Microgrids in New England Technical Challenges & Opportunities

Similar documents
Community Clean Energy Resiliency Initiative PON-ENE BESS Request for Proposals Question and Answer Log

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems

Mapping Document for FAC-010-3

Critical Load Serving Capability by Microgrid using 100% Renewable Energy

Micro-Grid Technology To improve Distribution Reliability and accessibility. Dhananjay Ketkar. Sudesh Kr. Nehru. November 2012

Microgrid Controller Standardization Approach, Benefits and Implementation

Microgrids & Leveraging Campus Utility Infrastructure

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015

Renewable Energy Impact to Distribution Network Performance and Reliability. ENGR. ROBERTO D. ISIP JR. Head, Network Asset Planning, MERALCO

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

Standard TPL System Performance Following Extreme BES Events

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets

ABA Smartgrids Webinar June 16,

Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects. System Protection Subgroup

NERC PLANNING STANDARDS

Navigating Local Utility Requirements for Microgrids: Lessons from New York

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

CHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X

Grid Technology for Enhanced System Resilience

A Market Solution to the Duck Curve

Public Utility District Number 1 of Snohomish County

Public Utility District Number 1 of Snohomish County. Facility Connection Requirements February 9, 2018

Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS

Operation of ESS Interconnected to the Distribution Feeder by Distribution Management System

Standard MH-TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements

Technical Requirements for Distributed Generation Connection

MATL Requirements Facility Interconnection Requirements

ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007

Standard TPL System Performance Under Normal Conditions

Design and Simulation of Micro-Power System of Renewables

Scheduled Outages and Service Interruptions in Connecticut. Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015

Assessing the Role of Energy Efficiency in Microgrids

Integrating Renewables and Distributed Energy Resources into California s Electricity Markets

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

Microgrid Planning and Design MCAS Miramar, US Air Force Academy, and Fort Carson

RE: Evidence Submission (2/4) on Community Solar to AUC DCG Review (22534)

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No.

RELIABILITY PLAN for the SERC Southeastern Subregion Reliability Coordinator July 14, 2016

Energy Sector Transformation Dialogue

Standard Development Timeline

AEP Guidelines for Transmission Owner Identified Needs

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

Understanding Microgrid & Energy Storage Feasibility Studies

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION

Distributed Energy Resources Roadmap

Setting the Stage for Microgrid Discussions NGA Energy Resilience Retreat June 29, 2017

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

Information Document Protection System Information ID# R

Kenya: Some Facts. Services, Industry, Mining. electricity inadequate (35% of households). Target is universal access of electricity l

NSPI BULK POWER FACILITIES CONNECTION GUIDE Report number NSPI-TPR-002-2

Standard 600 Determine Facility Ratings, System Operating Limits, and Transfer Capabilities

Standard Development Timeline

Presentation to the U.S. Department of Energy by the IEEE Joint Task Force on QER

TTC/ATC 1.0 DEFINITIONS

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Impacts and Needs for Renewables in Distributed ib t Generation

Microgrids and Integration of Clean Energy

Seminar on African Electrical Interconnection. Module 7 - Market Operational Structures

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF Sheet No. 691 ORIGINAL VOLUME NO. III

An Oracle White Paper June Microgrids: An Oracle Approach

1 Descriptions of Software Demonstration of Intentional Islanding

DISTRIBUTED RENEWABLE ENERGY GENERATION POLICY

Planned Islanding and Energy Storage at BC Hydro

Union Power Cooperative

Consolidated Authoritative Document Glossary

Overview of the Sheffield-Highgate Export Interface (SHEI)

Small Generator Interconnection Procedures (SGIP) Customer Guide

Microgrid Summary/Best Practices

RTO Overview and Day 2 Markets. EAI Technical Conference May 26, 2011

Omaha Public Power District Facility Connection Guide

PRC-006, PRC-007, and PRC-009 Mapping to Proposed Continent-Wide Standard

Microgrids A Possible Future Energy Configuration?

Non-transmission Alternatives Process. The Vermont Experience. Hantz A. Présumé Principal Engineer System Planning

1 Descriptions of Function

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

List of training courses on electrical power system for Cambodia, Laos, Vietnam and Thailand (CLVT) countries

Proposed Resource Loss Protection Criteria

Investigation of 2006 Oahu Island-Wide Power Outage PUC Docket Number

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW)

Session of HOUSE BILL No By Committee on Energy, Utilities and Telecommunications 1-26

Operating Procedure PURPOSE... 1

Distributed Energy Resource Management System (DERMS)

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Joint Testimony of

Plant Load Factor: 50%

SRRTEP Meeting 2019 Annual Assumptions for Pepco

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Connection Study Requirements

TPL 001 AB 0 System Performance Under Normal Conditions

Benefits from Generation and Storage on the Distribution System

AGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM

New Brunswick Electricity Business Rules. Chapter 3 Reliable Operations

Standard FAC System Operating Limits Methodology for the Planning Horizon

Updated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations

NPCC 2009 New England Interim Review of Resource Adequacy. NPCC 2009 New England Annual Interim Review of Resource Adequacy

NALCOR ENERGY. Comments on Draft Request for Proposals for Clean Energy and Transmission

Patrick Administration Awards $18.4M to Communities for Energy Resiliency Projects

Transcription:

Microgrids in New England Technical Challenges & Opportunities October 10, 2012

Agenda I. What is a Microgrid? Examples Elements to Consider II. Why a Microgrid? Improved Reliability Utility Guiding Principals Role of the Utility III. Technical and Regulatory Considerations Microgrid Grant and Loan Program IV. Questions/Discussion 1

Agenda I. What is a Microgrid? Examples Elements to Consider II. Why a Microgrid? Improved Reliability Utility Guiding Principals Role of the Utility III. Technical and Regulatory Considerations Microgrid Grant and Loan Program IV. Questions/Discussion 2

3 What is a Microgrid? Definition of a Microgrid: Means a group of interconnected loads and distributed energy resources within clearly defined electrical boundaries that acts as a single controllable entity with respect to the grid and that connects and disconnects from such grid to enable it to operate in both gridconnected or Island Mode. (As defined in Public Act 12-148 7)

Typical Distribution System Typical Distribution Substation Typical Distribution Circuit(s) Approximately 8-15 Miles Long Serving approximately 1,000 5,000 customers Critical Load Customer Load 4

Typical Emergency Generation Typical Distribution Substation Typical Distribution Circuit(s) Approximately 8-15 Miles Long Serving approximately 1,000 5,000 customers Critical Load Customer Load Generator 5

Typical Overhead Infrastructure Microgrid Typical Distribution Substation Typical Distribution Circuit(s) Approximately 8-15 Miles Long Serving approximately 1,000 5,000 customers C Critical Load C C Customer Load Generator Breaker Closed REMARKS: 1. Generators operational during normal and emergency conditions. 2. Overhead infrastructure that allows export of power to grid. 3. Drawing does not include required communication control layer and microgrid management system. 6

Typical Underground Infrastructure Microgrid Typical Distribution Substation SW SW Typical Distribution Circuit(s) Approximately 8-15 Miles Long Serving approximately 1,000 5,000 customers C Critical Load C SW C SW Customer Load Generator Breaker Closed Switch REMARKS: 1. Generators operational during normal and emergency conditions. 2. Underground infrastructure that allows export of power to grid. 3. Each critical load connected to a switch. 4. Drawing does not include required communication control layer and microgrid management system. 7

Example of Critical Load Locations 8 Electric Distribution Company Distribution System Representative locations of critical facilities Colored lines represent actual circuits with approximately 8 MVA of load.

9 Elements to Consider Managing a Microgrid is like managing a very small vertically integrated electric utility without a transmission component but with generation and distribution components System configuration must be known at all times and be factored into normal grid switching and operating protocols by both the distribution company and the company operating Microgrid interconnection Characteristics: Has Distributed Resources and load Ability to disconnect and parallel with distribution system Intentional and planned islanding

Technical and Operational Considerations Technical: Proper control of voltage/frequency /power quality Protection schemes and modifications Changes in power-flow magnitude and direction Steady state and transient conditions Reserve margins, load shedding, demand response, and cold load pickup Operational: Safety Lockout/tag-out Protection coordination Load to generation matching Load (phase) imbalance Microgrid communications, monitoring and dispatch (mini EDC) Ongoing maintenance 10 Technical

Economic Considerations balancing cost and reliability Cost Reliability Key Considerations: Geographic dispersion of critical loads Initial cost to install required facilities Life of installed system may vary and is important Monitoring and control of installed system Maintenance and troubleshooting of installed system Generation must be capable of continuous operation (weeks) Non-Microgrid and Microgrid customer impacts 11

Agenda I. What is a Microgrid? Examples Elements to Consider II. Why a Microgrid? Improved Reliability Utility Guiding Principals Role of the Utility III. Technical and Regulatory Considerations Microgrid Grant and Loan Program IV. Questions/Discussion 12

Improved reliability To achieve high reliability during an extreme weather event; the following must be taken into account in addition to the technical and operational considerations discussed previously: Facilities serving the Microgrid are most reliable if constructed underground Provide adequate and reliable generation Access to an uninterruptable fuel source for the generator Generator must poses black start capability Generator must be able to follow load 13

Utility s Guiding Principles Ensure the safety of customers and utility employees at all times Maintain distribution system grid reliability Microgrids are viewed as a potential grid resiliency tool Microgrids must increase reliability for its customers Non Microgrid customers will not be adversely impacted Microgrid costs allocated in a balanced approach Operationally sound Capable of intentional islanding on demand and automatically Capable of return to normal grid supply without adversely impacting customers 14

Role of the Utility Perform feasibility evaluation under the DEEP Phase 1 RFP for submitted projects Accept Microgrid projects Interconnection Application Review projects in accordance with the Generator Interconnection Fast Track and Study Process ( Guidelines ) Execute a standard Operating Agreement between Microgrid owner and utility that will define the roles and responsibilities for the installation, operation and maintenance of the Microgrid during normal and abnormal system conditions. Protection coordination with grid distribution system infrastructure Participation in development of Microgrid standards and guidelines 15

Agenda I. What is a Microgrid? Examples Elements to Consider II. Why a Microgrid? Improved Reliability Utility Guiding Principals Role of the Utility III. Technical and Regulatory Considerations Microgrid Grant and Loan Program IV. Questions/Discussion 16

Microgrid Grant and Loan Pilot Program The CT Microgrid Program developed by Department of Energy and Environmental Protection (DEEP) Envisions Three Types of Microgrid Projects: Repurpose Existing Distributed Generation Reconfigure Existing Distributed Generation New Generation Total Amount of Grants and Loans Awarded Not to Exceed $15 million Grants and Loans Awarded to Selected Projects to Assist With: Cost of Design Engineering Services Interconnection Infrastructure

Technical and Regulatory Considerations Will a Project Conflict with Existing Utility Franchise Rights or be Regulated as a Utility? In general, to address franchise concerns, unless the Microgrid is located entirely on private property, the incumbent electric utility would own the wires utilized by the developer.

Technical and Regulatory Considerations How Will a Microgrid Project be Interconnected? Directly to the Grid? What Voltage? Each project will be evaluated individually. However, developers should follow the existing interconnection procedures Guidelines for Generator Interconnection Fast Track and Study Processes dated May 12, 2010. The size and/or voltage of a project will dictate whether the participation and involvement of ISO-NE is required.

Technical and Regulatory Considerations Will the Microgrid Power Be Fed into the Grid or Serve its Own Customers Directly? The individual project design will dictate where power flows. When connected in parallel with the electric distribution system, behind customer s meter, the Microgrid can serve its customer loads, and also potentially export any excess energy produced through existing net metering provisions. When the Microgrid separates from the electric distribution system, the Microgrid would only serve the customer loads for which it has been designed.

Technical and Regulatory Considerations Will the Developer Be Charged Separately for Using the Utility Distribution System? Yes. The charges will be determined by the applicable tariff.

Technical and Regulatory Considerations Will an Operational Agreement be Required? Yes. Currently, however, no standard agreement is yet available.

Technical and Regulatory Considerations What Operational Obligations Will Be Required? The generation source will need to respond quickly and run continuously for an extended period of time with the ability to balance load and generation. No specific operational obligations have yet been developed.

Technical and Regulatory Considerations How Will the Load be Metered? The specific metering configuration will be determined on an individual project basis. In general, submetering is permitted in Connecticut only in limited circumstances. In any event, the Developer will be responsible for ensuring the load is supplied.

Technical and Regulatory Considerations Who Will Own the Power Delivered into the Grid? When and how title to the power is transferred has not yet been developed. How this is determined may impact the final design configuration of individual projects.

Technical and Regulatory Considerations How Will the Developer be Paid for the Power Supplied? The payment mechanism is still unclear at this stage. Options include market pricing, as well as bi-lateral agreements.

Technical and Regulatory Considerations Who Pays the Developer for the Power? The answer to this question will depend on both the individual Microgrid design, as well as when title to the power transfers and to whom.

Questions/Discussion Jim Mader, Senior Project Manager; UI jim.mader@uinet.com Einat Dorobantzu, Manager Technology Integration; &P einat.dorobantzu@nu.com Jim King, Partner; Couch White, LLP jking@couchwhite.com