HOW DESIGN INFLUENCES COST

Similar documents
CARPENTER STATUTORY DECLARATION OF WORK EXPERIENCE

Effect of Changes in Layout Shape on Unit Construction Cost of Residential Buildings

Working Together to Deliver High Levels of Construction Quality

WASSCE / WAEC BUILDING CONSTRUCTION SYLLABUS

BUILDING CONSTRUCTION

What is NUFORM HOUSE KIT?

MATERIALS AND RESOURCES

Quantification of Construction Waste Amount

CBM Engineers India COMPANY PROFILE. Structural Engineering Firm established in 1975 in Houston, Texas - USA Services Offered:

CARPENTRY WORKPLACE TASKS - CHECK LIST (Note: for employer reference only)

Drawings shown within this brochure is the Preston CarPark Innovation Concept and patents filed in August 2018.

RENOVATING AN AGING HOME: Answers to Frequently Asked Questions

Good Construction Practices Part I

Permit Procedures For New Construction, Additions, and Alterations

The Consumer s Guide to. Basement Renovations. The Consumer s Guide to Basement Remodeling Total Renovations

SRT351 - ASSIGNMENT 1 PART A Jessica Chapman, Darcy Dunn, Harrison Jess, Lyndall Morris

ARUN CONSTRUCTION SERVICES. Proactive and reactive property maintenance

1. Remove worn-out old plaster (or any other finishing).

Basis of Structural Design

(T022) Level 3. Design economics and cost planning

Before You Start Renovating Your Bathroom

GRADE 11 NOVEMBER 2011 CIVIL TECHNOLOGY

REQUIREMENTS FOR INDOOR INSTALLATION OF PADMOUNTED TRANSFORMERS

CONSEQUENCES OF INCORRECT DESIGN AND UNQUALIFIED REALIZATION ON RELIABILITY AND EFFECTIVENESS OF RADON REDUCTION MEASURES

* RESIDENTIAL PLAN REVIEW *

106 TALL BUILDINGS: A STRATEGIC DESIGN GUIDE

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

T I M B E R E N G I N E E R E D S O L U T I O N S

IDEA Architectural Design Competition 2018

City of Omaha Plans and Permits Commercial Alterations and Conversions Building Permit Submittal Checklist

TERRACE FACTORY - TYPE A1

Bathrooms. Custom cabinetry INCLUDED

Flexible Building Design

AN EMPHATIC TIME AND COST SAVER TECHNIQUE- KUMKANG ALUMINUM FORMWORK SYSTEM

CATAMARAN TOWER - 1 Seef Area Plot 19, 20

Appendix A WORK PROCESS SCHEDULE AND RELATED INSTRUCTION OUTLINE

Request for Proposal (RFP) Building Repair and Renovation Project. Instruction to Bidders (Project Management Consultants) & Eligibility Criteria

OPITZ Construction Systems Made to Measure

6D-BUILDTECH Building Systems. Products and services. Introduction

Capability Statement

ibuild Modulars SMART2 LOW cost for owners HIGH utility for occupants

Garage Conversions. Technical Issues

Planning a basement 22/6/2018. Elaine Toogood Senior architect The Concrete Centre. June

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

The SIPs Process. 1 Why SIPS? What is the typical process for building a home using SIPS Industries? The Factory Process...

Study: Construction Process at Plot 22, Shivaji Nagar, Govandi, Mumbai

modular scaffolding R+

Building Elements. Roof Wall. Slab/beam. Superstructure. Column. Basement. Substructure. Foundation

Permit Application Commercial / Industrial / Multi-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE

IMTO Italian Mission to Oman University of Pisa ARCHITECTURAL REPORT (FEBRUARY - MARCH 2014) ARCH. STEFANO BIZZARRI, ARCH.

EXPANDABLE DWELLING SYSTEM FOR CHEAP AND FAST ERECTION AND DISMANTLING

Trade Licensing Guide Queensland. Use this guide to verify which licensed trade you need for your home improvement job

A Solid Foundation Solution for Homeowners. from

Passive House Project documentation

Homeowners Responsibility

Fundamentals of Building Construction: Materials and Methods

COMMERCIAL BUILDING PERMIT APPLICATION

Overview. Introduction to Housing Solutions 2-3. Why Modular Housing 4-5. Standarised Designs Apartments Warranties.

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017

Residential Patio Cover Specifications

Office Building. Analysis #2: Utilizing a Matrix Schedule

Stop the damaging effects of foundation settling...

ibuild Modular Buildings Cyclone Rated Termite Resistant Superfast Assembly Worldwide Delivery

Permit Application Commercial / Industrial / Mutli-Family BUILDING, ELECTRICAL, MECHANICAL, PLUMBING, BUILDING SEWER & WATER SERVICE (Form #2)

Associate-Membership Examination

Measuring Walls in Accordance with ARM4 - An Introductory Demonstration

APPLICATION AND CERTIFICATE FOR PAYMENT

Innovation Construction CIC: B2B Event on MiC

These systems are evaluated on the basis of serviceability issues such as:

TERMS OF REFERENCE UPGRADING THE FISHERY SECTOR IN SOUTH SUDAN CONSTRUCTION OF A FISH MARKET FACILITY IN NIMULE, SOUTH SUDAN

Electric Service Standards

Property Condition Assessment

Reinforced concrete double walls

Magnum Board Coatings

Reinforced concrete double walls

KANSAS. Crossover. The Kansas Department of Transportation finds a new solution for stream crossings.

Mbrico Tile Rooftop/Raised Floor Installation Guidelines

RESIDENTIAL BUILDING PERMIT GUIDE FOR MULTI-FAMILY DWELLINGS

Estimate FOR THE SEPTIC TANK

Construction applications

Construction and Civil Contracting SLIPFORM CONSTRUCTION

BUILDING TECHNOLOGY CON1018W GROUP ASSIGNMENT

THE CORPORATION OF THE TOWNSHIP OF HAMILTON HOME BUILDER S GUIDE PART I MUNICIPAL BUILDING REQUIREMENTS

GRADE 12 SEPTEMBER 2012 CIVIL TECHNOLOGY

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options

Bruce Park Toilet Site. = Post and rail fence = Concrete pad as per PS1 design

3. The Building Cost Information Service BCIS

Outdoor + Switchgear, Walk-in Equipment Buildings Low & Medium Voltage NEMA 3R

Factsheet no. 7: Agrocolumna warehouse, Copăceni, Romania

THE CORPORATION OF THE TOWNSHIP OF HAMILTON HOME BUILDER S GUIDE PART I MUNICIPAL BUILDING REQUIREMENTS

Estimated Cost Ranges for Completing Residential Flood Protection Projects

SAMPLE. Slab On Ground Construction. Carpentry - Residential Construction. Product Code: 5597

Inspection requests submitted by 2:30pm will be scheduled for the following business day unless otherwise requested.

DESIGNING COMMERCIAL SUB-SLAB DEPRESSURIZATION SYSTEMS

INTERNSHIP REPORT GOUTHAM.J

STEPPING STONES DAYCARE NEW LISKEARD PUBLIC SCHOOL

The Homeowner s Building Application Checklist for Constructing a Residential Addition

Relevant issues of booth construction

Two complete sets of plans that are legible and drawn to conventional scale are required to be submitted with the Building Permit Application Form.

SITE VISIT REPORT DATE: JOB: NO. OF VISIT: PAGE OF : PURPOSE OF VISIT: CONTRACTOR: Items to be checked Observations Actions SETTING OUT

Transcription:

HOW DESIGN INFLUENCES COST moladi is an affordable housing technology that seeks to reduce the unnecessary costs involved in the construction industry. A key aspect of our function is to educate and guide our clients to optimise their projects by providing them with the knowledge and technology to become more efficient and reduce cost. Many contractors and clients refer to building costs as a rate per square meter, however, this method of expressing the cost of buildings is not always reliable, although it is the most convenient way for conventional contractors to provide cost comparisons for planning. It is important for people to recognise why this method of costing a structure is largely dependant on the shape, layout, and other variables that are specific to the client s design. IRREGULAR SHAPED FLOOR PLANS The overall shape of a building has a marked effect on the total cost of building the structure. It is generally accepted that the more regular the shape of a building is, the more cost effective it would be to build. FLOOR PLAN B

Referring to the above examples, both floor plans have the same total floor area, however the cost to build the structure of floor plan B will be higher than that of floor plan A. The factors influencing the increase in cost between floor plan B, when compared to floor plan A, are attributed to the following factors; The perimeter to floor area ratio of floor plan B is higher than that of floor plan A. Floor plan B requires 19.5% more external walling to enclose the same floor area than that of floor plan A. The excavation costs for the foundation will increase by between 6% to 20% for floor plan B. There is an increase of wall volume of over 22% for floor plan B in comparison with floor plan A. This will result in an increase in material quantities needed for the mortar mix, as well as the amount of formwork, reinforcing and labour required to build the wall structure of the unit for floor plan B. The drainage costs will increase by approximately 25% due to the extra rodding and inspection eyes, as well as the extra length of piping needed. Other additional costs will also result from other elements of the building, such as the roofing, due to the work being complicated by the shape. REGULAR SHAPED FLOOR PLANS Although the illustrations and explanations above have described how irregular shapes of floor plans and designs can effectively increase the overall cost of a structure, regular shapes with longer and narrower proportions are less economical to build. If we assume a cost per square meter of wall area is R140, for a 150mm wall, we are able to calculate the relationship between the below examples in terms of cost. ; Cost/m² = length of wall x wall height x walling cost per square meter area Cost/m² = 40 x 2,7 x 140 100 Cost/m² = R151.20

FLOOR PLAN B FLOOR PLAN B; Cost/m² = length of wall x wall height x walling cost per square meter area Cost/m² = 58 x 2,7 x 140 100 Cost/m² = R219.24 It is important that both the architect/designer and client are fully aware of the additional costs (or savings) that probably will arise from even small changes in the shape of the house. They can then adopt a rudimentary cost benefit approach in considering the advantages of different shapes in seeking a suitable balance between cost, aesthetics and functional aspects. INTERNAL WALLS AND LAYOUTS The variable shape and lengths of the internal walls have also been excluded from these examples, however, it has been clearly illustrated how they could potentially affect the cost of building a home. The design of any structure is a critical phase in the cost implications of your project.

; Total Length of 150mm External Walls = 28.8m Total Length of 100mm Internal Walls = 14m Calculated Cost per Square Meter; Assumed Cost Quantity Total 150mm External Wall R140/m² 77.8m² R10 892 100mm Internal Walls R120/m² 37.8m² R4 536 Bathroom R10 000 1 R10 000 Internal Doors R1 300 3 R3 900 External Doors R2 000 2 R4 000 Window I R1 500 3 R4 500 Window II R650 2 R1 300 R39 128 Therefore the total cost per square meter of floor plan A would be R757.85, excluding finishes. FLOOR PLAN B FLOOR PLAN B; Total Length of 150mm External Walls = 32m Total Length of 100mm Internal Walls = 18.4m Calculated Cost per Square Meter; Assumed Cost Quantity Total 150mm External Wall R140/m² 86.4m² R12 096 100mm Internal Walls R120/m² 49.7m² R5 964 Bathroom R15 000 1 R15 000 Internal Doors R1 300 4 R5 200 External Doors R2 000 1 R2 000 Window I R1 500 7 R10 500 Window II R650 2 R1 300 Window III R400 1 R400 R52 460

Therefore the total cost per square meter of floor plan B would be R1 008.85, excluding finishes. FLOOR PLAN C FLOOR PLAN C; Total Length of 150mm External Walls = 40.4m Total Length of 100mm Internal Walls = 9.6m Total Length of 150mm Internal Walls = 5.4m Calculated Cost per Square Meter; Assumed Cost Quantity Total 150mm External Wall R140/m² 109.1m² R15 274 100mm Internal Walls R120/m² 25.9m² R3 108 150mm Internal Walls R140/m2 14.6m² R2 044 Bathroom R15 000 3 R45 000 Internal Doors R1 300 3 R3 900 External Doors R2 000 3 R6 000 Window I R1 500 6 R9 000 Window II R650 3 R1 950 R86 276 Therefore the total cost per square meter of floor plan C would be R1 659.15, excluding finishes. Although the above comparisons have been roughly estimated with assumed costs, it is generally accepted that a more simplified design, or decrease in detail, will result in a more cost effective rate per square meter. DETERMINING ECONOMICS OF DESIGN It is not always necessary to request a detailed cost estimate to guage the economical advantages when comparing floor plans. A viable method of briefly calculating the perimeter/floor ratio will be able to indicate the more economical option for your proposal. FLOOR PLAN B

; In the case of a 2,7m wall height, the perimeter/floor ratio is calculated as follows; Perimeter : Floor = Area of wall perimeter Total floor area Perimeter : Floor = 41 x 2.7 100 Perimeter : Floor = 1:0.11 FLOOR PLAN B; In the case of a 2,7m wall height, the perimeter/floor ratio is calculated as follows; Perimeter : Floor = Area of wall perimeter Total floor area Perimeter : Floor = 50 x 2.7 100 Perimeter : Floor = 1:0.35 It is generally agreed that the lower the perimeter/floor ratio, the more economical the design will be. Therefore, again, floor plan A is notably the more economical of the two proposals in this example. VARIABLES AFFECTING COST It is very important to mention that the examples above have excluded a number of influential factors in determining the cost effectiveness of a structure. There are a number of aspects that should be considered during the design phase of your project. 1. Floor to ceiling height; By increasing the height of the walls, the cost of the structure will increase. 2. Finishing materials; The desired finishes for your project should be carefully considered and must be decided on according to the budget. Each item included in the specification will accumulate to contribute to the overall cost of the structure. 3. Building material costs; The cost of building materials will vary greatly from country to country, even from city to city. It is crucial that the client should investigate the most economical supplier close to the project site, as every moladi cost estimate is calculated with those costs supplied by the client to ensure that the information supplied is as accurate as possible. 4. Amortised cost of the formwork; The moladi technology is cost effective due to its repetitive application. It is affordable due to the fact that the moladi formwork is used on a repetitive basis for up to 50 reuses per kit; this results in the cost of the formwork being amortized over the construction of 50 units. The less re-uses the purchased formwork kit has the greater the overall cost of a single unit. 5. Duration of construction; A key aspect of savings is the speed of construction. Less time on site, or the faster the project is completed, results in a more economical project and greater savings. 6. Labour; With a shorter duration of construction, the cost of on-site labour per structure will be drastically reduced. The amortisation of the moladi technology allows for labourers to move from one construction site to another, ensuring that their employment is secured. We encourage our clients to understand the importance of cost effective design that is balanced with aesthetics and social acceptability.