Retro-Commissioning for Existing Facilities

Similar documents
NEBBinar: Managing Building Performance through Commissioning. March 28, 2013

Technical Retro-Commissioning of Existing Buildings

Building Control Strategies That Work to Improve Your Energy Bottom Line

Retrocommissioning Investigation Report

Higher Value Commissioning

Commissioning & Retro-Commissioning Helping You Get the Most of Your Facilities

Retro-Commissioning in Hospitals

NEBBinar: Retro-Commissioning for Comfort and Energy Efficiency. August 21, 2013

Reducing Hospital Energy Use and Maintaining Savings. Glen Anderson, PE

Strategies for Persistence: Measurement and Verification. Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions

George Bourassa, National Director, Commissioning Services Robert Bucey, Program Manager RETRO-COMMISSIONING

A. The purpose of this section is to specify Division 23 responsibilities in the commissioning process.

Project Information. Measure Description

Identify and Quantify Mission-Critical Factors (How to Perform a Critical Audit) Neil Maldeis, Energy Solutions Engineering Leader, Trane

NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings. March 5, 2014

Introduction to Building Analytics

An Introduction to The Retro-Commissioning Process For Existing Buildings

City of Fort Collins Building Automation Systems Enhances Savings and Commissioning Efficiency Works Training

How LEED & The Retro-Commissioning Credits Produce Energy Savings. James Vallort Vice President Environmental Systems Design, Inc.

SMART HVAC & LIGHTING SYSTEMS. Savings From Two Major C&I End Uses

OAKDALE CHILLED WATER PLANT CAPACITY UPGRADES UI PROJECT INSTALL CHILLERS SECTION COMMISSIONING

Xavier Energy Initiative

Existing Building Cx: Processes & Results A Cultural Journey. Barry Abramson Senior Vice President Servidyne

Building Operator Certification Level I

Retro-Commissioning for Energy Efficiency

Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619

Building Commissioning, Energy Efficiency & Building Automation Systems

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing.

Teague Research Center

Existing Building Commissioning (or Retro-Commissioning)

Monitoring-Based Commissioning: A Case Study in Higher Education. Janelle H. Griffin, PE, CCP, LEED AP

Commercial Retro-Commissioning Program Manual for 2015 SECTION 1

Persistence Tracking in a Retro-commissioning Program

Commercial Retro-Commissioning Program Manual for 2019 SECTION 1

Commissioning for the 2015 IECC Code. Lunch & Learn Presentation O Connell Robertson - TEMA March 10, 2016

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.

Pay Now or Pay Forever Commissioning the Design of Control System Software

KCAHE 2011 ANNUAL CONFERENCE LOW ENERGY HEALTHCARE DESIGN

Commissioning & Retro-Commissioning Meet Energy Code

Management Committee December 3, Johnson County Community College Retrocommissioning Report

Promulgation Details for 1 RCNY

Steps to Making Existing Commercial Buildings Become High Performance. Jim Bochat

FOUR YEARS OF ON-GOING COMMISSIONIONG IN CTEC-VARENNES BUILDING WITH A BEMS ASSISTED CX TOOL

Mission Critical Commissioning for Healthcare Facilities

SECTION TESTING, ADJUSTING, AND BALANCING FOR HVAC. B. Testing, adjustment, and balancing of refrigerating systems.

Absolute Energy Raters Commissioning Plan Outline Template

Chilled Water System Optimization

CHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM

Retrocommissioning Investigation Study of the Sheraton Chicago Hotel

Retro-commissioning and on-going commissioning 23 November 2016

Success with MEASUREMENT & VERIFICATION

Retrocommissioning: A Persistence Study

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

SKILLS INVENTORY FOR BUILDING OPERATORS

Can You Afford Not To Retro-Commission Your Facility In These Lean Times? Wednesday, October 3, :00pm 2:15pm

Retrocommissioning Within the U.S. Green Building Council s LEED for Existing Buildings (LEED-EB) Certification System

Three Case Studies of the Application of Energy Systems Optimization Best Practices for Automatic Demand Response

RETRO-COMMISSIONING: AN OWNER S LOOK AT THE TRUE COSTS AND RETURN ON INVESTMENT. Adam Renzi, PE

Energy Modeling Applications for Existing Buildings

Georgetown University New Science Center

FACILITIES MANAGEMENT

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL

The Benefits of Building Commissioning. Jay Cederberg, P.E. Energy Solutions Specialist

SECTION COMMISSIONING

SECTION COMMISSIONING

Building Controls Strategies Conference. Retro-Commissioning with BAS Overview. 10 March Steve Brown, CAP ESD Controls Team Leader

BEYOND O&M. Shawn Maurer SEDAC Building Energy Specialist. Smart Energy Design Assistance Center (SEDAC), University of Illinois at Urbana Champaign

CONSTRUCTION REQUIREMENTS

Monitoring-Based Commissioning Best Practices Award Welch Hall

CONTINUOUS COMMISSIONING OF SALT LAKE COMMUNITY COLLEGE SOUTH CITY CAMPUS

Steve Harrell, LEED AP, CEM, CxA SSRCx Dr. David Claridge, P.E. Energy Systems Lab, Texas A&M University

Introduction. Agenda. New and Existing Facilities. Cx Programs & Terminology. Building Commissioning. Commissioning. D.

Recommissioning Workshop

5/7/2012. Agenda. What is High Performance? Ensuring a Successful Transition to Sustainable, High-Performance Operations

Case Study for Fortune 500 Telecom: Retrofitting Pneumatic Controls for Energy Efficiency

Commissioning at NYP. Joseph Lorino, PE, LEED Corporate Director April 1, 2014

Improving the efficiency, occupant comfort, and financial well-being of campus buildings

05/14/2012 THE CRIME OF IMPROPER ENERGY MANAGEMENT AGENDA

201 Charlotte Street, Brisbane, Queensland

WHOLE BUILDING RETROFITS: A CONTRACTOR/SUPPLIER DEMONSTRATION

RE-COMMISSIONING BY: BERNARD (BERNIE) W. NELSON P. ENG., PE., LEED AP, CEM C.E.S. GROUP. <insert your logo here> Twitter hashtag: #psforum

You Can t Afford Discomfort. Dan Int-Hout Chief Engineer, Krueger Richardson, Texas

Cost Savings from Operational Energy Efficiency: A Case Study from WCSU. Tom Arnold Vice President, Energy Efficiency & Carbon Solutions

Karl Helmink, P.E., CEM Retrocommissioning Manager University of Illinois. Retrocommissioning Saving the Planet One Building at a Time

9/13/2011. Mark Hanicits, Director of Facilities and Safety, MetroSouth Medical Center. Terry Malloy P.E., Cxa, Project Manager, Teng & Associates

DUKE UNIVERSITY CONSTRUCTION STANDARDS

Recommissioning Energy Savings Persistence

ENGINEERING UPDATE WHITE PAPER: BUILDING PERFORMANCE METRICS. price-hvac.com. May 2013 Vol. 10

Commissioning Toolkit for In-House Commissioning of Small Buildings

ENERGY MODELING TOOLS: SOLUTIONS FOR CREATING A HIGH PERFORMANCE BUILDING. Presented by Neil Maldeis Energy Solutions Engineering Leader, Trane

Measuring Up. Tools for High Performance Building Performance. RESNET 2008 San Diego, CA February 20, 2008 Bill Spohn. Bill Spohn, testo, inc.

Intelligent. Powerful. Proven. usa.siemens.com/demandflow

B. System Design and Performance Requirements

Optimizing Central Chilled Water Systems

What to Expect in the Existing Building Commissioning Process

MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS

Energy Savings Audit

Air-Water Systems. Chilled Ceilings and Beams TROX USA. Principle of Operation. Radiant Effect on Occupants. Early 1980 s. Chilled Ceiling Panels

Commissioning for Energy Savings

Transcription:

Retro-Commissioning for Existing Facilities Tom Meyer Director, Technical Programs National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, Maryland 20877 (301) 977-3698 www.nebb.org tom@nebb.org

WELCOME! 2

Discussion Points What is Cx and RCx? Optimization of HVAC Systems Optimization of Control Systems Electrical System Evaluation and Improvement System Performance and Operations Evaluation Operator Instruction and Training 3

COMMISSIONING (Cx) 4

Flavors of Commissioning (Cx) New Construction Commissioning (NC- Cx) Retro-Commissioning (RCx) Ongoing/Continuous Commissioning 5

Defining Retro-Commissioning (RCx) Retro-Commissioning: The systematic process by which systems are tested and optimized to perform interactively to meet the current operational needs of the owner. This may include remedial design and construction to accomplish this goal. 6

Defining Retro-Commissioning (RCx) All forms of building commissioning share the same goals: Produce a building meeting the unique needs of its owner and occupants Operate as efficiently as possible, while providing a safe, comfortable work environment Operated and maintained by a well-trained staff or service contractor. 7

Cx vs. RCx Drivers Cx Owner Performance Requirements (OPR) RCx Current Facility Requirements (CFR) 8

Why is RCx Important? Commercial Buildings Year Built % of Building Stock Age 1960 to 1999 66% 2000 to 2003 9% 2004 to 2010 7% Taken from DOE 2010 data 9

How to improve Building Performance? Make what we have work through RCx Keep what we have working through Operations for Performance 10

Building Performance Building Performance is dependant upon 4 legs of the stool Take one away and you have an unstable building 11

Building Performance What s not working? Commissioning Most buildings are not working correctly when they are turned over to the owner Construction is driven by schedule and costs, not performance 12

Building Performance What s not working? Operations Most buildings do not measure performance so they do not improve Since performance is not measured, operators are not held accountable for performance 13

RCx Process Initial Site Review The Owner and the Cx provider survey the facility to determine the extent and purpose of the project. 14

RCx Process RCx Pre-Site Investigation Before beginning site investigation field work the Cx: Create RCx Plan Review existing documents Review utility use and costs (Energy Audit) Review maintenance management work orders Perform Management & Operator 15

RCx Process RCx Site Investigation The site investigation phase includes Cx Team work activities: Occupant interviews Change of use for occupancy and change of use from original design (CFR) Heat load study (if required) 16

RCx Process RCx Investigation and Analysis As issues are discovered the Cx analyzes each issue and associated causes and impacts: Analyze interaction between systems Create an issue report including: Description of the issue Recommend corrective action Estimated costs Estimated savings, payback and ROI 17

RCx Process RCx Corrective Actions The Owner decides which corrective actions implemented and when. Contract for remedial design Procure contractors or equipment Perform corrective construction 18

RCx Process Retro-Commissioning Retro-commission and optimize energy-using building systems: HVAC Systems HVAC Control Systems Lighting Systems Electrical Systems 19

OPTIMIZATION OF HVAC SYSTEMS 20

Report Cards Comfort Costs Energy Maintenance Reliability 21

Report Cards DIS - Comfort 22

Report Cards Costs Energy Maintenance Reliability 23

AIR SIDE PERFORMANCE ISSUES Mechanical Issues Maintenance Lowest possible filter drop 300 FPM or Less Low Pressure Drop Pleated Material Clean coils and condensate pans Clean fan blades Tight balanced fan belts Lubricated and adjusted dampers Seal all air leaks Annual sensor calibration and point checks 24

AIR SIDE PERFORMANCE ISSUES Mechanical Issues Air Balance Low Pressure Balance At least one grille should be 100% open Proportional Balance Cooling diversity no lower than 75% % AHU CFM to total of all Zone CFM Heating diversity no lower than 100% 25

AIR SIDE PERFORMANCE ISSUES Mechanical Issues Design Duct Taps Duct Transitions 26

AIR SIDE PERFORMANCE ISSUES Mechanical Issues Design Flex Duct Max Length 6 27

AIR SIDE PERFORMANCE ISSUES Mechanical Issues Design System Effect 28

WATER SIDE PERFORMANCE ISSUES Mechanical Issues Maintenance Clean coil tubes Clean strainers Correct suction pressure 12#-15# at pump suction No air in system (Auto vents) 29

WATERSIDE PERFORMANCE ISSUES Mechanical Issues Water Balance Low Pressure Balance Coil Valve Trains Pump Balance Valves Chilled Water Diversity no lower than 80% Hot Water Diversity should be 100% 30

WATERSIDE PERFORMANCE ISSUES Mechanical Issues Design Counter Flow CW Coil Coldest water enters at air leaving side of coil CW Return Cold Water CW Supply 31

WATER SIDE PERFORMANCE ISSUES Mechanical Issues Operation Running Multiple Pumps 2.0" Fan 2 1.3" 2.0" Fan 1 0.75" 900 CFM 1500 CFM Fan 1 Fan 2 PARALLEL FANS 800 CFM SERIES FANS 32

OPTIMIZATION OF CONTROL SYSTEMS 33

Things to Check Sequence of operation appropriate? Is it set up like it s supposed to be? 34

WATER SIDE PERFORMANCE ISSUES Control Systems Sequence of Controls Schedule Control CW Leaving Temperature / Chiller T >10 Lowest possible lift Condenser Water Temperature Normal Design 85 / 95 Intel Study Recommends 5 Above Wet Bulb» Cold water OK if lift is small or newer chillers 35

CONTROL PERFORMANCE ISSUES Control Systems Sequence of Controls Schedule Control Setpoints Occupied 75-78 Unoccupied 84-86 Dead Band Control Difference between cooling and heating action Dead Band 2-4 36

CONTROL PERFORMANCE ISSUES Control Systems Sequence of Controls VAV Supply Air Temp Reset Control Reset from terminal unit load Not average load but low or high select Supply Air Pressure Reset Control Make sure this does not fight temp control CW or HW Temp Reset Control Reset from valve position CW or HW Pressure Reset Control Make sure this does not fight temp control 37

CONTROL PERFORMANCE ISSUES Control Systems Sequence of Controls Air Side Economizer Control Verify Operation Db Control Run FPT Data Trend Analysis Room Temperature Supply Duct Temperature CW Differential Temperature Condenser Water Temperature 38

ELECTRICAL SYSTEM EVALUATION AND IMPROVEMENT 39

Systems Controls Lighting Plug Loads Process Loads 40

Report Cards Comfort Costs Energy Maintenance Reliability 41

Report Cards Comfort 42

Report Cards Costs Energy Maintenance Reliability 43

Process Perform a detailed electrical site investigation Deferred Maintenance Equipment Assessment Load Balance Equipment Thermal Image 44

ELECTRICAL PERFORMANCE ISSUES Electrical Systems Verify phase loading of panels, should be within 10% of each other (Move loads to balance) Verify power factor, should be greater than 0.87 (Install capacitors to correct) Perform infrared survey of breakers. Make sure no breaker is overloaded (Install larger breaker and wire) Perform power quality survey with a power quality meter data log 45

SYSTEM PERFORMANCE AND OPERATIONS EVALUATION 46

SYSTE M 47

Process Perform a detailed control system inspection Point to Point Verification Test Sensor Calibration Function Test Sequence Review 48

OPERATIONS Bad List Disable Schedule to get the space in temperature in the morning Disable or override setpoint reset to make it colder or hotter Override any automatic setpoint reset Override control point output with manual switch Allow deferred maintenance items to exist 49

OPERATIONS Good List Find the cause and fix it instead of reacting to symptom Document any temporary measures taken and change them back as soon as issue is resolved Measure performance often to see how you are doing Energy Comfort 50

OPERATIONS 51

OPERATIONS Collect Data Utility Bill or Submeter Data Analyze & Normalize Data Normalize for standard days per month Normalize for annual weather data 52

OPERATIONS Compare Data to Baselines Compare to last years data Compare to national data base (Energy Star) Report Results To Management, Operators and Occupants Make Corrections Verify Implementations Start the Process Over 53

Measurement Protocols ASHRAE PMP Best Practice Guide Energy Use Performance Water Use Performance IEQ Performance Lighting Performance Acoustic Performance Comfort Performance 54

OPERATOR INSTRUCTION AND TRAINING 55

Considerations Personnel Turnover 56

Task Assignment Considerations Right person for the right job? 57

Considerations Operator = building user? Building performance affected by users 40% 58

Real Training Considerations On the actual system, components and how it integrates into the building system 59

Considerations Solving service call systems without clearly understanding the ripple effect 60

Considerations As designed vs. As Operated 61

Considerations To what level should we train O&M staff? Basis of training How do the pieces fit together Cause and effect 62

Considerations Effective maintenance request system Users are less likely to fiddle around or selfhelp when an responsive maintenance system exists Chronic maintenance problems become visible allowing for proper fixes reducing user discomfort/dissatisfaction. Avoid possible higher repair/replacement/operating costs 63

Considerations If building performance is way off design projections it could be due to: Systems not properly designed Systems not properly installed Systems not properly commissioned Systems not properly operated/maintained Systems not appropriate for current use 64

THE HORIZON 65

The Horizon Water Energy and water nexus CBECS Revitalized Revision to include water consumption Emphasis on Commissioning Consolidation and Control Government Policy 66

CONCLUSION 67

QUESTIONS? 68

Retro-Commissioning for Existing Facilities Tom Meyer Director, Technical Programs National Environmental Balancing Bureau 8575 Grovemont Circle Gaithersburg, Maryland 20877 (301) 977-3698 www.nebb.org tom@nebb.org