January 3, 2018 MEMORANDUM. Council Members. John Ollis, Power System Analyst. SUBJECT: Marginal Carbon Emissions Rate Study Draft BACKGROUND:

Similar documents
July 5, 2018 MEMORANDUM. Power Committee. John Ollis, Power System Analyst. SUBJECT: Wholesale Electricity Price Forecast BACKGROUND:

March 31, 2015 MEMORANDUM. Power Committee. SUBJECT: Reporting Power System Carbon Footprint BACKGROUND:

AVOIDED CARBON DIOXIDE PRODUCTION RATES IN THE NORTHWEST POWER SYSTEM

November 10, Tom Eckman, Ben Kujala, John Ollis, Gillian Charles and Massoud Jourabchi

November 6, SUBJECT: Briefing on the effect of compound climate events on adequacy in the Pacific Northwest

June 5, 2018 MEMORANDUM. Council Members. John Fazio, Senior Systems Analyst. SUBJECT: Briefing on Adequacy Analysis and Report BACKGROUND:

November 6, SUBJECT: Report on California s 100 Percent Clean Energy Act

March 7, SUBJECT: Update from Portland General Electric on Their IRP

MEMORANDUM. April 29, Council Members. Charlie Black, Power Planning Division Director. SUBJECT: IHS Report on Columbia Generating Station

March 5, SUBJECT: Additional Background Materials for Scenario Input Assumptions

MEMORANDUM. April 2, Council Members. Charlie Black, Power Planning Division Director. Primer and Briefing on Generating Resources

MEMORANDUM. March 5, Council Members. Charlie Black, Power Planning Division Director. Primer and Briefing on Generating Resources

December 5, SUBJECT: Puget Sound Energy Demand Response, Behind-the-Meter Technology, and Future Risks

April 30, 2013 MEMORANDUM. Council Members. Gillian Charles, Power Planning Division. Update on the Region s Wind Development

MEMORANDUM. January 6, Power Committee. Maury Galbraith. Draft Sixth Plan Electricity Price Forecasts

December 5, SUBJECT: Briefing on Public Generating Pool Decarbonization Study. Therese Hampton, Public Generating Pool, Arne Olsen, E3

November 8, 2016 MEMORANDUM. Power Committee. Tina Jayaweera and Charlie Grist. SUBJECT: Stock Turnover Primer BACKGROUND:

October 3, 2017 MEMORANDUM. Council Members. Jennifer Light and Charlie Grist. SUBJECT: Regional Conservation Progress Report BACKGROUND:

July 5, SUBJECT: Portland General Electric Demand Response programs

September 13, Council staff is working with PNUCC and BPA to analyze the effects of wind resources on the

MEMORANDUM. January 29, Power Committee. Brief Progress Report on the Power Plan

July 1, SUBJECT: PNUCC presentation: Carbon - a Northwest perspective

April 28, SUBJECT: Northwest Regional Forecast Presentation by Pacific Northwest Utilities Conference Committee

MEMORANDUM. February 25, Power Committee Members. Status of Power Plan and Getting to the Draft

Draft RFP for Redevelopment of the Regional Portfolio Model

May 9, This presentation will summarize some key takeaways from the most recent Pacificorp Integrated Resource Plan (IRP) filed in April 2017

November 6, SUBJECT: Update on the Natural Gas Pipeline Rupture in British Columbia

MEMORANDUM. December 3, Power Committee. Jeff King, Senior Resource Analyst. Assessment of coal generating resource potential

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

July 5, SUBJECT: MT Renewable Action Plan (BPA and Montana Partnership)

October 4, SUBJECT: Economics of Utility-Scale Energy Storage Systems (ESS)

Overview of the Northwest Power and Conservation Council s Power Plan Development Process. Webinar. October 15, Agenda

Economic Planning Study. May 13, 2014

California s Solar Buildout: Implications for Electricity Markets in the West

2017 IRP Advisory Group. July 21, 2017 IRPAG

June 12, forecast from Northwest Natural Gas Association shows the two forecasts are close.

Northwest Power and Conservation Council

MEMORANDUM. July 2, Council Members. Charlie Grist and Howard Schwartz. Panel on Implementation of Conservation

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Chapter 2. Direct Testimony of Joseph P. Hoerner and Shayleah J.

MEMORANDUM. February 24, Council Members. Shirley Lindstrom. Panel on Idaho energy policy

Idaho Power s Transmission System. Greg Travis Nov. 8, 2018

July 30, Study of Non-Energy Environmental Benefits of Energy Efficiency Measures that Displace Wood Burning

May 1, SUBJECT: Update on Habitat monitoring and evaluation strategy

Boardman to Hemingway Transmission Line Project

June 6, SUBJECT: Update on MCS-1 Hard to Reach EE Markets Analysis

February 5, SUBJECT: Release draft white paper on the value of energy efficiency for comment.

PGE s 2013 Integrated Resource Plan

2011 IRP Public Input Meeting. December 15, Pacific Power Rocky Mountain Power PacifiCorp Energy

May 25, Update on Centralia Coal Plant Retirement Agreement

CONTENTS. Forward Executive Summary The Council s Resource Adequacy Standard Recent Adequacy Assessments... 8

Selected Findings from Scenario and Sensitivity Analysis Conducted To Date. August 6, 2015

Wednesday, April 28, 2010

Analysis of Beyond the Fence Solutions When the Fence Surrounds Four States

SYSTEM OPERATIONAL AND RELIABILITY BENEFITS TOOL ( SBT )

NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN STRAWMAN 1

November 6, SUBJECT: Streamflow and Temperature Projections of the Latest Climate- Change Datasets for the Columbia River Basin

November 7, SUBJECT: Power System Value of Conserved Irrigation Diversions

CHAPTER 3: RESOURCE STRATEGY

Production Cost Modeling for High Levels of Photovoltaics Penetration

Analysis Regional Portfolio Model Results. Conservation Resources Advisory Committee September 2, 2015

CONTENTS. Forward Executive Summary The Council s Resource Adequacy Standard Recent Adequacy Assessments... 9

2017 IRP Update. Proposed Long Term Resource Strategy Proposed Conservation

Electric Analysis PSE Integrated Resource Plan. Contents. Chapter 6: Electric Analysis

Bulk Energy Storage Resource Case Study Update with the 2016 LTPP Assumptions

Resource Plan Decisions

The Southwest Intertie Project: Assessment of Potential Benefits

Western Electricity Coordinating Council Regional Planning Project Review Loads and Resources Working Group

Overview and Background: Regulation of Power Plants under EPA s Proposed Clean Power Plan

100% Fossil Free Electricity. June 27, 2018

Pacific Northwest Low Carbon Scenario Analysis

Power Integrated Resource Plan PWP Presentation

California Grid Operations: Current Conditions and Future Needs

November 8, SUBJECT: Update on Wind Technology and Development Trends

July 7, Charlie Grist, Tom Eckman, Tina Jayaweera, Kevin Smit. SUBJECT: Model Conservation Standards for the Seventh Power Plan

Beyond LCOE: The Value of CSP with Thermal Energy Storage

A Revised Resource Adequacy Standard for the Pacific Northwest. NERC LOLE Work Group November 7-8, 2011 Austin, TX

Draft 7 th Plan Scenarios Proposed for Testing

Renewable Energy, Power Storage, and the Importance of Modeling Partitioned Power Markets

December 4, See attached materials for outline and background.

Regional Resource Adequacy Studies

PC24 High RE w/o Eldorado-Moenkopi

January 4, Mark Fritsch, project implementation manager Nancy Leonard, fish, wildlife and ecosystem M&E manager

2017 PSE Integrated Resource Plan. Electric Analysis

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans

Pacific Northwest Power Supply Adequacy Assessment for 2019 Final Report

February 26, Assessment of geothermal generating resource potential

Wholesale Electricity Transactions A State Regulatory Perspective

Pacific Northwest Low Carbon Scenario Analysis

Common Case Process. Jon Jensen Staff Engineer System Adequacy Planning

Portland General Electric 2016 Integrated Resource Plan. OPUC Public Meeting December 20, 2016

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

ENTERED 06/17/05 BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON LC 36 ) ) ) ) ) DISPOSITION: PLAN ACKNOWLEDGED

Resource and Financial Impact of Clean Line P&E HVDC Delivered Wind Resources for TVA

ISO Transmission Planning Process. Supplemental Sensitivity Analysis: Benefits Analysis of Large Energy Storage

Market Design and Renewables in the U.S.

February 26, Transmission Planning Overview for March 5 Web Conference

APPENDIX I PLANNING RESERVE MARGIN STUDY

PUBLIC UTILITY DISTRICT NO.1 OF FRANKLIN COUNTY INTEGRATED RESOURCE PLAN PREPARED IN COLLABORATION WITH

2013 Integrated Resource Plan

Transcription:

Henry Lorenzen Chair Oregon Bill Bradbury Oregon Guy Norman Washington Tom Karier Washington W. Bill Booth Vice Chair Idaho James Yost Idaho Jennifer Anders Montana Tim Baker Montana January 3, 2018 MEMORANDUM TO: FROM: Council Members John Ollis, Power System Analyst SUBJECT: Marginal Carbon Emissions Rate Study Draft BACKGROUND: Presenter: Summary: John Ollis This presentation will update the Power Committee on the revised results of the Marginal Carbon Emissions Rate Study, per the methodology recommendations of stakeholders and staff. Staff will be seeking release of the draft study in a following Council presentation. Relevance: The study of avoided carbon dioxide production rates of the northwest power system will evaluate what the implied avoided emissions rate is in the WECC by reducing 100 MW of Pacific Northwest load in every hour of four test years (2016, 2021, 2026 and 2031), and the implications for regional conservation replacing the need for that production. The results will summarize the findings into an annual avoided carbon dioxide emissions rate (lbs per MWh) for the years of the study for two scenarios analyzed in the 7 th Power Plan: Existing Policy and Average Social Cost of Carbon. Workplan: N/A 851 S.W. Sixth Avenue, Suite 1100 Steve Crow 503-222-5161 Portland, Oregon 97204-1348 Executive Director 800-452-5161 www.nwcouncil.org Fax: 503-820-2370

Background: The cost of future carbon dioxide regulation has been a significant factor in resource planning in the Pacific Northwest. To avoid making higher cost resource choices, a direct evaluation of this risk requires an estimate of the carbon dioxide emissions avoided by purchasing conservation or another resource. The Council has periodically produced this study using the AURORAxmp model to help inform Council staff and regional stakeholder analysis. Per the discussion in the January and February 2017 Power Committee, and April Council Meeting, AURORAxmp has been used as the Council s wholesale market electricity price forecasting model. The first draft of the study was released for public comment in April 2017. In response to that public comment, staff developed, in conjunction with the System Analysis Advisory Committee, a slightly different methodology for calculating the best estimate for an avoided carbon dioxide emissions rate. This updated draft reflects the new methodology and results. More Info: The second 2017 Marginal Carbon Emissions Study Draft will be available for preview before the meeting. For SAAC discussion of study, see https://www.nwcouncil.org/energy/saac/meetings/2017_10_06-webinar/ For initial paper, see https://www.nwcouncil.org/energy/2017-04-marginal-carbon-draft/ For initial paper, see Marginal Carbon Emissions Study initial scope 2008 Marginal Carbon Emissions Study: https://www.nwcouncil.org/media/29611/2008_08.pdf For more information please contact John Ollis.

Marginal Carbon Dioxide Production Rate Report: Methodology Discussion Power Committee John Ollis January 9 th, 2018

Why We Are Having This Discussion Again. 1. Stakeholder response to first draft asked for more involvement and input on methodology. 2. Multiple meetings with SAAC resulted in updated methodology. 3. Similar average results, but larger ranges and different reasoning. 4. Approval to release second draft of study. 2

Similar Results, But Different Methodology Annual Avoided Emissions Rate (lbs. of CO 2 per kwh) Scenario Existing Policy Social Cost of Carbon 2016 1.83 1.40 2021 0.91 0.58 2026 0.93 0.70 2031 0.97 0.55 Modern natural gas-fired combined cycle unit emits 0.8 to 0.9 lbs. of CO2 per kwh. Conventional coal-fired steam unit emits roughly 2.1 to 2.4 lbs. of CO2 per kwh. Peaker gas units have a larger range of emissions rates 1.1 to 1.7 lbs. of CO2 per kwh. Initial methodology (April 2017): 1.16 to 1.75 lbs. per kwh for existing policy scenario 3

Why the Methodology Change? Draft Study Response Staff released its updated draft marginal carbon study in April 2017 Significant stakeholder response Concerns included: 1. Metric used for evaluation 2. Low prices in spring not implying hydro as marginal 3. Less stakeholder involvement than most Council processes 4

SAAC Direction on Methodology Change In August, System Analysis Advisory Committee meeting members suggested the following: WECC-wide look at Avoided Carbon Emissions Rate Look at deltas in emissions for flat load decreases of 1, 10, 100 and 250 MW, see if there is a major difference in results Use delta emissions to calculate avoided emissions rate 5

October 2017 SAAC Discussion: Delta Test Conclusions The delta tests for flat demand reduction, yield similar results with 100 MW determined to be the best choice by the SAAC: 1. The change in load effects has the biggest effect on the dispatch of coal units in Arizona, Colorado, Nevada, Utah, and Wyoming, and gas units in California and the PNW. 2. The major driver of the emissions change is the change of dispatch in the coal units. 3. The difference in load change yields hourly and monthly results that may move emissions up or down, but in general on an annual basis and long-term, reduction in load reduces emissions. Key finding: 1 and 10 MW pretty insignificant in terms of the total output of the WECC, the results from this study were noisy and inconclusive. 6

WECC Avoided CO2 Emissions Rate for 2021: Updated Methodology The average avoided emissions rate over the output changed in the WECC from the flat drop of 100 MW is EEEEEEEEEEEEEEEEEE 100 EEEEEEEEEEEEEEEEEE 0 OOOOOOOOOOOO 100 OOOOOOOOOOOO 0 =.91 lbs/kwh Variable Definition: 1. EEEEEEEEEEEEEEEEEE 100 is the emissions in the WECC with 100 MW less load run 2. EEEEEEEEEEEEEEEEEE 0 is the emissions in the WECC in the base run 3. OOOOOOOOOOOO 100 is the output in the WECC with 100 MW less load run 4. OOOOOOOOOOOO 0 is the emissions in the WECC in the base run 7

WECC Emissions Rate Changes by Zone Notice the spreads are large but the net effect may still be small depending on how much output is increased or decreased at that emissions rate 8

WECC-wide data questions Change in fuel usage at plants What types of plants are driving the emissions rate? Change in delta emissions and output Where are plants changing output? What is driving the large emissions changes? Is this driven by regional exports? Variability in production from the hydro system? 9

Box Plot Review Since we need to look at distributions of results... Lower boundary on box: 25% quantile Middle line: 50% quantile Upper boundary on box: 75% quantile Min and max whiskers: (Min Observation-1.5*IQR, Max Observation+1.5*IQR) IQR is Interquartile range 10

WECC Output Change As expected, this is close to 100 MW less output in the WECC corresponding to the flat load drop of 100 MW in the PNW Westside. 11

12 WECC Output by Zone

WECC Emissions Change For context, all the changes in emissions are very small (<<1%) in comparison to the total amount of WECC Emissions in a month. 13

WECC Emissions Change by Zone Notice that most of the emissions change happens in a few zones and not much in the NW 14

Output Change By Hour There are some patterns here, like more variation around the daily load shape in certain zones. 15

Emissions Change By Hour There are some similar patterns here, like more variation around the daily load shape in certain zones. 16

Emissions Rate Change By Hour There are some similar patterns here, like more variation around the daily load shape in certain zones. 17

18 Coal plant fuel usage in Arizona changes the more than any fuel by month, but why?

19 Coal usage drives WECC emissions change Coal usage in Arizona fluctuates by month and by water condition

20 In the east side of the region, gas usage changes, but not often and not much.

8000 Monthly Average Regional Exports to California 7000 6000 5000 Megawatts 4000 3000 2000 1000 0 1 2 3 4 5 6 7 8 9 10 11 12 Rating Max Utilized Average Utilized Min Utilized 21

The Region Transmission Topology in AURORAxmp Everything flows here... 22

What are we optimizing? The optimization in AURORA is focusing on meeting load at the lowest cost. Optimizing for the lowest CO2 emissions would be a different objective. Since the stack is filled with varied fuel types big rate swings may happen hour to hour, but in general there seems to be an avoided carbon rate that is similar to that of a CCCT. 23

2021 WECC Resource Portfolio - Good Hydro Conditions Average Capability (MW) 50000 45000 40000 35000 30000 25000 20000 15000 10000 Coal Fuel Oil Geothermal Hydro NG Baseload NG Peaker Nuclear Other Biomass and Must-Run Solar Wind Over 27000 MW of nearly 118,000 MW of WECC fossil fuel and biomass generation capability is associated with minimum generation requirements. 5000 0-10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 330 360 460 490 Dispatch Cost (in $ per MWh) Demand Range 24

2021 WECC Resource Portfolio - Poor Hydro Conditions Average Capability (MW) 50000 45000 40000 35000 30000 25000 20000 15000 10000 Over 6900 amw difference in capability in bad hydro versus good hydro years. Coal Fuel Oil Geothermal Hydro NG Baseload NG Peaker Nuclear Other Biomass and Must-Run Solar Wind 5000 0-10 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 330 360 460 490 Dispatch Cost (in $ per MWh) Demand Range 25

Annual Avoided Emissions Rate (lbs. of CO 2 per kwh) Scenario Existing Policy Social Cost of Carbon 2016 1.83 1.40 2021 0.91 0.58 2026 0.93 0.70 2031 0.97 0.55 Modern natural gas-fired combined cycle unit emits 0.8 to 0.9 lbs. of CO2 per kwh. Conventional coal-fired steam unit emits roughly 2.1 to 2.4 lbs. of CO2 per kwh. Peaker gas units have a larger range of emissions rates 1.1 to 1.7 lbs. of CO2 per kwh. 26

Next Steps Continue Stakeholder Involvement Met with System Analysis Advisory Committee to vet methodology and assumptions, and discuss results. Updated report to reflect stakeholder feedback, revised methodology and results. Put study out for second round of public comment. 27

Approval to Release Study? Questions? 28

Additional Content for Reference 29

Review of Methodology Similar to 7 th Plan Balancing Study setup Instead of using AURORAxmp for resource expansion within region, use RPM results from 7 th Power Plan. Each of 10 scenarios will be considered under all 80 hydro conditions instead of just average hydro conditions. 2016, 2021 (Min and Expected DR), 2026, 2031 run with No Carbon Price and Social Cost of Carbon All scenarios will be run with regional reserve requirements and hydro methodology similar to what was used the 7 th Power Plan Balancing and Flexibility study. 30

Review: Capability of Current Models AuroraXMP Hourly Dispatch Limited intra-hour reserve accounting capability. Extremely limited hydro dispatch capability GENESYS Hourly Dispatch Limited intra-hour reserve accounting capability. Uses hydro shapes from TRAP TRAP Hydro Shaping Algorithm Accounts for intra-hour reserves held on hydro

Regional Balancing Reserves Assessment by BA Reserves Assigned to Hydro Generation TRAP Reserves Assigned to Thermal Generation AuroraXMP Adjusted Hydro Shape Per System Dispatch GENESYS Reserve Adjusted Hydro Dispatch WECC-wide hourly dispatch of all resources Find marginal unit and calculate CO2 emissions rate

Determine Amount of Reserves Required by Balancing Authority Used the 95% Confidence Interval load following requirements for each of the 28 not generation-only BAs (Base Case for the PNNL NWPP EIM Study). The data set is described in more detail in the following report http://www.pnnl.gov/main/publications/external/technical _reports/pnnl-22877.pdf This is not the only dataset available, but seemed most reasonable to Council Staff based on data needs: 1. Monthly and hourly reserve requirement data for all WECC BAs. 2. Current regional portfolio conditions. Some reserves have been modified to reflect utility feedback

Assigning Reserves to Hydro/Non-Hydro Units Assumption: Total reserve requirements for each BA can be met by resources within each BA (with exception of long term Mid-C hydro Power Purchase Contracts). Identify resources that CAN provide reserves. Use commitment optimization functionality in AURORA to assign reserves to regional resources. Note that BPA reserve requirements are assigned to certain regulated hydro dams in TRAP and GENESYS to ensure hydro shape going into AURORA considers the flow and capability constraints on regulated hydro.

Commitment Optimization An commitment/dispatch algorithm that minimizes cost by co-optimizing the assignment of the following to resources in a footprint within the constraints applied to the system: 1. Energy 2. Ancillary Services Constraints on transmission, ramping, unit capability considered in the commitment and dispatch. 35

Range Available on Resources to Meet Reserve Requirements Hydro and Thermal units have a wide variety of operational capabilities including ramping, fuel supply/constraints, available transmission, and operating range of the generator.

Known Issues with Reserve Assignment Reserve Distribution: In Region Based on anecdotal information in IRP s and Staff judgment. Unregulated hydro not counted in reserve provision. Reserve Assignment: Out of Region, in WECC Probably mostly assigned to Non-Hydro except certain BA s like SMUD that have hydro resources. Currently only contingency reserves are held explicitly. Seasonality In operations, reserves are probably assigned differently by season (Spring Runoff considerations, etc.). Only Winter and Summer seasonal information available in PNNL dataset.

Proposed Methodology Regional Intra-Hour Reserves assigned to Hydro and Non- Hydro Intra-Hour Reserves to Hydro Units TRAP AuroraXMP GENESYS

TRAP Data Input and Calculation TRAP takes the information about INC and DEC reserve requirements held on particular plants and raises minimum hydro capability to account for DEC and lowers maximum hydro capability to account for INC reserves while pushing as much generation as possible into on-peak hours. Calculations repeated to determine 2, 4 and 10 hour max and min generation levels for each of the 14 hydro periods (Monthly, with 2 periods in April and August).

Proposed Methodology Regional Intra-Hour Reserves assigned to Hydro and Non- Hydro TRAP Reserve Adjusted Hydro Shapes AuroraXMP GENESYS

GENESYS Data Input and Calculation GENESYS takes the 2, 4, and 10 hour reserve adjusted max and min generation constraints for all 14 periods, and develops hourly hydro flows for each of the 80 water years. The hourly hydro shaping for a particular simulation considers the sampled hourly load and wind generation data, a simple resource stack of other non-hydro resources, and any other flow/spill information not in TRAP.

Proposed Methodology Regional Intra-Hour Reserves assigned to Hydro and Non- Hydro TRAP AuroraXMP Adj. Hydro Shape Per System Dispatch GENESYS

Aurora Inputs from GENESYS GENESYS will output an hourly hydro shape for a particular sample year of load, hydro and wind. Staff proposes doing 80 sample years to start. Hourly loads and wind data can be input to Aurora, and hydro ranges for Aurora dispatch can be derived by taking the max and min of the hourly hydro generation during each on and off peak period. This will limit Aurora s ability to dispatch hydro within a tight band, but will still allow for some flexibility in the Aurora hydro dispatch. Hourly data sets (Load i, Wind i, HydroMax i, HydroMin i ) where, HydroMax i = Max(HourlyHydroGen i {on/off peak}) HydroMin i = Min(HourlyHydroGen i {on/off peak})

Proposed Methodology Regional Intra-Hour Reserves assigned to Hydro and Non- Hydro TRAP Reserves Assigned to Non-Hydro Units AuroraXMP GENESYS

Aurora Non-Hydro Inputs and Dispatch Assign the remaining operating reserve requirements to the previously identified non-hydro reserve carrying units in the region. Utilize AURORAxmp to determine marginal unit within the region for each of the 80 simulations The marginal price is based on the variable cost of any discretionary energy or load following down above the minimum generation segment. During dispatch, Aurora will also assign contingency reserves (spinning and supplemental) to the appropriate units.