EPCOR Distribution & Transmission Inc.

Similar documents
ENMAX Power Corporation

Alberta Electric System Operator Needs Identification Document Application

Canadian Natural Resources Limited

NOVA Chemicals Corporation

Alberta Electric System Operator Yeo 2015S Substation Needs Identification Document

Decision D ATCO Electric Ltd. Swan Hills F.P.L. 744S Substation Decommission and Salvage. November 8, 2018

Pembina NGL Corporation

Harvest Operations Corp.

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013

Aquatera Utilities Inc.

Decision MEG Energy Corp. Amend Christina Lake Industrial System Designation. December 15, 2011

Seven Generations Energy Ltd.

Suncor Energy Inc. Errata to Decision Firebag Substations and Power Plant Expansion and Industrial System Designation Amendment

NaturEner Wild Rose 1 Energy Inc.

SunEEarth Alberta Solar Development Inc.

Signalta Resources Limited

C&B Alberta Solar Development ULC

Pteragen Canada Inc.

Decision Cenovus FCCL Ltd.

TransAlta Corporation

C&B Alberta Solar Development ULC

The City of Red Deer

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018

Grande Prairie Generation, Inc.

Nexen Inc. OPTI Canada Inc.

Decision B. St. Pierre kW Photovoltaic Micro-Generation System. May 15, 2013

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

C&B Alberta Solar Development ULC

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Alberta Power (2000) Ltd.

Nexen Inc. and CNOOC Canada Inc.

Solar Krafte Utilities Inc.

Greengate Power Corporation

Grizzly Oil Sands ULC

AltaGas Utilities Inc.

Burdett Solar GP Corp.

Oldman 2 Wind Farm Limited

Pengrowth Energy Corporation

Connacher Oil and Gas Limited

AltaGas Utilities Inc.

Ellerslie Substation Expansion

C&B Alberta Solar Development ULC

ATCO Electric Ltd. ATCO Gas (a division of ATCO Gas and Pipelines Ltd.) ENMAX Power Corp. EPCOR Distribution and Transmission Inc. FortisAlberta Inc.

Renewable Energy Services Ltd.

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017

EDF EN Canada Development Inc.

Substation Developments Environmental Guidelines Checklist for Applicants

Decision Syncrude Canada Ltd. Mildred Lake Power Plant. July 17, 2014

E.L. Smith Solar Farm Project Open House. Lower Level

HYDRO AND ELECTRIC ENERGY REGULATION

E.L. SMITH SOLAR FARM PROJECT UPDATE

Alberta Electric System Operator AltaLink Management Ltd. Alberta-Pacific Forest Industries Inc.

SUNDANCE 7 January 2014

SemCAMS Area Project Description

Oldman 2 Wind Farm Limited

Alberta Electric System Operator

Decision D Alberta Ltd. (BluEarth) Bull Creek Wind Power Project Noise Complaints

May 8, 2017 EASB File #: Transaction #:

ALBERTA ENVIRONMENT ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT APPLICATIONS NO AND ENVIRONMENTAL IMPACT ASSESSMENT

THE PROJECT. What is happening? Why is this facility needed? Why did you choose this location?

May 1, To: Parties currently registered on Proceeding Distributed Generation Review Proceeding Application A001

Up to 9.5MW AC solar project located near Burdett, Alberta

October 30, 2012 Our File:

EAST-WEST TIE TRANSMISSION PROJECT

SEATON MUNICIPAL TRANSFORMER STATION. Welcome to our Public Information Centre

Alberta Electric System Operator

Decision FortisAlberta Inc. Micro-Generation Determination. December 16, 2008

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement

SECURE Energy Services Inc. Proposed Conklin Class II Landfill Portions of: NE W4, SE W4 and NW W4

APPENDIX A-5: Public Information Centre. PIC #1b. Documents

Project Location. The CEC is a 320 MW combined-cycle power generation

ENVIRONMENTAL SCREENING REPORT

Notice of Technical Meeting

EPCOR Distribution & Transmission Inc.

Alberta Electric System Operator

AMHERST ISLAND WIND ENERGY PROJECT CONSULTATION REPORT. Appendix C. Project Notices

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4

EOG Resources Canada Inc.

THE LEGISLATIVE FRAMEWORK FOR MUNICIPAL PLANNING, SUBDIVISION, AND DEVELOPMENT CONTROL

Ontario Corp. as general partner for and on behalf of Illumination LP 545 Speedvale Ave W Guelph, Ontario N1K 1E6

SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT DESIGN AND OPERATIONS REPORT. Attachment D. Property Line Setback Assessment

ATCO Gas and Pipelines Ltd.

NOTICE OF PREPARATION OF AN ENVIRONMENTAL IMPACT REPORT

LETTER OF NOTIFICATION FOR THE DON MARQUIS-BIXBY 345 KV TRANSMISSION LINE PROP STRUCTURE PROJECT

MATL Requirements Facility Interconnection Requirements

Welcome to our Information Centre

Capital Power Generation Services Inc.

Site C Clean Energy Project Agricultural Mitigation and Compensation Plan

BC Hydro Silverdale Substation Project Ensuring a Safe and Reliable Supply of Electricity to Mission For Generations

Alberta Energy Capacity Market Framework Engagement December 2017

Understanding Bill 50

Welcome to our Open House!

Tariffs January 1, 2017

Environmental Assessment Program

1. Description of and Rationale for Proposed Change

A Guide to the Municipal Planning Process in Saskatchewan

December 2, 2016 EAB File #: Transaction #:

Connection Process Update Stakeholder Information Session. Metropolitan Conference Centre Ave SW, Calgary April 16, 2015

Review Zone Application for D&R Canal Commission Decision

Transcription:

Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions December 19, 2016

Alberta Utilities Commission Decision 22229-D01-2016 Victoria E511S Substation Breaker Additions Proceeding 22229 Application 22229-A001 December 19, 2016 Published by the: Alberta Utilities Commission Fifth Avenue Place, Fourth Floor, 425 First Street S.W. Calgary, Alberta T2P 3L8 Telephone: 403-592-8845 Fax: 403-592-4406 Website: www.auc.ab.ca

Alberta Utilities Commission Calgary, Alberta Decision 22229-D01-2016 Proceeding 22229 Victoria E511S Substation Breaker Additions Application 22229-A001 1 Decision summary 1. In this decision, the Alberta Utilities Commission must decide whether to approve an application from (EDTI) to alter and operate the Victoria E511S Substation. The need for the proposed development was approved by the Alberta Electric System Operator (AESO) pursuant to an abbreviated needs approval process established under ISO Rules Section 501.3. After consideration of the record of the proceeding, and for the reasons outlined in this decision, the Commission finds that approval of the project is in the public interest, having regard to the social, economic, and other effects of the project, including its effect on the environment. 2 Introduction and background 2. EDTI, pursuant to Permit and Licence 21415-D02-2016, 1 is the operator of the Victoria E511S Substation located in lots 195 to 197 inclusive and 232 to 238 inclusive, Block 4, Plan B3, Subdivision Hudson Bay Reserve, in the northwest quarter of Section 5, Township 53, Range 24, west of the Fourth Meridian, known municipally as 10520 104 Street N.W., Edmonton. 3. On December 1, 2016, pursuant to ISO Rules Section 501.3 Abbreviated Needs Approval Process, EDTI received approval from the AESO for the need to alter the Victoria E511S Substation. 4. On December 2, 2016, EDTI filed an application with the AUC for approval to alter and operate the Victoria E511S Substation. The application was filed pursuant to sections 14 and 15 of the Hydro and Electric Energy Act and registered as Application 22229-A001. 5. Due to the minor nature of the application, a notice of application was not issued and, therefore, a hearing was not required as the Commission considered that its decision or approval would not directly and adversely affect the rights of a person pursuant to Section 9 of the Alberta Utilities Commission Act. 3 Discussion 6. Pursuant to the abbreviated needs approval process, the AESO issued the approval in response to a request from EDTI s distribution function for a system access service request to supply power to three new buildings in downtown Edmonton; Arena Retail Complex, 1 Substation Permit and Licence 21415-D02-2016, Proceeding 21415, Application 21415-A001, May 6, 2016. Decision 22229-D01-2016 (December 19, 2016) 1

Victoria E511S Substation Breaker Additions Delta Hotel and Stantec Tower. EDTI s distribution function also requested a change in demand transmission service contract capacity at the Victoria E511S Substation from 133.92 megawatts to 140 megawatts. 7. EDTI submitted a facility application proposing to alter Victoria E511S Substation by installing two new 15-kilovolt (kv) circuit breakers in breaker cells V42 and V48 and to modify existing protection and control systems and supervisory control and data acquisition systems to accommodate the new 15-kV circuit breakers. Breaker cells V29, V42 and V48 would be connected to EDTI s distribution system that would be constructed by EDTI s distribution function. 8. EDTI indicated that upon completion of the proposed project, the Victoria E511S Substation would contain the following major equipment: one 450-megavolt-ampere (MVA), 240/72-kV load tap changer transformer four 50/66.7-MVA, 72/14.4-kV transformers one 240-kV circuit breaker nine 72-kV circuit breakers 72 15-kV circuit breakers an enclosure surrounded by a chain-link fence and other substation equipment as described in the application and other previous approvals pertaining to the substation 9. The proposed project would not require an expansion of the existing Victoria E511S Substation fenceline. All work would be conducted within the existing Victoria E511S Substation building. 10. EDTI conducted a participant involvement program in accordance with the requirements of Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments. The participant involvement program included notification being sent to 1,800 occupants, residents and landowners within the first row of development surrounding the project by using Canada Post s bulk mail service. Additionally, EDTI indicated that it had sent project-specific information packages to other organizations including the City of Edmonton, the Downtown Edmonton Community League, eight stakeholders who met the criteria for consultation and one other company that EDTI elected to notify. EDTI also conducted personal consultation with 10 property owners directly adjacent to the Victoria E511S Substation. EDTI stated that it has not received any questions, comments or concerns from stakeholders regarding the project and is not aware of any outstanding stakeholder issues or concerns for the project. 11. EDTI confirmed that no equipment containing insulating oil would be added, removed or disturbed as part of this project. EDTI stated that there would be no new effects on soils, terrain, vegetation, wetlands, wildlife habitat, fish and fish habitat, ground and surface water, air quality, drainage or aquatic resources as a result of the project. Further, EDTI indicated that no equipment containing polychlorinated biphenyl would be added, removed or disturbed as part of the project. 12. EDTI received Historical Resources Act approval from Alberta Culture and Tourism for the project on October 17, 2016. 2 Decision 22229-D01-2016 (December 19, 2016)

Victoria E511S Substation Breaker Additions 13. EDTI indicated that generally work would occur between 7:30 a.m. and 5 p.m. on weekdays with occasional overtime as required. EDTI indicated that a noise impact assessment was not required pursuant to Rule 012: Noise Control because the equipment proposed to be added to the substation would not be noise-producing and the project does not involve the addition of any new structures in the vicinity of noise-producing equipment that could result in any new reflective noise. 14. EDTI added that the proposed project would include the installation of equipment within the existing substation fenceline, into a previously approved substation building and, therefore, no potential visual effects are anticipated. 15. The proposed project cost is estimated to be $167,000 (within +20 per cent/-10 per cent accuracy in $2016) allocated fully to the customer, EDTI s distribution function. There would be no system costs associated with the proposed project. 4 Findings 16. Pursuant to Section 1.4.1(b) of Rule 007, the Commission finds that a needs identification document was not required for the proposed project because the proposed project is a minor addition to an existing substation approved by the AESO pursuant to an abbreviated needs approval process established under ISO Rules Section 501.3. 17. The Commission finds that the application to install two new 15-kV circuit breakers and associated substation equipment at the Victoria E511S Substation, filed by EDTI pursuant to sections 14 and 15 of the Hydro and Electric Energy Act, complies with the information requirements prescribed in Rule 007. The application is also consistent with the need identified in the AESO s approval letter pursuant to its abbreviated needs approval process. 18. The Commission is satisfied that the participant involvement program undertaken by EDTI meets the requirements of Rule 007. 19. The Commission finds that the technical and environmental aspects of the proposed project, as submitted by EDTI, fulfill the requirements of Rule 007. 20. The Commission accepts EDTI s statement that there will be no continuous noise-producing equipment added to the Victoria E511S Substation and finds that the proposed development meets the requirements of Rule 012. 21. The Commission accepts EDTI s assertion that the proposed project will not result in any new environmental impacts because the alteration is to occur on the existing substation property within a previously approved substation building. 22. The Commission is satisfied that there are no outstanding concerns associated with the alteration and operation of the substation and finds the proposed project to be in the public interest pursuant to Section 17 of the Alberta Utilities Commission Act. Decision 22229-D01-2016 (December 19, 2016) 3

Victoria E511S Substation Breaker Additions 5 Decision 23. Pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act, the Commission approves the application to alter and operate the substation and grants EDTI the approval set out in Appendix 1 Substation Permit and Licence 22229-D02-2016 December 19, 2016 (Appendix 1 will be distributed separately). Dated on December 19, 2016. Alberta Utilities Commission (original signed by) Henry van Egteren Commission Member 4 Decision 22229-D01-2016 (December 19, 2016)