Peak and off-peak electricity distribution charges

Similar documents
CMP271 Initial thoughts on Cost Reflectivity of GB Demand Transmission Charges

CMP282: The effect Negative Demand has on Zonal Locational Demand Tariffs

Network Rail s response to ORR s 2018 Periodic Review (PR18) consultation on charges recovering fixed network costs.

Principles of cost recovery: electricity tariff design

REVENUE SUFFICIENCY GUARANTEES AND COST ALLOCATION William W. Hogan i May 25, 2006

Tackling Tariff Design. Making distribution network costs work for consumers

Open Networks Project

Electricity Charging Seminar Level Playing Field

INFORMATION MANAGEMENT AND THE BENEFIT OF CHANGE MANAGEMENT

By 22 nd June 2018

User manual for the dcmf.co.uk EDCM workbooks

Charging Delivery Body. 8 th August 2018

GAS DISTRIBUTION TRANSPORTATION CHARGING METHODOLOGY

CMP266 Removal of Demand TNUoS charging as a barrier to future elective Half Hourly settlement

ORR consultation on on-rail competition: Options for change in open access Network Rail s response

SP Energy Networks Business Plan

Representation - Draft Modification Report 0541A/B

NEWFOUNDLAND BOARD OF PUBLIC UTILITIES DATA RESPONSES TO THE CONSUMER ADVOCATE. Provide a copy of the report to the Board concerning Newfoundland

MARK SCHEME for the May/June 2010 question paper for the guidance of teachers 9772 ECONOMICS. 9772/02 Paper 2 (Essays), maximum raw mark 75

Contents 1 Summary 3 Any Questions? 2 Summary of Proposals and Background Information 6 3 Impact of the Proposal and Workgroup Discussion 23 Contact:

Producer Theory - Monopoly

A new framework for digital publishing decisions 95. Alastair Dryburgh. Alastair Dryburgh 2003

Marginal Costing Q.8

Improving Selection to the Foundation Programme. Legal opinion, July 2011

recent Input Methodologies (IM's) Review Forum held on July 2015 and present a major user perspective on our experience of the current DPP.

Improving the way we price our network services. Consultation paper

A Thought Leadership White Paper By Howard W. Coleman, MCA Associates

CMP266 Removal of Demand TNUoS charging as a barrier to future elective Half Hourly settlement

Staff Paper 12. Update on value chain analysis Introduction

Amendment to charge control on Mobile Network Operators

The 10 Big Mistakes People Make When Running Customer Surveys

Supply and Demand Cont d

DCUSA Charging Methodologies Pre-Release: 1 April 2018

Engineering, Economics and Regulation of the Electric Power Sector TERM PAPERS

Future of Gas Entry Tariff Regime Draft Decision (CER/15/057)

REVENUE SUFFICIENCY GUARANTEES, COST CAUSATION, AND COST ALLOCATION William W. Hogan i October 9, 2008

Transmission System Capability and the Decision to Abolish the Snowy Region

Demand based network tariffs offering a new choice

Electricity Prices in the Tennessee Valley

P2 Performance Management

Shift factors in ERCOT congestion pricing

RSM 392H1: Competitive Strategy

1 The Modification Proposal

Principles of implementation and best practice regarding FL-LRIC cost modelling

The basics of modelling

CASH FLOW IS KING WHITE PAPER

CUSC Amendment Proposal Form CAP: 162

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Current & future grid infrastructure. Lewis Dale Regulatory Strategy Manager

CHAPTER IV COST STRUCTURE OF ELECTRICITY

Switching focus. Making employment and pay better for people with disabilities - Who is responsible for it?

Cost-reflective pricing and the electricity distribution networks

This is the midterm 1 solution guide for Fall 2012 Form A. 1) The answer to this question is A, corresponding to Form A.

Study on the value of flexibility in the management and design basis of distribution networks in France

The Proposer recommends that this Modification should be treated as urgent and should proceed as such under a timetable agreed with the Authority.

ECONOMICS. Chapter 4 The Market Strikes Back

GSR016: Small and Medium Embedded Generation Assumptions

Submission on the Consultation Paper Transmission Pricing Review: - High Level Options

Payback & Return Analysis for Solar in Mueller - Revision 1

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Differential Analysis: Relevant Costs the Key to Decision Making

ECONOMICS. Chapter 4 The Market Strikes Back

Behaviour Based Maturity Model

Eastland Network Limited. Pricing Methodology Disclosure

Test Management is Risk management. Risk Based Testing

Exam #2 (100 Points Total) Answer Key

Retail-Level Transactive Control Linked to Wholesale LMPs

The Proposer recommends that this Modification should be treated as urgent and should proceed as such under a timetable agreed with the Authority.

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

ECONOMICS 103. Topic 5: Externalities. External costs and benefits

ASIC speaks on Improving and Maintaining Audit Quality & The Role of Others

The future of outbound is Precision Dialling How to optimise your outbound contact activities

Adam Smith Theorem. Lecture 9 Monday, Sept 28. Lecture. 1. More about Pareto Efficiency. 1. Midterm two weeks from today. In class, Monday, Oct 12.

OPERATIONAL CASE STUDY AUGUST 2016 EXAM ANSWERS. Variant 2. The August 2016 exam can be viewed at

CONTRACTUAL AND REGULATORY REFORM WORKSTREAM. RDG vision for the charges and incentives regime in the long run

Témoignage de Mme Judy W. Chang de The Brattle Group sur la politique d'ajouts au réseau de transport

Cambridge University Press Modeling Monetary Economies, Second Edition - Bruce Champ and Scott Freeman Excerpt More information.

eni proposed UNC Mod 501C

REVISED TARIFF STRUCTURE STATEMENT. ActewAGL Distribution Electricity Network

Propane. A game changer for a low-emission Canada now. Affordable and accessible now. Ontario Access to Natural Gas Act, 2018 (Bill 32)

GUIDANCE PAPER: CALCULATION METHODOLOGY FOR DISTRIBUTION LOSS FACTORS (DLFs) FOR THE VICTORIAN JURISDICTION

Fundamentals Level Skills Module, Paper F5. 1 Edward Limited. (a)

Increasing Value Add by: Sheila Julien, Senior Associate

Local Government and Communities Committee. Planning (Scotland) Bill. Submission from Shepherd and Wedderburn LLP

ECONOMICS 103. Topic 3: Supply, Demand & Equilibrium

de Neufville + Scholtes D R A F T September 9, 2009

Slippery Slopes and Spider Webs

In this update: P7. Energy Live Expo

UC Berkeley Haas School of Business Economic Analysis for Business Decisions (EWMBA 201A) Fall 2013

Congestion Revenue Rights

THE IMPROVEMENTS TO PRESENT LOAD CURVE AND NETWORK CALCULATION

Chapter 2 Valuing the Environment: Concepts

First published in Squandered; how Gordon Brown is wasting over one trillion pounds of our money, Constable, London,

How to convert your inventory into smart inventory

ANSWER: c TOPICS: Section 1: Capitalism and Wealth

Customer Profitability Analysis

2 The Action Axiom, Preference, and Choice in General

Defect Escape Analysis: Test Process Improvement. Author: Mary Ann Vandermark IBM Software Group, Tivoli Software January 23, 2003

Your budgeting companion

Community Empowerment (Scotland) Bill. Policy Memorandum. Easy Read version

Transcription:

Peak and off-peak electricity distribution charges 24 November 2017, Franck Latrémolière, Reckon LLP 1. Setting different charges for peak-time and off-peak use of electricity distribution systems is common enough. But are the methods used to set these differentials reputable? 2. The answer, obviously, is that it depends. It would be very ambitious to try to classify all the methods that have been used; so I am not going to do that. 3. Instead I use just a few examples which I happen to know something about: (a) The TURPE, which is the system used to set most electricity network use of system charges in France. (b) The CDCM (common distribution charging methodology), which is the system used to set electricity distribution use of system charges in England, Wales and Scotland. This actually provides two examples because the CDCM changes significantly for charges after 1 April 2018, with the implementation of a modification known as DCP 228. French TURPE 4. Under the TURPE, the allocation of network capacity costs to unit rates is done in three steps: (a) First the costs of network capacity are allocated to each hour within the year. (b) Then within each hour the costs are shared between the units distributed within that hour. (c) Then a statistical technique is used to convert different prices in each hour into something more manageable like a five-rate seasonal time of day tariff. 5. Once costs are allocated to hours, sharing them between users is uncontroversial. The main properties of the TURPE therefore derive from the method used for the first step of the allocation. 6. The TURPE decision document expressly rejects something it calls marginal costs, because that would recover all the money from peak-time users. Instead the method used is labelled as incremental costs, and works as follows in respect of each network level: (a) The hours in the year are sorted in order of increasing load. (b) For the first hour to be taken out of that list, which is the hour with the lowest load, the cost of the capacity needed to meet that load is shared across all the hours in the year. 1

(c) Then, for each subsequent hour in the sorted list, the annual cost of the additional capacity needed to meet the additional load in that hour is shared with all the remaining hours in the list. (d) The last hour in the list, being the hour with the highest load, bears the full annual cost of the last little tranche of network capacity. 7. A simple example might help. Let s say that, for a section of network, load is 100MW for 8,520 off-peak hours in the year, and 200MW for 240 peak hours, and that network capacity costs 50/kW/year. The total annual cost of 10 million is split into two 5 million increments, one shared between all 8,760 annual hours giving 571 an hour, and one shared between 240 peak hours giving an extra 20,833 for each peak hour, making a total of 21,404. The unit rates are therefore 0.571p/kWh off-peak and 10.702p/kWh at peak time. Figure 1 illustrates these calculations. Figure 1 TURPE allocation of capacity costs to hours 8. At first sight, and bearing in mind my earlier advice to privatise costs and socialise benefits, 1 this sounds good. Each hour is paying for the total cost of the capacity that it uses, scaled down by the number of other hours that each tranche within this capacity is being shared with. That way of scaling down is a sound way of sharing the network benefit that arises from the fact that the same network infrastructure provides distribution capacity at different times. 1 http://dcmf.co.uk/hector-2017-11-19.html 2

9. Of course, a sound method of socialising benefits would provide no protection against an unsound method of privatising costs. 10. Given that the method was based on slicing the year into individual hours, one crosscheck that seems useful is to confirm that the end results are providing a good split of network benefits between users that have realistic all-year load profiles. 11. Let s take someone consuming 100kW at all times. That person is using 100kW of network capacity, worth 5,000 a year. 12. So what share of network benefit does TURPE give them? For the off-peak hours, 100kW represents 0.1 per cent of the total load so a 100kW flat load picks up a charge of 0.571 an hour, totalling 4,865. For the peak hours, it s 0.05 per cent of 21,404 times 240 hours, which comes to a further 2,568. So under TURPE the flat load is paying 7,433 a year, for capacity worth only 5,000. Something has gone wrong. 13. The reason for the error is that the product that the distribution system really provides is network capacity, which is available at all times, and not the transport of electricity at particular times. 14. There is nothing wrong with charging for a capacity service on a consumption basis, provided that the charges are constructed in a way that does not attempt to double charge customers for the underlying capacity. Thus, a 100kW flat load customer who only uses 100kW of capacity should not pay more than the cost of 100kW of capacity. TURPE violates that constraint. 15. A better cost-allocation method can be constructed by analysing the consequences of a rule against multiple charging for the same capacity. After the flat load constraint, the next constraint would come from a hypothetical customer who takes a flat load in every hour except the lowest-load hour, and so on. Figure 2 illustrates this decomposition of total demand in the same simple case as figure 1. 16. The resulting allocation is simpler than TURPE: the 10 million total gets split into two 5 million pots, one recovered from 100MW of flat load and the other recovered from 100MW of peak-time-only load. 3

Figure 2 Sensible allocation of capacity costs to hypothetical customers 17. Under TURPE, the analysis of demand as a collection of individual loads in individual hours led to a lot of network benefits to be shared back. This alternative way of packaging demand, because it implies more intelligent customer behaviour, does not: the total network capacity required is equal to the sum of the capacity used by each user group. 18. Translated into unit rates, at first sight this approach would mean charging zero at all times except in the peak hour where the unit rate could be very high in cases where the maximum load is reached in a single hour (or half hour, or quarter hour). But of course all the analysis above only holds for a single transformer or circuit. In reality, costs need to be calculated and allocated in respect of broad sections of networks containing many assets, which peak at different times. Using the distribution of peaking times in the analysis will ensure that the total cost of a network level is spread over hundreds or thousands of hours in a year. 19. The apparent network benefits that were being shared in TURPE were an artefact of an assumption of inefficient packaging of demand, which led to multiple charging of flat loads for the same capacity. The sharing of the false network benefits across all users mitigated that multiple charging somewhat, but not enough to prevent flat loads from incurring excessive charges. 20. As a result of these defects, the TURPE unit rates might put the distributor in breach of the prohibition on abuse of a dominant position, in two ways. 4

21. There is exploitative abuse because the distributor is using the dominant position arising from its incumbency/concession status to charges prices to flat loads that amount to double-charging for the cost of the relevant capacity, which it could not have done if there had been normal and sufficiently effective competition for the provision of network capacity. 22. There is discriminatory abuse because an all-year flat load and a part-year flat load which are both active at peak time are being charged materially different prices even though they use the same network capacity. British CDCM before DCP 228 23. The CDCM before DCP 228 operates on the basis of things it calls peaking probabilities, which are really peaking frequencies: the proportion of assets at each network level which have their peak within each time band. This is consistent with the idea advocated above of allocating the cost of each asset to its peaking time, and then recognising that there will be a distribution of peaking times and therefore a spreading of costs. 24. There are some incredibly weird and complicated adjustments to peaking probabilities which take place within the Multi sheet of the CDCM spreadsheet model. Whilst these adjustments bring a degree of opacity and some real defects to the methodology, and make forecasting of tariffs harder than it should be, I do not think that they lead to a lot of systematic distortion between peak and off-peak unit rates. 25. The CDCM includes, alongside estimates of network capacity costs, an element of residual revenue or revenue matching which is often positive and large. A major reason for that is that the main cost analysis excludes the majority of costs of repairs and renewals, particularly for low-voltage local distribution infrastructure. 26. In the pre-dcp 228 CDCM, the missing money is instead recovered through an uplift to the costs of the highest voltage level of the network, allocated between unit rates in the same way as these costs (except where doing so would lead to negative prices). This means that the missing charges are levied primarily on peak-time units. 27. The effect of this approach is that peak-time units get overcharged, as they pay for costs which should have been covered primarily from fixed and capacity charges. The magnitude of the error varies a lot between the 14 distribution areas. 28. That misallocation of costs, bad though it might be, does not create a distortion between flat and peaky loads like TURPE does. With the pre-dcp 228 CDCM, people might be charged too much for top-level network capacity, but the overcharge is not discriminatory between different load profiles. British CDCM after DCP 228 29. DCP 228 changes the CDCM by replacing the residual charge/credit on peak-time consumption with a residual charge/credit applied uniformly to units distributed (except where doing so would lead to negative prices). 5

30. This flat charge creates a discrepancy similar to TURPE. Like TURPE, it introduces material discrimination in charges between flat loads and less flat loads that use the same amount of network capacity. Thus, DCP 228 is a change for the worse. 31. Ofgem approved DCP 228 on the grounds that the pre-dcp 228 process of charging peak-time units for the missing money introduces a distortion to the differences between the unit rates and that DCP 228 removes much of this distortion. 2 32. So here is the nub. I care about discrimination identified by comparing a flat load with a less flat load that uses the same services from the distribution network. I want to apply the same /year distribution charges to a factory that works 24 hours a day and a factory that works business hours only, if all relevant parts of the distribution system are sized by reference to loads during business hours only. 33. In its DCP 228 decision, Ofgem cared about distortions between the charge for a unit of electricity taken at peak time and the charge for a unit taken off peak. This means that Ofgem was not comparing a 24-hour factory with a business-hours factory: instead it was comparing a 6 am to 3 pm office with an 11 am to 8 pm office, and wanted to make sure that the higher distribution charges levied on those who prefer a lie-in did not exceed the costs attributable to consumption during the evening peak. 34. It did not matter to Ofgem that they were allowing discrimination against the factory that would be creating economic growth by moving to 24-hour operation using spare electricity distribution capacity. It did matter to Ofgem to ensure that the incentive against having a lie-in was not too strong. By their priorities you shall know them. By the way 35. A unit rate calculation methodology that looked similar to TURPE was discussed in the context of the recent CDCM review: I think that it is option 2B in the final report. 3 36. The difference was that costs were split between distribution units in different time bands in one step (instead of being split between hours first). But the principle, effect and defects are the same as with TURPE: in particular, that method would doublecharge flat loads for network capacity. It looks like British electricity distributors can be as wrong as the French, sometimes. Shameless plug 37. Go to dcmf.co.uk/models to explore further how this works in practice in the CDCM. The spreadsheet model generator at dcmf.co.uk/models is useful because it can give you a wide variety of charging models populated with any of the input data published by distributors since 2010. 2 3 https://www.ofgem.gov.uk/publications-and-updates/distribution-connection-and-use-system-agreement-dcp228-revenuematching-cdcm http://www.energynetworks.org/electricity/regulation/distribution-charging/distribution-charging-working-groups.html 6