Shatin to Central Link (SCL) Cross Harbour Section. Professional Forum II 4 th December 2009

Similar documents
Harbourfront Commission

Ms. Lydia LEE, SRE Mr. Eric WONG, SRE } Mr. Freddie CHAN, SRE } Mr. Terry SIU, SRE } Ms. Remmy CHU, RE } Ms. Christy CHUNG, RE } Ms.

THE UNIVERSITY OF HONG KONG LIBRARIES. ^^^u^^ Hong Kong Collection

4 Major Challenges 2,000. with Constructing the Hung Hom Section. hours. Aug. of work everyday. On average. Hung Hom Section newsletter.

Task Force on Kai Tak Harbourfront Development

All Drill and Blast Tunnelling Works for Shatin to Central Link Completed

Task Force on Kai Tak Harbourfront Development. Central Kowloon Route. Proposed Temporary Government Land Allocation for Works Area at Kai Tak

An Overview of Public Landing Facilities around Victoria Harbour

1. ORIGINAL CONSTRUCTION SEQUENCE PRESENTED IN THE APPROVED EIA REPORT

Task Force on Kai Tak Harbourfront Development

Harbourfront Commission

Victoria Harbour: Marine uses, Land Water Interfaces, and Issues

Water Quality of Victoria Harbour and its Typhoon Shelters

The Planning and Construction of Cross Boundary Railway Projects

MTR Shatin to Central Link Contract 1103 Hin Keng to Diamond Hill Tunnels Hong Kong, China

Temporary Works Excellence Award 2017 MTRC Contract 1128 SOV TO ADMIRALTY TUNNELS

Construction of Bridges

Mobile Realtime Air Monitoring Platform -MAP 18 Districts June 2010

Acoustic Vinyl Barrier Mat. Effective Construction Noise Mitigation Measure

Construction of the Superstructure of Major Sea Crossings

Topic: Site Formation

Hong Kong International Airport Medium & Long Term Development Plans. The British Chamber of Commerce 18 July 2012

IN COMPLIANCE WITH EUROPEAN STANDARD

Post-earthquake response plans for State Highways in the Wellington Region

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways. Environmental Measures for New Railway Projects

AL-AMEEN ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK

An introduction to HS2 Ltd s approach to managing noise. Community Forums, Sept 2012

The HKIE Structural Examination Written Examination 2017

Central - Wan Chai Bypass and Island Eastern Corridor Link (CWB) Introducing Air Purification System in Road Tunnels

Sandpoint Junction Connector

Wholesale food and fish markets along Victoria Harbour

POSTER PAPER PROCEEDINGS

Railway Model Aids Designers and Tenderers

Harbourfront Commission

PIANC Commission Working Group Report Reviews

Code of Construction Practice Part B: Site Specific Requirements

Future Development of HKIA. Planning of the Three-Runway System. Presentation to Hong Kong Air Cargo Forum. 19 June 2013

VALLIAMMAI ENGINEERING COLLEGE DEPARTMENT OF CIVIL ENGINEERING CE RAILWAYS AIRPORT AND HARBOUR ENGINEERING QUESTION BANK

MARINA PHASING AND COSTS

The Chartered Institute of Logistics and Transport in Hong Kong (CILTHK) Submission for Policy Address (17 August 2018)

Independent Technical Review of the George Massey Crossing. December, 2018

The Construction of Deep and Complex Basements and underground structures within extremely difficult urban environment.

3.0 PROJECT DESCRIPTION

Appendix A: Project Characteristics

UNIVERSITY OF HONG KONG LIBRARY. Hong Kong Collection. gift from Hong Kong Gov't Printer

Conversion table working groups Name working group Old number New number Conception des barrages mobiles et de barriers anti-tempĂȘtes PIANC WG 101

2-2 ALTERNATIVES CONSIDERED AND ELIMINATED

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok

UNIVERSITY OF HONG KONG LIBRARY. Hong Kong Collection. 61 ft from Information and Public Relations Unit, Lands & Works Dept., Goverrment Secretariat

Annex C. Port Zoning and Operational Opportunities and Constraints

Where the Ocean Meets Land. Coastal Engineering

ORAL PAPER PROCEEDINGS

Deviation from a Railway Group Standard

I213. Westhaven Tamaki Herenga Waka Precinct

New Developments of the Constanza Port relevant to MoS project initiatives Kiev, 4 th of July, 2011

John Costello. AGE :64 NATIONALITY British

Construction of a Semi-Buried Building A Super-sized Shopping Mall : The Festival Walk

Recent Major Cable-Stayed Bridges in Shanghai

Marine Portfolio

Design of Izmir Bay Crossing Bridge

F3. Coastal Marina Zone

Project Update. for the. Community Liaison Group

Distribution Restriction Statement Approved for public release; distribution is unlimited.

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

GLOBELINK A STRONG PLAN FOR REAL CHANGE 1

Contract No. NE/2015/01 Tseung Kwan O Lam Tin Tunnel - Main Tunnel and Associated Works

Port of Long Beach Port Master Plan Overview December 22, 2008

Presentation for Roads Australia Miller Street, Sydney 3 April creating public Pacific Highway delivering value for money

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways

GLOBE LINK CONNECTING SOUTH AUSTRALIA TO THE WORLD

The HKIE Structural Examination Written Examination

ANNEX 2: PRIORITY "PRE-IDENTIFIED PROJECTS ON OTHER SECTIONS OF THE CORE NETWORK (RAILWAYS, INLAND WATERWAYS, ROADS, MARITIME AND INLAND PORTS) "

Illiana Corridor. Stakeholder Alternatives Summary PHASE I STUDY. October 25, 2011

Marine Portfolio

LARGE-SCALED BRIDGE PROJECTS IN RECENT HONG KONG. Raymond W M Wong, Division of Building Science & Technology, City University of Hong Kong

Appendix 8: Best Practicable Environmental Option (BPEO) Assessment

Case examples for the construction of complex basement

Hong Kong 2030+: Towards a Planning Vision and Strategy Transcending Response April 2017

Managing Extreme Sea Level Rise Scenarios Tony Gioiello Chief Harbor Engineer

Report to: Greater Cambridge Partnership Joint Assembly 18 January 2018

7. Value Management Workshop

Re-imagining Hong Kong with a Game-Changer. Enhanced East Lantau Metropolis. Q&A Guide

Welcome. About the Proponent. About the Proposed Project. The Proposed Project is now in the Regulatory Review period of the schedule.

Illawarra Business Chamber/Illawarra First. Submission on NSW Draft Freight and Ports Plan

E13: MANAGEMENT OF TRAFFIC DURING CONSTRUCTION

Detroit River International Crossing Study Canadian Frequently Asked Questions. Q. Why have you decided to focus on this area of analysis?

FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN. EB3679 February 2011

Policy context & Projects on the comprehensive network

SR 15 SECTION 088 CSVT SOUTHERN SECTION PUBLIC MEETING MAY 25, 2017

Outline of Presentation

In Your Area 2: North Acton to Northolt

15A NCAC 07H.0308 SPECIFIC USE STANDARDS FOR OCEAN HAZARD AREAS (a) Ocean Shoreline Erosion Control Activities: (1) Use Standards Applicable to all

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.

REPORT Condition D19 Permanent Noise Barriers

3 Documentation of Alternatives

ARROW ENERGY ARROW LNG PLANT. May 15 th to 19 th 2012

EIA Case Study of Implementing Mitigation Measures in Hong Kong

Contract No. HY/2010/02 Hong Kong Zhuhai Macao Bridge Hong Kong Boundary Crossing Facilities Reclamation Works Regular Marine Travel Routes Plan

Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road Section between Scenic Hill and Hong Kong Boundary Crossing Facilities

Large-scale site formation for a residential development at Sheung Shing Street, Ho Man Tin

Transcription:

Shatin to Central Link (SCL) Cross Harbour Section Professional Forum II 4 th December 2009 22/06/2010 Page 1

Agenda Public Views To summarize the views sought in the consultation activities throughout the past months. The Preferred Scheme Westerly Alignment To update the design development of the SCL Cross Harbour Section. Extent of Reclamation To discuss the extent of reclamation. Q&A 22/06/2010 Page 2

Immersed Tube Tunnel - Alignment Envelope HUNG HOM STATION Existing Cross Harbour Tunnel Envelope for Cross Harbour Tunnel Options WESTERN ALIGNMENT CORRIDOR ENDORSED AT PROFESSIONAL FORUM NO.1 EASTERN CORRIDOR WESTERN CORRIDOR Central Wanchai Bypass (CWB) SLIP ROAD NO.8 EXHIBITION STATION 22/06/2010 Page 3

Public views Introduction Line 1 (Myriad MM Regular pt. 22, Line Spacing pt. 28) Introduction Line 2 Introduction Line 3 22/06/2010 Page 4

Consultation activities Major stakeholders in Causeway Bay Typhoon Shelter (CBTS) Private mooring users Anchorage area users Royal Hong Kong Yacht Club mooring users Buildings with sea water intake at CBTS Professional Groups Professional Forums Harbour-front Enhancement Committee Presentations to professional institutes (including CILTHK, HKCA, HKIA and HKIP) 22/06/2010 Page 5

Consultation activities (cont d) General Public District Councils Information Paper to all 18 District Councils Presentations to Wan Chai, Eastern, Yau Tsim Mong, North, Kwun Tong and Southern District Councils Public Forums at NT, Kowloon and HK Island Exhibitions Digest 22/06/2010 Page 6

Major views The majority of people agreed that there is an overriding public need for the SCL. Many people urged for its early completion. The finding that there is no reasonable zero reclamation option is supported. The vast majority preferred the Westerly Alignment in view of less impact to the Causeway Bay Typhoon Shelter (CBTS) and more direct route. 22/06/2010 Page 7

Other views Some stakeholders suggested that the SCL alignment should avoid passing through the CBTS. Some suggested that the CBTS breakwater should be relocated northward to provide more sheltered space such that the construction of the SCL within the CBTS could be expedited. Some suggested that the immersed tube tunnel method be adopted in the CBTS to reduce temporary reclamation. 22/06/2010 Page 8

Why Alignment Can t Avoid CBTS? Introduction Line 1 (Myriad MM Regular pt. 22, Line Spacing pt. 28) Introduction Line 2 Introduction Line 3 22/06/2010 Page 9

Alignment to North Point / Fortress Hill HUNG HOM STATION Fortress Hill / North Point Stations not capable of accommodating interchange passenger movements Existing buildings form barrier NORTH POINT Principal destination on north shore of Hong Kong Island FORTRESS HILL CENTRAL EXHIBITION STATION TIN HAU ADMIRALTY WAN CHAI CAUSEWAY BAY Constraint caused by Island Line capacity 22/06/2010 Page 10

Alignment to West of Existing Cross Harbour Tunnel No cross platform interchange with NIL Shared use of existing West Rail tunnel not possible due to capacity constraints Clash with Coliseum foundation Very deep alignment to pass under CWB tunnels Cross Harbour Gas Main Cross Harbour Tunnel SCL tunnels very deep to pass under Cross Harbour Tunnel in rock Very deep Hung Hom Station significant impact on East Rail to the north 22/06/2010 Page 11

Other Views Temporary breakwater Immersed tube extended into CBTS Introduction Line 1 (Myriad MM Regular pt. 22, Line Spacing pt. 28) Introduction Line 2 Introduction Line 3 22/06/2010 Page 12

Other Views TEMPORARY BREAKWATER For forming more sheltered space to north of CBTS Cannot be justified as It requires additional temporary reclamation; and Preferred scheme requires no additional moorings to be moved out of CBTS IMMERSED TUBE EXTENDED INTO CBTS Similar extent of mooring area affected A significant section of existing breakwater must be removed to float units into place 22/06/2010 Page 13

Part 2 Design Development Introduction Line 1 (Myriad MM Regular pt. 22, Line Spacing pt. 28) Introduction Line 2 Introduction Line 3 22/06/2010 Page 14

Cross Harbour Section SCL IMMERSED TUNNEL FAIRWAY Gas Main BRIDGE PROTECTION FENDERS SCL ALIGNMENT Cross Harbour Tunnel LIMIT OF DREDGING FOR IMT TUNNEL PROTECTION LAYER CBTS CUT & COVER SECTION IMMERSED TUNNEL SECTION CWB BREAKWATER IMMERSED TUNNEL SECTION CUT & COVER SECTION MARINE TRAFFIC FAIRWAY 22/06/2010 Page 15

Scheme Presented in Previous Forum Introduction Line 1 (Myriad MM Regular pt. 22, Line Spacing pt. 28) Introduction Line 2 Introduction Line 3 22/06/2010 Page 16

Westerly Alignment - Option 2 TS3(E) & TS3 (W) Completed Tunnel Tunnel Structure Completion of SCL from SVB 22/06/2010 Page 17

Westerly Alignment - Option 2 To be completed after CWB construction TS3(E) & TS3 (W) Completed Tunnel 22/06/2010 Page 18

Westerly Alignment - Further Opportunities for Earlier Completion Can works in this area be completed earlier? TS3(E) & TS3 (W) Completed Tunnel 22/06/2010 Page 19

Westerly Alignment - Further Opportunities for Earlier Completion Requirements for Earlier Completion Need to provide sufficient navigation channel and work space in CBTS Proposed revised temporary reclamation and mooring arrangement have to be accepted by concerned stakeholders Some additional moorings (compared to CWB) may need to be relocated outside CBTS Timely authorization of SCL 22/06/2010 Page 20

Developments Since Previous Forum Hung Hom Landfall Essentially as presented at Forum No.1 Causeway Bay Typhoon Shelter Extensive liaison on integration with Central Wanchai Bypass Extent of SCL works to be carried out by CWB agreed Discussion with Stakeholders, Marine Department and Highways Department on Marine construction access Mooring provisions Mitigating impacts on RHKYC operations 22/06/2010 Page 21

Causeway Bay Typhoon Shelter - Further Option development 22/06/2010 Page 22

SCL Works to be Constructed Under CWB Project SCL Tunnel by SCL Project SCL Tunnel by CWB Project To Hung Hom Station Existing Permanent Seawall Proposed Extent of SCL Tunnel to be Constructed by CWB Area of Temporary Reclamation Left by CWB Project at End of Stage 2 Police Officers Club / SVB Approx.160m Shatin to Central Link Causeway Bay Typhoon Shelter Central - Wan Chai Bypass (CWB) Original TS4 Revised TS4 Temporary Seawall to be Constructed after the Authorization of SCL Project Victoria Park Road 22/06/2010 Page 23

SCL Works with Causeway Bay Typhoon Shelter With CWB Stages 1 & 2 At End of CWB Stage 3 CAUSEWAY BAY TYPHOON SHELTER CAUSEWAY BAY TYPHOON SHELTER CWB TUNNEL LEGEND COMPLETED TUNNEL BY CWB BY MTRC TEMPORARY SEAWALL With CWB Stage 4 Following CWB Completion Final SCL Section Completed 18 Months After CWB Works CAUSEWAY BAY TYPHOON SHELTER CAUSEWAY BAY TYPHOON SHELTER CAUSEWAY BAY TYPHOON SHELTER CWB TUNNEL No additional moorings to be relocated out of CBTS Exploring potential for previously affected PMA moorings to return to CBTS on completion of CWB works 22/06/2010 Page 24

Minimising Reclamation - Causeway Bay Typhoon Shelter Introduction Line 1 (Myriad MM Regular pt. 22, Line Spacing pt. 28) Introduction Line 2 Introduction Line 3 22/06/2010 Page 25

Temporary Reclamation at Causeway Bay Typhoon Shelter Existing breakwater to be removed and then rebuilt after tunnel construction completed Temporary seawall cope line Temporary piles required for reprovisioning of Royal Hong Kong Yacht Club operating jetty. (Exact location to be agreed with the Yacht Club) Temporary rock bund to provide transition between temporary seawall / breakwater wall and existing breakwater Temporary wall Temporary seawall cope line Interface between CWB and SCL temporary reclamation 22/06/2010 Page 26

Cross Section to North of Breakwater Temporary reclamation width 62m (Approx.) 20m (approx) 20m (approx) Reinstatement to existing seabed level after tunnel construction completed Sea level Original sea bed Dredge level SCL Tunnel Temporary wall 22/06/2010 Page 27

Construction through Breakwater Stage 1 Causeway Bay Typhoon Shelter Temporary seawall Existing breakwater Causeway Bay Typhoon Shelter 92m approximately Cut-and-cover tunnel Immersed tube tunnel Mean sea level Existing CBTS North Breakwater Infill with mass blocks (no dredge) C&C tunnel to be constructed Temporary seawall Temporary wall 22/06/2010 Page 28

Reprovisioning of Royal Hong Kong Yacht Club Operating Facilities REPROVISIONED RHKYC FACILITIES TEMPORARY JETTY (POSITIONING TO BE AGREED WITH RHKYC) 22/06/2010 Page 29

Minimising Reclamation At Hung Hom Landfall Introduction Line 1 (Myriad MM Regular pt. 22, Line Spacing pt. 28) Introduction Line 2 Introduction Line 3 22/06/2010 Page 30

Hung Hom Landfall Cut & Cover Tunnel To Hung Hom Station 20m approx. 93m approx. 20m approx. International Mail Centre Hung Hom Bypass Temporary works area Freight Pier Cut-and-cover tunnel 20m approx. 62m approx. 20m approx. Immersed tube tunnel 22/06/2010 Page 31

Temporary Reclamation at Hung Hom Longitudinal Section Fill and armour protection layer on tunnel to match IMT Extent of cut-and-cover section dictated by requirement to avoid underwater blasting of rock Cut-and-cover section Existing seawall to be removed and rebuilt Rock head Proposed SCL track level Existing fender pile to be removed and rebuilt after construction 22/06/2010 Page 32

Realigned Fender Piles NEW FENDER PILES EXISTING FENDER PILES PILES TO BE REMOVED HUNG HOM BYPASS FENDER PILES TO BE REINSTATED REALIGNED FENDER PILES 22/06/2010 Page 33

Reinstatement of Freight Pier To Hung Hom Station International Mail Centre Hung Hom Bypass Freight Pier Part of freight pier to be demolished 22/06/2010 Page 34

Summary Reclamation Requirements PERMANENT Relocated fender piles TEMPORARY HUNG HOM STATION Hung Hom landfall Relocated fender piles LOCATION APPROXIMATE AREA Hung Hom Landfall 1.0 Ha Causeway Bay Typhoon Shelter/ Adjacent to Breakwater Royal Hong Kong Yacht Club Jetty 2.2 Ha RHKYC jetty CBTS EXHIBITION STATION ADMIRALTY STATION 22/06/2010 Page 35

Conclusions There is a clear and present need for the SCL to cross the harbour This should follow the Western alignment parallel to the Cross Harbour Tunnel Construction will be by Immersed Tube / Cut-and-cover methods Reclamation will be required but this has been minimised 22/06/2010 Page 36

Way Forward Complete Cogent and Convincing Materials Report Gazette the SCL upon completion of the preliminary design and first round of public consultation Continue liaison with key interfacing stakeholders 22/06/2010 Page 37