Transmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008

Similar documents
Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012

Regional Planning at Midwest ISO. Mr. Clair Moeller Vice President, Transmission Asset Management

Expanding Transmission Capacity: Options and Implications. Jennifer Curran Director Transmission Strategy April 30, 2009

ATC Network Customer Meeting Planning Update

PJM Wind Integration Initiatives

Illinois State Institute for Regulatory Policy Studies Conference

Update on Transmission Planning for Wind Power in the Upper Midwest

Mid-Continent Independent System Operator (MISO) Overview. INCMA February 15, 2017

Transmission & Integration

Leading Insights into Solar

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Renewables Curtailment in China is there light at the end of the tunnel? Liutong Zhang

Storage as a Transmission Asset:

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Renewable Grid Integration Assessment Overview of Thailand Case study

SPP at a Glance. Located in Little Rock. Approximately 600 employees

CO2, SO2 and NOX Emission Rates. March 15, 2018

The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT. David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Outline. Introduction to Wisconsin. Barriers to Generating Electricity from. Incentives and Regulations Intended to

Wind Generation and Grid Operations: Experience & Perspective

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

Business Practice Manual for The Transmission Planning Process

Operations Report. Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, PJM 2018

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Peter Randall Solar Kingdom Ltd

Agenda. Natural gas and power markets overview. Generation retirements and in developments. Future resource mix including large hydro

PJM ENERGY PRICES 2005 Response to Howard M. Spinner Paper

The Integration Challenge

Transmission and Interconnectors

2016 ISO Flexible Capacity Needs Assessment: Study Methodology, Assumptions, and Preliminary Results

CO2, SO2 and NOX Emission Rates. August 21, 2015

Assessing the Flexible Capacity Requirements for 2018 through 2020

BRITISH INSTITUTE OF ENERGY ECONOMICS. RENEWABLES AND CCGTS: COMPETITORS OR COMPLEMENTARY? 11 October 2012 Andrew Morris

Eastern Wind Integration and Transmission Study

Electric Sector Restructuring and Utility GHG Emissions: Trends and Opportunities in the US

Operations Highlights

Eastern Wind Integration and Transmission Study

FLEXIBILITY HOW TO CONTRIBUTE TO THE STABILITY OF THE GRID THANKS TO THE FLEXIBILITY OF YOUR PRODUCTION PROCESSES?

Draft 2011 Long-term Transmission Plan. Stakeholder Session June 20, 2011

Solving Climate: The Need for Zero Carbon On-Demand Power

Operations Report. Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, PJM 2018

Operations Report. Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, PJM 2018

For Bandon Utilities Commission

Resource Planning. EE 590 Iowa State University. October 22, 2008

Reforming the Mexican Electricity Market: Design and Regulatory Issues

Wind Development in the Midwest

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Transmission Cost Allocation in the Midwest

The Role of Transmission The Electrical Interstate Highway System

Generation Interconnection Process. SWANA Spring Conference Atlantic City, NJ April 18, 2016

Outlook for Natural Gas Demand for Winter

Truly Collaborative Transmission Planning: Breaking the Log Jam. Susan N. Kelly VP, Policy Analysis and General Counsel 9/21/06 HEPG Session

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component

Pumped hydro Storage Plants

APS Renewable Energy. Overall Commitment and Distributive Energy Program. Arvin Trujillo 4CPP-Government Relations

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

Presentation for the Local Government Commission and the Community Environmental Council. July 13, 2007

Energy: Global, National and Vermont Contexts

Schedule 2 TECHNICAL INFORMATION

Results of California s Renewable Energy Program and Agricultural Biomass to Energy Program (SB704)

The State of Wind Energy in New England

MISO PJM Cross-Border Planning

Energy Uplift (Operating Reserves)

System Needs: An Energy Planning Perspective. Randy Reimann

Joe McDonald.

Storage as a Transmission Asset:

Electric Forward Market Report

The Future of Electricity: A Market with Costs of Zero? Marginal

Preliminary Assumptions for Economic Studies DRAFT. Planning Advisory Committee June 16, Wayne Coste Principal Engineer

Regulatory Challenges, Developments, and Issues Confronting the IUB

2010 RTO Metrics Report: NESCOE Data Summary

OPALCO 2015 IRP Overview. December 2015 Board Meeting

Eastern Wind Integration and

Greater Philadelphia Chapter of the Association of Energy Engineers

Transmission Expansion Advisory Committee

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

Modernizing the Electricity Grid MILESTONES

The Future of Electricity: A Market with Costs of Zero? Marginal

2018 Draft Policy Initiatives Roadmap. Market and Infrastructure Policy December 7, 2017

PJM Renewable Integration Study. Ken Schuyler Renewable Energy in West Virginia June 5, 2014

Integrating Renewable Energy Resources into the Transmission Grid

Moving to a competitive low-carbon

Solar Integration into the PJM Grid

Advancing Renewable Alternatives

Eastern Interconnection Wind Integration & Transmission Study

2017 Project Prioritization & Budgeting Process

PJM Interconnection. Drexel University Great Works Symposium May 13, 2010

Reforming the Mexican Electricity Market: Design and Regulatory Issues. Juan Rosellón DIW Berlin and CIDE

Broader Regional Markets

California Independent System Operator Corporation. California ISO. Invoicing WECC NERC/ERO Costs. March 29, Prepared by: Michael Epstein

NJ Solar Market Update

Energy Uplift (Operating Reserves)

ICF Benefit Study of the Midwest ISO Market Presentation to the Midwest ISO Board of Directors

Reducing Peak Energy Demand: The Hidden Benefit of Cool Roofs

Committees on Energy Resources and the Environment and Electricity

Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process. Planning Advisory Committee September 26, 2018

Energy visions under TYNDP 2017 and impacts on network development

edart Roadmap As of February 21 st, 2018

Overview and Latest Topics Related to Energy Systems in the U.S.

Transcription:

Transmission Planning at the Midwest ISO Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008

Midwest ISO: What We Do Monitor flow of power over the high voltage transmission system Schedule transmission service Manage power congestion through security-constrained economic dispatch Operate day-ahead and real-time energy markets Regional transmission planning Today s Focus

Key Issues Currently Impacting Transmission Planning ( Planning Activities Key Issues Congestion Renewable Policy Operational Impacts Load Growth and DSM Aging Infrastructure Fair Cost Allocation New Generation and Demand Response Changing Regulatory Requirements 3

Transmission Design Goal One robust transmission system Wind Introduces Energy Resources to a transmission system designed for capacity delivery Transmission Value Drivers have historically not been well understood

Midwest ISO Transmission Studies Short term Primarily bottom up analysis of transmission to reliably serve load and generation (i.e. to meet NERC Planning Standards) Includes analysis of transmission facilities needed to reliably serve Generator Interconnection and Transmission Service Requests Mid term 5 to10 year+ Targeted studies to address specific areas of concern / need Current examples include studies to address Narrowly Constrained Areas in market and Generation Outlet for wind in western Midwest ISO Long term - 15-20 years Top down energy delivery studies focused on economic value Reliability analysis follows Up to four generation scenarios to bookend probable outcomes Includes Joint Coordinated System Plan

2008-2027 Future Generation Scenarios irement 2008-2027 (MW) Additional Capacity Requi 90,000 80,000 76,334 67,560 70,000 1,235 1,425 60,000 50,000 61,167 42,780 1,235 40,500 40,000 1,425 12,600 30,000 3,520 3,600 1,600 20,000 6,000 1,902 700 10,000 20,400 16,800 9,120-3445 Reference Renewable Current Queue* Nuclear Coal CC CT Wind Behind the Meter Demand Response Midwest ISO longterm planning process models alternative scenarios of future generation needs Scenarios support a transmission planning approach which attempts to maximize optionally of the transmission grid, given an uncertain future Renewable future assumes 20% renewable mandate across Midwest ISO footprint * Requests under evaluation in queue as of March 7, 2008; wind includes 231 MW of other renewables

Transmission Expansion for Renewable Future year 2021 40,000 MW Midwest ISO Black dotted - 800 kv HVDC Blue dotted - 765 kv AC Yellow dotted - 345 kv AC

Queue Evolution * Number of Requests GW of Requests 214 54 Currently Active: 367 Requests (300 wind) 16 8 11 14 Currently Active: 83.5 GW (67.0 GW wind) 3 3 2 131 12 1 79 12 5 8 11 43 90 13 5 20 51 18 99 165 2004 2005 20 2007 2008 YTD 76 7 66 24 46 8 13 11 12 2 2 3 5 14 5 11 3 4 2004 2005 20 2007 2008 YTD Wind Coal Natural Gas Nuclear Other * All requests received as of May 14, 2008

MW Requested 30000 25000 20000 15000 Active Queued Requests by State Other Nuclear Coal Gas Wind 10000 5000 0 KY MT OH WI MO IN MI IA IL ND SD MN

Location of Currently Queued Requests

3 P s of Queue Reform Process Success in queue reform rests on addressing each of the 3 P s Currently working on solutions targeted at interconnecting generation more efficiently: Process: focus study efforts on those generation projects ready to achieve interconnection Physics: Regional Generation Outlet Study is the first step in using alternative planning methods to indentify network upgrades to support interconnection of large quantities of generation in remote areas Policy: Opening dialogue on items such as cost sharing and recovery Filing to FERC on proposed changes to process expected mid-june 2008

Current Queue Example: Buffalo Ridge Area Add CapX, 1900 Add BRIGO, 1200 Next upgrade, 825 Today s level, 425 A snapshot of the Buffalo Ridge area indicates that generator requests significantly exceed current transfer capability.

Current Queue Example: Group Study Process Under the current group study process, all generation requests meeting the location and time-based criteria are considered, independent of demand for power in the region, resulting in restudy Start Feasibility Study Complete Feasibility Study Start Impact Study Interim Results: $164M in upgrades Complete Impact Study: $122M in upgrades Start Impact Restudy; Start part of Facilities Study Complete Impact Restudy; $14M in upgrades Complete Facilities Study (Phase I) Start Impact Restudy; Restart Facilities Study Complete Impact Restudy; $14M in upgrades Jun- 05 Jul- 05 Aug- 05 604 MW 8 Requests Sep- 05 Oct- 05 Nov- 05 Dec- 05 Jan- Feb- Mar- 580 MW 7 Requests Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- 244 MW 3 Requests Dec- Jan- 07 Feb- 07 Mar- 07 Apr- 07 194 MW 2 Requests

Targeted Planning Study: Regional Generation Outlet Study drives greater integration between longer and shorter term planning processes by holistically addressing transmission requirements associated with interconnecting large quantities of wind generation Scope of work: Determine distribution of wind sites across footprint to maximize ease of wind integration Assess year-by-year aggregate wind mandates for all states in Midwest ISO, and associated renewable capacity requirements Develop five year road map of transmission projects to interconnect wind generation informed by the queue and consistent with mandates

Conditions Precedent to Increased Transmission Build A robust business case for the plan Need to demonstrate that the hypothesized benefits exist, including evaluation of alternatives Regulators are the judge of the business case Increased consensus around regional energy policy Does not exist today around wind, for example, across the Midwest ISO footprint A regional tariff that matches who benefits with who pays over time For example, beneficiaries of wind may be due to public policy, rather than load flow or economic benefit analyses which are the current basis for cost allocation Cost recovery mechanisms that reduce financial risk Investors in these projects need to be assured of cost recovery