STATUS REPORT NO 18 [As on September 30, 2017] This report is intended as a status report and covers only the activities completed till date, non-completed works and work-in-progress. A. Project Details No 1 Project Name CATAMARAN -1 2 Location Plot 19,20 at Seef 3 Contractors Kooheji Contractors 4 Consultant Aref Sadeq Consultant 5 Interior design IDA interiors 6 Built up area 44,602.00 meter square 7 Start Date March 27,2016 B. Work progress status: 1. Mock up flat in the 5 th floor Completed works 1. Plaster, Tile work and First Coat of Painting is completed 2. MEP works also completed 3. Gypsum work 4. Bathroom shower enclosure sample was fixed 5. Light Fittings (Spotlights is fixed) 6. Vanity (Samples are fixed) 7. Sockets and Switches are fixed 8. Sanitarywares are fixed 9. Joinery works (doors, kitchen, wardrobes sample) STATUS REPORT Page 1
10. Shower Glass Partitions and Mirrors in Bathrooms 11. Kitchen and Appliances 12. Revised samples for kitchens, doors and wardrobes are requested to be fixed for approval. 13. Aluminum Cladding and Glazing Works (preparation is in progress) Balance works 14. Other Fitted and Loose Furniture 15. Wooden Skirting 16. A/C Unit 2. Mock up floor ( 13 th floor) Completed works 1. Bathroom Wall and Floor Tiling Works 2. Wet Area Waterproofing 3. First Fix Electrical, Plumbing & HVAC Works 4. Gypsum Ceiling Framing Works 5. Floor Tiling for Apartments 6. Second Fix Electrical, Plumbing and HVAC Works (above Ceiling and below Floor Tiles) is in progress Balance works 1. Gypsum Ceiling (fixing of Gypsum Boards) is in progress 2. Floor Tiling for Corridors and Lift Lobby 3. Fixing of A/C Units is in progress 3. Completed works: Activity Completed STRUCTURAL Works 1 Substructure 100% 2 1 st to 4 th Floor slab & 4 th Floor Pool Deck 100% 3 6 th to 35 th Floor slab 100% 4 7 th to 26 th Level Block Work 100% 5 5 th to 18 th Floor Plastering 100% 6 19 th to 21 st Floor Plastering 40% 8 5th Level Mock Up Flat 100% 9 6 th to 18 th Floor Wall Painting Preparation 100% STATUS REPORT Page 2
10 3 rd Parking Wall Painting Preparation 90% MEP Works 11 5 th to 23 rd Floor 1 st Fix MEP Works excluding HVAC 100% 12 5 th to 21 st Floor 2 nd Fix MEP Works (above Ceiling) 90% 13 5 th to 7 th Floor Ducting Works for HVAC 50% FINISHING Works 14 13 th Floor Gypsum Ceiling 60% 15 13 th Floor Tiling Works 80% 16 13 th Floor Bathroom Wall & Floor Tiling 100% 17 5 th to 7 th Floor Bathroom Wall & Floor Tiling 50% 4. Work scheduled for next month (October 2017): a. Roof and Upper Roof Level Slab Completion b. 19 th, 20 th, 21 st, 22 nd and 23 rd Floor Wall Plastering Completion c. 27 th, 28 th, 29 th, & 30 th Floor Block Work d. 24 th, 25 th, & 26 th Floor MEP 1 st Fix Completion e. 8 th, 9 th, 10 th, 11 th, 12 th, & 14 th Floor Bathroom Wall and Floor Tiling Completion f. Completion of 13 th Floor Gypsum Ceiling and Floor Tiling g. Fixing of Aluminum Frames for Curtain Wall STATUS REPORT Page 3
C. Progress Photos CITY CENTER VIEW STATUS REPORT Page 4
CITY VIEW STATUS REPORT Page 5
SEA VIEW STATUS REPORT Page 6
CITY VIEW STATUS REPORT Page 7
FIXING OF ALUMINUM FRAMES for CURTAIN WALL 13 th FLOOR (MOCK UP FLOOR) GYPSUM CEILING WORKS STATUS REPORT Page 8
13 th FLOOR (MOCK UP FLOOR) GYPSUM CEILING WORKS STATUS REPORT Page 9
6 th to 9 th FLOOR BATHROOM WALL TILING WORKS STATUS REPORT Page 10
5 th to 8 th FLOOR MEPF WORKS (above Ceiling) STATUS REPORT Page 11
5 th to 8 th FLOOR MEPF WORKS (above Ceiling) 18 th to 22 nd FLOOR FIRST FIX MEPF WORKS (above Ceiling) STATUS REPORT Page 12
5 th to 7 th FLOOR ELECTRICAL WORKS prior to FLOOR TILING 15 th to 18 th FLOOR PAINTING PREPARATION STATUS REPORT Page 13
19 th to 21 st FLOOR PLASTERING WORKS STATUS REPORT Page 14
23 rd to 26 th FLOOR BLOCKWORKS STATUS REPORT Page 15
29 th, 30 th, 31 st, & 32 nd FLOOR COLUMN REINFORCEMENT and FORMWORKS STATUS REPORT Page 16
29 th, 30 th, 31 st, & 32 nd FLOOR SLAB SUPPORT 29 th, 30 th, 31 st, & 32 nd FLOOR SLAB STEEL FIXNG STATUS REPORT Page 17
29 th, 30 th, 31 st, & 32 nd FLOOR SLAB STEEL FIXNG 29 th, 30 th, 31 st, & 32 nd FLOOR SLAB CONCRETING STATUS REPORT Page 18