INTERNATIONAL SEMINAR LONG TUNNELS

Similar documents
D&B versus TBM some case stories

The Stendafjellet Rock Quarry and Underground Waste Disposal site

MTR Shatin to Central Link Contract 1103 Hin Keng to Diamond Hill Tunnels Hong Kong, China

Vest Process Propane Cavern Project, Norway

How to achieve faster drifting in mining, some aspects. SME Denver February 2007 Gunnar Nord Atlas Copco Rock Drill AB Sweden

The project. The Follo Line Project is currently the largest transport

Semmering Base Tunnel Large Caverns in Challenging Conditions

Internal report no. 2217

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

MODERN PRE-INJECTIONS IN UNDERGROUND CONSTRUCTION WITH MICROCEMENTS AND LIQUID COLLOIDAL SILICA FOR WATER INGRESS REDUCTION AND GROUND IMPROVEMENT

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES

TBM experiences from the Koralm railway tunnel (Austria) and re-use of TBM muck. Gerhard HARER

SPECIAL PROVISION Description of Project, Scope of Contract, and Sequence of Work

SECTION EXCAVATION AND FILL

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

THE GROUNDBREAKING TUNNEL

Pump storage hydro power plant (PSKW) Reißeck

SELECTION OF CONSTRUCTION METHODS IN ROCK TUNNELING

Peter J Tarkoy, PhD, Geotechnical and Construction Consultant

Challenges in designing a complex urban tunnel in Tehran metropolitan (Arash-Esfandiar-Niayesh) Islamic Republic of Iran

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations.

Annex V Concrete Structures Removal Plan

The government of the SOCIALIST REPUBLIC OF VIETNAM HO CHI MINH CITY PEOPLE S S COMMITTEE TUNNEL JAPAN. Official Development Assistance

SUB-SLAB DIAGNOSTICS

The Drainage Basin. From Peaks of Colorado to Mexico 1,400 miles Drains 242,000 square miles of Western US Colored River because of sediments

BRILLIANT EXPANSION PROJECT

FAST-Tunn Future Advanced Steel Technology for Tunnelling

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

Stack Parking Surface Mounted Stackers

Construction Specification for General Excavation

Tunnel. Immersed Tunnels

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

UNDERGROUND CHARACTERISATION AND RESEARCH FACILITY ONKALO ANTTI IKONEN, MIA YLÄ-MELLA, TIMO ÄIKÄS POSIVA Oy Olkiluoto, Finland

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

D-Raintank. Forward-Looking Rainwater Drainage. Collecting Drainage Saving

Asphalt on Concrete Base with Waterproofing Membrane

Geo-treatments in Constructing a Tunnel in Karst Strata: Lessons Learned from the Metro Subway Project in Guangzhou, China

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

Underground Waste Depositing at Odda, Norway

Global Leaders in Tunnel Ventilation

SECTION GENERAL EXCAVATION

Appendix 15 Estimated costs of dams

Loss Control TIPS Technical Information Paper Series

Bridge Life Cycle Optimisation

Design of Izmir Bay Crossing Bridge

Figure Inlet protection (Source: Minnesota DOT)

ArmorFlex. Articulating Concrete Block Revetment System

CONSTRUCTION MANUAL 2.5 x 5 UNITS

The Follo Line Project METHOD DEVELOPMENT: TOWARDS A MORE SUSTAINABLE RAILWAY

JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project

Project: King Abdulaziz International Airport KAIA 2

CROSSRAIL INFORMATION PAPER D24 TUNNELLING DURATION AND CONSTRUCTION STRATEGY

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways

ENVIRONMENTAL MANAGEMENT PLAN FOR DALPATPUR STONE QUARRY AT VILLAGE DALPUTPUR TEHSIL KHURAI AND DISTRICT SAGAR [MP], AREA (0.

Figure (12.1) Foundation Grouting

ILC ASIAN DRAFT SCHEDULE

406 - PIPE SEWERS - MTC FORM 406

maximum mobility, easy operation.

PRELIMINARY VENTILATION AND COOLING DURING THE CONSTRUCTION OF THE BRENNER BASE TUNNEL

TUNNEL CONSTRUCTION GUIDELINES 05 - GUIDANCE NOTE ON PRE-EXCAVATION GROUTING FOR

SECTION EARTHWORK

SECTION 303 CULVERTS

100% Payment. 105% Payment #

Select Subgrade Material, Compacted

rapid tunnelling thanks to efficient SePArAtion. Low-impact mechanized tunnelling: Integrated solutions.

An alternative mining method at the Kvannevann Mine, northern Norway

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

APPLICATION FOR PIPE OR WIRE OCCUPANCY

Crushing Optimizing the Process

2019 Semester Terms and Dates Summary

BASE CONSTRUCTION MATERIALS A Aggregate

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

Section 02 SUBSTRUCTURE

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations.

2.1.4 PROJECT CONSTRUCTION

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

BIRCOsir. Installation Instructions. A number of details must be observed when installing BIRCOsir. For a comprehensive description please read here.

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

The Aizhai Suspension Bridge is

Installation Guidelines

Redi Rock Specification and Installation Manual

1 HB By Representative Greer. 4 RFD: Transportation, Utilities and Infrastructure. 5 First Read: 03-MAR-15. Page 0

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG

Technical Documentation

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS

HUDSON TUNNEL PROJECT

DIFFICULT GROUND SOLUTIONS:

Best Practices for Building High-Performance Resource Roads. Road Drainage. Developed by: The Roads and Infrastructure Group

New Bridge over Llobregat River

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

Tunnel Ventilation System Design and Air Quality. Peter Gehrke and Andrew Purchase

CHAPTER 3 EXCAVATIONS

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

B510-5 REMOVAL-PAVEMENT WORK OPSS 510. CDED B Removal CDED B Reclaim Asphalt Pavement

Wastewater Capital Projects Management Standard Construction Specification

Presentation Outline

Effect of Niche-Tunnel Face Distance and Excavation Time in Tunnel Construction

Transcription:

INTERNATIONAL SEMINAR LONG TUNNELS Desafío para el Diseño, Construcción y Operación Challenges for Design, Construction and Operation Construction of long road s in Norway including the Lærdal Chief Scientist Professor Eivind Grøv SINTEF/NTNU and SKAVA when in Chile Past President Norwegian Tunnelling Society Past Vice President ITA 17, 18 y 19 de Octubre 2012 Santiago, Chile PIARC CHILE

Construction of long road s in Norway Long traffic s in Norway 3 of the 10 longest road s in the world are in Norway 30 (++) road s are longer than 5 km Appr. 10 of these are subsea s Appr. 5 are longer than 10km 2 railway s are longer than 10 km, dating back to the nineties and the seventies Plans are under preparation for Follo-Ski 2 x 20 km rail way s Rogfast 2 x 25 km sub sea road to -390 Ryfast 2 x 14,3km sub sea

Construction of long road s in Norway Motivation for our study: How to better plan the physical construction of long s Tunnelling, short or long s is basically a matter of logistics It is the master minding of careful and intelligent logistics and planning Often this is the contractors competitive edge Having reached that recognition does it really matter whether the is 5 or 25 km long? The challenge is: how to achieve an industrial production process when there is one access for all works to be done. Is it relevant to leave the solely to complete excavation works?

Construction of long road s in Norway Key-issues to be focused during construction: Health and safety aspects Ventilation Mucking out/transportation Initial support become permanent support Time schedule How to improve these aspects? Problem defined as; limited access & confined space

Project Type of project Tunnel length Construction of long road s in Norway Overburde n Tunnel width Number of exits/entran ces Number of working faces Maximum length of face Constructio n time (mobilisatio n to opening of the s) Lærdal Road Folgefo nn Road Bømlafj ord Sub sea road Eiksun d Subsea road Atlanterh avs Subsea road Frøya Subsea road Korgfjel let Road Steigen Romerikspo rten Oslofj ord Road Railway Subsea road Gudvang en Road 24.5 km 11 km 7.9 km 7.765 km 5.727 km 5.3 km 8.533 km 8.060 m 14.58 km 7.306 m 11.424 km 1400 m >800 m rock cover for 20 km 9 m (dual lane, single tube) 2 + 1 adit 8 m (dual lane, single tube) 262 meter below sea level, min. 35 m rock cover 11 m (triple lanes single tube) 287 meter below sea level Partly 11.5 m and partly 9.5 m (single tube, 2/3 lanes) 245 m below sea level. Approxima tely 40 m rock cover 11 m (single tube, mostly three lanes) 164 m below sea level. Rock cover 41-155 m. 8 m (single tube, two lanes) 10 to 250 m 134 m below sea level (min. 32 m rock cover) 8 m 7 m 11 m 11 m (three lanes) 2 2 2 2 2 2 2 2 + 2 adits 2 + 1 adit 4 2 2 2 2 2 2 2 6 4 2 Approx. 9 km July 1995 Novemb er 2000 Approx. 6 km May 1997 May 2001 Approx. 4 km Septemb er 1997 - Decembe r 2001 Approx. 5 km February 2003 February 2008 Approx. 3 km. August 2006 spring 2009 (planned) Approx. 8 m 2.6 km 4.5 km 4.3 km 3.6 km 3 km 6 km January 1998 1997 June 2000 October 2001 Septemb er 2005 1987-1990 August 1994 - August 1999 April 1997 - June 2000 2 Opened in December 1991

Construction of long road s in Norway Project Lingvang Breidal Tyin Svea Dividalen Troll Langevann, IVAR Type of project Water transfer Water transfer Headrace Coal transport Access to radar site Subsea pipeline Water transfer Tunnel length 8.9 km 10 km 11,3 km 5.7 km 9.8 km 7.5 km 7.8 km Tunnel width 5 m 5 m 7 m 3.6 m (18 m 2 ) 6.6-8.6 4 m (25 m 2 ) (20 m 2 ) m Overburden Approximately 600 m Up to 1000 m rock cover. Up to 600 m (half of is below a glacier) 180 m below sea level (7m piercing) Number of exits/entrances Number of working faces Maximum length of face 1 2 1 + 1 adit 1 1 (+ 1 adit for air and dump site) 1 1 + 1 adit (?) 1 2 3 1 1 4 2 (?) 8.9 km 5 km 4.4 km 5.7 km 9.8 km 3.6 km 4 km (?) Tunnelling method Construction time (mobilisation to opening of the s) Notes Drill & blast Drill & blast Drill & blast Drill & blast Drill & blast Drill & blast 2005 2008 October 2001 September 2003 November 2002 December 2003 Started in permafrost September 1990 September 1993 1400 m height difference or 1 : 7 uphill October 1991 January 1996 Lowest level 240 m below sea level Drill & blast April1997 November 2002

Construction of long road s in Norway A crucial parameter when it comes to long s, large cross sections width > 8m: Room for efficient loading, transportation and mucking out, no need for niches Sufficient ventilation and large size vent ducts, two way Multitasking in terms of several activities taking place simultaneously as the face is progressing Whilst small cross sections: Lack of room makes the entire logistic exercise difficult

Construction of long road s in Norway Norwegian contract practice On one hand: The Owner carries the risk for the ground conditions The Owner is responsible for the collection of information on ground conditions. All information is disclosed to the tendering contractors for their own interpretation. The Owner provides his interpretation of the situation in terms of estimates on quantities on rock support, grouting etc. Whilst: The Contractor carries the risk for the appropriate and efficient handling of the works and focus on improving his technical and organizational performance. The contracts include regulations for extension of construction time based on actually performed quantities, Standard capacities, or equivalent time system.

Construction of long road s in Norway Risk sharing principle

Construction of long road s in Norway Project references

Construction of long road s in Norway The Lærdal, - the longest road in the world, and open for general public traffic

Construction of long road s in Norway Implemented in the Lærdal Tunnel Rock Crystals Zhongnanshan Tunnel, China, The worlds longest twin tube : 18 km

Construction of long road s in Norway Sectional completion-lærdal Most of the permanent rock support was installed at or close to the face. The lower part of the road embankment was replaced every week to be able to have an appropriate transport surface. Work was going on continuously with the construction of the ditch and with the installation of drainage pipes, cable canals and cables. Twice a year the permanent road embankment was established in addition to the first layer of asphalt. This was the permanent road construction, but approval was granted for use in the construction period.

Construction of long road s in Norway Entrance to the 11 km long Folgefonn

Construction of long road s in Norway Sectional completion - Folgefonn Blast and excavate the and the ditch simultaneously. Install all permanent rock support at the face, or at least before the installation of the ventilation duct. Install all equipment in the ditch in sections of 1000-1500m. Utilize the excavated rock as road embankment. A temporary asphalt layer to be laid allowing transport to take place on a covered surface. Installation works, except rock support, were not allowed to take place closer than 400m from the face.

Construction of long road s in Norway The Bømlafjord sub-sea south of Bergen 7,9 km long sub sea Reaches to - 240m At the steepest inclined 8,5% One contractor at each side

Construction of long road s in Norway Sectional completion - Bømlafjord subsea The contractor completed sections with length of approximately 1000 m. Due to the poor quality of the rock all blasted rock needed to be replaced, and the sectional completion included a complete re-establishing of the road embankment. The completion included rock support, ditches, drain pipes, man holes, cable canals and electrical/fiber-optic cables. The completion included also a first layer of asphalt.

Construction of long road s in Norway Bømlafjord, - disadvantages of not using sectional completion experienced by the second contractor A permanent sand filter facility had to be established outside the to clean drainage water due to large production of fines. The material in the road embankment of the temporary road in the was crushed due to the load from the heavy traffic. Additional ventilation fans due to large amounts of dust and exhaust air. Dirty working conditions affected negatively the Health and Safety aspects in the. Frequent local replacement of road embankment to maintain construction traffic.

Construction of long road s in Norway The feedback from owners and contractors: Significant challenge to the contractor in planning his works Increased manning and demand on equipment Improved Health&Safety during construction Owners report time savings Reduced cleaning of interior Contractors valued aspects related to transport and hauling, increased efficiency, reduced maintenance on equipment and tear & wear Everyday production increased The contract has to address specific instructions, time and incentives

Construction of long road s in Norway Time is money in the ling industry! Potential advance rate (good fair rock conditions, easy or no pregrouting, min. support): 4,8 m net penetration per round, 2 rounds per day, 6 days per week: 58 m/week High intensity pre-grouting, increased support: 2 rounds per every 2 nd day: 29 m/week Very poor rock: 1 round per day, net penetration 2,5 m: 15 m/week Projects have had up to 175m/week with drilll&blast Various comparisons done suggest a factor from 3-10 more cost efficient ling in Norway! Lærdals appr. 8.2 mill Euro per km Romeriksporten railway appr. 16 mill Euro per km One needs to ask WHY!!!

Construction of long road s in Norway Aspects to be focused during construction High capacity equipment, multi-skilled workmen at the ling face allowing high utilisation of the equipment. Adaptability to the actual ground conditions, careful following-up of the encountered rock mass by mapping and classification for a best fit of rock support measures. Observation of the ground behaviour by visual surveying and physical measurements if required fulfilling the intentions of the Observational method. Installation of permanent rock support as close to the face as practically possible fulfilling the criteria for permanent support work.

Construction of long road s in Norway Unique Co-operation at the site Constructive cooperation between the representatives of the involved parties. Experienced professionals participating in the decision making. Solve conflicts at construction site by negotiation after the technical issues have been settled.

Construction of long road s in Norway Hard rock environment The Scandinavian host rock varies from poor to extremely good rock. Folding, faulting and high tectonic stresses influence the quality of the rock Weakness zones can exhibit great variation in quality, Q-values may vary from extremely poor to good The width of such zones may vary from a few centimeters to tens of meters Permeability may vary significantly The CHALLENGE: to deal with frequently changing ground conditions It is typical Hard Rock not necessarily Good Rock

Construction of long road s in Norway Conclusions! Take care of your logistics! All parties benefit from a reduced construction period! Sectional completion is a way to secure this goal for long construction Sustainability and CO2 emission are issues to keep in mind also The ultimate goal of our efforts: Reduce the construction time on overall, not sub optimize single activities Thank you for your kind attention!