Foundation instruction manual. 99 ft² (9,2m²)Grillkota

Similar documents
Underground Exhaust System

MACHINE-LAY Installation Manual

Gravity Wall. A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures

Installation Guidelines

stone oasis collection oasis circle patio (diameter ) instruction guide

Porcelain Paver Installation Guide

HOW TO INSTALL PATIOS AND WALKWAYS STEP 2 STEP 1. For all Patios and Walkways. The base is the most important step in your patio and walkway projects.

HOW TO INSTALL PATIOS AND WALKWAYS STEP 2 STEP 1. For all Patios and Walkways. The base is the most important step in your patio and walkway projects.

STRAIL level crossing systems & STRAILastic track damping systems

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

SAND INSTALLATION GUIDE

Installation Manual. Bigfoot Systems Inc. EM

Figure Inlet protection (Source: Minnesota DOT)

ASSEMBLY AND OPERATING MANUAL LTW SLIDE RAIL SYSTEM - Type PV

GROUNDtrax GROUNDGRIDZ

Bio-Sand Filtration Filter Casting Instructions

EZ BASE. Paver Base System ECHNICAL DATA SHEET TECHNICAL DATA SHEET TECHNICAL DATA SHEET TECHNICAL DATA SHEE UPDATE APPLICATIONS PROPERTIES

SECTION PIPE INSTALLATION

Hardscaping Installation Manual

378 - POND NATURAL RESOURCES CONSERVATION SERVICE CONSERVATION PRACTICE SPECIFICATION I. SCOPE

CONSTRUCTION SPECIFICATION FOR CONCRETE UNIT PAVERS

TRUEGRID Permeable Paver Technical Specifications

RUSTIC FIRE PIT SIENNA QUARRY GRAY TAN AUTUMN BLEND.

ASSEMBLY AND OPERATING MANUAL LTW SLIDE RAIL SYSTEM - Type FP

Instructions for 12 and 15 IGT systems (12 pictured)

PaveDrain Installation Manual. Table of Contents. Hand-Placement of individual PaveDrain Units. PaveDrain End Cap

STRAIL - installation instructions. Subject to technical changes / December STRAIL level crossing systems & STRAILastic track damping systems

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

Amendment -1. Date: NIT No. RECPDCL/CSR/CWC/ /3368 dt:

Water for the World. 7 y

PROVEN 15/TM1500 FOUNDATION INSTRUCTIONS

innostrail - installation instructions Subject to technical changes / January 2010 STRAIL level crossing systems & STRAILastic track damping systems

CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS

Mix and lay concrete tutor notes

4 EXTREME FOUNDATION PANELS

How To Construct a Ferro Cement Tank

36" CRESTONE FIRE RING

SEMPLICE OUTDOOR FIREPLACE KIT

CRESTONE STRAIGHT FIRE PIT SKU:

Installation Instructions

CONCRETE FOOTINGS AND WALLS Job Ready Checklist

SECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS

Sanitation Marketing Toolkit MANUAL FOR PRODUCTION AND INSTALLATION OF POUR-FLUSH LATRINES

ASHWELL FIRE PIT SIENNA QUARRY GRAY TAN AUTUMN BLEND. Plan Date: June 2016

TOWN OF LAFAYETTE SPECIFICATIONS FOR HIGHWAY CONSTRUCTION. June 1984

Appendix 4. Bills of Quantities

GRAVITY RETAINING WALL TECHNICAL MANUAL

Construction Procedures

Garden WallScape Installation Guide

Anchorplex retaining wall construction guide

28 BELGIAN WEDGE FIRE RING

Vitripiazza Installation Guide

BELMURO WALL SYSTEM INSTALLATION GUIDE

Estimate FOR THE SEPTIC TANK

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3

CONTENTS. Cellular Confinement System INTRODUCTION MATERIALS Multi-Cell Fill... 2

State of Nevada Department of Transportation Materials Division

GUIDELINE FOR PLANTED INFILL INSTALLATIONS. Please read prior to installation, and have proper equipment and safety precautions in place.

Every effort has been made to accurately represent the colors. However, the colors may vary slightly due to the concrete manufacturing process or

CONCRETE SLABS Job Ready Checklist

1.20. Technical Data. Rigidly Laid with Raised Kerb Edge SLABS.

Construction Procedures

CIVIL WORKS Mahesh G. Nair

Application Guide for MasterTop dry shakes. MasterTop 105. February 2016 Page 1 of 15

NOVEMBER 2016 GRANDWALL. retaining walls installation guide

Retaining Wall Products

Conergy SolarFamulus II

WARNING- THIS EQUIPMENT IS DESIGNED FOR ADULTS ONLY. ONLY HEALTHY PEOPLE AGES 13 AND UP SHOULD USE THE EQUIPMENT.

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES

SECTION 02215BP TRENCHING AND BACKFILLING

Construction Equipment. Doosan Hydraulic Breaker. HB series

HUITEX GEOCELL INSTALLATION MANUAL

Application Guide for MasterTop Dry Shakes MasterTop 200

Assembly and Installation Instructions Grease Separator KLsepa.pop

De Montfort Mark 7 Incinerator (Flatpack)

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

Guidelines to installing the ACO Sport range of products

MSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS

Construction Specification for Concrete Unit Pavers

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

Bio-Sand Filtration Filter Construction Guidelines

ROAD AND RAILWAY CONSTRUCTION

Commonwealth of Pennsylvania PA Test Method No. 507 Department of Transportation October Pages LABORATORY TESTING SECTION. Method of Test for

Innovative products for road construction and landscaping. landscaping. For cost-effective securing and maintenance of road verges.

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

Description Unit Quantity Rate Kshs. Amount Kshs.

Specification Guide and Installation Overview

SECTION STRUCTURAL EXCAVATION FOR STRUCTURES

INSTALLATION MANUAL IN-GROUND

Silva Cell. Silva Cell Two-Deep Installation Instructions. Helping Trees Live in the Urban Environment

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

Building. Anchorplex. Retaining Wall Systems

SECTION DECORATIVE METAL AND GLASS RAILING

C. Foundation stabilization for pipe and utility structures.

Handbook 2: Working to keep District roads in good condition

Fast drying and setting cement for floor screeds (24 hours) hydraulic binder for shrinkage - compensated screeds

LAMINATE GENERAL INSTALLATION INSTRUCTIONS FOR ANGLE-TO-ANGLE FLOORING

LAMINATE GENERAL INSTALLATION INSTRUCTIONS FOR DROP LOCK FLOORING

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3

Instructions for 12 IGT system

Transcription:

Foundation instruction manual 99 ft² (9,2m²)Grillkota

Foundation plan 6-in 8-in Seite 2

Foundation plan 6-in 8-in Seite 3

Construction of a concrete foundation Fig. 1 fig.1 Stake out the areal of where the foundation shall be placed. (Use the Foundation plan frome side 2.) Fig. 2 fig.2 Dig up around 12-16in (30-40cm) of soil, depending on the soil structure. Fig. 3 fig.3 Place the tubes as specified on page one of the manual. (see fig.) Seite 4

Construction of a concrete foundation Fig. 4 fig.4 Fill the pit with (0-5 granulation) gravel. The gravel should be level with the surface once the gravel has been compacted. fig.5 Now build the wooden framework. (About 6in (15cm) high) Support these from the outside so that it doesn't break appart.measure the diagionals.place a pipe approx. 6in (15cm) away from the edge of the framework for potential electrical power supply. Fig. 5 Fig. 6 fig.6 Lay builders film (polythylene) onto the gravel to prevent entrapped moisture in the concrete foundation. Seite 5

Construction of a concrete foundation Fig. 7 fig.7 Cut out a reinforcement mat (Q131) to size. Fill the pit half way with concrete (C 25/30) and place the reinforcement mat within. Fig. 8 fig.8 Now fill up the frame uptp the edge with concrete. Compact and level out the concrete surface. Fig. 9 fig.9 After approx. seven days the concrete should be solid enough for further construction. (Depending on weather conditions). Cover the foundation with either tarpaper or put down builders film during assembly. Minor hight differences may be corrected during construction, however major differences may affect the stability of the Kota which could invalidate the warranty. Seite 6

Construction of a foundation using paving stones Fig. 10 fig.10 Stake out the areal of where the foundation shall be placed. Fig. 11 fig.11 Dig up around 12-16in (30-40cm) of soil, depending on the soil structure. Fig. 12 fig.12 Place the tubes as specified on page one of the manual. (see fig.) Seite 7

Construction of a foundation using paving stones Fig. 13 fig.13 Fill the pit with gravel (0-5mm granulation). Once the gravel has been compacted it should be level with the ground. Using a flat bladed shovel dig a groove of approx. 5in (12cm) depth for the edging stones. Fig. 14 fig.14 Set the 20cm edging stones into concrete making sure that they protrude 10cm out of the ground. Measure the diagonals and check drying times. Place a pipe approx. 6in (15cm) away from the edge of the frameworkfor potential electrical power supply. Seite 8

Construction of a foundation using paving stones Fig. 15 fig.15 Fill the area with rubble or smaller stones so that after compressing you still have 5cm to the upper edge of the edging stones. Even out the area. Fig. 16 fig.16 Lay out the area with 2.3in (6cm) thick paving stones. Compact the paving stones by using a vibration compactor 220-280Ib (100-130kg) and a rubber plate. Do this until the paving is flush with the edging stones. Fill the gaps and joints with Sand. Minor hight differences may be corrected during construction, however major differences may affect the stability of the Kota which could invalidate the warranty. Seite 9

Construction of a strip foundation Fig. 17 fig.17 Stake out the areal of where the foundation shall be placed. Fig. 18 fig.18 Dig out the outer frame approx. 31,5-35,5in (80-90cm). (appox. 12in (30cm) wide). In the area of the center struts approx. 12in (30cm). lay the pipes as shown in the foundation instructions. Seite 10

Construction of a strip foundation Fig. 19 fig.19 Fill the excavations with earth-moist concrete (C25/30) leaving a 2in (5cm) gap to the edge of the surface. Put in 0,4in (10mm) reinforcing rods in various hights. fig.20 Put the concrete blocks in the moist concrete so that they protrude 4in (10cm) above the ground. Make sure the surface is even. Place the enforcement rods into the blocks and fill these with concrete. The foundation should be ready for further construction within seven days. (Depending on weather conditions). Fig. 20 Minor hight differences may be corrected during construction, however major differences may affect the stability of the Kota which could invalidate the warranty. Seite 11