Unit 2 Primary Containment Vessel Internal Investigation

Similar documents
Primary Containment Vessel Internal Investigation, Sampling and Analysis

Advanced Technologies for Fuel Debris Retrieval towards Fukushima Daiichi Decommissioning

Research and Development Programs for Decommissioning of Fukushima Daiichi Nuclear Power Station

WM2015 Conference, March 15 19, 2015, Phoenix, Arizona, USA

Overview of IRID R&D -Focusing on Debris Investigation-

IRID Annual Research Report 2015

Current Status and Challenges at Fukushima Daiichi Decontamination and Decommissioning

R&D for Fuel Debris Retrieval

Estimation of current status inside RPV and PCV at Fukushima daiichi NPS

OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D

F, 3 Toyokaiji Building, Nishi-Shimbashi, Minato-ku, Tokyo , Japan Published: March 2016

Technical Strategic Plan for Decommissioning of the Fukushima Daiichi. Nuclear Power Station of. Tokyo Electric Power Company Holdings, Inc.

Annual Research Report

The Soundness of Unit 4 Reactor Building and Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station

Importance of Innovation for D&D at Fukushima Daiichi NPS

Current Situation of Fukushima- Daiichi Nuclear Power Plants and Difficulties in the Defueling Plan

4. Current Status (1) Fukushima Daiichi Nuclear Power Station

Approaches to the decommissioning and contaminated water management for Fukushima Daiichi Nuclear Power Station

Topics Fukushima 15 September 2015 No.70

R&D of nuclear decommissioning under an integrated management sy

Replacement Works for the Steam Generator and the Reactor Pressure Vessel Upper Head

The 4th Progress Report

Annual Research Report 2016

Side Event of IAEA General Conference. Severe Accident Analyses of Fukushima-Daiich Units 1 to 3. Harutaka Hoshi and Masashi Hirano

INTRODUCTION IN FUKUSHIMA WATER LEAK PROBLEM

Unit 4. Storage and handling. Fuel debris removal. Scenario development & technology consideration. Design and manufacturing of devices / equipment

Implementation Plan of the measures to be taken at Fukushima Daiichi Nuclear Power Station designated as a Specified Reactor Facility (outline)

Unit 4. Storage and handling. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration

Expert Panel on Monju Decommissioning 6 th March 2018

Recommendations are based on validity of above assumptions.

R&D activities related to the fuel debris retrieval from the Fukushima Daiichi NPS

FUKUSHIMA DAIICHI BWR REACTOR SPRAY AND FEED WATER SYSTEMS EVALUATION FOR EARLY FAILURE Dean Wilkie

150MM FREE STANDING WOOD FIRE FLUE KIT MKIII INSTALLATION INSTRUCTIONS

Fukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami

Examination into the reactor pressure increase after forced depressurization at Unit-2, using a thermal-hydraulic code

150MM FREE STANDING WOOD FIRE FLUE KIT MKIII INSTALLATION INSTRUCTIONS

150MM FREE STANDING WOOD FIRE FLUE KIT MKIII INSTALLATION INSTRUCTIONS

Decommissioning of Dairyland Power s Lacrosse Boiling Water Reactor

Efforts to Decommission the TEPCO Fukushima Daiichi Nuclear Power Station

Specification (Summary version for reference)

NUCLEAR. Nuclear Reactor Pressure Vessel Seals

Overview of the Disaster Situation and the Restoration Condition at Fukushima Daini Nuclear Power Station

Lessons learned from ongoing decommissioning project of Fugen NPS

Unit 1. Unit 2. Unit 3. PCV gas phase temperatures (recent quarter) * The trend graphs show part of the temperature data measured at multiple points.

Strategy of the decommissioning of Fukushima Daiichi Nuclear Power Station and revitalization movement of the Hamadori

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

Efforts for the restoration at Fukushima Daiichi Nuclear Power Plants

PIP PCEPA003 Process Analyzer System Field Installation Guidelines

Nuclear Damage Compensation & Decommissioning Facilitation Corporation (NDF) and Strategic Plan for Decommissioning of Fukushima Daiichi NPS.

Unit 4. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration. Design and manufacturing of devices / equipment

Fukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka

COFRENTES UNDERVESSEL PROJECT IN RFO 16 (2007) [ Replacement of all the CRDH undervessel piping]

Unit 4. Storage and handling. Fuel debris retrieval. Storage and handling. Scenario development & technology consideration

UNIVERSITY OF ROCHESTER ENVIRONMENTAL HEALTH & SAFETY

Immediate Countermeasures

Maintenance Technologies for SCC which Support Stable Operations of Pressurized Water Reactor Power Plants

MVV ENVIRONMENT DEVONPORT SEPTEMBER 2017 OUTAGE MECHANICAL WORKS SPECIFICATION.

Information on Status of Nuclear Power Plants in Fukushima

Mid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Units 1-4, TEPCO Digest Version

Information on Status of Nuclear Power Plants in Fukushima

UK ABWR - NEW NPP DESIGN FOR UK

Information on Status of Nuclear Power Plants in Fukushima

The EPR Reactor: Evolution to Gen III+ based on proven technology. Andrew Teller, Senior Technical Advisor, AREVA

Progress Status Classified by Countermeasures

Unit 4. Storage and handling. Fuel debris removal. Scenario development & technology consideration. Design and manufacturing of devices / equipment

Immediate Countermeasures

Information on Status of Nuclear Power Plants in Fukushima

Conergy SolarFamulus II

NEW TREATMENT CONCEPT FOR STEAM GENERATORS- TECHNICAL ASPECTS

Revised Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima

15 April 2015 Nuclear Regulation Authority, Japan. 1. Overview

Berkeley Boilers Project. Studsvik Symposium April 2014

Accident Progression & Source Term Analysis

h Installation Manual

West Valley Demonstration Project. Project Update

Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station

Mechanical Structure Design Features of the KALIMER-600 Sodium-cooled Fast Reactor

The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations

Major Influential Issues on the Accident Progressions of Fukushima Daiichi NPP

Installation Instructions

AREVA: Experience in Dismantling and Packing of Pressure Vessel and Core Internals

Unit 4. Storage and handling. Storage and handling. Fuel debris retrieval. Scenario development & technology consideration

Information on Status of Nuclear Power Plants in Fukushima

Results of the Sixth Soundness Inspection of Unit 4 Reactor Building at Fukushima Daiichi Nuclear Power Station

Installation Manual For Conical Tanks. INSTALLATION and MAINTENANCE INSTRUCTIONS FOR CONICAL TANKS

IRID Annual Research Report

Fukushima Daiichi Decontamination and Decommissioning : Current Status and Challenges. Alios Iwaki Performing Arts Center August 6, 2018.

NRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station

Outline of New Safety Standard (Design Basis) (DRAFT) For Public Comment

Information on Status of Nuclear Power Plants in Fukushima

Electrical Isolation

Fukushima Daiichi Nuclear Power Station Unit No.1

Passive Heat Removal System Testing Supporting the Modular HTGR Safety Basis

2. Roadmap towards Restoration from the Accident

NDE SOLUTIONS INTERCONTRÔLE NONDESTRUCTIVE EXAMINATION

Mid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Station Units 1-4, TEPCO

TRANSPORTATION AND OTHER DAMAGE

Transcription:

Unit 2 Primary Containment Vessel Internal November 30, 2017 Tokyo Electric Power Company Holdings, Inc.

1. Conditions inside the Unit 2 PCV According to accident development analysis, it is assumed that part of the melted fuel fell to the plenum at the bottom of the Reactor Pressure Vessel (RPV) or onto the pedestal, with some still remaining in the core. PCV Internal January, March 2012 Muon measurement suggests that most of the fuel debris is at the bottom of the RPV. FW CS Muon measurement suggests that there is fuel on the outer periphery of the core X-53 penetration It is assumed that there is a hole either at or near the center of the RPV based on the conditions of the surrounding CRD observed during the PCV Internal and from the damage seen to grating. X-6 penetration Internal January, February 2017 CRD Rail August 2013 Past Area Steam was observed during the PCV Internal. 1

2. PCV Internal results in Jan. Feb. 2017 It was found that a part of grating was missing during the pre-investigation of the inside of the pedestal conducted through the guide pipe during the PCV Internal from January to February, 2017. Lower part of CRD CRD housing support brackets PIP cable CRD replacer Access to underground Slot Opening TIP guide pipe support Fallen grating Flat bar Slot opening CRD rail end Reference Inside Unit 5 pedestal Fallen object TIP guide pipe support Deformed grating Flat bar Area not complied with image processing TIP guide pipe Reference Photo taken during periodic inspection inside Unit 2 pedestal The TIP guide pipe and its supports were removed to inspect Unit 5. Images provided and processed by the International Research Institute for Nuclear Decommissioning (IRID) 2

3. Outline of the next PCV Internal Plan :Conditions under the platform where fuel debris may exist will be examined. opening Control rod drive (CRD) replacement rail Primary Containment Vessel (PCV) RPV area Camera hung down point It may not be possible to lower the investigation device due to conditions below the platform Control Rod Drive (CRD) Housing PCV penetration pipe used before (X-53 penetration) Approx. 7.2m PCV penetration pipe to be used (X-6 penetration) Area to be investigated Opening (slot) Basement 3

4. method (1/2) The telescopic device used in the PCV internal investigation conducted between Jan. to Feb. 2017 will be improved so that it can extend the length of the guide pipe and has a camera-mounted investigation device affixed to the end After the investigation device reaches the area above the missing part of the grating inside the pedestal, the camera will be lowered to examine under the platform. This improvement will enable the investigation device to reach the end of the guide pipe inside the pedestal, much further than during the investigation conducted in January~February, and allow conditions above the platform, such as the CRD housing, to be reexamined. Tip bend control box Isolation valve PCV Guide pipe (Φ110mm) Extendable concentric cylinders with different diameters PCV penetration pipe (X-6 penetration) Cable drum Alternative shield Cable Control Rod Drive Cable feeding machinery Long shot camera unit Telescopic top outline view Pan-tilt camera, light Outline of pre-investigation inside the pedestal (Telescopic investigation device) 4

4. method (2/2) Just like the PCV internal investigation conducted in January~February, a boundary will be formed as shown below by sealing the sliding part of the guide pipe with double O-rings and pressurizing the pipe with nitrogen to prevent gas inside PCV from leaking outside and affecting the surrounding environment during the investigation. A similar boundary will be formed for the sliding part of the cable as well. Dust concentration will be monitored during the operation to check that gas inside the PCV does not leak or affect the surrounding environment. Tip bend control box Isolation valve PCV Guide pipe (Φ110mm) Extendable concentric cylinders with different diameters PCV penetration pipe (X-6 penetration) Cable drum Control Rod Drive Pressured nitrogen Isolation valve (open) Inside of PCV Cable Boundary Pressured nitrogen Sliding part of guide pipe is sealed with O- rings. Sliding part of cable is sealed with O-rings. Sliding part of cable sealed Pan-tilt camera, lighting 5

5. Process flow plan Operation FY2017 December January February Advance preparation Training On site preparation PCV Internal PCV Internal 6