New regulation for biomass and biogas power projects in Indonesia

Similar documents
Indonesia update: Tariff framework for renewable energy

REPORT FEBRUARY 2017 VOL PRATT S ENERGY LAW

Insights and Commentary from Dentons

PLN appointing renewable energy developers for direct selection panel. January 2018 Joseph Kim, Sean Conaty and Robin Musch

INDONESIA S NEW DEVELOPMENT IN POWER AND RENEWABLE ENERGY SECTORS by Hapsari Arumdati

SOLAR PV IN INDONESIA TAKING ADVANTAGE OF THE NEW LANDSCAPE

Regulation and Development of New and Renewable Energy in Indonesia

EMR for People s Welfare

SOLAR PV PROMOTION PROGRAM IN INDONESIA

SECTOR OVERVIEW. Government of Indonesia, State Electricity Corporation (PLN). Electricity Power Supply Business Plan (RUPTL ). Jakarta.

TABLE OF CONTENTS ABBREVIATIONS PREAMBLE NATIONAL ENERGY REGULATORY FRAMEWORK FINANCIAL INCENTIVES REGULATORY FRAMEWORK MINI HYDRO POWER GEOTHERMAL

Risk Identification and Mitigation for Small Scale Renewable Energy Power Projects in Indonesia

NERSA Consultation Paper

POLICY ON SOLAR AND BIOENERGY DEVELOPMENT IN INDONESIA

(4 November 2016 to date) ELECTRICITY REGULATION ACT 4 OF 2006

TECHNICAL ASSISTANCE RELATED TO THE SUSTAINABLE AND INCLUSIVE ENERGY PROGRAM, SUBPROGRAM 2

FEED-IN TARIFF FOR INDONESIA S GEOTHERMAL DEVELOPMENT

Indonesia's Energy Transit: Struggle to Realize Renewable Potential

ASSESSING AND ENHANCING CAPACITY FOR GBEP SUSTAINABILITY INDICATOR EVALUATION IN INDONESIA

Terms of reference INDIVIDUAL CONSULTANT PROCUREMENT NOTICE

ZAMBIA REFIT POLICY 2015 GENERAL OVERVIEW

Hybrid Power Generation Project Using Biogas and Solar Power Implementing Entity: Next Energy & Resources Co., Ltd.

SECTOR ASSESSMENT (SUMMARY): ENERGY

The Role of Renewable Resources: A Hybrid System of Wind and Solar Energy 1)

PREPARING A NEW ERA OF THE MINING LICENSE a brief legal update on the implementation of the tender system

RENEWABLE ENERGY AS A NATIONAL DEVELOPMENT PRIORITY

BUSINESS INFRASTRUCTURE ON RENEWABLE ENERGY POWER PLANT. Indonesia Clean Energy Development (ICED) Project. Bill Meade 13 March 2013

Table Geothermal Potential in Indonesia, as of April 2016

HYBRID SUSTAINABLE ENERGY SUSTAINABLE ENERGY HYDROPOWER ELECTRICITY DISTRIBUTION GREEN FINANCING BIOMASS CLIMATE INVESTMENT MINI-GRID

COORDINATING MINISTRY FOR ECONOMIC AFFAIRS REPUBLIC OF INDONESIA REGULATION STRATEGY TO IMPROVE DEVELOPMENT OF RENEWABLE ENERGY IN INDONESIA

TONGA POWER LIMITED REQUEST FOR PROPOSALS INDEPENDENT POWER PRODUCERS. for SOLAR PHOTOVOLTAIC GENERATION 5 APRIL, 2018 RFP - TPL SOLAR IPP

W I N D A N D S O L A R R F Q / R F P P R O C E S S

Guideline for Claims of Made with Renewable Energy or Reduced Carbon Footprint Based on Power Purchase Agreement

A MEANDERING PATH ENERGY

Bauxite Mining and Alumina Refinery Investment Environment in Indonesia

Grid connected Renewable Generators and Net-metering Amendment Policy

SECTOR ASSESSMENT (SUMMARY): ENERGY. 1. Sector Performance, Problems and Opportunities

CUC s Response to Alternative Energy

Promoting Geothermal Energy Utilization in Indonesia Challenges and Opportunities

LAW OF MONGOLIA ON ENERGY. February 1, 2001 Ulaanbaatar city. ( Turiin medeelel #6, 2001) CHAPTER ONE GENERAL PROVISIONS

Support for Competitive Procurement of Renewables in Mongolia

1. INTRODUCTION. Name of Feed-in Approval Holder (FiAH) : Future Atlas Sdn Bhd (FASB)

INDONESIAN PARTICIPANTS REVIEW CALIFORNIA S RENEWABLE ENERGY PLANS

Opportunities and challenges of the Indonesian electrification drive. March 2015

Renewables in Vietnam OPPORTUNITIES FOR INVESTMENT

Wind Energy Legal Framework in Hungary. Dr. Zsófia Szerda GO EAST Seminar, Berlin, 9 December 2010

Auctions preparation, course, wins. Katarzyna Szwed Lipińska, counsellor at law Director, Department of Support Systems Energy Regulatory Office

Institute for Global Environmental Strategies, Kawasaki City Government

MONGOLIA COUNTRY PROFILE 88

MINISTER OF TRADE REPUBLIC OF INDONESIA REGULATION OF THE MINISTER OF TRADE OF THE REPUBLIC OF INDONESIA NUMBER: 97/M-DAG/12/2014 CONCERNING

Renewable energy: Investing in Africa

External Announcement

GoI s Policy on Renewable Energy Development

Client Alert. Finance & Projects Jakarta. New Geothermal Law Finally Issued

LAW OF MONGOLIA ON ENERGY CHAPTER ONE GENERAL PROVISIONS. Article 1. The Purpose of the Law

Renewable Auction Mechanism (RAM): New Procurement Tool for Distributed Renewable Generation National Summit on RPS

SMART, EFFICIENT AND SUSTAINABLE ENERGY SOLUTIONS IN INDONESIA KEY OPPORTUNITIES FOR SWEDISH COMPANIES AND TECHNOLOGIES JUNE 2017

Independent Power Producer procurement Improving integration with municipal distributors

THE GOLD STANDARD PROGRAMME OF ACTIVITIES GUIDANCE DOCUMENT

Mining Investment in Indonesia

Fiscal Support for the Efficient and Sustainable Management of Natural Resources in Indonesia: Renewable Energy and Forestry Resources

By: Dr. Dadan Kusdiana Director for Bioenergy

Outline of the Revised Renewable Energy Act

Long Island Power Authority Seventh Revised Leaf No. 16

REGULATION OF THE FINANCIAL SERVICES AUTHORITY NUMBER 35/POJK.04/2014 CONCERNING CORPORATE SECRETARY OF ISSUERS OR PUBLIC COMPANIES

NEW AND RENEWABLE ENERGY POLICY

Renewable Energy & Energy Efficiency in Egypt

Egyptian Renewable Energy plan

The Renewable Energy Term Market in Argentina: Resolution No. 281-E/2017

Stakeholder Comments Template. Subject: Small and Large Generator Interconnection Procedures Draft Final Proposal and Meeting

Labelling provision in Directive 2003/54/EC

Renewable Energy. Development Plan. Presented in Japan-Indonesia Business Forum for Energy Efficiency, Conservation and Renewable Energy

INDONESIAN NUCLEAR POWER PROGRAM

Independence Freedom Happiness No: 11 /2017/QD-TTg Ha Noi, 11 th April 2017 DECISION. On the

Streamlining and simplification of the administrative procedures for renewable energy projects

LAW ON PUBLIC ENTERPRISES Official Gazette of the Republic of Macedonia no. 38/96; 9/97

Presentation of. Clean Energy Asia 2013: Renewable Energy Policies in Indonesia A Report Card. Mini hydro power plants

Off-grid opportunities and sustainability in Indonesia: Sumba Iconic Island: 100% renewable energy by 2025

Current situation and expected development of renewable energy sources

INDONESIA POWER MARKET OUTLOOK TO 2030, UPDATE 2014 MARKET TRENDS, REGULATIONS AND COMPETITIVE LANDSCAPE

CHAPTER AUXILIARY SERVICES. Prequalification of Contractors for Educational Facilities Construction 8.272

Small scale Hydro Electric Power IPP compliance with legislation and REBID process

Grid-connected Biomass & Biogas Power Investment in Indonesia:

Rules on Initiation of Power Procurement and Review of Power Purchase Agreements. Eng. Anastas Mbawala, EWURA

A Roadmap for Photovoltaic Auctions in Israel Targets and vision Honi Kabalo - Head of Renewable Energy, Electricity Regulatory Authority

ACEF Deep Dive Workshop. 5 8 July 2017 Manila, Philippines

CLEAN ENERGY HANDBOOK FOR FINANCIAL SERVICE INSTITUTIONS

Incentives to Increase Renewable Energy. Linda M. Wagner Senior Legal and Policy Advisor Illinois Commerce Commission

REGULATION OF THE MINISTER OF ENERGY AND MINERAL RESOURCES NUMBER 19 OF 2009 ON NATURAL GAS BY PIPELINE BUSINESS ACTIVITIES

CLEAN ENERGY CENTER OF EXCELLENCE

Bank Indonesia issues new e-money regulation

Overview of the South Africa s Independent Power Producers Procurement Programme

Strategic Analysis of the Global Status of Carbon Capture and Storage

Greening the electric power generating system: application of optimization model and sectoral approach in Indonesia

ATTACHMENT N. Small Generator. Interconnection Procedures and Agreement. (For Generating Facilities No Larger Than 20 MW)

Section 3 TERMS OF REFERENCE (TOR)

Renewable Energy in Egypt Ehab Ismail Amin New and Renewable Energy Authority

Developing Potential JCM Model Projects

ADVISORY. Indonesia s New Construction Law. Overview. Main Provisions. 26 January 2017

Indonesia s Geothermal Development: Where is it Going?

Transcription:

New regulation for biomass and biogas power projects in Indonesia (MEMR Regulation 21 of 2016) Speed read Shortly after the issuance of a new regulation for the development of solar power projects in Indonesia, the Government of Indonesia is now introducing a new regulation on the purchase of electricity by PLN from biomass and biogas power projects (Minister of Energy and Mineral Resources Regulation No. 21 of 2016 Reg 21/2016). These are the key features of the new regulation: Biomass and biogas power projects are to be awarded on the basis of a direct appointment process; Feed-in tariffs (FITs) available both for conventional IPP projects and projects which involve the sale of excess electricity to PLN; No more restriction on the capacity of biomass and biogas power projects that can be developed and benefit from the FITs; A standard power purchase agreement (PPA) to be issued by PLN and which will need to be signed within 30 days from award of the relevant project by MEMR. Reg 21/2016 has been in force since 4 August 2016 but PLN has yet to issue the model PPA to be used for biomass and biogas projects. Clearly, this new regime is another effort to boost the development of electricity generation in order to achieve the ambitious objectives set by the Government of Indonesia which include the 35GW programme and specific targets to increase the share of renewables in the energy mix.

Reg 21/2016, which revokes the previous MEMR Regulation No. 27 of 2014 (Reg 27/2014) on the same matter, introduces improved Feed-in-Tariffs (FITs) which are now denominated in US Dollar as well as simplified requirements applicable to independent power producers (IPPs) wishing to sell all or part of the output of biomass of biogas power projects to PLN. We set out below the key features of the new regulation including the process to apply for and develop biogas and biomass projects. In addition, you can find a detailed chart setting out the process for the award and development of biomass and biogas projects as well as the new applicable FITs and differences with Reg 27/2014 in separate schedules by clicking on this link. 1. Procedure for the purchase by PLN of electricity from biomass and biogas power plants Reg 21/2016 contemplates a system by which biomass and biogas IPP projects are awarded to interested developers on the basis of a direct appointment and through a two-step process consisting of (i) a candidacy phase where an interested party submits an application to become a selected developer (Developer) and (ii) a development phase which goes from the signing of a PPA with PLN to the commercial operation date (COD) of the relevant project. Please refer to the timeline appended in Schedule 1 for an overview of the process. 1.1 Candidacy phase The candidacy phase includes (a) the submission to the Directorate General of Renewable Energy and Conservation of Energy at MEMR (Direktorat Jenderal Energi Baru Terbarukan dan Konservasi Energi or EBTKE) of an application to become a Developer, (b) the verification of applications by EBTKE, and (c) the appointment as a Developer by the MEMR. (a) Application to become a Developer: The application has to be in accordance with the template included in schedule III to Reg 21/2016 and needs to contain the following documents: (i) Profile of the applicant; (ii) Feasibility study which has been verified by PLN (within 30 working days from submission by the applicant) and which has to contain among others: (A) An estimate of the total investment required for the development of the project; (B) The construction schedule up to COD; and (C) The interconnection study to PLN s network; (iii) A statement on the prioritisation of the use of local goods and/or services together with supporting data in accordance with Minister of Industry Regulation No. 54 of 2012 which sets out the applicable minimum levels of goods and services which have to be sourced locally for the development of power projects; and (iv) Evidence of financial capability. (b) Verification of applications by EBTKE: EBTKE will then verify and assess the application 1 and report its findings and conclusions to the MEMR within 7 working days from the complete submission of the application. (c) Appointment of Developers: Where EBTKE approves an application, the MEMR will then issue to the applicant its appointment as Developer (MEMR Approval Decree) within 7 working days from receiving the recommendation from EBTKE. (d) Only Indonesian entities may become a Developer Reg 21/2016 provides that to become a Developer, Applicants need to be Indonesian incorporated entities that engage in the supply of electricity as (one of) their business activity(/ies). Such legal entities may be in the form of a foreign investment company (PT PMA), provided that the following foreign ownership restrictions applicable under Government Regulation No. 44/2016 on the List of Business Fields Which Are Closed and Conditionally Open to Investment (Negative List) are complied with: For projects with a capacity of more than 10MW: the maximum foreign ownership is 95%; For projects with a capacity of 10MW or less: the maximum foreign ownership is 49%. 1 According to Art. 7 para. (2) and (3) of Reg 21/2016, the evaluation will be carried out by an evaluation team consisting of a representative from the EBTKE, the Directorate General of Electricity, the Secretariat General of Energy and Mineral Resources as well as other relevant institutions, who will carry out an administrative, technical, and financial evaluation of the application.

1.2 Development phase Reg 21/2016 further sets out the following steps that need to be undertaken after the appointment as a Developer: (a) PPA signing, (b) financial close, (c) obtention of IUPTL, (d) report on construction progress and (e) commercial operation date (COD). (a) PPA signing: Reg 21/2016 provides that a power purchase agreement (PPA) must be signed with PLN within one month from the appointment as a Developer. The PPA shall have a term of 20 years from COD and can be extended. Should the signing of the PPA be delayed for any reason, EBTKE will engage with PLN and the Developer to facilitate the signing of the PPA. A copy of the signed PPA must be submitted to EBTKE. Reg 21/2016 provides that a model PPA will be provided by PLN to EBTKE within 30 working days from its issuance (i.e. by 15 September 2016). (b) Financial Close: A Developer must achieve financial close for a given project within 12 months from the execution of the relevant PPA and provide to EBTKE the proof of financial close having occurred. If financial close is not achieved within this timeframe, the appointment as Developer will be revoked. (c) IUPTL: After the above steps have been completed, the Developer has to apply to obtain an Electricity Supply Business License (Izin Usaha Penyediaan Tenaga Listrik or IUPTL), which should, in principle, be issued within three working days as of the complete submission of the required documents 2. The Developer must then submit a copy of the IUPTL to EBTKE and PLN within three working days from issuance. (d) Report on Construction Progress: The Developer must submit a report to EBTKE on the construction progress of the project every 6 months from the date of the MEMR Approval Decree up to COD. (e) COD: COD must take place within 36 months from the execution of the PPA. If COD is not achieved within this timeframe, PLN will reduce the applicable FIT progressively and up to 8% depending on the duration of the delay, and if such delay is in excess of 12 months, the appointment as Developer will be revoked. Further, should such revocation occur, the relevant Developer will be prohibited from applying to become a Developer for a period of two years from the revocation date. 2. Feed-in tariffs and project capacity The FITs set out in Reg 21/2016: Include the interconnection costs (i.e. the transmission line from the power plant to PLN s network); Cannot be negotiated nor escalated and are as stated in the PPA; Will be paid in Rupiah using the Jakarta Interbank Spot Dollar Rate (JISDOR) agreed in the PPA as a reference; Involve a certain multiplying factor ( F factor ) depending on the location of the project (for example, if a biomass or biogas project is to be developed in Riau, the applicable FIT will be 1.6 times that applicable for projects in Java). Please refer to Schedule 2 and Schedule 3 for an overview of the FITs respectively for biomass and biogas projects. We understand that the proposed FITs for both biomass and biogas projects are in the upper range of FITs applicable to similar projects across the region and, when applying the multiplying factor, the FITs applicable to projects developed in Indonesia s outlying islands appear to be fairly attractive. Further, it is worth noting that the capacity of biomass and biogas projects is no longer limited as it used to be under Reg 27/2014, but instead, the FIT regime is now split between projects with a (i) capacity of up to 20 MW (which are split further into low voltage and medium-tohigh-voltage projects); (ii) capacity ranging from 20 MW to 50 MW; and (iii) capacity above 50 MW with the FIT applicable to smaller projects being up to 50% higher (without the multiplying factor) than that applicable to large scale projects. For example, the FIT for a low voltage biomass power project of less than 20MW to be developed in Java has a FIT of USD 16,00 cent/kwh whereas a high voltage biomass power project of more than 50MW on the same island will have a FIT of USD 10,80 cent/kwh. 2 Presidential Regulation No. 4/2016 on Acceleration of Power Infrastructure Development, Article 19(3).

3. Excess power Reg 21/2016 also regulates the purchase by PLN of excess electricity from biomass and biogas power plants including applicable FITs (please refer to Schedule 4 and Schedule 5 for an overview of the applicable FITs). The only difference with the FITs applicable to traditional IPPs where the entire output of the plant is sold to PLN is that there is no multiplying factor applicable to the FITs for the purchase of excess electricity. Reg 21/2016 also specifically provides that PLN can negotiate a lower tariff than the applicable FIT for the purchase of excess power if PLN and the relevant developer agree on such lower tariff. In such case, PLN will report the agreed tariff to EBTKE and no further approval is required from the MEMR. The term of excess power PPAs will be determined based on an agreement between PLN and the relevant developer which holds an operating licence for the power plant which will sell excess power to PLN. Typically, PPAs for excess power have a substantially shorter term than that of PPAs applicable to traditional IPPs. 4. Implementation and transitional provisions 4.1 Implementation Reg 21/2016 has entered into force since its issuance on 4 August 2016 and does not require further implementation measures. 4.2 Transitional provisions The transitional provisions of Reg 21/2016 provide that: For Developers that have obtained an IUPTL, signed a PPA and started operations, the tariff under the PPA can be adjusted to become 85% of the relevant applicable FIT under Reg 21/2016. For Developers that have obtained an IUPTL but have not yet signed a PPA nor started operations, the tariff will be in accordance with the relevant applicable FIT under Reg 21/2016. In each case, the adjusted tariff will be reflected in the PPA without possibility of negotiation or escalation and is non-retroactive. Such adjustments do not require an approval from the MEMR and will be valid up to the end of the term of the PPA. 5. Closing remarks Reg 21/2016 marks another step in the right direction to provide a comprehensive framework for the development of renewable energy projects in Indonesia (including appropriate FITs) to accelerate the development of such projects and attempt to meet the ambitious objective which has been set by the Government to increase the share of renewables in the energy mix from about 10% currently to 23% by 2025. PLN will have an important role to play in the implementation of Reg 21/2016 and, eventually, in the shaping and ultimate success of the new regime given that the project award process which is contemplated by Reg 21/2016 is based on direct appointment and that PLN will have to review and, in practice, sign off on the feasibility study of any project which constitutes the key part of the application to become a Developer. Further, the terms of the model PPA to be issued by PLN will also very much determine whether the new framework, including the level of the various FITs, is bankable and can constitute a suitable platform for the development of a wider stream of biomass and biogas projects in Indonesia. From our discussion with officials from EBTKE, we understand that Reg 21/2016 will gradually be socialised until the end of the year but interested developers may approach EBTKE at any time to solicit projects based on the process and regime enacted by the new regulation. For Developers that have obtained an IUPTL, signed a PPA, but have not yet started operations, the tariff under the PPA can be adjusted to become the relevant applicable FIT under Reg 21/2016.

Contact information Frederic Draps Foreign Legal Consultant Tel +62 21 2995 1710 frederic.draps@allenovery.com Daniel Ginting Partner Tel +62 21 2995 1701 daniel.ginting@ allenovery.com Michael Tardif Foreign Legal Consultant Tel +62 21 2995 1702 michael.tardif@allenovery.com Allen & Overy means Allen & Overy LLP and/or its affiliated undertakings. The term partner is used to refer to a member of Allen & Overy LLP or an employee or consultant with equivalent standing and qualifications or an individual with equivalent status in one of Allen & Overy LLP s affiliated undertakings. CA160931