SCR RETROFIT FOR NO X REDUCTION EXPERIENCES IN CHINA & POLAND TWO COUNTRIES WITH COAL AS DOMINATING FUEL SOURCE

Similar documents
Up gradation of Boilers to Implement New Pollution Norms

Managing the Catalysts of a Combustion Turbine Fleet

STEAG Energy Services LLC. Engineering and Consulting Services with a focus on the environment.

World Pollution Control Association 2018 KCP&L Seminar June 5-6, SCR Design and O&M Best Practices. Scott Hiedeman

Duke Energy Seminar September 3 5, 2008 Concord, NC

FCCU NO x Reduction - SCR Retrofit. October Vice President of Engineering KTI Corporation

SCR for NO x Control in Coal-fired Power Plants

YARA Environmental Technologies GmbH

Ammonia Injection and Mixing Systems 101

SCR-Catalyst Management. Dr. Dirk Porbatzki UTG / Catalyst & Oil Management

Controlling NOx and other Engine Emissions

NOx CONTROL FOR HIGH ASH COAL-FIRED PLANT 12 TH E C C R I A, 5-7 S E P T E M B E R , C A R D I F F, UK

Power-Cost Alternative De-NOx Solutions for Coal-Fired Power Plants

Reinhold Environmental Ltd.

Gas Cleaning by SCR and ESP

Reduction Systems and Equipment at Moss Landing Power Plant

GE solutions for NOx compliance and increased availability for WtE / Biomass plants

TruePeak TDLS200. NH 3 Slip Measurement. <Document Number> Copyright Yokogawa Electric Corporation <date/time>

Worldwide Pollution Control Association

Enhancing Capacity Empowering Nation. Technological Parameters in selecting systems to control emissions in Thermal Power Plants

De-NOx Concept to commissioning

Energy Production Systems Engineering

EXPERIENCE WITH DESIGN, INSTALLATION AND OPERATION OF A SCR UNIT AFTER A FCCU

Meeting New Environment Norms - Challenges and Possibilities. Presented by: A.K.Sinha General Manager NTPC Limited

Steinmüller Engineering Conference Modernization and Optimization of Flue Gas Cleaning Plants

ES Stationary SNCR TECHNOLOGY. NOx REDUCTION IN UTILITY & INDUSTRIAL BOILERS

German experience on compliance of environmental norms by thermal power generation companies

ESP and Fabric Filter Technology for Dedusting - Comparison and Optimization -

NO x Reduction at Consumers Energy Dan E. Karn Generation Station

Reinhold Environmental Ltd.

OMV INNOVATIVE ENERGY SOLUTIONS STRABAG ENERGY TECHNOLOGIES GMBH

TECHNICAL PUBLICATION

Tools for Optimizing Gas Turbine SCR Performance

Transactions on Ecology and the Environment vol 1, 1993 WIT Press, ISSN

Industrial Gas Analyzers in Applications Information

Low-Temperature SCR. Intelligent and Cost-Effective Regeneration without Excess Emissions. 1. Pollutant capture principle...408

SCR CATALYST PERFORMANCE UNDER SEVERE OPERATION CONDITIONS

FIRST APPLICATION OF BABCOCK-HITACHI K.K. LOW SO 2 TO SO 3 OXIDATION CATALYST AT THE IPL PETERSBURG GENERATION STATION

Optimal Design and Operation of SNCR System for a 150t/h CFB Boiler and Discussion on the Measurement of Flue Gas Components

nat Presentation Title ( Arial, Font size 28 ) Control of Sulphur Dioxide, Oxides of Nitrogen and Mercury Date, Venue, etc..( Arial, Font size 18 )

CORMETECH SCR CATALYSTS FOR COAL-FIRED GENERATORS

AQCS (Air Quality Control System) for Thermal Power Plants Capable of Responding to Wide Range of Coal Properties and Regulations

CEMENT GAS CLEANING AND COOLING SOLUTIONS

Recovery Boiler SCR - A Challenge and an Opportunity in Retrofit Cases

NTPC O&M Conference Performance and Optimization of Water Utilisation Increase of Existing Power Plants. Speaker Name; Tufani Ram 13-14/02/2013

Catalyst Pluggage Reduction for Roxboro U3

CFD-study of a 230 MWe coal fired boiler to predict the influence of secondary fuels on slagging, fouling, CO corrosion and NOx formation

Duke Energy Seminar September 3 5, 2008 Concord, NC

Worldwide Pollution Control Association

Tailor-made SNCR to Meet Future Emission Standards for Power Boilers

Monitoring and Optimizing Fuel Feed, Metering and Combustion in Boilers June 13, 2013

Gas Turbine SCR Performance Optimization and Management

Euan Evenson Praxair, Research and Development

Retrofit of Rodenhuize 4 power station: The Max Green and Cold Back-up-projects

Gas Flow How to Improve It to Enhance ESP, Boiler, FGD, SCR, SNCR Performance

Post-Combustion NOx Control - Program 73

Low Emission Water/Steam Cycle A Contribution to Environment and Economics. Peter Mürau Dr. Michael Schöttler Siemens Power Generation, (PG) Germany

Emission Challenges in Cement Making due to alternative Fuels

Oslo, February 17th, 2010

Our Realization POLAND

AIRHEATER FOR INDUSTRIAL BOILERS

Worldwide Pollution Control Association

NOx Reduction: Flue Gas Recirculation vs Selective Catalytic Reduction. Presented by Jason Jacobi October 28, 2015

Energy Efficiency: Best Practices Thermal Power Stations

SCR Retrofit Improves Performance

natcom burner solutions Advanced burner technology for stringent emissions requirements

Integrating ADAir Mixer Technology to Optimize System Performance with DSI Applications

PPC specializes in maximum efficiency air pollution control equipment using a variety of different

Ways to Improve Performance of Marginal ESP s

Duke Energy Seminar September 3 5, 2008 Concord, NC

Emissions Control Project

Control Device Technology

Gas Flow How to Improve It to Enhance ESP, Boiler, FGD, SCR, SNCR Performance

Combustion Optimization & SNCR Technology for coal fired power stations and retrofit experience

FULL-SCALE INVESTIGATIONS ON CO- FIRING OF STRAW

NEW TECHNOLOGIES IN COAL-FIRED THERMAL POWER PLANTS FOR MORE EFFECTIVE WORK WITH LESS POLLUTION

Application of Electrostatic-Fabric Integrated Collector for 660MW. Power unit of Coal-fired Boilers

Mercury Oxidation Across SCR Catalyst at LG&E s Trimble County Unit 1

SCR Control Strategy and CEMS for an Ultra-Low NO x Emitter

we focus on your process Systems Page 1

Field trip to Arnoldstein WTE facility Arnoldstein, Austria, December 19, by Werner Sunk

Minimizing Ammonia Consumption in DeNOx Plants In situ Laser Gas Analyzer LDS 6 Monitors NH 3 Slip in Real-time

Flue Gas Cleaning of Coal-fired Power Plant and SEC Technology. Shanghai Electric Power Generation Environment Protection Engineering Co., Ltd.

VarioClean - NO x. Nozzle lances and systems for gas denitrification

Flow Modeling for Chemical Processing

Acerra WtE plant plant block diagram MSW receiving section Combustion and flue gas cleaning

EFFECTIVE WAY TO BOOST YOUR UREA PLANT CAPACITY - REVAMPING OF FERTIL UNIT

CMI Energy Aftermarket Solutions

The Value Proposition of Circulating Fluidized Bed Scrubbing Technology. Robert Giglio Foster Wheeler Global Power Group

SCR and Zero-Slip TM Technology

Brian M. King P.E., Power & Industrial Services Corp. 821 NW Commerce Dr, Lee s Summit, MO ,

Your partner for the right solution

Diode laser analyser LS4000 Ammonia slip measurement for DeNOx process

Integrated production of liquid sulphur dioxide and sulphuric acid via a lowtemperature

PROJECT DESCRIPTION - GENERAL DATA OF THE PROCESS

Biomass Combustion Technology

High efficiency NOx control solutions for Power Plants

metals temperature limits.

Environmental Control Solutions

Sulfur Tail Gas Thermal Oxidizer Systems By Peter Pickard

Transcription:

SCR RETROFIT FOR NO X REDUCTION EXPERIENCES IN CHINA & POLAND TWO COUNTRIES WITH COAL AS DOMINATING FUEL SOURCE Abstract: The key focus of this paper are the following topics: solutions to retrofit an SCR system into an existing boiler with limited space; key requirements to ensure high performance and safe operation; comparison of honeycomb and plate type catalysts in a long-term perspective; anhydrous ammonia, ammonia water and urea, which reagent to choose; catalyst testing and optimized management to reduce operation costs. These topics are outlined in case studies of SCR systems in successful long-term operation. The market penetration of the SCR technology in these coal dominated countries reflects the fulfilment of the strict government requirements. The case studies specifically pay attention on the challenges of retrofitting a high performance DeNOx technology into a coal fired boiler during operation, with minimized boiler shut down period. They also highlight important design factors and technical solutions to ensure reliable operation with low maintenance needs and cost. Furthermore, a comparison of honeycomb and plate type catalyst is discussed to highlight the advantages and risks of each technology under long time operation. Special attention is paid on the impact on the overall plant behaviour and the reuse of old catalyst. In addition, Yara as one of the world largest ammonia/urea producer, will propose advantages and disadvantages of anhydrous ammonia, ammonia water and urea as reagent specifically for the SCR use. Special attention is paid to the operational aspects, such as handling and safety. Catalyst testing is key to ensure an optimized management strategy and as a result reduced operation cost. The paper will also examine the most important catalyst deactivation mechanisms and demonstrate strategies on how to remove these impacts to recover original plant performance. Authors Richard Budin richard.budin@yara.com Wolfgang Kurka wolfgang.kurka@yara.com Manfred Ryba manfred.ryba@yara.com

1. CASE STUDY LAZISKA (POLAND) INTEGRATING AN SCR IN THE 2 ND BOILER PATH 2010 an DeNOx retrofit project was started to ensure all 4 boilers (original build in 1969) of TAURON Wytwarzanie S.A. in Laziska (Picture 1) fulfil the NOx regulations before 2016. The boilers are fired with hard coal and the SCR High Dust technology was chosen as best solution in addition to the existing low NOx burner and OFA. As space is limited, the SCR was integrated in the 2 nd path of the boiler. To ensure the optimum temperature window for the catalyst the existing ECO was split into two parts and the reactor have been installed in between. The reactor design consider 2 original catalyst layers and ½ spare layer for future installation on top of the second layer. Each layer is further equipped with sonic horns to keep the catalyst clean. No steam blowers have been installed as plate type catalyst have been selected and hard coal is used as fuel. The integration of the SCR system was quite challenging as each boiler as split into 4 independent areas; front and back side as well as left and right side. As it can be seen in Picture 2 the integration of the catalyst was even more complicate as the boiler have 3 APH. One for the left, one for the right side and one for the ECO bypass which is n Picture 2 Picture 1 used to balance the overall temperature profile of the boiler. But in case of using the ECO bypass, a significant amount of flue gas is also not treated by the SCR system. Therefore the remaining flue gas stream need to be cleaned more efficient. As a result a complex control system have been applied to make sure the correct amount of ammonia is injected in each section of the boiler. The result is shown in below Graph 1 where a homogenous NOx distribution at boiler outlet have been demonstrated. Graph 1

Below Picture 3 visualize the retrofit of the SCR in the 2 nd boiler path. On the left side of the picture the original situation is shown. On the right side the layout after integrating the SCR reactor and ammonia injection system is indicated. The site erection period took about 6 months as major Boiler modifications have been performed, such as Cutting 2 nd boiler path and lowering bottom part Split existing ECO into 2 stages Reinforcement of steel structure Adding SCR reactor and catalyst Picture 3 During the first year of operation an abnormal increase of pressure drop have been detected. The increase over operation time was in an much higher extend then in reference cases and occurred in several steps. After a deep dive into the problem it was identified that periodically large amount of fly ash was falling down from the heat exchanger surface of the boiler on the top of the catalyst (Picture 4). This happened specially during fast load changes and was worsen by the fact that the boiler have no soot blowing system installed. As a countermeasure YARA developed (and patented) an ash particle screen system which can be installed on the top of the catalyst (Picture 5). With this solution we ensured a safe and continuously operation of the boiler within the promised parameters. Below Table 1 display the guarantee and actual performance. Picture 4 (before) Picture 5 (after) Table 1 This performance have now been fully demonstrated for years. Boiler 1 & 2 have already passed successfully the 3 years guarantee period. Boiler 3 is expected to follow within this year and Boiler 4 within 2018.

2. CASE STUDY FPG (CHINA) INSTALLING THE SCR ON TOP OF THE APH The first approach and target is to use the existing steel structure. Modifications may be required such as crating openings in the structure for flue gas duct penetrations or re-enforcing the existing structure for additional weights. Below pictures show an example where the SCR system was retrofitted into the existing boiler / APH structure without building new columns. After re-calculation and re-engineering some of the existing structure have been removed to give space for the flue gas ducts. In addition new structure for achieving the necessary strength and creating the necessary operation and maintenance platforms have been added (Picture 6). Further the existing beams have been reinforced by adding stiffeners and changing the H-beams to box-beams as it can be seen in the Pictures 7 and 8. Picture 6 All modification of the steel structure, the installation of the SCR reactor and remaining system were executed during normal operation of the boiler. YARA applies a special design for coal fired SCR systems which reduce the required space, but also reduce the risk of catalyst plugging. In this design the reactor, ammonia injection grid (AIG) and flue gas ducts are combined in one single equipment (Picture 9). This reduce the needed footprint. In addition less construction material is required which results in less new additional weight. The reactor with the related internals is further designed in modules which reduce the construction period. After finishing the main installation, the tie-in work was performed during the boiler overhaul period. This was scheduled for 4 weeks but could be finished in less than 3 weeks. Even the time schedule was very tight, safety & health was one of the highest priorities for the execution and the project was executed without any accident. The performance test demonstrated excellence performance as it can be seen in Table 2. The basis of this success is in a goo CFD modelling and the High Performance Ammonia injection System of YARA; as together with the catalyst these equipment are the heart of the SCR technology. Table 2 Pictures 7 and 8 Picture 9 The catalyst as main equipment to reduce the NOx emission and the AIG which ensures that the ammonia is well distributed and mixed with the NOx. Without an homogenous distribution, the catalyst could not perform his duty. For this reason, YARA developed an high efficiency AIG. The technology of this new design is a multiple nozzle grid for adjusting the ammonia flow individual for each sector according to the actual needs, combined with a static mixer system for high efficiency mixing of the ammonia with the flue gas but keeping pressure drop at a minimum.

The design is further considering the proper distribution of the ammonia into the flue gas with a minimum effect on the overall system pressure drop (typically below 10 Pa) as an important issue. This SCR was equipped with a plate type catalyst (Picture 10), but YARA also have good operation experience with Honeycomb catalyst (Picture 11). Both catalyst types can achieve the same performance, but having slightly different advantages and disadvantages. Depending on each case, YARA will choose the best catalyst type. One key characteristic for Indian applications is the erosion behaviour. Both catalyst types show sufficient erosion resistance as long as the flow design is proper done and the flow velocity is not too high. An critical impact on this behaviour is an high amount of erosive components in the fly ash (e.g. SiO2). This shall be taken into account during the overall SCR design. In case of steam blower use, it is very important to ensure that the steam is superheated. Otherwise severe catalyst erosion will occur. Below pictures show the Boiler Island before (Picture 12) and after (Picture 13) SCR retrofit. Picture 10 Picture 11 Picture 12 (before SCR retrofit) Picture 13 (after SCR retrofit) 3. SELECTION OF THE REAGENT YARA one of the world largest producer of nitrogen based products (such as ammonia and urea) offers all kind of reagent storage, preparation and supply plants. This include solutions for the use of Solid urea Urea solution Anhydrous ammonia Ammoniawater

Typically anhydrous ammonia is selected for larger consumptions due to logistic reasons, but having the disadvantage of being the most dangerous chemical out of the choices. The counterpart is the urea technology which is a total safe solution, but having the disadvantage of being typically the most expansive regent in terms of investment and operation cost. This paper will therefore focus on the ammonia water which provides a good compromise out of the above options. Ammonia water is easy to handle, safe and can be installed and operated with low operation cost. The storage of the aqueous ammonia is done by using a closed storage tank equipped with vacuum breaker and overpressure safety valve. In addition a gas seal tank is installed in case of an emergency situation. This system design avoids bad smelling and ensures the highest safety for the operator by applying a none pressure storage system (Picture 14). For the supply of the aqueous ammonia to the vaporizer pulsation free pumps are used. This is a big advantage compared to dosing pumps. For the control of the aqueous ammonia flow a FCV is used which ensures the quickest and most accurate response. Picture 14 The standard procedure is to heat up the dilution air by using an electrical heater and then evaporate the ammonia water by using a vaporizer. This needs a high amount of electrical energy which is very expensive in operation. To vaporize the ammonia water, YARA have developed a special technology to reduce the operation cost and prove this technology already in many applications all over the world. In this case only a small LP steam heater (optional) is required for a pre-heating of the dilution air above dew point. The final heating is done by using a gas/gas heater in the SCR reactor (Graph 2). Graph 2 With this solution the heat from the flue gas can be used and secondary energy consumption is avoided. As the temperature drop in the SCR system is typically less than 1 C the impact can be negligible. The same count for the pressure loss at is in the range of 1 Pa. 4. CATALYST MANAGEMENT YARA have the technology and long-time experience for plate and honeycomb type catalyst. As a result of our after sales service during the operation of the SCR systems YARA also know about the behaviour of the catalyst during commercial use. Based on this knowledge, YARA developed a Catalyst Management program consisting of re-use of old catalyst (regeneration and repair) and delivery of new one to reduce the operation cost. This regeneration technology is based on the following main benefits for the customer: reduces total operation costs dramatically avoids unnecessary raw material consumption avoids excessive generation of waste materials

YARA have the technology and long-time experience for plate and honeycomb type catalyst. As a result of our after sales service during the operation of the SCR systems YARA also know about the behaviour of the catalyst during commercial use. Based on this knowledge, YARA developed a Catalyst Management program consisting of re-use of old catalyst (regeneration and repair) and delivery of new one to reduce the operation cost. The technology is suitable for plate and honeycomb catalyst. The following example is a reference case for a 550 MW coal fired power plant (Taichung Power Station of TPC) which is equipped with a 6 mm pitch plate type catalyst. Target of the performed regeneration was to restore the catalyst activity to ensure the NOx removal performance and not exceed the guaranteed SO2/SO3 conversion rate. Further the removal of dust plugging shall reduce the pressure drop to minimize the power consumption on the IDF and therefore to reduce the operation cost of the Power Plant. In the first step the catalyst elements (boxes) have been removed from the modules and mechanically cleaned. This is very important as between the elements heavy dust deposit occurs and to ensure full performance with low pressure drop this plugging shall be removed. In the next step the catalyst was regenerated in a 2 step washing process including re-coating of the catalyst. Due to a dust removal step in the washing water, the water management could be optimized. The waste water was treated by the existing plant in the Power Station and had a similar characteristic as the air-pre heater washing water. After drying the catalyst it was re-installed and a performance test have been carried out. The below Table 3 show the test results - analysed by an government authorized 3rd party under design conditions. Table 3 The regeneration can be typically performed during the boiler overhaul period (about 3 weeks). The catalyst will be dismantled from the reactor and moved to the on-site regeneration equipment where the catalyst modules will be prepared for cleaning procedure. The space requirement is about 200 m2. It is not mandatory to have all space at one location. Setting up a proper logistic allows splitting the required space into several areas. Below table show an example for catalyst management of an 550 MW SCR in a coal fired boiler. The given cost are for one Layer catalyst replacement / regeneration. As it can be seen, the regeneration cost is about 50% of the cost compared to a new catalyst, considering the additional cost for dismantling and installation of catalyst are in both cases equivalent.