New Passenger Terminal Zagreb International Airport October 2014

Similar documents
About Viadukt. Our vision. Our mission

ENVIRONMENTAL MANAGEMENT SYSTEM AT ZAGREB INTERNATIONAL AIRPORT

Manx Accredited Construction Contractors Scheme 2018/19

Factsheet no. 2: SEGRO warehouse, Slough, UK

Section 6 - Bill of Quantities Bill Nr. 1 Preliminaries

Aviation Capital Construction Program Update

Reliance House Investors Report. IR11 September 2018

Vienna International Airport Renovation of Checkin

Midfield Satellite Concourse (MSC) & Baggage Optimization Project (BOP) BOAC Status Update May 4, 2017

Contract No. EX CS001 - Construction of an Annex to Baptist Lui Ming Choi Secondary School at Yuen Wo Road, Shatin, New Territories.

The HKIE Structural Examination Written Examination

CATAMARAN TOWER - 1 Seef Area Plot 19, 20

Section 4 - Design and Construction Overview

Construction Method Statement

Buildings Construction Procurement Strategy

Contract No. EX CS001 - Construction of an Annex to Baptist Lui Ming Choi Secondary School at Yuen Wo Road, Shatin, New Territories.

San Francisco International Airport Collaborative Project Delivery Process

Buildings Construction Procurement Strategy

Capability Statement. January Airports

Concepts. Products. Service. Providence Tower, London

Application of Building Information Modelling (BIM) in the Hong Kong Housing Authority s Public Housing Developments

Doing Business with the Metropolitan Washington Airports Authority

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017

HILLVIEW ELEMENTARY ADDITIONS AND ALTERATIONS Grove City Area School District

Hong Kong International Airport Medium & Long Term Development Plans. The British Chamber of Commerce 18 July 2012

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16

GAUTENG DEPARTMENT OF INFRUSTRUCTURE DEVELOPMENT

WOODFORD LEISURE CENTRE REFURBISHMENT

Fundamentals of Building Construction: Materials and Methods

School Assessment Report

Preliminary Inspection Plan Certification On Site Inspection. Ancillary Design... Ancillary Construction Inspecti... Testing Requirement

Preliminary Inspection Plan Certification On Site Inspection. Ancillary Design... Ancillary Construction Inspecti... Testing Requirement

DOCUMENT BID DOCUMENT

Commercial Structures

Unit Rate. Subtotal in SDG. Site Clearing Preliminary Works. 1.0 Job. Excavation & Earth Works. Stone Masonry Works in foundation 100 M.

Airport Construction Project Risk Management. Presented by: Mindy Price- Direct Effect Solutions

ALFA. Pre Fab Multi Storey Steel Buildings Engineering - Design Manufacture, Erection TurnKey Solutions ALFA PEB LIMITED. Pre Engineered Building

Thesis Proposal 12/13/06

Mondol Fabrics Ltd. Nayapara,kasimpur, Gazipur ( N, E0) 8th March 2014

Project: King Abdulaziz International Airport KAIA 2

Project Manual Index of Specifications Shenandoah Schools Concession Building

201,500 SF ON ACRES

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

PAGE 2-3 VILLAGE BELLE HOTEL & APARTMENTS PAGE 4-5 GARDEN STATE HOTEL PAGE 6 MUNICH BRAUHAUS PAGE 7 TERMINAL 2 MELBOURNE AIRPORT

AIRWAYS CROSSING PHASE II BUILDING INFORMATION 5305 McCall Way N.E. T2E 7N7

Update on FCPS Construction/Renovation Projects. July 2016

ArcelorMittal Europe - Long Products Sections and Merchant Bars. Office Building ArcelorMittal in Esch Alzette

School Assessment Report

Macau International Airport Environmental Optimization Design Competition Rules and Regulations

CF PROJECT DETAIL PRODUCTS AND INFORMATION CAN BE AMENDED WITHOUT PRIOR CONSENT TO MAINTAIN THE COMPANY POLICY OF CONTINUED IMPROVEMENT J ONES

How to Estimate the Cost of a Medical Office Building Using Conceptual BIM (DProfiler)

Construction OS&H Project planning and control for safe OS&H

Alif Apparels Ltd. (9813) Goldstar Garments Ltd. (9844)

Construction of Transfer Plate - from various case studies. Presentation prepared by Raymond Wong

G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

Structural Technical Report I October 5, 2006 Structural Concepts / Structural Existing Conditions Report

PLANNING & DEVELOPMENT AIRPORT INFRASTRUCTURE MANAGEMENT MICHAEL SHEEHAN SR DIRECTOR OF AIM DEVELOPMENT


Minimum Standards for Construction of Aircraft Hangars MINIMUM STANDARDS FOR CONSTRUCTION OF AIRCRAFT HANGARS

Division D CONSTRUCTION

NEW MNIR DESIGN INTERNATIONAL OPEN DESIGN COMPETITION COST PLAN ANALYSIS MNIR REDEVELOPMENT ELEMENTAL COST PLAN

A PLEASANT FLIGHT BEGINS AND ENDS AT THE AIRPORT. KONE solutions for airports

CAC Meeting Construction Update April 8, 2014

BUILDING THE MERSEY GATEWAY a step by step guide

ROOSEVELT ISLAND OPERATING CORPORATION OF THE STATE OF NEW YORK DESIGN OF TWO NEW ELEVATORS FOR MANHATTAN TRAM STATION

Prepared by Elie F. Issa, Eng. D.E.C. August 2016

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION

REEF RESIDENCE ON PLOT NO. JVC13JHRA002, JUMEIRAH VILLAGE CIRCLE, DUBAI, UAE.

DESTINATION: LA MERCY

Thesis Proposal. Matthew R Peyton

Concepts. Products. Service. Rotunda Birmingham

MARCH BOND & TIF PROJECT UPDATE. Grapevine-Colleyville ISD

The International Committee of the Red Cross

City of Kansas City AIRPORT COMMITTEE BRIEFING. New Terminal Evaluation for Kansas City International Airport. March 15, 2016

Airport Passenger Terminals

HURON PUBLIC WORKS BUILDING HURON, SOUTH DAKOTA BID NO R

January 14, 2006 Structural Thesis Proposal: Structural and Breadth Redesign Options

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #8

Suman Fashion Garments Ltd. Nipunika Ltd. Cha-72/1/B, Moddha Badda, Holland Centre, Progoti Sarani, Dhaka ( N, E) 09 March 2014

Distribution Center 1 + 2

Weill Cornell Medical Research Building 413 E. 69 th Street New York, NY

Schedule T5. Tender Documents. This tender is for: Tender Documents: The documents issued for this tender include the following: Tender Schedules

Modular System Advantages

Maine Turnpike Authority

Update on FCPS Construction/Renovation Projects. June 2016

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

School Assessment Report

WELCOME. NEW NORTH CONCOURSE PACKAGE #3 Open House 10/20/2017

CONSTRUCTION SPECIFICATION FOR SITE RESTORATION FOR UNDERGROUND UTILITIES

Table of Contents 2. Structural Systems.4 Foundations.4 Floor System...4 Columns..5 Lateral System...5

L-MOD Case Study. Atlanta Hartsfield-Jackson International Airport. New South McCarthy Synergy, A Joint Venture

PROGRESS R E P O R T M A R C H

City Of Mendota Construction Procedures

TABLE OF CONTENTS DIVISION 1 GENERAL REQUIREMENTS

Detailed Estimating-Introduction. Dr. Al-Hammad

6.0 TERMINAL REQUIREMENTS AND ALTERNATIVES

Mastering the Challenges: Lessons from the Recent Past. Chris Harris, Operations Manager, Turner International Middle East Ltd

Subcontractor Pre-Qualification Statement Hunt / Moss, A Joint Venture

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Final Publishable Summary

Transcription:

New Passenger Terminal Zagreb International Airport October 2014

Contents: 1. Project Overview 2. Zagreb Airport Presentation 3. Work Progress & Site Photos 4. NPT Key Dates

Project Overview 1

Introduction to the Project Scope of Project: the financing, design, building, operation and maintenance of a new passenger terminal and related infrastructure at Zagreb Airport, Republic of Croatia; the operation and maintenance of the 2 M pax capacity existing passenger terminal at Zagreb Airport and related infrastructure under a concession approach. The new Terminal will be constructed in two Phases namely Phase 1 initially and Phase 2 in time, when certain conditions are experienced to increase from 3.5 to 5 and more M pax annual figures. Philosophy: The new terminal building is aimed to give a new face to Nation's capital and help Zagreb to fully exploit its potential as a center of attraction in Europe. The new terminal building is projected to stand out in the region with its contemporary design and state-of-the-art technological infrastructure. Integrating design, construction and operations in the terminal would be crucial to ensuring passenger satisfaction. Zagreb International Airport would have significant role in the region, due to the total investment and professional engagement of all partners in the consortium. For the next three years, consortium will be focused on attracting new airlines to increase passenger numbers and air traffic figures.

Introduction to the D & B Contract D&B Contract between MEĐUNARODNA ZRAČNA LUKA ZAGREB d.d. and BOUYGUES BATIMENT INTERNATIONAL, dated 30 November 2013. Scope of Construction Works Highlights: Refurbishment of Existing Terminal building (BHS/Check-ins/Departure Area/Duty Free shop) Detailed Design development Construction of new Passenger Terminal Building for phase 1, Apron+Taxiways connecting to existing runway+external works. Drainage of existing runway, taxiways, apron Enabling works, airside & landside works, services & utilities, terminal building & building services, aeronautical equipment, lifts & escalators, project management and other responsibilities are carried out under the D & B contract. Scheduled Completion: 36 months, Dec 2013-Dec 2016

1 Zagreb Airport - Presentation 2

Introduction to Project Master Plan Existing Terminal New Passenger Terminal

New Passenger Terminal 3D

New Passenger Terminal 3D

Main Consultants & Architects External Works Viadukt (Equity Partner in the Concessionaire of Zagreb International Airport) is the subcontractor for the entire scope of the External Works. Consultants & Designers IGH, Kincl & Neidhardt & Radic are the Designers of the project (Croatian). Team completed by the input of International consultants: Wind Tunnel test (Waker), Fire strategy (Exova), Acoustic specialist (BYTP), IT (C2S) Road Traffic & Drainage consultant (Egis), Airport Equipment specialist (ADPI). 1

Main Subcontractors for the Project > Viadukt - In charge of all external works including, roads, parking, Apron, taxiway, viaduct, underpass, airside and landside drainage system with retention basin and pumping complex > Kamgrad Concrete structure works and internal partition (brickwall and drywall) > ZM Roof Steel Structure and Facade > KFK Roofing Contractor

Major Project in Croatia in numbers 65 000 m2 of floor area 35 000 m3 of concrete (NPT) 5 000 tons of rebar 2 000 Tons of steel structure 3D Frame Roof Roofing: 35.000 m2 Excavation: 500.000 m3 Concrete: 40.000 m3 (ext works) Drainage: 35.000 ml Asphalt : 250.000 m2 8 Contact stands (PBB) Number of BBI staff: 65 Actual number of workers: 450

Design Features The NPT is a 4-level building, comprising of the rectangular main body (passenger processor), extending into two asimetrical piers (western pier for international departures and arrivals, eastern for domestic traffic). First two levels are used for arrivals and the second two for departures. Connected to the north façade are 8 PBB's. Structural frame of the building consists of the reinforced concrete circular columns and beams with combined 7,2 m and 14,4 m spans, the post-tensioned concrete slabs and the 4 reinforced concrete cores containing vertical communications. Departure level is accessible to vehicles by the reinforced concrete viaduct on the front façade. Above the concrete structure is the undulating steel spatial frame, combining the roof of the main body and piers with the northern façade. Steel frame forms the double height volume of space on both landside and airside. South, east and west facades are made as flat aluminum curtain walls with structural glazing. Roof is partially glazed, and partially covered with state-of-the-art aluminum cladding. The building contains all the needed infrastructure of the 21st century airport terminal and is designed to be operated under schengen regime.

Design Features Steel Structure 3D

Design Feature Roofing Roof layers from Steel structure to Standing Seam Section on Roof gutters 3D modeling Zagreb International Airport

Design Feature Facade 3D modeling of connection between Terminal Building and Piers Typical detail Terminal Straight facade North Facade 3D modeling

1 Work Progress & Site Photos 3

Current Work Progress EXISTING TERMINAL WORKS completed Section 1 Construction works in Domestic boarding lounge: Increasing of the domestic departure lounge by adding app. 200 m2 on the 1 st floor, with café bar and connection for the planned smoking cabin. Section 2 Construction works in International boarding lounge: Duty free shop extension New Café bar Smoking cabin preparation works Women toilets extension New passenger services counters Section 3 Construction works in Gate 7 area: Installation of the evacuation door. Section 4 Capacity Check-in increase: Additional third check-in line with four new counters is provided to increase the capacity of the existing terminal. New baggage handling line added into the sorting area. Section 5 Light improvements: Lighting of public area in front of check-ins is improved. Section 6 Car parks improvements: Car parks No 1 & 3 completely new asphalt surface and markings, repair of drainage Substantial completion date was scheduled for 25.11.2014, but the final handover planned for 07.09.2014. (2,5 months in advance)

Beginning of the Works (1/4) End May: foundations progress Mid April : platform ready to start foundations End April : first crane installation and start of foundations

Beginning of the Works (2/4) End June: GF columns, start of verticals Mid June: backfilling in progress October: 2nd Level End July: Level 1 slab

Underpass Progress View of underground section S Section S12 in progress Opening of Underpass Section T7 covered

External Works February: fencing (airside/landside) and tree felling January: starting of the site - demolition March April: preparation of platform for NPT

Existing Terminal

NPT Key Dates 4

NPT Key Dates NPT Key Activities/Dates Execution of D&B Contract 30.09.2013 Execution of Concession Agreement/Financing Agreement 02.12.2013 Site Handover Date 05.12.2013 Site Commencement Date 18.12.2013 1 st Stone Laying Ceremony 21.05.2014 Expropriation of Land Plots for New Terminal building Footprint 30.05.2014 Expropriation of other Land Plots (Car Park etc.) 04.09.2014 Existing Military Base Decanted 17.09.2014 Existing Terminal Works including International Boarding Lounge Completion 29.09.2014 Underpass (overpass) and Landside Service Road Access 06.10.2014 NPT Forthcoming Key Activities by End 2014 Completion of Detail Design Commencement of Structural Steelworks Commencement of MEP Installations in NPT Commencement of Retention Basin Area Works NPT Construction Future Key Activities Dates New Terminal Building External Envelope 26.03.2016 New Roads Connection to Access the New Terminal Building 06.05.2016 Start Testing and Commissioning 29.05.2016 Substantial Completion Date 03.12.2016 Above contractual completion dates may be subject to earlier achievements, if a power on construction progress is effective.

Thank You