Applying landforming to reclamation: A case study in Central Appalachia

Similar documents
GEOMORPHIC LANDFORM DESIGN PRINCIPLES APPLIED TO AN ABANDONED COAL REFUSE PILE IN CENTRAL APPALACHIA 1

CCR Rule Operating Criteria Closure Plan

Typical Local Erosion Control Requirements (Storm Water Management Authority, Inc.)

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

INITIAL RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART 257

PEARCE CREEK CONFINED DISPOSAL AREA MODIFICATION

RUN-ON AND RUN-OFF CONTROL PLAN 40 C.F.R. PART PLANT DANIEL NORTH ASH MANAGEMENT UNIT MISSISSIPPI POWER COMPANY

RETENTION BASIN EXAMPLE

Diversion Dikes. Fe=0.95

Manual for Erosion and Sediment Control Updates

Sediment Control Practices

Earth Dikes and Drainage Swales

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY

Since the Game Lands are publicly owned, reclamation can be done with Project 500 bond issue funds. E. D'Appolonia Consulting Engineers, Inc.

Suggested Stormwater Management Practices For Individual House Lots

Description. Installation and Implementation Requirements

ET COVER SYSTEM IN ARID ENVIRONMENTS

Technical Memorandum

VISUAL SITE INSPECTION REPORT 2018

AREA XXVI Total

EAGLE DRAINAGE DESIGN STANDARDS

SC-01 Surface Outlet and Baffle Sediment Basin

Operating and Reclamation Plan

Landfill design General principles

Black Butte Copper Project Mine Operating Permit Application (Revision 3) Water Management During Construction and Operations

CE 585 Construction Site Erosion Control The University of Alabama Tuscaloosa, AL. New Chevrolet and Cadillac Dealership Jasper, AL

DEPARTMENT OF ENVIRONMENTAL QUALITY WATER BUREAU PART 17. SOIL EROSION AND SEDIMENTATION CONTROL

Coal Combustion Residuals (CCR) Run-on and Run-off Control System Plan

CHAPTER 13 STRIP MINE RECLAMATION AND SOLID WASTE LANDFILL

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY

WQ-06 SAND FILTER. 1.0 Sand Filter. Greenville County Technical Specification for: 1.1 Description

Warner Robins Stormwater Local Design Manual

New techniques for stabilizing, amending and revegetating mine waste

TEXAS WESTMORELAND COAL COMPANY. Jewett Mine DS E-11 Civil Structure

Closure Plan Limited Purpose Landfill TransAlta Centralia Mine

APPENDIX C DURING CONSTRUCTION BMP TABLES

Lake Lorelei Property Owners Association Rip Rap Standards Recommendations. Revision 0 February 2018

Storm Water Permitting Requirements for Construction Activities. John Mathews Storm Water Program Manager Division of Surface Water

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GASTON GYPSUM POND ALABAMA POWER COMPANY

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

Appendix E. Coordinating Erosion and Sediment Control With Low-Impact Development Planning

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY

4.4.5 Grassed Swale (also known as Enhanced Swale or Biofiltration Swale)

POST CLOSURE PLAN. CFR (d) GERS Landfill. Mitchell Power Plant Marshall County, West Virginia. October, 2016

Technical Memorandum Mine Plan of Operations Stormwater Assessment

Stormwater Local Design Manual For Houston County, Georgia

C-1. Infiltration System

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

Porous Pavement Flow Paths

Environmental Management Chapter ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT WATER DIVISION - WATER QUALITY PROGRAM ADMINISTRATIVE CODE

Watershed size and name: The drainage area is acres. The pond is located within the Ohio River watershed. (2016 Inflow Design Plan)

Example 1: Pond Design in a residential development (Water Quantity calculations for a Wet Pond and Wet Extended Detention Pond)

GRADING, EROSION AND SEDIMENTATION CONTROL

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Construction Inspection Checklists

MODEL Stormwater Local Design Manual. City of Centerville

Chapter 3 Dispersion BMPs

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY

Jacobi, Toombs, and Lanz, Inc.

LANDFILL CLOSURE PLAN ENTERGY ARKANSAS, INC. INDEPENDENCE PLANT CLASS 3N CCR LANDFILL PERMIT NO S3N-R2 AFIN

Chapter 6 Erosion & Stormwater Study Team

3.11 Sand Filter Basin

Shirley E. Clark, Ph.D., P.E. October 5, /30/2012

Contents. Drainage Analysis: Hunters Trace, Westpointe, and Hunters Creek

Bowling Green, Kentucky Stormwater Best Management Practices (BMPs) Sediment Management Practices (SMPs) Activity: Temporary Inlet Protection (TIP)

Page 1 of 6 Permit No: MN R J. Mineral Mining and Dressing

Geomorphic Reclamation on the Lionkol Project SUBMITTED TO: American Society of Mining and Reclamation June 2014

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY

2015 ANNUAL ENGINEERING INSPECTION REPORT ENTERGY WHITE BLUFF PLANT CLASS 3N LANDFILL PERMIT NO S3N-R3 AFIN:

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose

CCR Impoundment Closure: Reshaping your Ash! 2017 MWCC Technical Conference

York County STORMWATER LUNCH & LEARN

METROPOLITAN UTILITIES DISTRICT No Page: 1 of 10

E. STORMWATER MANAGEMENT

Chapter 2: Selecting Best Management Practices (BMPs)

North Omaha Ash Landfill Run-on and Run-off Control System Plan

B. Install storm drain inlet protection to prevent clogging of the stormsewer and sediment loads to downstream stormwater facilities or waterbodies.

Run-on and Run-off Control System Plan

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

POST CLOSURE PLAN. CFR (d) Pond 1. Clinch Power Plant Russell County, West Virginia. November Prepared for: Appalachian Power Company

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

PRELIMINARY DRAINAGE STUDY

AND HOW IT RELATES TO TITLE 25 CHAPTER 102 or What We Look For and Why. Southeast PA Conservation Districts June 26, 2009 Creamery, PA

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. Part PLANT MCINTOSH ASH POND 1 GEORGIA POWER COMPANY

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

STANDARD GRADING AND SOIL EROSION & SEDIMENT CONTROL PLAN FOR SINGLE LOT SINGLE FAMILY RESIDENTIAL CONSTRUCTION AND MINOR EARTH DISTURBANCES

The Good, The Bad, and The Ugly

Guidance on each of the 23 basic elements follows: Plan Index showing locations of required items: The plan index should include a list of the

Lockatong and Wickecheoke Creek Watersheds Roadside Drainage Retrofits

E&S BMP DESIGN. Working Toward a Better Conclusion

Flow Diversion Banks: General

Closure Plan Ash Disposal Area PGE Boardman Power Plant

VISUAL SITE INSPECTION REPORT

Appendix K: Soil Erosion and Sedimentation Control Plan Check List

Storm Water Pollution Prevention Plan (SWP3) Checklist

POST CLOSURE PLAN. CFR (d) GERS Fly Ash Pond. Big Sandy Plant Louisa, Kentucky. October, 2016

HISTORY OF CONSTRUCTION 40 CFR (c)(1)(i) (xii) PLANT HAMMOND ASH POND (AP 2) GEEORGIA POWER COMPANY

Lansing Generating Station Project No Closure Plan for Existing CCR Revision: 1 TABLE OF CONTENTS

Erosion and Sediment Pollution Control Guidelines for Residential Lots with soil disturbance of less than 1 acre (see exceptions)

Transcription:

Applying landforming to reclamation: A case study in Central Appalachia Leslie Hopkinson, John Quaranta April 12, 2017 Department of Civil and Environmental Engineering West Virginia University WEST VIRGINIA UNIVERSITY Department of Civil and Environmental Engineering

Outline Geomorphic reclamation Royal Scot reclamation project Topography Cap and cover Drainage Soil amendment and vegetation Conclusions 2

Geomorphic landform design is a potential approach to reclamation not widely applied east of the Mississippi. Simulates undisturbed channel and basin geomorphology Applied in Western US and abroad Erosional and geotechnical stability benefits observed (OSM, 2006) (OSM, 2006) 3

4 (Shor and Gray, 2007)

Challenges in Central Appalachia: Conventional Landforms Continual maintenance High flow velocities Sediment transport Geologically Young landforms Geomorphic Landforms High precipitation Increased stream impact Perceived increase in cost Reluctance of industry change

Royal Scot Coarse Coal Refuse Facility: Cease and Desist Order: 2001 Due to consistent water quality violations Groundwater seeps throughout the area Consistent with acid mine drainage Water quality is a perpetual problem Highest single cost for an abandoned site in West Virginia PROJECT GOAL: Minimize perpetual water treatment costs by segregating storm water and groundwater flows

Royal Scot Demonstration Site 2015 OSMRE Applied Science Program Collaborators: WVU Department of Civil and Environmental Engineering West Virginia Water Research Institute West Virginia Department of Environmental Protection 7

Royal Scot demonstration site Located in Greenbrier County, WV Coarse coal refuse disposal site Abandoned in 2001 Ridge-top location 8

Royal Scot Site Design Considerations Boundaries Water quality Existing features Active Mining Permit to the North and West Collection Pond (Stormwater & Groundwater) Highwall Pit Sludge Pit Treatment Ponds Discharge Point Seeps Interception Pond Private Forest Land to South and East Seeps downslope

Royal Scot Coarse Coal Refuse Pile: Barren Coal Refuse Negligible vegetation Erosion throughout Steep slopes + 2:1 Access Road Erosion Interception Pond

Interception Pond: Underdrain is plugged No controlled outlet Pond invert is on rock Rock mass is heavily jointed Seepage Seep response tests conducted by WV DEP Flow paths Response time Interception Pond Western View Interception Pond Eastern View Erosion

Sludge Pit: Water Treatment Pond Disposal of pond sediment Air dry sediment in the Sludge Pit Sediment contains heavy metals Sludge Pit Sludge

Adjacent Highwall: Highwall Pit Active mining permit Access must be maintained Western limit to the reclamation Advanced Sediment Transport Ponding and Erosion

Existing Site: Limit of Disturbance Advanced erosion Barren Sludge Pit Interception Pond Adjacent Permits Seeps throughout Ongoing water treatment Limit of Disturbance

Royal Scot Reclamation Objective: Develop a reclamation alternative utilizing geomorphic landform design principles at the Royal Scot Coarse Coal Refuse Facility 1. Reduce stormwater infiltration 2. Segregate stormwater and groundwater flows 3. Minimize construction costs

Basic approach: Regrade site, decrease infiltration, and manage runoff 16

Basic approach: Regrade site, decrease infiltration, and manage runoff 17

Final design Four geomorphic watersheds Connected by benched slopes Draining to perimeter channel Pond sized for 100-yr event

Final design Four geomorphic watersheds Connected by benched slopes Draining to perimeter channel Pond sized for 100-yr event

Final design Four geomorphic watersheds Connected by benched slopes Draining to perimeter channel Pond sized for 100-yr event

Final design Four geomorphic watersheds Connected by benched slopes Draining to perimeter channel Pond sized for 100-yr event

Final design Four geomorphic watersheds Connected by benched slopes Draining to perimeter channel Pond sized for 100-yr event

Example longitudinal profile North North South South 23

Example longitudinal profile North North South Existing South Design 24

Results: Earthwork Quantities Description Unit Cut Fill Total Area [acre] 21.6 23.4 47.0 Volume [yd3] 267,730 295,839 (28,109) Avg. Depth [ft] 7.66 7.84 - Cut : Fill [_] - - 0.90 [yd3] - - (28,109) Import Note: 1.95 acre at grade *Contours shown on 5ʹ intervals

Results: Slope Distribution Region % Slope Acres % of Total Dark Blue < 15 20.1 42.9 Cyan 15 to 25 7.6 16.2 Green 25 to 35 7.9 16.8 Yellow 35 to 45 7.3 15.5 Orange 45 to 50 4.0 8.5 Red > 50 0.1 0.1

Results: Geomorphic Channels Bed Slope Varies Riprap Liner D50: 9.0 to 12.0 inch Channel Filter D50: 3.0 inch Vegetation Liner Type 1 Cap Flow Reach Liner Length Peak Flow Bottom Width Depth Bed Slope Bedding D₅₀ Filter D₅₀ [Name] [Mat l] [ft] [cfs] [ft] [ft] [ft/ft] [in] [in] Channel A 1 Rip Rap 399 23.4 6.0 0.8 0.12-0.20 9.0 3.0 Channel A 2 Rip Rap 114 5.0 5.0 0.6 0.19 9.0 3.0 Channel B 1 GRASS 475 19.3 4.5 2.3 0.02-0.03 GRASS Channel B 2 Rip Rap 190 11.1 4.0 0.9 0.04-0.09 9.0 3.0 Channel B 3 Rip Rap 67 5.9 3.5 0.7 0.12 9.0 3.0 Channel C 1 Rip Rap 519 25.9 6.0 0.8 0.12-0.24 12.0 3.0 Channel C 2 Rip Rap 103 3.5 4.0 0.6 0.20 12.0 3.0 Channel D 1 Rip Rap 313 18.2 5.5 0.8 0.12-0.27 12.0 3.0 Channel D 2 Rip Rap 201 7.0 4.5 0.6 0.26 12.0 3.0 *Channels shown in Blue

Example geomorphic channel (GLD A) Cross-section Plan view Existing Design Longitudinal

Results: Conventional Ditches Bed Slope 50% Riprap Liner D50: 15.0 to 18.0 inch Channel Filter D50: 3.0 inch Flow Reach Liner Length Peak Flow Bottom Width Channel Depth Bed Slope Bedding D₅₀ Filter D₅₀ [Name] [Material] [ft] [cfs] [ft] [ft] [ft/ft] [in] [in] Ditch F Rip Rap 155 16.9 4.0 1.1 0.50 18.0 3.0 Ditch G Rip Rap 160 5.9 2.0 1.1 0.50 18.0 3.0 Ditch H Rip Rap 130 7.8 3.5 1.1 0.50 15.0 3.0 *Channels shown in Blue

Example drainage on benched slope (Ditch F) Cross-section Longitudinal Existing Design

Results: Perimeter Ditches Bed Slope 2.0 to 15% Riprap Liner D50: 9.0 to 12.0 inch Channel Filter D50: 3.0 inch Flow Reach Liner Length Peak Flow Bottom Width Channel Depth Bed Slope Bedding D₅₀ Filter D₅₀ [Name]* [Material] [ft] [cfs] [ft] [ft] [ft/ft] [in] [in] P. Ch. West - 1 Rip Rap 756 108.8 10.5 1.8 0.02 9.0 3.0 P. Ch. West - 2 Rip Rap 1,514 68.3 7.0 1.8 0.02-0.15 9.0 3.0 P. Ch. East - 1 Rip Rap 350 69.6 8.0 1.7 0.10 12.0 3.0 P. Ch. East - 2 Rip Rap 1,142 57.7 8.0 1.7 0.06 9.0 3.0 *Channels shown in Blue

Cap and cover: 2 Layer Design Growth Layer: Mixture of shale and MGro in fixed volumetric ratio. Initial results from the 60% shale: 40% MGro blend have been favorable. (started here) 60/40 Mgro Geotechnical properties being defined in laboratory testing Proposed thickness = 1 feet 2 Layer Final Cover System Growth Layer Impermeable Layer Site Coarse Coal Refuse (CCR) Impermeable Layer Intended for seepage infiltration control Compacted coarse coal refuse Preliminary thickness ranges = 1 2 ft Refuse pile material (Cut / Fill) Assess necessary compaction Homogeneous Source of the acid mine drainage Field self weight ranges 80 to 90 pcf. Thickness varies 10 ft to 120 ft. 34 Typical MGro sample

Cap and Cover (CAT.com 2016) Slope Stability and seepage analysis performed by Stevens et al. (2016) Finite elemental slope stability Finite element seepage modelling 3 cap thickness evaluated Material property evaluation MGro and coal refuse Failure Planes (FOS<1.5) No flowlines through hydraulic barrier

Results: Cap Types Minimize infiltration Maintain stability Establish vegetation MGro Soil Amendment Type 1 Type 2 Type 3 Type 4

Results: Cap Type 1 (Stevens 2015) 3ʹ 1ʹ 2ʹ Growth Zone 60% refuse : 40% MGro Barrier Zone: 2.0 thickness Minimum infiltration Compacted coal refuse Onsite

Results: Cap Type 2 (Stevens 2015) 2ʹ 1ʹ 1ʹ Growth Zone 60% refuse : 40% MGro Barrier Zone: 1.0 thickness Slightly increased infiltration Pore pressure reduction Compacted coal refuse Onsite Located on lower face of conventional profiles

Results: Cap Type 3 D max 2ʹ 9ʹʹ 9ʹʹ 2ʹ Channel Bedding Resists flow shear forces Channel Filter Inhibits sediment transport of the base material (Refuse) Barrier Zone: 2.0 thickness Compacted coal refuse Onsite

Results: Cap Type 4 Barrier Zone: 3.0 thickness Doubles as road wearing surface Coarse coal refuse Onsite

Tested mixtures of short paper fiber (MGro) and Coarse Coal Refuse (CCR) 60% MGro 40% CCR 80% MGro 20% CCR 100% CCR Week 5: 60/40 80/20 Refuse Percent Cover (%) 90 60 30 0 Biomass (g) 25 20 15 10 5 60/40 80/20 Refuse 0 60/40 80/20 Refuse

Conclusion: Sustainable landforms Four geomorphic watersheds Flow shear force is conservatively designed with self healing flexible membrane channel lining Stormwater infiltration reduction Cap Structure Barrier Zones radial draining, fast but stable channels

Conclusions: Continued Segregate stormwater and groundwater Sludge Pit was capped and the embankment was not included within any excavation Hydraulic network captures 87% of the rainfall Sediment Pond is filled, allowing an impermeable invert to be constructed Sediment Pond is designed as dry and dewaters in 68 hours Minimize construction costs Earthwork balanced Onsite material used for the Barrier Zone throughout Minimal import for soil amendment Channel liner may be produced onsite

Acknowledgements The work described in this publication was supported by Grant/Cooperative Agreement Number S15AC20020 from the Office of Surface Mining. Its contents are solely the responsibility of the authors and do not necessarily represent the official views of the OSM. This work is also in collaboration with the West Virginia Department of Environmental protections. The authors would like to thank Mike Sheehan, Nathan Parks, Dave McCoy, Jason Fox, and Mike Richardson for their continued support.

QUESTIONS? WEST VIRGINIA UNIVERSITY Department of Civil and Environmental Engineering