CONDENSATION INDUCED WATER HAMMER

Similar documents
Oil Sands Development in Canada by SAGD - Further Challenges to Improve Efficiency -

Improving Evaporator Reliability for Produced Water Re-Use in Northern Alberta SAGD Facilities

Analysis of the Presence of Vapor in Residual Heat Removal System in Modes 3/4 Loss-of-Coolant Accident Conditions using RELAP5

OUTLINE OF MIZUSHIMA LNG RECEIVING TERMINAL AND MAIN CHARACTERISTIC OF EQUIPMENT COST REDUCTION

SMR/1848-T21b. Course on Natural Circulation Phenomena and Modelling in Water-Cooled Nuclear Reactors June 2007

ANALYSIS ON NON-UNIFORM FLOW IN STEAM GENERATOR DURING STEADY STATE NATURAL CIRCULATION COOLING

Condensate Line Sizing for Gravity Returns from Steam Traps and Heat Recovery

2/24/2011. Energy Efficiency. Fluid Sealing Association. The Beginning. Fluid Sealing Association

Lessons Learned from an Unusual Hydrogen Reformer Furnace Failure

Downsizing a Claus Sulfur Recovery Unit

SECTION PLUMBING PIPING SYSTEM

Challenges in Industrial Waste Heat Recovery. Texas Technology 2006 Showcase Tony Dafft December 6 & 7, 2006

Flexible Operation. Integrating thermal power with Renewable Energy & Challenges. Y M Babu Technical Services, Noida

Quality, Sustainability and Business Efficiency Through Innovation & Good Engineering. Presented by Cameron Roberts, July 2017

Model Predictive Control of Once Through Steam Generator Steam Quality

Department of Mechanical Engineering. MSc/PGDip/PGCert in Energy Systems and the Environment. Specialist Modules

Groundwater Supply Development at Canadian Natural Resources Limited s In Situ Oil Sands Operations

AP1000 European 15. Accident Analysis Design Control Document

Energy Efficient. & Cost Saving. Continuous Boiler Blowdown Package Heat Recovery Systems. 20 Models from 1,200 pph to 50,000 pph Capacity

SUPERSTEAM USG LINE UNFIRED STEAM GENERATOR. Humidification. Sterilization. Pharmaceutical

is a paradigm shift in produced water treatment technology occurring at SAGD facilities?

ISPE NORDIC COP CLEAN UTILITIES SEPTEMBER Juha Mattila Senior Product Manager STERIS FINN-AQUA, FINLAND

Jared Wynveen, P. Eng McDaniel & Associates Consultants Ltd. 2014

Shutdown and Cooldown of SEE-THRU Nuclear Power Plant for Student Performance. MP-SEE-THRU-02 Rev. 004

2016 Sluggin It Out Conference Mike Verney Associate

Consolidated Edison Company of New York Water Hammer Predictor Model Update

PCM Vulcain. High Temperature Package. Artificial lift for enhanced oil recovery

Boiler Energy Efficiency & Overview of Economizers

OFI Testing Equipment Retort Analysis Instructions Part #s ,14,80 Page 1 of 4 RETORT ANALYSIS

Production Engineering ALI NOORULDEEN

SECTION 7.0 WATER SOURCE MANAGEMENT TABLE OF CONTENTS

GEOTHERMAL POWER PLANTS FOR MEDIUM AND HIGH TEMPERATURE STEAM AND AN OVERVIEW OF WELLHEAD POWER PLANTS

CONDENSATION IMPLOSION EVENT IN STRATIFIED WATER- STEAM SYSTEM

STEAM TURBINE-GENERATOR & AUXILLIARY SYSTEMS Presentation by: RANA NASIR ALI General Manager, Power Plants Projects, at PITCO November 02, 2017

Modeling Techniques for Increased Accuracy

Maxi-Therm Since 2002, throughout North America, Maxi-Therm has been manufacturing innovative packaged solutions for informed specifiers.

GROUSE GROUSE IN SITU OIL SANDS PROJECT. Proposed Development Plan. Plain Language Project Summary

VVER-440/213 - The reactor core

PMAX Cycle Isolation Module Greg Alder

JAPAN CANADA OIL SANDS LTD. HANGINGSTONE DEMO PROJECT 2004 Presented on Monday, March 7, 2005 Presentation Outline

Boiler Efficiency Testing. To understand the operation of a fire tube boiler To determine the operating efficiency of the boiler

2015 IPC Sections 308 through 316

Designing wet duct/stack systems for coal-fired plants

Appendix B. Glossary of Steam Turbine Terms

Water and Energy Efficiency Challenges in Oil and Gas Development

Steam Cycle Chemistry in Air-Cooled Condensers. NV Energy ACC User s Group * November 12-13, 2009 Andrew Howell * Xcel Energy

Introduction to Condensate Recovery

Corrosion in GASCO Habshan CBA Units and its mitigation

Heavy Oil Systems Experience and expertise to enhance productivity

Draft proposals for Test methods for close-coupled solar water heating systems - Reliability and safety

6.1 Introduction. Control 6-1

Fouling Resistant Once Through Steam Generators (OTSG)

4th Class Power Engineering (PEN) Curriculum Mapping

System & Equipment Checkout Procedure Client Name Plant Location

Proxy Model Based on Butler s SAGD Theory

Grand Composite Curve Module 04 Lecture 12

2012 IPC Sections

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS

Example Pressurized Water Reactor Defense-in-Depth Measures For GSI-191, PWR Sump Performance

Cycle Isolation Prioritization and Organization

UTILITIES DISTRIBUTION EXPANSIVE FORCES STEAM SESSION 11 J. MICHAEL CARSON PE

Suitable for use in a variety of fluid systems.

Piping Vibration Risks and Integrity Assessment

ENGINEERING MECHANICS 2012 pp Svratka, Czech Republic, May 14 17, 2012 Paper #17

R13 SET - 1 '' ''' '' ' '''' Code No: RT31035

DYNAMICS OF BASELOAD LIQUEFIED NATURAL GAS PLANTS ADVANCED MODELLING AND CONTROL STRATEGIES

Building Hydronic Systems Pressure Profile

Module 05 WWER/ VVER (Russian designed Pressurized Water Reactors)

Supersedes: 11/15 (Rev. 03) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager

YARWAY WYE-TYPE PIPELINE STRAINERS 900 SERIES

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events

Ms.P.Aileen Sonia Dhas

NATIONAL CERTIFICATION EXAMINATION 2004 FOR ENERGY MANAGERS

Overview of Gas Collection and Control Systems. 9, December 2010 Novi Sad, Serbia

THERMAL POWER PLANT SIMULATOR TPP 200 LABORATORY EXERCISE TUTORIAL N4: INTRODUCTION TO THE HEAT PRODUCTION SYSTEM

JAPAN CANADA OIL SANDS HANGINGSTONE SAGD PROJECT

NGAWHA GEOTHERMAL FIELD EXPANSION PROJECT. GEOTHERMAL FLUID CONVEYANCE SYSTEM

Heat Recovery Steam Generators for Flexibility

Solar Tower Receivers. The Power to Change the World

WELLHEAD POWER PLANTS

Company Introduction HEATERS. Joint Venture: TIME FOR A COOL CHANGE

Centerpoint Energy. Energy Efficiency & Technology Conference. Steam and Process Heat Recovery. May 23, 2017

20/06/2011 Seminar on Geothermal Exploitation Santiago de Chile

Detailed Performance Report, Phase 2 Refrigeration System Conversion to R-434A (RS-45) For

Industrial Thermal Utilities

Module 9 : Sewage And Storm water Pumping Stations. Lecture 11 : Sewage And Storm water Pumping Stations

Problems at the Cumene Production Facility, Unit 800

Who We Are. Largest district steam system in the U.S. Deliver energy at competitive costs. Customer Focused

Chapter 8. Vapor Power Systems

Applying Dynamic Process Simulations Toward Flaring Reduction

SAGD Water Disposal Options, Associated Impacts, and Strategies to Improve Environmental Footprint. Basil Perdicakis, January 27, 2011

Observations from Several Condition Assessments of Prestressed Concrete Cylinder Pipe used at Energy Generation Facilities

SIMPACK - MODEL DEVELOPMENT PACKAGE FOR POWER PLANTS

RELAP 5 ANALYSIS OF PACTEL PRIMARY-TO-SECONDARY LEAKAGE EXPERIMENT PSL-07

Temporary Steam Plant Guidelines

AP1000 European 9. Auxiliary Systems Design Control Document

MTBE Production. Process Description. Possibility of Changing Process Feed Conditions

A Comparison Study between the Newly Developed Vertical Wells Steam Assisted Gravity Drainage and the Conventional SAGD Process

Welcome Everyone. Not Quite this kind! Geothermal Heat Pumps are a indirect solar heating system! Introduction to Geothermal

Coker Safety and Reliability Lessons Learned

Transcription:

CONDENSATION INDUCED WATER HAMMER RISKS AND ISSUES ASSOCIATED WITH SAGD OPERATIONS Jeff Dancey, P. Eng. Baker Engineering and Risk Consultants, Inc.

OUTLINE CONDENSATION INDUCED WATER HAMMER (CIWH) - EXPLANATION STEAM ASSISTED GRAVITY DRAINAGE (SAGD) OPERATIONS OVERVIEW RISKS OF CIWH IN SAGD FACILITIES MANAGING THE RISKS

CONDENSATION INDUCED WATER HAMMER

WHAT IS CIWH CIWH CAUSED BY COLLAPSE OF STEAM BUBBLE REQUIRES SUB-COOLED CONDENSATE (> 36 F) TO INTERACT WITH STEAM MAXIMUM IMPACT PRESSURE CAN RUPTURE PIPING (JOUKOWSKY EQUATION - ρc 2 ) SLUG FLOW CAUSED BY ACCELERATION OF WATER SLUGS DOWN A PIPE IMPACT PRESSURE BASED ON SPEED OF TRANSPORT FLUID (ρυ 2 ) PIPE MAY MOVE, NOT ENOUGH PRESSURE TO BREAK

CIWH MECHANISM 1. STEAM IS ALLOWED TO FLOW OVER AN ACCUMULATION OF COOLED CONDENSATE. 2. THE HOT STEAM COLLAPSES ON CONTACT WITH THE SUBCOOLED CONDENSATE THIS DRAWS MORE STEAM INTO THE LINE. 3. ENOUGH FLOW OCCURS TO FORM A WAVE IN THE LIQUID CONDENSATE THAT CONTACTS THE TOP OF THE PIPE, ISOLATING A POCKET OF STEAM. 4. THE TRAPPED STEAM POCKET RAPIDLY CONDENSES, CAUSING THE BUBBLE TO COLLAPSE AND CREATING A PRESSURE WAVE DUE TO THE IMPACT OF THE WATER.

WHY SO FEW FAILURES?

THE YETI EFFECT JOUKOWSKY EQUATION PREDICTS VERY HIGH CIWH VALUES NOT REALISTIC MANY FACTORS LIMIT THE ACTUAL IMPACT OBSERVED SIZE OF THE COLLAPSING BUBBLE PRESSURE OF STEAM PRESENCE OF BUBBLES/NON-CONDENSABLES IN WATER PRESENCE OF ENTRAINED WATER DROPLETS IN VAPOR FRICTIONAL EFFECTS OF WALLS ON WATER ACCELERATION EXPERIMENTS SHOW A LARGE RANGE OF PRESSURES FOR THE SAME CONDITIONS ONLY A FEW REACH DANGEROUS LEVELS

PIPING LAYOUT IS CRITICAL ONLY OCCURS IN HORIZONTAL RUNS WHERE L/D > 24 WILL NOT OCCUR IN PIPING WITH MORE THAN 5 DEGREE ANGLE VERTICAL PIPING WILL NOT EXPERIENCE CIWH DEAD LEGS, COMMON HEADERS, LACK OF DRAINAGE ALL POSE RISKS AVOIDING CIWH PHYSICAL PROPERTIES ARE CRITICAL OCCURS ONLY IF WATER IS >20 C BELOW STEAM TEMP STEAM PRESSURE DIRECTLY IMPACTS MAXIMUM HAMMER PRESSURE Rule #1: Don t mix steam and cold water!

SAGD OPERATIONS - OVERVIEW

STEAM ASSISTED GRAVITY DRAINAGE - SUMMARY 1. 2 PARALLEL HORIZONTAL WELLS ARE DRILLED, VERTICALLY OFF- SET. 2. STEAM GENERATED IN THE PLANT IS PUMPED DOWN THE TOP WELL. 3. BITUMEN MELTS AND A BITUMEN/WATER MIX IS RECOVERED FROM THE BOTTOM WELL. 4. OIL AND WATER ARE SEPARATED AT THE PLANT. 5. RECOVERED (PRODUCED) WATER IS CLEANED AND RE-USED. 90% OR MORE MUST BE RECYCLED. 6. BITUMEN IS COMBINED WITH A DILUENT AND SHIPPED.

WHY IS CIWH AN ISSUE FOR SAGD?

PAST HISTORY MEG ENERGY PIPELINE FAILURE 24 STEAM PIPELINE SUPPLYING SAGD WELLS PIPELINE FAILED CATASTROPHICALLY AND RUPTURED REGULATOR CONCLUDED FAILURE WAS DUE TO CIWH

STEAM PRODUCTION IN SAGD OTSG s BFW Supply SAGD PLANTS: PRODUCE HIGH PRESSURE STEAM (>1000 PSI) PRODUCE STEAM WITH HIGH CONDENSATE CONTENT SHARED PIPING AND HEADERS HAVE LARGE STEAM PIPELINES TO PRODUCTION WELLS HP Separator LP System To Pipeline

EACH OTSG SUPPLIES STEAM FOR MULTIPLE ONCE-THROUGH STEAM GENERATORS (OTSG) AN OTSG IS NOT A BOILER! WATER FLOWS THROUGH THE OTSG IN TUBES. THERE IS NO DRUM. GENERATED STEAM IS TYPICALLY 75-85% QUALITY. INDIVIDUAL OTSG S TYPICALLY PROCESS OVER 100,000 KG/HR OF WATER. A SINGLE PHASE IN A SAGD PLANT WILL TYPICALLY BE 4 TO 6 OTSG S WITH SUPPORT EQUIPMENT.

STEAM PRODUCTION ISSUES START-UP DESCRIPTION: WATER FLOW BEFORE FLAME FLOW IS KEPT IN THE LOW PRESSURE HEADER DURING LIGHT-OFF RAPID HEATING STEAM IN WATER SWITCH FROM LP TO HP HEADER RISKS: SHARED HEADERS THE LP HEADER IS FLOODED AT EVERY START RISK OF DEAD LEGS, LOW POINTS COLLECTING CONDENSATE POTENTIAL FOR BFW TO BE SENT INTO HP HEADER

STEAM PRODUCTION ISSUES TRIPS/SHUTDOWNS: GAS AND FLAME TRIPPED AS A RESPONSE TO MOST FAILURES WATER FLOW IS MAINTAINED TO COOL TUBES FLOW DUMPED FROM HP TO LP HEADER RISKS: DUMPED FLOW WILL FLASH IN THE LP SYSTEM LP HEADER MAY HAVE TRAPPED CONDENSATE SYSTEM FAILURE/OPERATOR ERROR CAN OPEN HP FLOW INTO THE LP HEADER

STEAM TO THE WELLS STEAM PIPELINE DESCRIPTION: HIGH PRESSURE (>1000 PSI) LARGE DIAMETER LONG (SEVERAL KILOMETERS) FOLLOW GROUND CONTOURS FEW STEAM TRAPS MINIMAL INSTRUMENTATION LINES RUN PARALLEL TO

STEAM PIPELINE ISSUES START-UP: START FROM COLD PIPE, ZERO PRESSURE START-UP IS SLOW CONDENSATE PRODUCED AT HIGH RATE RISKS: CONDENSATE IS COLD CONSTANTLY CHANGING TEMPERATURE, PRESSURE EQUIPMENT FAILURES, DELAYS, ARE COMMON WEATHER CAN BE AN ISSUE

STEAM PIPELINE ISSUES TRIPS: PLANT WIDE TRIPS (POWER, CONTROL SYSTEMS, GAS, ETC.) STOP STEAM PRODUCTION STEAM PIPELINES LOSE PRESSURE QUICKLY RISKS: LOST PRESSURE = LOST TEMPERATURE INABILITY TO READ PIPELINE LEVELS, TEMPERATURE DIFFICULTY REMOVING CONDENSATE IN EMERGENCIES PRESSURE TO RE-START QUICKLY

STEAM TO THE FORMATION SAGD WELL DESCRIPTION: GROUPED INTO PADS OF MULTIPLE WELLS STRICT PRESSURE CONTROLS ON FEED MULTIPLE OPERATING MODES SENSITIVITIES CHANGE AS WELL AGES LONG HORIZONTAL RUNS SENSITIVE TO OUTAGES

WELL CIRCULATION ISSUES CIRCULATION DESCRIPTION: STEAM IS INJECTED TO BOTH WELLS CHAMBER IS NOT DEVELOPED RISKS: LOST STEAM CAN CAUSE RAPID COOLING FORMATION GEOLOGY IS NEVER CERTAIN OPERATED IN START-UP FOR 60-90 DAYS

SAGD CONVERSION ISSUES CONVERSION DESCRIPTION: STEAM TO PRODUCER IS STOPPED OCCURS AFTER PRESSURE TRANSMISSION PROVED WELLS CAN BE STARTED ON LIFT GAS OR ESP RISKS: UNKNOWNS IN PIPE AND FORMATION POTENTIAL FOR STEAM BLOW-THROUGH TO PRODUCER VERY LIMITED INSTRUMENTATION

MANAGING THE RISKS

CPF DESIGN RECOMMENDATIONS REDUCE SHARED HEADERS ALWAYS ENTER A SHARED HEADER AT THE TOP ALWAYS LEAVE A SHARED HEADER AT THE BOTTOM ENSURE DRAINAGE IS NOT BLOCKED BY ELEVATION CHANGES STEAM TRAPS ARE NOT ALWAYS ENOUGH MINIMIZE LONG HORIZONTAL LINES CIWH POORLY UNDERSTOOD ENSURE ADEQUATE REVIEW RISK NOT APPARENT ON P&ID S MODEL REVIEWS ESSENTIAL

CPF OPERATION RECOMMENDATIONS TRAIN OPERATORS, MAINTENANCE, ENGINEERING AND MANAGEMENT IN CIWH ALARM STEAM TRAPS ADD INSPECTION PORTS TO PIPE INSULATION INTERLOCK BLOWDOWN SYSTEMS MONITOR TEMPERATURE AND LEVEL IN CRITICAL PIPING DON T DRAIN UNDER PRESSURE WRITE, REVIEW, RETAIN DETAILED PROCEDURES

PIPELINE AND WELL RECOMMENDATIONS ROBUST PIPELINE CONDENSATE STATIONS INCREASE MONITORING ON PIPELINE P, T ALARM/INTERLOCK ON LEVEL AND TEMPERATURE DESIGN WELL-PADS FOR STABILITY IMPROVE WELL MONITORING WRITE, REVIEW, RETAIN DETAILED PROCEDURES

THANK YOU/QUESTIONS? Jeff Dancey, P. Eng Senior Consultant Baker Engineering and Risk Consultants, Inc. JDancey@BakerRisk.com 289-288-0104