or minutes Market Depth Curve Incremental/Decremental As viewed by each area 7

Cost Model PowrSym3 is a least cost generation model Marginal costs are: Last unit dispatched Purchase power Unserved energy cost Dump power cost Vary by area Wheeling costs Transmission constraints 8

Maintenance Maintenance Scheduler Module: Internal model with as objective functions: Levelized LOLP Least Cost Allows combination of objective functions Allows External schedule Will schedule in mixed mode 9

Maintenance Evaluator (PME) Designed to evaluate maintenance options under uncertainty A Monte Carlo risk model works through a wide range of uncertainties producing a probabilistic evaluation of maintenance schedules and options Not just a single expected result but also a graphical depiction of the range of possible outcomes 10

Probabilistic Model Monte Carlo iterative model Unit outages and deratings Network outages or deratings Wind & Solar variance Hydro variance Load variance Average results Range of results across the draws 11

Sample Monte Carlo Analysis The following graph shows resulting production costs for a one week extension of an outage. The y axis is percent chance of falling in that bracket and the x axis is system production cost increase in $100,000 increments. 12

Monte Carlo Analysis 35 30 25 20 15 Series1 10 5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 13

Monte Carlo Analysis A simple computation would likely yield the $500,000 result, but the risk analysis yields an expected cost of $742,000 and some probability that costs could exceed $2 million. Similar graphs can be produced for changes in other outputs such as marginal costs, fuel consumption and emissions. 14

Reliability model Standard LOLP calculation Does not include wind/solar variation Does not include all unit operating constraints Does not include network constraints LOLE calculation Probability and depth Includes load, wind and solar variation Includes unit operating constraints Includes network constraints Results from Monte Carlo draws 15

Reserves Model Spinning, operating, standby, turndown System, Control Area, Area Units Standard, quickstart, nonfirm Min and Max contribution Ramping limits 16

Unit Commitment Heuristic, DP, or combination Minimum up/down times Start costs Multi-state stations Pumped and Conventional Hydro 17

Unit Dispatch Economic Observing Constraints Combined Heat and Power Units Multi-Area including transmission constraints Equal incremental cost 18

Multi Area The system may be divided into areas Areas may be grouped into control areas Adapted, robust spinning and operating reserve model (including turn-down reserves) 19

Multi Area Areas are connected by links with capacity, loses, and transmission charges parameters Link parameters may vary by direction of flow and by time of day. Transfer Capabilities (NTC & PTDF) 20

Multi Area 100 MW NOR 3550 MW 3350 MW SV 2150 MW 1850 MW FI 700 MW 1000 MW 720 MW 1700 MW 1300 MW DK-W 600 MW DK-E GB 1000 MW NL 1500 MW 600 MW 5650 MW NODE 5400 MW D 2300 MW 2000 MW B 2200 MW 3200 MW 2750 MW F MW MW AC Interconnection DC Interconnection Source: 21

Wind Power Wind is treated as a resource Hourly Generation derived from Wind Patterns (not Negative Load approach) No practical Limit on Number of Wind Farms Multiple wind regimes linked to multiple wind farms. Each wind farm has its own conversion equations. 22

Wind Power Uncertainty on Wind Power Generation (Monte Carlo) Different options for the curtailment (inflexible to flexible) Option to use wind power prediction models and wind prediction accuracy functions in the unit commitment Prediction on hourly basis (rolling horizon) 23

Wind Power Case Study The Netherlands 20 System Load, Generation (GWh/h) System load / Production [GWh/h] 16 16 12 8 4 4 0 Minimum Load Issue Solutions: - International Exchange and Markets - Flexible Base-Load Units - Demand-Side Management - Energy Storage 0 24 48 72 96 120 144 Hour of the week Unusable Wasted production Wind from wind power Usable Wind production Power from wind power Thermal Conventional production Generation and exchange + Exchange System System load Load Monday Tuesday Wednesday Thursday Friday Saturday Sunday Source: 24

Wind Power Case Study The Netherlands Impact of Wind Generation on HOB s production 30000 27500 25000 22500 Boiler production 20000 17500 15000 12500 10000 Base Case Perfect Pred Extra Boilers No Import 7500 5000 2500 0 0 1 2 3 4 5 6 7 8 Installed wind capacity Source: 25

Wind Power Case Study The Netherlands Measures to improve wind deployment (source: TenneT analyses) Base case (no measures) CAES storage (1.4 GW / 20 GWh) OPAC storage (1.4 GW / 20 GWh) PAC storage (1.9 GW / 20 GWh) Heat Boilers (1.8 GWth) Wasted wind 0 1 2 3 4 5 6 7 8 9 10 Installed wind power [GW] Source: 26

Cogeneration (CHP) Unique methodology and simulation technique Gives a direct lowest cost solution (not iterative) for serving the combination of electric and heat loads Heat areas with unique hourly heat loads, served by unique combinations of CHP units, heat-only boilers or heat storage units Heat networks with capacity limits and losses Two concomitant heat extractions possible (low and high temperature) 27

Emissions Dispatch Multiple Effluents SO 2 / NO X / CO 2 / OTHERS PowrSym3 reports the emission levels Operations may be influenced by prices attached to various effluents (option) 28

Fuel Contracts and Limitations Fuels may be input as a station parameter or fuels may be input as their own entity In the second case: Fuels may be shared by multiple stations A station may have access to multiple fuels Station capacities and efficiencies may vary by fuel selection Fuels may be blended Fuels may have varying transportation costs to the various stations 29

Fuel Contracts and Limitations Energy Limited Fuel Dispatch (ELF) Multiple fuel contracts with different prices, reliability and limits Quantity and prices may vary by hour Inventories, storage rate limits Each fuel delivery, inventory, or transportation constraint can be probabilistically derated Integrated with Monte-Carlo simulation 30

Fuel Contracts and Limitations Use of residual Blast Furnace Gas (BFG) and Oxygen Converter Gas (OCG) Low calorific value Fluctuating quantities Support firing of natural gas (NG) needed Automatic correction of unit efficiency and capacity, function of the amount of BFG burned Different prices for BFG, OCG and NG 31

Energy Storage Time related constraints are a major factor in the pump hydro dispatch: Turn-down limits on large thermal power plants may create low cost pumping opportunities even in high load periods Cogeneration and power exchange contracts may have time-of-day provisions not following always system load swings Availability of variable sources such as wind and solar. 32

Energy Storage Such constraints often cause pumped hydro operation to deviate from the intuitive schedule of pumping during lowest load hours and generating during highest load hours Solved by VALUE OF HOURLY ENERGY, not just load leveling (valley filling peak shaving technique) 33

Energy Storage Value of Energy Method: Places a cents/kwh value on the energy in storage, defined relative to pumping mode When marginal cost of other resources < the pumping energy value, the plant would be operated in pumping mode (subject to storage availability) 34

Energy Storage Value of Energy Method (contd.): Generating value is the pumping value divided by plant net efficiency + plant variable O&M cost When system marginal cost > generating value of energy, the plant is operated in generating mode 35

Energy Storage Value of Energy Method (contd.): A reservoir empty condition is not allowed during a period of high marginal cost. This requirement places a lower bound on the pumped hydro energy value An additional lower bound is defined by the requirement that sufficient pumping energy must be available to replace generation energy plus efficiency losses over the study horizon 36

Energy Storage Value of Energy Method (contd.): The value of energy which results in optimal pumped hydro scheduling can now be defined as the higher of these two lower bounds. The first bound will control for projects with small reservoirs and the second bound for larger reservoirs 37

Energy Storage and Adequacy For speeding-up the calculations for large Monte Carlo adequacy studies, a simplified, quick pumped hydro scheduler has been developed. 38

Energy Storage Low head pumped storage systems high variation of the available capacity 39

Energy Storage Low head pumped storage systems high variation of efficiency 40

Hydro Logic Hydro may be modeled by a loadleveling method, including the variation in wind/solar generation. Alternatively hydro (or a portion of the hydro) can be modeled by the value of energy method Forward of information (reservoir levels, spillage) from week to week 41

DP Algorithm Models for multi-mode combined cycle units (also CHP) in different states (GT, GT+ST, ST) and, of course, single-state units Three states plus off-line, may be extended to additional states Modeling of state transitions, up and down (transition times, transition cost) Uses DP logic to optimize state selection Important option because of increasing number of Combined Cycle units 42

Advantages of PowrSym3 Combination of LP, heuristics and DP makes the model very accurate, while maintaining a very high computational speed This delivers operation quality answers, the model being also in operation in dispatch centers 43

Advantages of PowrSym3 The accuracy, in combination with the high speed allow for adequate security analysis of very large systems, while considering chronological and correlation aspects within market simulation. 44

PowrSym4 Enhancements Combining market simulation with load flow calculations: Increased uncertainty of load flows due to increased liberalization and large-scale integration of RES (wind) Necessity to combine Unit Commitment & Economic Dispatch (UC-ED) with load flow simulations 45

PowrSym4 Enhancements Results from UC-ED, defined with PowrSym4, form input for load flow models (like PSS E or others) PowrSym4 accepts NTC or PTDF factors from the load flow models 46

PowrSym4 Enhancements Results from all daily load flows of a year give a good approximation of all possible combinations between load and generation throughout that year Technique applicable for use in combination with any load flow model 47

Power Transmission Distribution Factors (PTDFs) The PTDF is the fraction of the amount of a transaction from one node (or zone) to a defined central node that flows over a given transmission line. Dynamic PTDF factors are relative to a given flow balance. 48

PTDF Factors The PTDF array can be very large, in theory a value for every branch relative to each node. In practice many of the array values are near zero and only the significant values are required for input. 49

PTDF Flow Calculations Flows between specific nodes are computed by: Scheduling a flow from the sending node to the central node. Scheduling a negative flow from the central node to the receiving node. 50

PTDF Flow Optimization The PTDF flow logic is integral to the PowrSym commit and dispatch logic. Flows are scheduling so as to find the least cost result with minimal un-served energy. 51

Locational Marginal Price (LMP) Forecasting Using PTDF PowrSym4 produces hourly LMP output for each zone in zonal studies and each node in nodal studies. The LMP output can be expressed as a range in Monte Carlo analyses. 52

Current Development Projects Improved method for use of multiple processors in large Monte Carlo studies. A faster PTDF algorithm. Additional features related to natural gas storage reservoirs. FBA-MC (Flow Based Allocation Market Coupling): zonal PTDFs will be used for linking commercial transactions to the physical structure of the grid. 53

Current Development Projects Allocation of social benefits per region or stakeholder group: Social welfare (benefits costs) PowrSym calculates the benefits for the entire system (market surplus = reduction of production costs) Assuming that electricity is sold at marginal cost in each node allocation per region or stakeholder group 54