4th International Engineering and Construction Conference - July 28, 2006

Similar documents
1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SECTION BORING AND/OR JACKING PIPE

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

UNDERPINNING A CRANE FOUNDATION

Concrete Pipe Jacking

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

ITEM 432 TUNNEL CONSTRUCTION

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

6 Preliminary Assessment of Construction Method and Constructability Issues

Experts in tunneling with Tunnel Boring Machines

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

TBM Selection and Specification

Concrete Pipe Jacking

Presented by: Frank Guyamier

SECTION 39 - MANHOLES TABLE OF CONTENTS

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

Multiple Large Diameter Microtunnels with Limited Ground Cover

Construction Technology B (CON4313)

Reinforced Concrete Microtunnelling Pipe Designed for Project Conditions and MTBM Machines

Review of Plans and Specs from a Constructability Perspective

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

SECTION DRILLED CONCRETE PIERS AND SHAFTS

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

3.6 Construction Methods

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

Construction OS&H Project planning and control for safe OS&H

Design Data 4. Jacking Concrete Pipe

An introduction to. pipe jacking

Every Day Counts Market Ready Options

From Colonia Jardín to Cuatro Vientos

Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati

DESIGN AND CONSTRUCTION OF HEAVY INDUSTRIAL ANCHORAGE FOR POWER-PLANTS

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

Pushing the Envelope For 100 Years

DESIGN AND CONSTRUCTION OF DERRY ROAD AND CANADIAN NATIONAL RAIL GRADE SEPARATION

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

Wastewater Capital Projects Management Standard Construction Specification

Large-diameter bored piles and Large-hole drillings Applications

ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES

DE-SPAN Design Guideline. Manufactured 100% indoors. Under 100% controlled conditions.

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

Pipe Jacking. Progress is built on ideas.

Trenchless Pipeline Crossings

Addendum Geotechnical Report Dewatering and Settlement Sanitary Sewer Improvements at Bush IAH, Project No. 699 HVJ Project No.

SPECIFICATION : BORING AND JACKING

Concrete Bridge Design and Construction series

Special Provision No. 421F01 April 2006

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

Tel: Neil: Tony: Website:

Trenchless Technology

SECTION STORM SEWER COLLECTION SYSTEM

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project

The Regional Municipality of Peel Basis of Payment

CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Final Estimates Level 2

B701 WATERMAINS- OPSS 701

CONSTRUCTION MANUAL. T-WALL Retaining Wall System FOR RAILROAD PROJECTS. The T-WALL Solution...

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

of GENERAL. A. Description

Design Data 4M. Jacking Concrete Pipe

American Concrete Pipe Association. Precast Box Culvert Installation Procedures

CONSTRUCTION SPECIFICATION FOR TUNNELLING

Learning Legacy Document Duration of data recorded (approx.) 1

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

UPSC ESE/IES Civil Engineering Syllabus

CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES PRECAST BOX CULVERTS CONSTRUCTION SPECIFICATION

B441 - WATERMAINS - OPSS GENERAL

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES

Horizontal Ellipse. Contact LSBC for additional sizes. Buried Ellipse for Pedestrian Traffic. Elliptical Stream Crossing

SECTION HORIZONTAL DIRECTIONAL DRILLING

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

STANDARD SPECIFICATIONS SECTION JACKED CASING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

2 Support of the cavity and settlement Support of the face Natural support Mechanical support...

Transcription:

4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast reinforced concrete box horizontally through the ground, usually beneath a road or railroad that must not be interrupted. The major advantage of the process is its essential simplicity. Only the exact prism of earth that will be filled by the jacked box is excavated. No intermediate ground supports are needed. The structure is built away from the roadway, in the clear, without the constraints of shoring and traffic controls. When the structure is ready, a shield is fitted to the front, hydraulic jacks are installed behind, and the box is pushed into final position while simultaneously the earth is excavated from within. The actual jacking generally takes only a few days to a week. During that time, traffic is proceeding overhead normally, unaware of the construction below. The non-disruptive nature of the process together with its inherent safety, simplicity and economy make box jacking a useful tool for the practicing civil engineer. This paper intends to bring a greater familiarity with the box jacking process to the reader and then give some considerations and guidelines to assist engineers in designing a project that can be built using the box jacking method. Schematic for box being jacked beneath railway Applications Some examples of potential box jacking projects include storm drains, bike or pedestrian trails, livestock or wildlife undercrossings, conveyors, pipeways and other industrial uses, small bridges, and roadways up to 4 lanes wide. Basically, applications of box jacking depend only on the creativity of the civil engineer designing the project. 1

Most box jackings Berkeley Engineering has been involved with have been for drainage. The paving incidental to increased urbanization causes larger instant runoffs and larger storm drains are then required. Where these larger channels must pass beneath highways, railroads or the like, tunneling will often be required. Up to 8 or 10 diameter, pipe jacking will often be utilized. But larger sizes are generally rectangular. Placing these larger channels by box jacking will often be the most economical and least disruptive method. General Description In principal, box jacking is very simple. The box is built on a greased launch slab lined up exactly with its final location. It is then pushed straight ahead, guided by curbs on the left and right to slide straight off the launch slab. A steel shield installed on the front cuts the hole with minimal overcut. Launch slab - looking towards backstop The force of the jacks is usually reacted against the earth at the back of the jacking pit but this is not absolutely necessary. A box could theoretically be pulled into place. During jacking, lubricant is pumped around the box to ease its passage through the ground. Upon reaching final location, grout is injected to displace the lubricant and permanently support the overlying ground. The box is best precast in one large block to the full length required. This is optimal, as rigidity and accuracy can be fairly guaranteed. Where space is limited the box can be cast in halves, thirds, or even more pieces. Although this reduces the total length of thrust column required, it introduces the requirement of employing great care in constructing subsequent box sections to make sure they are exactly aligned with the initial pieces. The box jacking process can be described in terms of its constituent subsystems, most critical and primary of which is dimensioning. The box must closely fill the hole being cut by the shield at the front, and obviously, not even slightly, overfill it. The mechanical subsystems are as follows: Jacking - backstop, thrust columns, hydraulic pumps, and jacks Excavation - shield, face control, digging equipment, transport. Ventilation - gas testing, fans and fanline. Lubrication - mixers, pumps, distribution piping and manifolds. Guidance - lasers, levels, steering provisos. 2

These systems, acting in concert, can propel the heaviest concrete structure straight into the ground, producing a complete installation with maximum ease and economy. To realize these potential benefits it is very helpful if the project is originally designed with box jacking in mind. Launch slab looking at portal wall Applying grease to launch slab Engineering What follows are some considerations and guidance for civil engineers designing typical underground projects where box jacking might be utilised: First, fully assess the negative impacts of open cut. Effects on traffic should be assessed. Many times detours and staged construction are mandated because they are perceived as the only viable method. But box jacking offers another alternative. Box jacking allows the economical placement of large structures under in-service arteries with no disruption. Layout: The best installation is provided by constructing the box full length in one piece exactly in line with its final location. Sometimes, of course, due to the constraints of the site this may not be possible. But, jacking a single straight box is so advantageous that extra effort to obtain temporary right-of-way or move interfering utilities may be well justified. At one end of the tangent there must be adequate work area to precast the box, in sections if necessary. Geology. Gather all available geological information - regional, local, and on-site borings. Often overlooked is site history. Investigating, to the extent practicable, the history of the site can be the best guide to what is there and can guide the boring program. Site preparation must be particular to the exact site. It s worth noting that compared to other tunneling methods box jacking is less sensitive to wet ground because the machinery is operating within the box on a concrete roadway. However, the launch slab must be very true and thought and analysis must be given to the elasticity of the jacking slab sub-bed. In very soft ground, strengthening ribs - like an I section can be built into the underside of the slab. Backstop and Jacking Pit: The reaction wall at the back of the pit and the necessary shoring can be one and the same. The jacking forces will be much greater than the active ground loads but still the ground loads must be supported before, between, and after the jacking loads. Reaction walls always seem to move back more at the top so one probably should start with the wall a few inches ahead of where you want it at the top. It will compress as the jacking forces build. 3

Provide space for the backstop but don t engineer it or prescribe backstop parameters. Allowable bearing stresses should not govern backstop design. Unless there are utilities within the failure prism of the ground the relevant parameter is ultimate strength. Design of the backstop should be generally left up to the contractor. For at-grade installations it is helpful if the designer can make available a source of borrow material from which the contractor can construct the backstop. Timing: For maximum economy, allow as much time as possible. It may be of advantage to put out the box jacked crossings first on a separate contract to allow that work to get ahead of the mainline channel construction without impeding it. In general, do not mandate around the clock jacking. Crews get stretched, unsatisfactory results may be produced and unsafe conditions may ensue. Around the clock jacking is not necessary. Box Modifications: Generally only one dimensional modification is done and that is to add thickness to the walls and invert slab so that the thrust of the jacks is backed up by plenty of concrete. Additional rebar, such as stirrups can be added in the local high stress area where the jacks push on the concrete. The box must be made accurately. This is probably the most critical point in the whole process. If the box has high spots outside the design line the force required to push it can be significantly increased. Slurry piping & rebar in box walls Casting roof & walls of box Overall, the essential subsystems can be outlined thus: 1. Site preparation access, dewatering, etc. 2. Jacking pit Shoring and reaction wall Launch slab 3. RCBox and adaptation for jacking a) Dimensional modifications and extra rebar. b) Extra close external tolerances c) Shield on front d) Embeds for lubricating slurry distribution e) Pressure cells and instrumentation f) Grout holes 4. Jacking System Jacks Hydraulic pumps, plumbing, oil reservoir Thrust columns to backstop Material Handling 4

5. Excavation System Face excavation Muck Transportation to Shaft Removal from Shaft 6. Ventilation System 7. Guidance System Steering Provisos Lasers 8. Communication Systems Shield entering ground Adding thrust columns after jacking 8' Summary Box jacking is basically quite simple and straightforward. Such projects will always be easier and more economical if consideration is given in the design stage to the box jacking option. There are critical areas such as tolerancing, face control, and effective lubrication which bear importantly on a successful outcome. Some owners have opted for prequalification of the jacking contractor. Another approach, gaining favor, is to put the job out as design-build. In any case, explicitly allowing box jacking as an option can return significant benefits to the public. Mucking tunnel w/cat 933 Jacking completed 5