TOLEDO COLLINS PARK WTP 40 MGD PLANT ADDITION DESIGN CONSIDERATIONS AND CHALLENGES

Similar documents
Integrating Ozone and Ion Exchange into a 40 Year Old Lime Softening Plant

Water Treatment Plant Phase 1 Upgrades CMAR Selection Pre-Submittal Meeting

Process Treatment Selection and. Jeff Macomber, P.E. One Water Conference August 28, 2014

Right click on the influent element and select name. Type Influent in the box. This should change the name of your element to influent.

Ann Arbor Wastewater Treatment Plant Facilities Renovations Project October 2017

Lake County WTP Improvements and Capacity Increase. OTCO 9 th Annual Water and Wastewater Workshop. Nick Pizzi Aqua Serv

EchoWater Project. Contractor Open House. January 14, Vick Kyotani Program Manager. Sacramento Regional County Sanitation District

Renovation of the Filters at the Soldier Canyon Filter Plant in Fort Collins, Colorado

Expanding Capacity and Treatment. Treatment Plant

Ready, Set, and Go: Deer Valley WTP East Basins Performance Testing, Start-Up, and Commissioning Toby Teegerstrom Brian Watson

Government Center Water Treatment Plant Kamphaeng Phet Province, Thailand

Green River Filtration Facility Plant Overview

Tiffin Water Treatment Plant. Comprehensive Facility Plan (Audit)

6.2.1 Intermediate Pumping Overview

LEARNING RESOURCE CENTRE AYRSHIRE COLLEGE MICROSOFT WORD USEFUL ESSAY FEATURES

MWMC Eugene-Springfield WPCF Facility Plan Secondary Clarifier Enhancement Alternatives

City of Fairfax, Virginia City Council Regular Meeting. Honorable Mayor and Members of Cfy ;ouncil Robert L. Sisson, City Manager /I.

HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN

WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES

Public Utilities Department City of Bossier City, Louisiana

Submerged Membranes to Replace Media Filters to Increase Capacity 4X for a Small Community. Richard Stratton, PE HDR Engineering, Inc.

Minneapolis Fridley Filter Plant Split

The city of Venice hired Camp

High Performance. Uniform Distribution

WATER INTAKE & DISTRIBUTION MM1

Optimizing the Ballasted Sedimentation Process at the Anacortes Water Treatment Plant Jeff Marrs Plant Manager Greg Pierson - HDR

NEW CLOTH MEDIA FILTER SYSTEM REPLACES 4 MGD TRAVELING BRIDGE FILTERS WITH 12 MGD CAPACITY IN EXISTING TANKAGE

Algae Removal from a Facultative Lagoon System Using Dissolved Air Flotation. J. Patrick Pierce, P.E. Environmental Treatment Systems, Inc.

Lessons Learned from CM-at-Risk and Design Build Projects at Water and Wastewater Treatment Plants. Lawrence H. Hentz Jr., P.E.

Dipti Shah, Town of Gilbert Tuesday, January 25, 2011

City of Enderby Water Treatment Plant

FAST TRACK PROJECT IMPLEMENTATION CHARLOTTE WATER IDLEWILD BOOSTER PUMP STATION PIPING IMPROVEMENTS

City of Gardiner, Maine Wastewater Committee Meeting. CSO Storage Tank & Screening Evaluation

CONTRAFAST. High-Rate Thickening Clarifier

THIS POLICY DOES NOT HAVE THE FORCE OF LAW

Rinconada Water Treatment Plant Reliability Improvement Project (RIP) Filter Pilot Study

SETTLING REVIEW CHECKLIST

Nakhon Sawan Water Treatment Plant Nakhon Sawan, Thailand

SYSTEMATIC APPROACH TO WATER TREATMENT PLANT PROCESS OPTIMIZATION

Innovative Approach to Expanding the Olentangy WTP

2015 HDR, Inc., all rights reserved.

Capital Investment Plan (CIP) Quarterly Report for the period ending December 2013

Altoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation

Wet Weather and Advanced Treatment: Procurement Strategies to Secure the Right Technology

MRI Wastewater Inclined Plate Settlers Performance Advantages

Greater Kegalle Water Treatment Plant Kegalle, Sri Lanka

Full Scale Testing to Demonstrate Anaerobic Selector Effect for Low Strength Wastewater

Project Name: Central WWTP Capacity Improvements and CSO Reduction Project. MWS Project Number: 14-SC-0153 Last Updated: 12/19/14

Innovative Improvements to a 53-Year Old Water Plant for HABs, Crypto, and Whatever Else the Maumee River Brings

Separations Overview TDRL Seminar

Ali Leeds, MWH Austin Peters, MWH

There is no sludge treatment process at NWTP. Sludge generated from sedimentation and backwashing is drained directly to the Khan River.

Lowering The Total Cost Of Operation

ATTACHMENT 1 GENERAL FACILITY INFORMATION. BOD5 mg/l mg/l TSS mg/l mg/l NH3-N mg/l mg/l

Innovative Hydraulics 915 Valley View Avenue Pittsburgh, PA (412)

WASTE WATER TREATMENT SYSTEM

Tampa Bay Water (TBW) is a regional

THE BOSSIER CITY WATER TREATMENT PLANT (Background and Current Process Layout )

Utility Partner Data Report

Oak Orchard Wastewater Treatment Plant. Wet Weather Operating Plan

PLAN SHEET INDEX TYPICAL ARCHITECTURAL DETAILS - WINDOW SCHEDULE AND DETAILS

rim-flo secondary Clarifier with Tow-Bro unitube sludge removal system

Optimizing Wastewater Upgrade Projects with Improved Hydraulics

Bekaa Valley 10 x 40 miles. Aitanit-Quraoun WWTP 5000m 3 /day Commissioned May Lake Qaraoun

Morningstar Direct SM Presentation Studio

Engineering Request for Qualifications (RFQ) BJWSA Project CIP #1366 Purrysburg WTP Expansion to 30 MGD Engineering Contract

Fridley Filter Plant Rehabilitation

Long Point Water Treatment Plant Process Evaluation and Design Upgrades for Performance Enhancement; Dover, DE

WinSLAMM v Program Modifications Final, 3/16/19

Product: ODTView. Subject: Basic Overview of Delivery and Orders Tab. Version: December 6, Distribution: Customer

Matt Leach, P.E. CH2M. Mark Eppich, P.E. City of Columbus Division of Water. S. Dean Ramsey, P.E. CH2M

~~~~ WWTP Master Plan Project

Managing Schedules in ADP Time & Attendance

Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment

FilterWorx Performance Filters EFFICIENCY AND INNOVATION BUILT INTO EVERY COMPLETE SYSTEM

Technical Memorandum. 1 Summary Findings and Conclusions. 2 Existing Primary Treatment Facilities

Request for Proposals

Wastewater Plant Tour. There Is Gold In Them There Plants

I am writing in response to your request for a Revenue Legal Opinion addressing the Sales Tax on the Wastewater Treatment equipment.

Please acknowledge receipt of both Addendum No. 0 1 (issued

Volume 1 Executive Summary

Lessons Learned from Walla Walla: Eastern WA s Largest GC/CM Water Project

Advancing the Design of a New 60 MGD Water Treatment Plant

Providing Infrastructure Redundancy at the Rocky River WWTP. Timothy McCann AECOM Keith Bovard Rocky River WWTP

DRINKING WATER CONSTRUCTION PERMIT APPLICATON

Environmental Improvements Associated with Springfield WWTP EHRT. Using the Compressed Media Filter Technology

Wilmette - Background

Self-Cleaning Trench-Type Wet Well Design

WinSLAMM v Program Modifications Final, 12/12/17

Meadowbrook-Limestone (MBLS) Wastewater Treatment Plant. Wet Weather Operating Plan

The High-Capacity. Inclined Plate. Settler System

Strength Development Plan

Reducing THM via Aeration: A Case Study August 28, 2014

Backup Generators Bacon Road Water Treatment Plant Case Study

City of Columbus Wet Weather Management Plan Update. Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

PRIMARY DRINKING WATER FROM WASTEWATER EFFLUENT: PILOT TEST EXPERIENCE AT THE MIAMI DADE SOUTH DISTRICT WWTP

Water Treatment Plant Improvements Study

Approaches to Filter Condition Assessment and Optimization

Evaluation of Cost and Benefits of CSO Treatment and Supplemental Aeration to Improve Water Quality in the Chicago Area Waterways

Transcription:

TOLEDO COLLINS PARK WTP 40 MGD PLANT ADDITION DESIGN CONSIDERATIONS AND CHALLENGES Kurt Smith, PE & Jack Kane, PE - ARCADIS Jim Donnell, PE - City of Toledo September 28, 2017

Collins Park WTP 40 MGD Plant Addition Purpose: h 20 MGD Redundancy - Allow basin maintenance year round yt 20 MGD Capacity - Address OEPA significant deficiency

Collins Park WTP Process Flow Schematic Kurt Smith Project Manager

Collins Park WTP 40 MGD Plant Addition DESIGN CONSIDERATIONS Pumped rapid mix Flocculation Sedimentation Effluent troughs Algae skimmers Recarbonation Ozone connection GAC Filters CHALLENGES Tight site constraints Other contractors Utility relocations Security Maintenance of plant operations (MOPO) Interconnections to existing East Plant Preservation of Lagoon E COST SAVINGS MEASURES Sedimentation basin size reduction 3D CAD benefits Design Construction Post Construction Prequalification of contractors Low bids

VERTICAL RAPID MIXER ALTERNATIVE RAPID MIX PUMP

WATER CHAMP RAPID MIX ALTERNATIVE

PUMPED RAPID MIXING SYSTEM Rapid mix pump rated for 2,000 gpm at 37 head with 30 Hp motor 10 DISCHARGE 12 SUCTION East Plant RAPID MIX PUMP

PUMPED RAPID MIXING SYSTEM East & West Plant rapid mix channels rated for 80 MGD each OVER BAFFLE UNDER BAFFLE ALUM FEED 8 X 15.5 CHANNEL (TYPICAL)

PUMPED RAPID MIXING SYSTEM Mixing energy exceeds 10-States Standards G-value of 750 fps/ft 10 DISCHARGE PIPE ALUM FEED INJECTION DIFFUSER NOZZLE

PUMPED RAPID MIXING SYSTEM RAPID MIX PUMP West Plant

FLOCCULATION BASINS BASIN 8 FLOC BASIN 10 DISCHARGE PIPE BASIN 7 FLOC DRIVES SODA ASH SPLITTER BOX LIME SLURRY SPLITTER BOX

FLOCCULATION BASINS 10 DISCHARGE PIPE ALUM FEED Basins 1 6 Upgrades Equipment interchangeable with Basins 7 & 8 INJECTION DIFFUSER NOZZLE

SEDIMENTATION BASINS SLUDGE DRAGS 10 DISCHARGE PIPE Basins 1 6 Upgrades Equipment interchangeable with Basins 7 & 8 SLUDGE CROSS COLLECTOR

EFFLUENT LAUNDER BUILDING 10 DISCHARGE PIPE EFFLUENT SUBMERGED ORIFICE INJECTION WEIRS DIFFUSER (TYPICAL) NOZZLE

EFFLUENT LAUNDER BUILDING 10 DISCHARGE PIPE FLOATABLES ALGAE SKIMMERS (TYPICAL) INJECTION DIFFUSER NOZZLE

RECARBONATION BASINS 10 DISCHARGE PIPE CO2 DIFFUSERS (TYPICAL) INJECTION DIFFUSER NOZZLE

OZONE FACILITY CONNECTION 10 DISCHARGE PIPE SETTLED WATER CONDUIT GATES FOR OZONE EFFLUENT CONDUIT KNOCKOUT WALL FOR OZONE INFLUENT CONDUIT

Filter Media Pilot 12 Sand Effective size 0.45 0.55 mm 24 GAC Effective size 1.0 1.2 mm GAC Filters Underdrains Leopold XA IMS 200 caps INJECTION DIFFUSER NOZZLE

SITE CONSTRAINTS OTHER CONTRACTORS Probable Project Costs Basin 7 $ 37,200,000 Basin 8 $ 33,400,000 TOTAL $ 70,600,000 Schedule Basin 7 & Basin 8 Operational by April 2020

SITE CONSTRAINTS OTHER CONTRACTORS Probable Project Costs Basin 7 $ 37,200,000 Basin 8 $ 33,400,000 Other Concurrent Projects CPEU $ 17,000,000 Schedules Basin 7 & Basin 8 Operational by April 2020 CPEU Operational by Sept. 2018

SITE CONSTRAINTS OTHER CONTRACTORS Probable Project Costs Basin 7 $ 37,200,000 Basin 8 $ 33,400,000 Other Concurrent Projects CPEU $ 17,000,000 Ozone $ 40,000,000 TOTAL $127,600,000 Schedules CPEU Operational by Sept. 2018 Basin 7 & Basin 8 Operational by April 2020 Ozone Facility Operational by July 2020

SITE CONSTRAINTS OTHER CONTRACTORS Additional Concurrent Projects CPEU Operational by Sept. 2018 Basin 7 & Basin 8 Operational by April 2020 Ozone Facility Operational by July 2020 Lagoon E Spent Lime Removal Completion by April 2018 Maintenance Facility Completion by December 2018 Basins 1 6 Upgrades Start Construction Jan. 2020

SITE CONSTRAINTS SECURITY & SOLUTIONS

SITE CONSTRAINTS SECURITY & SOLUTIONS

MAINTENANCE OF PLANT OPERATIONS (MOPO) Kurt Smith Project Manager

PRESERVATION OF LAGOON E Kurt Smith Project Manager

PRESERVATION OF LAGOON E & UTILITY RELOCATIONS BASIN 8 50 FEET Kurt Smith Project Manager LIMITS OF EXISTING LAGOON E 2:1 SLOPE STRUCTURAL EMBANKMENT

PRESERVATION OF LAGOON E Kurt Smith Project Manager EXISTING LAGOON CAPACITY REDUCED FROM 41.8 MG TO 33 MG OR 21% REDUCTION

SEDIMENTATION BASIN SIZE REDUCTION Negotiations with OEPA Based on historic plant performance Based on old design text books 4 hours without sludge equipment Based on conservatism of 10- States Standards Kurt Smith Project Manager Cost Savings Benefits Detention time reduced from 4 hours to 3 hours ~ $5.8 M savings Provides space savings for new Ozone Facility SPACE SAVINGS FOR OZONE FACILITY

DESIGN PHASE - Excellent 3D visualization - Interactive tool with Owner - Design progress meetings - Freedom Navisworks software (for the novice) - Clash detection to: - Improve quality of bidding documents - Minimize change orders - Bidding Phase - Provide to Contractors 3D CAD BENEFITS Kurt Smith Project Manager

3D CAD BENEFITS CONSTRUCTION PHASE (CONTRACTOR) - Quicker orientation of project estimators, managers & trades - More efficient coordination of trade disciplines to resolves conflicts - Decreases errors and corrections in field - Higher reliability of expected field conditions and plan drawings - Allows for more prefabrication offsite with higher quality and lower cost - Reduce RFI s and expedite construction schedule Kurt Smith- Creates a safer workplace Project Manager - Construction sequencing

3D CAD BENEFITS POST CONSTRUCTION - Develop 3D views for O&M Manuals - CMMS (computerized maintenance management system) - Add asset information to model for O&M/asset management - Freedom Navisworks software (for the novice) - Interactive tool for operator and safety training Kurt Smith Project Manager

PREQUALIFICATION OF CONTRACTORS Prequalification Process - Received 6 proposals - Short listed to 4 Contractors to bid Evaluation Process - Bonding - Verifiable statement confirming financial wherewithal - Planned approach Kurt Smith to the project - ReferencesProject Manager - Construction Experience - Water/wastewater projects - Large excavation - Workforce & Workload - Corporate Health, Safety & Environmental Program Control Quality and Risk Reduction

LOW BIDS CONSTRUCTION BID RESULTS BASIN 7 AND BASIN 8 PROJECTS Description Basin 7 Basin 8 Engineer s Estimate $37,740,000 $32,820,000 Average of Bids Kurt Smith $36,337,865 $33,319,259 Project Manager Low Bid $28,387,750 $26,694,200 Cost Below Average of Bids $7,950,115 $6,625,059 % Below Average of Bids 21.9% 19.9%

Thank you!

3D CAD BENEFITS Kurt Smith Project Manager

Collins Park WTP 40 MGD Plant Addition DESIGN CONSIDERATIONS Pumped rapid mix Flocculation Sedimentation Effluent troughs Algae skimmers Recarbonation Ozone connection GAC Filters CHALLENGES Tight site constraints Other contractors Utility relocations Security Maintenance of plant operations Interconnections to existing East Plant Preservation of Lagoon E COST SAVINGS MEASURES Sedimentation basin size reduction 3D CAD benefits Design Construction Post-construction Pre-qualification of contractors Low bids

Collins Park WTP 40 MGD Plant Addition DESIGN CONSIDERATIONS Pumped rapid mix Flocculation Sedimentation Effluent troughs Algae skimmers Recarbonation Ozone connection GAC Filters CHALLENGES Tight site constraints Other contractors Utility relocations Security Maintenance of plant operations Interconnections to existing East Plant Preservation of Lagoon E COST SAVINGS MEASURES Sedimentation basin size reduction 3D CAD benefits Design Construction Post-construction Pre-qualification of contractors Low bids

Title Text DESIGN PHASE

Title Text

Title Text

Title Text COST SAVINGS SDFD SDFDSF SDFSDF DSFSDF

SITE CONSTRAINTS OTHER CONTRACTORS Probable Project Costs Basin 7 $ 37,200,000 Basin 8 $ 33,400,000 Other Concurrent Projects CPEU $ 17,000,000 Ozone $ 40,000,000 TOTAL $127,600,000 Schedules CPEU Operational by Sept. 2018 Basin 7 & Basin 8 Operational by April 2020

SITE CONSTRAINTS OTHER CONTRACTORS Probable Project Costs Ozone Facility $37,200,000 Schedule Ozone Facility Operational by July 2020

Title Text

Title Text

Kurt Smith Project Manager

Kurt Smith Project Manager Probable Project Costs Basin 7 $48,700,000 Basin 8 $43,400,000 TOTAL $92,100,000

Logo protection zone Template Layout Tips Paragraph level First level bullet Second level bullet Third level bullet To turn the guides on and off: right click > grids and guides > guides or Alt + F9. To get bullets use Increase list level or Shift + Alt + The grid is laid out in six columns and is designed to provide a flexible layout while still allowing for breathing room and white space. Text and images should not extend past blue lines. (Full size images would be an exception)

Guidance Always ensure that if you are presented with an Enable Content and / or Enable Editing option/s on opening a document, that you DO enable the content and / or editing by clicking on the buttons presented There are sixteen layouts in each master (one with logo, and another without) to choose from to suit your needs and help keep your presentation consistent Incorporating slides from another presentation: Click on New Slide on the Slides ribbon group, under the Home ribbon tab and scroll down and choose the layout you want to use Copy your slides (Ctrl + C) and insert a new blank slide layout in your new presentation and paste your slides (Ctrl + V) into your new presentation (not behind any of the other layouts, especially not behind the title or divider layouts) The small Paste clipboard icon will appear at the bottom of the slides you have copied in, click on the arrow on the icon and choose use destination theme, this will ensure that your slides will use the correct colour pallet throughout the document You may need to correct some colour combinations, any other anomalies, and choose the layout design you require for each slide i.e., Title and Content, Title only, Blank etc and a certain amount of tidying will normally be required You can also use the Keep Source Formatting option but ensure that you change the colour palette for the slides you have copied in to our Arcadis Brand palette. If you are still having problems try opening a blank new PowerPoint document (Ctrl +N) and paste your slides into this before pasting it into the new template Alternatively, you may need to copy each of the elements of the design into the new template individually using the Paste Special / Unformatted Text option and reapply formatting in the new template this may be long winded, but can often be safer and ensures more consistent application of the branding Kickers / takeaways should be short, sharp and to the point, the text size is set and should not be made smaller if you do not need to use a kicker, please just delete the text box