Status of the FRM-II Project at Garching. Hans-Jürgen Didier, Gunter Wierheim Siemens AG, Power Generation (KWU), D Erlangen

Similar documents
German contribution on the safety assessment of research reactors

VVER-440/213 - The reactor core

COLD NEUTRON SOURCE AT CMRR

Argonne National Laboratory 9700 S. Cass Avenue, Bldg. 207 Argonne, Illinois USA. TtiIe: Coordinator for Analysis

THE ROLE OF A RESEARCH REACTOR IN THE NATIONAL NUCLEAR ENERGY PROGRAMME IN VIETNAM: PRESENT AND FUTURE

JORDAN RESEARCH AND TRAINING REACTOR UTILIZATION FACILITIES

The design features of the HTR-10

The "Réacteur Jules Horowitz" : The preliminary design

LABGENE CONTAINMENT FAILURE MODES AND EFFECTS ANALYSIS

Safety of Experimental Facility in JRR-3

COMPARATIVE STUDY OF TRANSIENT ANALYSIS OF PAKISTAN RESEARCH REACTOR-1 (PARR-1) WITH HIGH DENSITY FUEL

UTILIZATION OF ETRR-2 AND COLLABORATION 1. INTRODUCTION

Legislative Framework for the Regulation of Decommissioning at Egypt. Prof. Dr. Farouk M. A. Rahman

ACR Safety Systems Safety Support Systems Safety Assessment

PARTIAL SAFETY ANALYSIS FOR A REDUCED URANIUM ENRICHMENT CORE FOR THE HIGH FLUX ISOTOPE REACTOR

CHALLENGES FOR THE RADIATION PROTECTION DEPARTMENT IN THE SCIENTIFIC ENVIRONMENT OF A RESEARCH REACTOR LIKE FRM II

NUCLEAR PLANT WITH VK-300 BOILING WATER REACTORS FOR POWER AND DISTRICT HEATING GRIDS

Research Reactors in Germany: An Overview

RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED

CANDU Safety #14 - Loss of Heat Sink Dr. V.G. Snell Director Safety & Licensing

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER C: DESIGN BASIS AND GENERAL LAYOUT

Burn up Analysis for Fuel Assembly Unit in a Pressurized Heavy Water CANDU Reactor

Enhanced CANDU 6. Safe, dependable and clean energy solutions

Core Management and Fuel Handling for Research Reactors

PRESENT STATUS OF THE HIGH TEMPERATURE ENGINEERING TEST REACTOR (HTTR)

NUCLEAR ENERGY MATERIALS AND REACTORS - Vol. II - Advanced Gas Cooled Reactors - Tim McKeen

INCREASINGTHENEUTRONFLUXATTHEBEAMTUBE POSITIONS OF THE FRG-1. P. Schreiner, W. Krull and W. Feltes*

Experimental Measurements for Plate Temperatures of MTR Fuel Elements at Sudden Loss of Flow Accident and Comparison with Computed Results

International Perspective on non-heu Mo-99 Production

Technical Meeting (TM) on Spent Fuel Storage Options IAEA Vienna, July

Power Stations Nuclear power stations

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Journal of American Science 2014;10(2) Burn-up credit in criticality safety of PWR spent fuel.

CNA Communications Workshop. Communicating About Nuclear Issues: Nuclear Power Plants. Darlington Generating Station April 8, 2004

Concept for a new research reactor in Ukraine

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

PUSPATI TRIGA REACTOR UPGRADING: TOWARDS THE SAFE OPERATION & FEASIBILITY OF NEUTRONIC APPROACH

Ageing Management in TR-2 and Related Legislation and Experience in TAEK

Examples of Research Reactor Conversion Assessment of Alternatives

IAEA Technical Meeting on Products and Services of Research Reactors 28 June 2 July 2010 IAEA, Vienna, Austria

DECOMMISSIONING OF THE IFIN-HH VVR-S NUCLEAR RESEARCH REACTOR Dr. Mitica Dragusin, IFIN-HH, Romania

Application of Selected Safety Requirements from IAEA SSR-2/1 in the EC6 Reactor Design

Dutch Safety Requirements for Nuclear Reactors: Fundamental Safety Requirements

Steam Generating Heavy Water Reactor SGHWR The final chapter

Safety reassessment of WWR-K RR related to HEU/LEU conversion and feedback from accident at the Fukushima-Daiichi NPP

Irradiation Facilities at the Advanced Test Reactor International Topical Meeting on Research Reactor Fuel Management Lyon, France

BN-1200 Reactor Power Unit Design Development

CHALLENGES WITH THE CONVERSION OF THE MITR

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

SAFETY ANALYSIS AND ASSESSMENT FOR TEMPORARY STORAGE OF 106 IRRADIATED VVR-M2 FUEL TYPE ASSEMBLIES IN DALAT REACTOR

Design Characteristics of the Cold Neutron Source in HANARO Process System and Architecture Design

Lecture (3) on. Nuclear Reactors. By Dr. Emad M. Saad. Mechanical Engineering Dept. Faculty of Engineering. Fayoum University

Scenarios of Heavy Beyond-Design-Basis Accidents in HTGRs N.G. Kodochigov, Yu.P. Sukharev

SMR An Unconditionally Safe Source of Pollution-Free Nuclear Energy for the Post-Fukushima Age

Charles Grant. International Centre for Environmental and Nuclear Sciences University of the West Indies

Demonstration Test Program for Long term Dry Storage of PWR Spent Fuel

Safety Design Requirements and design concepts for SFR

ABSTRACT. 1. Introduction

THE PRESENT STATUS AND FUTURE POTENTIAL APPLICATIONS OF RRS IN CIAE. 1. BRIEF INTRODUCTION TO RRs IN CIAE AND THEIR UTILIZATION

The Characteristics and Irradiation Capabilities of MARIA research reactor in NCBJ Świerk

Safety Provisions for the KLT-40S Reactor Plant

Small Modular Nuclear Reactor (SMR) Research and Development (R&D) and Deployment in China

The U.S. Advanced Neutron Source

Safety design approach for JSFR toward the realization of GEN-IV SFR

KIPT ACCELERATOR DRIVEN SYSTEM DESIGN AND PERFORMANCE

CAREM Prototype Construction and Licensing Status

Core Management and Fuel handling for Research Reactors

Safeguards at research reactors: Current practices, future directions

Safety Aspects of SMRs: A PRA Perspective

REPORT FROM THE COMMISSION TO THE COUNCIL AND THE EUROPEAN PARLIAMENT. Operation of the High Flux Reactor in the period

IAEA Course on HTR Technology Beijing, October 2012

DOSE CALCULATION FOR ACCIDENT SITUATIONS AT TRIGA RESEARCH REACTOR USING LEU FUEL TYPE

Nuclear Research Institute. Nuclear Research Institute CONTENTS

HTTR test program towards coupling with the IS process

LEU Conversion of the University of Wisconsin Nuclear Reactor

BN-350 REACTOR SPENT FUEL HANDLING

CANDU Safety #1 - CANDU Nuclear Power Plant Design Dr. V.G. Snell Director Safety & Licensing

Thermal Response of a High Temperature Reactor during Passive Cooldown under Pressurized and Depressurized Conditions

2012 Deep River Science Academy Summer Lecture GENERATION IV SUPERCRITICAL WATER-COOLED REACTOR

Conversion of MNSR (PARR-2) from HEU to LEU Fuel

Safety Requirements for HTR Process Heat Applications

THE ROLE OF REGULATORY AUTHORITY IN SAFE OPERATION OF RESEARCH REACTOR

An Overview of the ACR Design

Chemical Engineering 693R

PALLAS A nuclear reactor

NUCLEAR FUEL AND REACTOR

CURRENT STATUS OF JMTR

ENVIRONMENTAL SAFETY OF NUCLEAR POWER PLANTS OF RUSSIAN DESIGN

SPENT FUEL STORAGE MANAGEMENT IN INDONESIA. SUMARBAGIONO Radioactive Waste Technology Center, Indonesian National Nuclear Energy Agency (BATAN)

The MIT Research Reactor as a National User Facility for Advanced Materials and Fuel Research

METHODOLOGY FOR ENSURING THE INTEGRATION OF ALARA INTO THE DESIGN OF

Module 06 Boiling Water Reactors (BWR)

THE NEW 10 MW(T) MULTIPURPOSE TRIGA REACTOR IN THAILAND

Reactivity insertions for the Borax accident in ORPHEE research reactor

Research Reactors Status and Potential Areas of Collaborations in EGYPT

Nuclear Reactors. 3 Unit Nuclear Power Station - Coastal Bryon Nuclear Plant, Illinois. 3 Unit Nuclear Power Station - Desert

HTR Research and Development Program in China

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level

Nuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level

CONVERSION OF THE GHANA'S MINIATURE NEUTRON SOURCE REACTOR FROM HEU TO LEU: 2017 REPORT

Transcription:

IGORR7 7 th Meeting of the International Group on Research Reactors October 26-29, 1999 Bariloche, Argentina Status of the FRM-II Project at Garching Hans-Jürgen Didier, Gunter Wierheim Siemens AG, Power Generation (KWU), D-91058 Erlangen Abstract: The FRM-II is a new research reactor at Garching near Munich with a maximal power of 20 MW. Because of its single element compact core it will provide a max. thermal flux of 8 10 14 cm -2 sec -1 outside of the core. It is presently under construction. All buildings are almost completely erected, the installation of the technical components is in progress and the non nuclear operation for testing has started. In accordance with the time schedule the nuclear commissioning will begin in January, 2001. The first partial licence for the concept of the whole plant and the erection of the reactor building was obtained in April, 1996 and the second partial licence for the erection of the complete facility was given in October, 1997. The third permit for the nuclear commissioning and operation is expected for fall 2000. The new German government is presently discussing which consequences a conversion of the FRM-II to reduced or low enrichment would have. From scientific, technical and economic reasons there is no doubt, however, that the FRM-II should best go into operation with highly enriched fuel as planned. Thus, the Technical University of Munich (TUM) as the overall manager and Siemens AG (KWU) being the general supplier are confident that this high flux neutron source will soon be available for the benefit of the national and international scientific community. Postal address of the authors: Siemens AG, KWU NLFM - Hans-Jürgen Didier Postbox 32 20, D-91050 Erlangen - Gunter Wierheim Reaktorstation, D-85747 Garching

-2- Contents Abstract 1. Introduction 2. Design Concept 2.1 Engineered Design Features 2.2 Building Concept 3. Licensing Procedure 4. Time Schedule 5. Progress on Site 6. Conclusion 1. Introduction For progress in the scientific fields of solid-state physics, chemistry, biophysics, molecular biology, material sciences and medicine the more than 40 years old research reactor FRM of the Technical University must be replaced by the new FRM-II being erected since August, 1996. The thermal neutron flux density will be 50 times higher, whereas thermal nuclear power will only be 5 times higher. Siemens was nominated the general contractor to design, build and commission the FRM-II reactor facility whereas TUM remained responsible for the experimental installations and the operator s requirements. The characteristic data of the facility are given in Tab. 1. Reactor type Power Core compact reactor core, light water cooled, in the center of a moderator tank of 2.5 m filled with heavy water 20 MW, thermal one cylindrical fuel element (d j =118 mm, d o =243 mm, 700 mm high) 113 involutely, bent fuel plates, cycle time about 52 days, 5 cycles per year. Coolant primary: light water from the pool with 1000m³/h at 37 / 52 C secondary: closed system of light water tertiary: transfer of the heat to the atmosphere by evaporation Pool ca. 700 m³ demineralized water, gate for separating the reactor and the storage pool Shielding lateral: 2.5 m water and 1.5 m heavy concrete vertical: about 10 m water Beam tubes 10 horizontal, 1 vertical, 2 oblique Neutron flux max. 8. 10 14 cm 2 s -1 thermal, unperturbed Tab. 1: Characteristic data This paper shows some basic information and the progress on the site in Garching near Munich since May, 1998 (IGORR 6).

-3-2. Design Concept The basic safety principle of the design is the 3-barrier concept and the securing of the maintaining of these barriers (fuel and cladding, pool water, confinement). Thus the radioactive fission products are kept back so that inadmissible radiation exposure in operation and after accidents can be avoided at every time. 2.1 Engineered Design Features In addition to inherent and passive safety characteristics as reactivity decrease e.g. after leakages of heavy water from the moderator tank or of light water from the core many constructive features make sure that only a low level of radiation exposure will occur in design basis accidents. These features are: - big volume of pool water as a heat sink - integrity of the pool with the primary cooling system - shutdown systems - shutdown cooling systems - confinement - reactor protection system - auxiliary safety-related systems 2.2 Building Concept The whole reactor plant consists of the following buildings: - UJA reactor building (40 m x 40 m, 30 m high) - UBA entrance building - UYH neutron guide hall (60 m x 25 m) - UJB basement of neutron guide hall - UTA building for auxiliary systems - UKA stack - URA tertiary circuit air cooler - UGX fresh water storage - UCX emergency control room - UBZ/URZ underground supplying ducts The arrangement of these buildings is shown in fig. 1. The reactor and the surrounding buildings contain the systems as listed in chapt. 2.1 to withstand a safe shutdown earthquake that means these systems are able to fulfil their safety functions during and after an earthquake. Additionally the reactor building is protected against the effects of an airplane crash. Therefore the outer walls and the roof are made out of 1.8 m thick reinforced concrete. The pool water always covers the fuel element in any post-accident phase because the integrity of the reactor pool is secured in consequence of its mechanical isolation from the outer building structure. Fig. 2 shows a vertical cross section of the reactor building. The separation of the experimental hall and the reactor hall at a height of 11.7 m can be recognized. In fig. 3 a schematic picture of the reactor and the storage pool is shown. The fuel element is located in the middle of the moderator tank. The two fast shut down systems and the primary cooling system can be identified, too.

-4-3. Licensing Procedure In April, 1996, TUM and Siemens got the first partial licence covering the general safety concept acceptance, site development and the erection of the reactor building. Immediately afterwards the site was established and the construction was started in August, 1996. The second partial licence was obtained in October, 1997. So it was permitted to erect all other buildings and to install and to commission the whole technical equipment. The third nuclear licensing step covering the nuclear operation is expected for fall 2000. The German government which changed from the conservative to the social democratic and green parties in fall of last year is presently discussing which consequences a conversion of the FRM-II would have to reduce the uranium enrichment from high to low. Table 2 shows an extract of the government report out of June, 1999 for the different fuel versions. FRM-II 2b 1) 3a 2) 3b 2) fuel U 3 Si 2 U 3 Si U-6Mo-Al U-6Mo-Al enrichment U-255 [%] 93 19.75 19.75 50 fuel density [gu/cm³] 1.5 / 3.0 5.8 7-8 4.0 / 8.0 diameter [cm] outside/inside 24.3 / 11.8 28.6 / 14.4 27.9 / 14.4 24.3 / 11.8 length fuel zone [cm] 70 80 80 70 thermal power [MW] 20 20 20 20 decrease of thermal neutron flux [%] of FRM-II 0 21 3) 21 3) 7 1) immediate conversion with change to version 3a later 2) change later after beginning with fuel of FRM-II as planned 3) as calculated by TUM this value amounts to about 25 % Tab. 2: Different inspected fuel versions for FRM-II The German federal government plans to decide towards the end of this year how to proceed. But from scientific, technical and economic reasons there is no doubt that the FRM-II should best start with highly enriched fuel as planned. 4. Time schedule The following table 3 gives an overview about the key project data from the beginning in 1980 till to the future (extract see fig. 4). 1980 1984 Proposals of the compact core concept 1984 1987 Feasibility study 1987 1988 Design study 1988 1992 Safety analysis and elaboration of safety analysis report 1989 First recommendation and preliminary classification of the project by the Federal Scientific Council 02/93 Application for license (first partial licence) 11/93 12/93 Presentation of the safety analysis report to the public 05/94 Second recommendation and enhancement of classification by the Federal Scientific Council, first public hearing 09/94 Turnkey contract with Siemens for design and construction of the FRM-II 12/94 Budget decisions by the parliament of the state of Bavaria 05/95 Final recommendation by the Federal Scientific Council 07/95 Presentation of the environmental impact statement to the public

-5-10/95 Second public hearing in connection with the environmental impact evaluation 04/96 First partial licence for the entire concept and for the erection of reactor building 08/96 Groundbreaking ceremony 01/97 Laying of the foundation stone 10/97 Second partial licence for the erection of all auxiliary buildings and the entire installations necessary to perform successfully the cold commissioning 08/98 Topping-out ceremony since 08/98 Installation of technical equipment, erection of other buildings (cont.) 01/99 Third public hearing in connection with the permission for operational water 11/99 Erection of all buildings completed 02/00 12/00 Cold commissioning phase fall/00 Third partial licence for hot commissioning expected 01/01 10/01 Hot commissioning phase (assumption: start with HEU, see chapt. 3) IGORR 6 see chapt. 5 IGORR7 Tab. 3: Key project data 5. Progress on Site The following pictures show the progress on the site in Garching near Munich since the IGORR 6-meeting in April/May, 1998. Fig. 5 98-08-24 Topping-out ceremony Fig. 6 Fig. 7 Fig. 8 Fig. 9 99-02-23 Experimental hall with reactor pool 99-04-29 Leakage test of reactor / storage pool 99-05-25 Total view of site 99-06-30 Reactor hall: reactor / storage pool with hot cell Fig. 10 99-08-12 Moderator tank during manufacture Fig. 11 99-08-31 Total view of site 6. Conclusion The new German high-flux research reactor of the Technical University of Munich planned, erected and to be commissioned by Siemens will soon be available for the benefit of the national and international scientific community. Under the condition that the third partial licence will be obtained as proposed the project progress will remain on schedule with regard to budget and time as planned.