PRODUCTIVITY IMPROVEMENT by APPLICATION of LINE BALANCING

Similar documents
Chapter 6 Planning and Controlling Production: Work-in-Process and Finished-Good Inventories. Omar Maguiña Rivero

Improvement of Productivity by New Approach-Lean Enterprise by MOST Way

Administration Division Public Works Department Anchorage: Performance. Value. Results.

Traffic Department Anchorage: Performance. Value. Results.

Technical note on seasonal adjustment for Non oil exports

Electric Forward Market Report

Productivity Improvement By Using Line Balancing And Automation Strategies in order To Improve overall Equipment Effectiveness

Traffic Division Public Works Department Anchorage: Performance. Value. Results.

TL 9000 Quality Management System. Measurements Handbook. BRR Examples

University of Michigan Eco-Driving Index (EDI) Latest data: August 2017

TOC IMPLEMENTATION - TANISHQ

REDUCING MANUFACTURING CYCLE TIME OF WAFER FAB WITH SIMULATION

SUPPLY CHAIN EXCELLENCE IN WIDEX. June 2016

MANAGEMENT OF MANUFACTURING SYSTEMS GBAT9102

AAPA. Port Operations/Safety and Information Technology Seminar

Woking. q business confidence report

National Institute of Technology Calicut Department of Mechanical Engineering PRODUCTION PLANNING (AGGREGATE PLANNING)

CI User Engagement Activities and Schedule Nov Apr 2013

Cattle Outlook. January, 2018

Line Balancing on AUDI B8 Cable Assembly Line using MUDA: A Case Study

Optimizing Inplant Supply Chain in Steel Plants by Integrating Lean Manufacturing and Theory of Constrains through Dynamic Simulation

Lessons learnt from XLP mining and ways to mitigate capital cutbacks. Presented by Charl Viljoen

Production Planning & Control BMM4823. Aggregate Planning. by Dr. Ahmad Nasser Mohd Rose

Extreme Agile Implementation and Creating a Value Delivery Office

Using Theory of Constraints and ABC to Enhance Cost Calculations at DuoGraphic B.V. - a Case Study -

Lean Cost Management at MarquipWardUnited: Lessons Learned & Corporate Insight: Part I

An Intelligent Monitoring And Identification Of Cutting Conditions (like Continuous Chip, Broken Chip) Of Chips And Chatter On Turning Operation

CAD/CAM CHAPTER ONE INTRODUCTION. Dr. Ibrahim Naimi

HKU announces 2017 Q4 HK Macroeconomic Forecast

7/8/2017 CAD/CAM. Dr. Ibrahim Al-Naimi. Chapter one. Introduction

AUSTIN AREA SUMMARY REPORT ON BUSINESS February 2018

Manufacturing Resource Planning

Vision To be a North American housing solutions provider recognized for sustainability and for leading a revolution in housing industrialization.

U.S. Farm and Retail Egg Price Relationships to 2005 Changing Share of the Consumer's Egg Dollar

Ch 19 Flexible Manufacturing Systems

HKU announces 2016 Q3 HK Macroeconomic Forecast

assessment regarding the effects of accuracy checks for infusion and syringe pumps on other clinical operations.

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012

Geographical Information System-Assisted Water Availability Analysis for Grenada MAP COMPENDIUM

San Francisco Housing Authority (SFHA) Leased Housing Programs as of January 31, 2016

THE VALUE OF DISCRETE-EVENT SIMULATION IN COMPUTER-AIDED PROCESS OPERATIONS

Antti Salonen KPP227 KPP227 1

MATERIALS AND SUPPLIES INVENTORY

Chapter 13. Lean and Sustainable Supply Chains

HKU announces 2018 Q1 HK Macroeconomic Forecast 1

A Stronger IT/Business Relationship

Challenges For Produced Water Optimization In The Permian: An Analysis Of SWD Supply and Demand

Finch Drinking Water System O. Reg 170/03 Schedule 22 - Summary Report for Municipalities

IMPROVING EFFICIENCY IN GARMENT INDUSTRY BY IMPLEMENTING SINGLE PIECE LINE PRODUCTION SYSTEM M Parthiban *1 & Adarsh H 2

CHAPTER 4.0 SYNCHRONOUS MANUFACTURING SYSTEM

edart Roadmap As of November 13 th, PJM 2017

TOCICO CONFERENCE The PECo Journey : The Fusion of Theory of Constraints, Lean and Six Sigma- Velocity

Innovation in Outbound Logistics. Gurgaon, 10 Nov 2016

Commodity Profile for Cotton- May, 2016

A Rational Approach of Lean Tool Implementation to SME - A Case Study

CAREER PLANNING WORKBOOK

The monthly variation of the Business Turnover 1 stands at 1.6%, after seasonal and calendar adjustment

Measuring Safety Performance

Street Maintenance Section Maintenance and Operations Division Public Works Department Anchorage: Performance. Value. Results.

CHAPTER 1 INTRODUCTION

REVENUE MANAGEMENT IN MARRIAGE HALL RAGUPATHY A SARAVANAN V.K-27047

Financial Intelligence NCIA 2016 National Training Conference Pittsburg April 18 th & 19 th

Continuing aggressively on. Even in the recession year (Validating Eli s views)

Inventory and Variability

Cotton Update. Hosted by United States Fashion Industry Association (USFIA) and Cotton Incorporated

The Intelligent Application of Automation: Finding the Proper Balance of Man and Machine

Heat Pump Field Trials and Implications for Design

Rainwater tank study of new homes

Corn and Soybean Market Update, August 9, 2017

Development of Material Handling System in a Manufacturing Company

ADAPTIVE THERMAL COMFORT - AN EXTENDED APPROACH FOR CONDITIONED INDOOR ENVIRONMENT USING COMPUTATIONAL FLUID DYNAMICS

National Capital Region Congestion Report

COURSE LISTING. Courses Listed. with Business Intelligence (BI) Crystal Reports. 26 December 2017 (18:02 GMT)

San Francisco Housing Authority (SFHA) Leased Housing Programs SEMAP updates as of June 7, 2016

Implementation of Lean Manufacturing System on Oil Pump

Outage Management Redesign Consultation Process (SE-109) Proposal for Process Redesign May 14, 2013

2017 KEY INSIGHTS ON. Employee Attendance and Tardiness

Eco-Impact Evaluator Project for ICT Equipment

Inventory Modeling. Session 11. Economic Order Quantity Quantity Discounts 11/1. Spreadsheet Models for Managers

QUALITY COST ANALYSIS IN AN INDUSTRY

Επιχειρησιακή Συνέχεια και Εφοδιαστική Αλυσίδα, 14 Οκτωβρίου Moving ahead in a changing environment

Inventory Control in Supply Chain Management: Concept and Workshop

PETRI NET VERSUS QUEUING THEORY FOR EVALUATION OF FLEXIBLE MANUFACTURING SYSTEMS

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

Raynet Software Lifecycle

Sustaining Our Buildings & Grounds

A how-to session featuring a behind-the-scenes look at how Best-in-Show winner, HCSS, decides when to outsource and when to create from within

U.S. Manufacturing Technology Orders Finish 2016 Down 4.0 Percent

Spicer Jodalli s ASME: A Journey to Create Win-Win Relationship with Suppliers

Project Risk Management Bootcamp. Contents are subject to change. For the latest updates visit

Recalculation of Seasonal Adjustment Factors

BRITISH INSTITUTE OF ENERGY ECONOMICS. RENEWABLES AND CCGTS: COMPETITORS OR COMPLEMENTARY? 11 October 2012 Andrew Morris

Value Sourcing. Henk Scheepers Senior Vice President Goodsflow Analyst s Day - Veldhoven The Netherlands November 13, 2003.

Feed Grain Outlook June 2, 2014 Volume 23, Number 33

3/17/2016. Ross Pruitt Associate Professor. What is happening? What may happen? Economic/management considerations

Optimization of Cycle Time for Wire Harness Assembly Line Balancing and Kaizen Approach

CO2, SO2 and NOX Emission Rates. March 15, 2018

World-class maintenance using a computerised maintenance management system

Summary for August 2014-August CBA Green Team

MM 323 MANUFACTURING SYSTEMS PRODUCTION AND LAYOUT TYPES

Transcription:

PRODUCTIVITY IMPROVEMENT by APPLICATION of LINE BALANCING Shamuvel VPandit 1, Sunil J Kadam 2, Avinash Kharat 3, Chetan U Nayakawade 4 Depart of Mechanical Engineering, Bharati Vidyapeeth s College of engineering, Maharashtra, India 1 Depart of Mechanical Engineering, Bharati Vidyapeeth s College of engineering, Maharashtra, India 2 Depart of Mechanical Engineering, Bharati Vidyapeeth s College of engineering, Maharashtra, India 3 Depart of Mechanical Engineering, SRM University Chennai, India 4 Abstract: This paper reveals the application of line balancing to improve the productivity of component under consideration. The company was facing problem for delivering the flywheel housing after increase in demand from their customer. The past data of component manufacturing process, resources required, work in process inventory and raw material inventory data was collected. When analysed the past data, constraints were observed on two machines in the production line which were needed to be focused. Eliminating the bottlenecks on these resources was the solution to cope up with the increased demand and also to minimize the raw material inventory as well as work in process inventory. The concepts described in Line Balancingwere applied to overcome the bottlenecks. The results obtained were at satisfactory level. The actual performance against the targeted level was measured and observed that productivity improved with considerable reduction in work in process as well as raw material inventories. Keywords:Line balancing, productivity, constraints, work in process inventory and raw material inventory I. INTRODUCTION Line balancing is a tool that can be used to optimize the workstation or production line throughput. This tool will assist in the reduction of the production time and maximizing the output or minimizing the cost. Assembly line is a flow oriented production system where the productive units performing the operation referred to the workstation and the work pieces move from one station to one station with some kind of transportation system. Normally there will be a problematic area in the production line or technically known as the bottleneck workstation [3]. Bottleneck is based on the analogy of the shape of a bottle. When liquid is poured into a bottle, the liquid will flow slowly at the bottlenecks that have a smaller parameter compare to the wider body. That is the conceptused for the term bottleneck in production line. At an assembly line, bottleneck is will create a queue and a longer overall cycle time. The cycle times of each process in the factory were gathered to give a better understanding of the bottlenecks that might exist and of the work content at each station [4]. Gathering detailed information on cycle times and work content for all workstation is important in order identify the bottleneck of the entire operation. II.CASE STUDY Company manufactures a variety of products for many customers spread across the country. Preliminary analysis of Engine Flywheel Housing products manufacturingon housing production lines was carried out. The target was on a specific type of housing product, theengine Flywheel Housing no. 39.468,manufacturing for oil Engine Company. The demand for these housing parts is around 1200 housings per month. Current output is in the range about 950-1000 housings per month. Thus, there is need to increase the productivity of housing product no. 39468 by improving performance of housing production line. This includes increasing capacity of machine resources, reducing work in process inventory and utilization of workforces. The company has offers this problem for productivity improvement of targeted housing product. It is proposed to apply line balancing approach to current problem by focusing on bottlenecks in the housing production line and improve the productivity of the housing product by taking care of capacity constraint resource. Copyright to IJIRSET www.ijirset.com 11495

A. Problem Associated with Company Existing Technique The company manufactures different types of housings on the housing production line according to customer demand. The production of housings carried out according to monthly demand from customers. Once the customers place order for any housing component, the production planning and control department prepare schedule for monthly production. They divide monthly production requirement into weekly production requirement and weekly into daily production requirement. The company was facing problem for delivering the selected flywheel housing product after its increase in demand from their customer. After studying the past data of housing component such as, manufacturing process, resources required, work in process inventory and raw material inventory, we found problems regarding dispatch and inventory control for the component. III. METHODOLOGY A. Identification of Constraint Resources in the Production Line Identification of constraint is most important step of the Line Balancing. The constraint identification process suggests that there are two most important steps determining the constraint.analysis of capacity and analysis of WIP accumulated in front of resource. B. Analysis of Total Available Capacity of Each Resource in the Production Line According to time study data analysis, average of total available capacity of each resource in the production line has determined which is shown in table I. Analysis of available capacity of each resource by considering cycle time as well as loading and unloading time require for each job on each resource in production line. Machine Name TABLE I TOTAL AVAILABLE CAPACITY OF EACH RESOURCE IN THE PRODUCTION LINE Cycle Time (min.) Loading and Unloading Time (min.) Total time per unit (min.) Turret Lathe 1 6.00 min 3.00 min 9.00 min Turret Lathe 2 6.00min 3.00min 9.00 min VMC 4 7.00 min 3.00min 10.00 min VTL2 8.50 min 3.00min 11.50 min HMC2 12.50 min ---- 12.50 min VMC1 5.00 min 3.00min 8.00 min Deburing and Chamfering 4.50 min ---- 4.50 in C. Analysis of Available Machine Capacity per Day Each Resource of the Production line All the machines in the production line can be operated in three shifts per day. For each shift the all machines are available eight hours. But the machines cannot run continuously throughout the shift due to number of reasons. Hence some allowances must be applied to this available machine capacity.there are three types of allowances that can be applied here. They are machine setup allowance, machine maintenance allowance and fatigue allowance of the operators. The machine setup allowance and machine maintenance allowance has considered on the basis of previous data and time study literature. TABLE III TOTAL AVAILABLE MACHINE CAPACITY PER DAY EACH RESOURCE IN THE PRODUCTION LINE Type of Allowance Percentage of Allowance Setup allowance 4% Maintenance allowance 3.6% Fatigue allowance of operator 7.4% Copyright to IJIRSET www.ijirset.com 11496

The total allowance considered 15% for each shift which is shown in table II. Therefore, machines are utilizes 410 minutes per shift including allowances.thus, the total available capacity per day for all the resources in line is 1230 minutes per day approximately. D. Analysis of Demand Placed on the Resources Demand placed on resources has analysed using total available capacity and demand per day. The demand per day of selected product is 120 housings. Analysis of demand Placed on the resources is given in table III. TABLE III ANALYSIS OF DEMAND PLACED ON THE RESOURCES Sr. No Machine Name. Total Time Required per Unit (min.) Demand perday Total timeper Day (min.) 1 Turret Lathe 1 9.00 min 120 housings 1080 min 2 Turret Lathe 2 9.00 min 120 housings 1080 min 3 VMC 4 10.00 min 120 housings 1200 min 4 VTL 2 11.50 min 120 housings 1380 min 5 HMC 2 12.50 min 120 housings 1500 min 6 VMC 1 8.00 min 120 housings 960 min 7 Deburing and Chamfering 4.50 min 120 housings 540 N E. Comparison of Total Available Capacity of the Resources and Total Demand Placed on the Resources Next step followed during implementation of Line Balancing is comparison between total available capacity of each resource and total required capacity (demand placed)on each resource in the production line. Identification of constraint resource by comparing available capacity and demand placed on each resource is shown in table IV..TABLE IV COMPARISON BETWEEN AVAILABLE CAPACITY AND DEMAND PLACED ON EACH RESOURCE Sr no. Machine resource Available Capacity (min.) Demand per Day (Required Capacity) (min.) Remark 1 Turret Lathe 1 1230 min 1080 min Non Constraint Resource 2 Turret Lathe 2 1230 min 1080 min Non Constraint Resource 3 VMC 4 1230 min 1200 min Non Constraint Resource 4 VTL 2 1230 min 1380 min Constraint Resource 5 HMC 2 1230 min 1500 min Constraint Resource 6 VMC 1 1230 min 960 min Non Constraint Resource 7 Deburing and Chamfering 1230 min 540 min Non Constraint Resource Copyright to IJIRSET www.ijirset.com 11497

From this information the available capacity of resources, Turret Lathe 1, Turret Lathe 2, VMC 4, VMC 1, Chamfering and Deburing resources is more than demand; hence these resources are identified as non-constraint resources (NCR). But available capacity of resources VTL 2 and HMC 2are less than required capacity (demand), hence VTL 2 and HMC 2 are identified as constraint resources (CR). F. Analysis of the Number of WIP Inventory Accumulated in Front of Each Resource The number of WIP inventory accumulated in front of each resource in the production line is important issue for identification of the constraint resource. This is because the fact that the constraint resource is associated with huge number of WIP inventory. Thus, the number of WIP inventory ahead of each resource may give an idea about the constraint resource. Analysis of WIP inventory of selected housing product manufacturing on production line has carried out; and observed that WIP inventory associated with HMC 2 machine and VTL 2 machine is huge amount. The average WIP inventory registered 207 housings before implementation of Line Balancing. G. Exploitation of the Constraint Resources Layout of housing production line before implementation of Line Balancing is shown in fig1. Turret Lathe 1 Turret Lathe 2 VMC 4 VTL2 HMC 2 Deburing & Chamfering VMC 1 Fig.1 Layout of Housing Production Line before Implementation of Line Balancing According to Line Balancing methodology, the resource whose capacity less than demand this resource identified as constraint resource and also the resource in front of maximum WIP inventory identified as constraint resource. Available capacity of the each resource in the housing production line is 1230 minutes per day. The demand placed on HMC 2 machine was 1500 minutes per day before Line Balancing. This means that capacity of HMC 2 machine was less than demand placed on it and maximum number of WIP inventory accumulated in front of HMC 2 machine. Hence HMC 2 machine has identified as constraint resource. HMC 2 machine utilized for side milling, side drilling, tapping and countering operations on selected housing product. For these operations, cycle time required on HMC 2 machine was 12.5 minutes. To overcome this problem, we introduced Tap Fast 1 machine. The tapping and chamfering operations of HMC 2 machine shifted on Tap Fast 1 machine. Therefore HMC 2 machine now utilizes only for side milling and side drilling operations. The cycle time of HMC2 has reduced up to 10 minutes and same operator works on HMC2 and Tap Fast1 machine. After performance of housing production line measured by introducing Tap Fast 1 machine, it is found that, VTL 2 machine has constraint resource because its capacity less than demand. Also in front of VTL 2 machine huge WIP inventory accumulated. The capacity of the each resource in housing production line is 1230 minutes per day. The demand of VTL 2 machine is 1380 minutes per day. This means that, capacity of VTL 2 machine less than demand placed on it. In front of VTL 2 machine we observed 5 parts WIP inventory accumulated per shift; hence VTL 2 machine identified as constraint resource. To overcome this problem, by introducing Turret Lathe 3 (TL 3) machine. Turret lathe 3 machine has maintained 5 housing parts (capacity buffer stock) in front of the VTL 2 machine and balance the production line. Total cycle time of (TL 3) machine has 16 minutes per job. After involving (TL 3) machine, it provided 5 parts per shift and line has balanced. Each shift TL3 utilize up to 80 to 90 minutes. Remaining 320 minutes TL3 utilized for machining of other Copyright to IJIRSET www.ijirset.com 11498

housing products and development work.layout of Housing Production Line after Implementation of Line Balancing shown in fig.2 Turret Lathe 1 Turret Lathe 2 VMC 4 VTL2 HMC 2 TurretL athe 3 Tap Fast 1 Deburing & Chamfering VMC 1 Fig. 2 Layout of Housing Production Line after Implementation of Line Balancing IV. RESULTS AND DISCUSSION To examine the impact of Line Balancing technique, performance measurement system has developed. After that, physical measurement of all performance measurement parameters carried out before and after implementation of TOC. The period from July 2012 to November 2012 represent pre-implementation period and post implementation period from December 2012 to April 2013. A. Effect of line Balancing Methodology on Average WIP Inventory The analysis of number of WIP inventory has carried out each week per month. 300 200 100 0 Work In Process 235 246 219 161 172 46 38 30 27 32 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 WIP Fig.3 Number of WIP inventory before and after of Line Balancing Fig.3 shows average number of WIP inventory before and after implementation of line balancing. From the above results, it is seen that there is considerable amount of reduction in number of WIP inventory of selected housing product due to implementation of line balancing technique. The average number of WIP inventory before implementation was 207 housings. This reduced to 35 housings per month after implementation of line balancing. B. Average Percentage of On Time Deliveries before and after Line Balancing. The average percentage of on time deliveries for selected housing product, before and after implementation of line balancing has measured. From fig. 4, it is seen that, the percentage of on time delivers almost good after implementation of Line Balancing i.e. December 2012 onwards. The on time delivers graphically represented by fig 4. Copyright to IJIRSET www.ijirset.com 11499

120% 100% 80% 60% 40% 20% 0% On Time Delivers 96% 97% 97% 98% 97% 80% 79% 81% 86% 85% ON TIME DELIVERS Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 Fig. 4 Percentage of On Time Deliveries before and after Line Balancing The average amount of on time delivers before implementation was 82%. This improves up to 97% after implementation i.e. 15% increment in on time deliveries after implementation of Line Balancing. This consequently resulted in improved throughput. C. Effect of Line Balancing Implementation, on Raw Material Inventory (RMI) The analysis of average number of raw material inventory before and after implementation of line balancing has carried out. Fig. 5 shows average number of WIP inventory before and after implementation of line balancing. 300 250 200 150 100 50 0 Raw Material Inventory (RMI) 268 276 255 193 204 73 67 56 54 60 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 RMI Fig. 5 Number of Raw Material Inventory before and after Line Balancing From above results, it is seen that there is considerable number of reduction in raw material inventory for selected housing product due to the implementation of line balancing technique. Average number of reduction in raw material inventory due to the implementation of line balancing for selected housing product is graphically represented in fig.5.the average number of raw material inventory before implementation was 239 housings. This reduced to 62 after implementation. Copyright to IJIRSET www.ijirset.com 11500

D. Effect of Line Balancing Implementation on Profit After implementation of line balancing technique we observed that, there is little additional investment in the machining cost of the selected housing product. The profit improvement due to the implementation of line balancing for selected housing product is graphically represented shown in fig.6. 500,000 400,000 300,000 343,184 339,268 348,524 369,172 Profit 364,900 410,468 413,316 415,808 416,876 415,096 200,000 Amount of Profit 100,000 0 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 Fig. 6Profit before and after Line Balancing The average profit before implementation was Rs.3,53,010/-. This improves Rs. 4,14,313/- after implementation i.e. 17% of profit improvement after implementation of line balancing. V. PRODUCTIVITY MEASUREMENT After the analysis of performance parameters such as on time deliveries, the productivity measurement has carried out for selected housing component. Productivity has measured in terms of labour, machine and material. The table V indicates analysis of labour productivity, machine productivity and material productivity. After measurement of productivity it is observed that, labour productivity improved by 2.59%, machine productivity improved by 17.19% whereas the material productivity improved by 15.87%. TABLE V ANALYSIS OF PRODUCTIVITY Type of Productivity Before Line Balancing After Line Balancing Improved Values Percentage of Improvement Labour Productivity 17.71 18.17 0.46 2.59% Machine Productivity 2.4195 2.8356 0.4161 17.19% Material Productivity 0.3787 0.4388 0.060 15.87% VI.CONCLUSION Line Balancing brings a new dimension to management philosophy and provides an adopted within a wide variety of organizations and settings; it appears that organizations using line balancing has determined that it can help them achieve a number of management objectives, including continuous improvement. By application of line balancing it is Copyright to IJIRSET www.ijirset.com 11501

possible to improve productivity by improving on time delivers, reducing inventory levels and better utilisation of resources. After implementation of line balancing, the analysis gives following results. 1. After implementation of line balancingthe demand achieved for selected housing product is increased from 82% to 97%, which has resulted on time delivers improved by 15%. 2. Initially the average amount of production of housing product was 992. After involving machines (Turret Lathe Machine 3 and Tap Fast Machine 1) on the suggested place the production of selected housing product is increased up to 1163. This results, increased in production volume by 17%. 3. The profit of selected housing product was Rs. 3,53,010/- before implementation of line balancing. Whereas after implementation of line balancingprofit is Rs. 4,14,313/-. This results profit increased by 17%. 4. After implementation of line balancing the labour productivity increased by 2.59%, machine productivity increased by 16.94% and material productivity increased by 15.87%. 5. The average amount of work in process inventory for selected housing product is reduced. Before implementation of line balancingwip was 207 housings and it is reduced up to 35 housings after implementation. This gives 83% reduction in work in process inventory. 6. The average amount of raw material inventory has considerably reduced; earlier it was 239 housings while it has come down to 62 housings. This gives 74% reduction in raw material inventory. REFERENCES [1] Nils Boysen, MalteFliedner, Armin Scholl, A classification of assembly line balancing problems, European Journal of Operational Research 183 (2007) 674 693. [2] PiluCrescenzi, Giorgio Gambosi, Gaia Nicosia, Paolo Penna, On-line load balancing made simple: Greedy strikes back, Journal of Discrete Algorithms 5 (2007) 162 175. [3] Hadikc-en, Kurs-ad Agpak, RecepBenzer, Balancing of parallel assembly lines,int. J. Production Economics 103 (2006) 600 609. [4] Chuan Shi, Stanley B. Gershwin, An efficient buffer design algorithm for production line profit maximization, Int. J. Production Economics 122 (2009) 725 740. [5] Gerald R. Aase, John R.Olson, Marc J.Schniederjans, U-shaped assembly line layouts and their impacton labor productivity: An experimental study, European Journal of Operational Research 156 (2004) 698 711. BIOGRAPHY Shamuvel V. Panditis Assistant Professor at Mechanical Department of BharatiVidyapeeth college of Engg., Kolhapur.Completed the PG Program in M E (MECH-PROD) from K I T s College of Engineering, Kolhapur. Assoi.Prof. S J Kadam is the Head of The Department of Mechanical Engg. With 13 years of experience in teaching flied. Completed PG program in ME (CAD/CAM). His research interest is in FEA, IC Engine, and Automobile. Avinash R. Kharatis Assistant Professor at Mechanical Department of BharatiVidyapeeth college of Engg., Kolhapur completed P G Program in M E (CAD/CAM/CAE) from K I T s College of Engineering, Kolhapur. The topic of his dissertation is effect of opening pattern on stress distribution of pressure vessel. Chetan U. Nayakawade is PG student studying M. Tech (CAD) in SRM University Chennai. Copyright to IJIRSET www.ijirset.com 11502