DFI DEEP FOUNDATIONS. Brazil s Megaproject Shipyard Winner of the 2010 Outstanding Project of the Year

Similar documents
DFI DEEP FOUNDATIONS. Aerial View of a Flood Control Project in San Juan, Puerto Rico: An OPA Finalist F E

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Ching Guan Kee ABSTRACT

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil

Lesson 2 Substructure. Dr S.Sreenath BSc Engg, MSc Engg, MSc (ICM), MBA, PhD

DEEP FOUNDATIONS. Rio de Janeiro Subway Line 4: An OPA Finalist. Battered Piles. Sheet Piling. Challenging SOE

Misan University - College of Engineering Civil Engineering Department

Overburden Effect on the Axial Resistance of Instrumented CFA Piles. Knoxville, TN 37922, ph ,

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

SECANT PILE. Introduction:

INNOVATIVE PILE EXTRACTION TECHNIQUE OF CFA PILES FOR THE NEW HARBOR BRIDGE PROJECT

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

Construction Technology B (CON4313)

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5. Turbine Foundation Construction Method Statement

The construction of deep excavation ditch in weak soil in St. Petersburg

Hamburg, GERMANY. Predöhlkai extension project Berth 1

Civil Engineering Construction I (CBE5031)

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

TABLE OF CONTENTS. 0 Structural calculations 0.1 General 0.2 Safety concept 0.3 Calculations for waterfront structures

UNDERPINNING A CRANE FOUNDATION

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk

Soil Services SCS Ferretti International Soil Services Soil Services Industrial Construction Infrastructures Real Estate Soil Services Soil Services

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

Earth Retention Systems

Geo24h. Buiding Service

Temporary Structures. Excavations and Excavation Supports

Development Island Vehicle Access

SHAFT CONSTRUCTION SECANT PILE

Earth Mechanics, Inc. Geotechnical & Earthquake Engineering

Northport Berth 3 design and construction monitoring

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding)

SUSTAINABLE FOUNDATION ENGINEERING MIXED-IN- PLACE TECHNIQUES FOR DURABLE CUT-OFF WALLS

Deep Foundations Institute Fall 2004 Fall 2004

Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization

Case Histories in Geotechnical Engineering

CUTTER SOIL MIXED WALL SHORING AND SEEPAGE CUT OFF OFFICE BUILDING NEAR WATERFRONT

Innovative Construction Technology

DFI DEEP FOUNDATIONS LANDMARKS ISSUE: SPECIAL. Deep Piles at Challenging Site Near Golden Gate Bridge: An OPA Contender F E

Seven Wonders of the Ancient World

Aveng Ground Engineering Profile

Prof. Nichols St. Nooshin Ahmadi Yasaman Bagheri Farzad Golestanirad. An Iconic Building And A Successful Stadium

Lesson Learned. Collapse of Diaphragm Wall Trench. Case study. Suez Canal Syphon Project

Expert Solution in BUILD ON US GEOTECHNICAL AND CIVIL ENGINEERING CONTRACTORS

Our Motto aims to be "NEW ZESCO" New Value Creater. Endless Innovation. Work with Passion for Stakeholders

MEMORANDUM. TO: STUART OLSON DOMINION CONSTRUCTION LTD. DATE: JANUARY 31, 14 ATTENTION: MR. Dave Bauder, Construction Manager KENNY K. C.KO, P.ENG.

Dr. Ahmed Hussien Elyamany 2017 Questions

MIDAS ELITE SERIES SOIL STRUCTURE INTERACTION ANALYSIS OF SKYSCRAPER IN BRAZIL RICARDO BORN

Safe, fast and simple: the DUKTUS pile is loadtested in South Africa

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

Challenges of Offshore Geotechnical Engineering

Bi-Directional Static Load Testing of Driven Piles

3.5 GEOLOGY, SOILS, AND GROUNDWATER

Grouting Bilfinger Spezialtiefbau GmbH

Experimental study on axial and lateral bearing capacities of nonwelded composite piles based on pile load test results

Design and performance of a 15m deep excavation for a wagon tippler

FIELD PERSONNEL 24 HOUR SUPPORT SPECIALIZED DREDGING, EXCAVATION & RECOVERY

A.Zh.Zhussupbekov Department of Civil Engineering and Engineering Mechanics, Columbia University, New York, USA

Forensics by Freezing

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN

The Aizhai Suspension Bridge is

KIEWIT FOUNDATIONS CO.

SOIL AND FOUNDATION INVESTIGATION PROPOSED DUPLEX 3966 VRAIN STREET DENVER, COLORADO

Steel screw settlement reduction piles for a raft foundation on soft soil

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates

A Vacuum Consolidation Method Application Case for Improving Dredging Slurry

Enabling Work Package for Emirates Pearl Tower and Bab Al Qasr Hotel

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

Ground Improvement. Cutter Soil Mixing Multi-Axis Soil Mixing Deep Soil Mixing Jet Grouting Vibro Systems Specialized Geotechnical Grouting

Contents. Glossary 9. Foreword 10

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

Walls generally range from 600 to 1500 mm thickness, in wide between 2000 and 3500 mm and can be excavated to depths of 60m or more.

KIEWIT FOUNDATIONS GROUP

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2

USE OF DIPP PILES FOR A NEW SUP BRIDGE IN WEST MELBOURNE

Case study on a deep excavation in Baku: Flame Towers project earth retaining system

AL HAMRA TOWER KUWAIT CITY, KUWAIT SARAH CLAUS, VICTORIA GARCIA, AMBER HOLDEN-O DONNELL, ERICA SCHNEIDER, HANNAH VOSSLER

The HKIE Structural Examination Written Examination 2017

FINITE ELEMENT ANALYSIS OF DEEP BASEMENT CONSTRUCTION OF BANK OF THAILAND ALONG CHAO PHRAYA RIVER CLOSED TO HISTORICAL PALACES

Diaphragm wall Construction

GeoEng2000 An International Conference on Geotechnical & Geological Engineering

This method significantly reduces the over-consumption of concrete and eliminates any risk of over-augering.

DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE FOUNDATION ENGINEERING UNIT 1

Testing of ground anchorages for a deep excavation retaining system in Bucharest

Sabah Shawkat Cabinet of Structural Engineering 2017

Foundation Innovations Ensure Successful Bridge Replacement

KIEWIT FOUNDATIONS GROUP

Upgrading Techniques for Quay Walls

Application of Vibro Techniques for Infrastructure Projects in India

Upon speaking with the representatives with Technical Foundations as well as Walder Foundations, it was determined that:

FOUNDATION & SHORING. Whatever it takes... We build your vision! WORLDWIDE EXPANSION

Jet Grouting to Increase Lateral Resistance of Pile Group in Soft Clay

Lecture 11. WATER PUMPING EQUIPMENT and DEWATERING SYSTEM

VIBRO REPLACEMENT COLUMNS FOR SHIPYARD INFRASTRUCTURE AT PIPAVAV, GUJARAT, INDIA

Transcription:

U N DAIONS IN O F P D DFI S I U DP FOUNDAIONS Fall 2010 he Magazine of the Deep Foundations Institute Brazil s Megaproject Shipyard Winner of the 2010 Outstanding Project of the Year

Aerial view of the Atlântico Sul megaproject Atlântico Sul Shipyard: Outstanding Project Award Winner Atlântico Sul Shipyard was established in November 2005 through a partnership between Camargo Corrêa, Queiroz Galvão, Samsung Heavy Industries from South Korea and PJMR, an equity holding and ventures management company in the shipbuilding and offshore sector. he partnership s goal was to be the biggest and most modern naval and offshore construction and repair shipyard in the southern hemisphere. his undertaking was a landmark in the revitalization of the Brazilian shipbuilding industry, with an approximate investment of $1billion (U.S.). he shipyard manufactures carrier vessels up to 500,000 DW, as well as offshore platforms of the semi-submersible type, FPSO (Floating Production, Storage and Off-loading), and tension-leg platforms, among others. It also offers a vast range of repair services for vessels and oil exploration units, taking advantage of the shipyard s strategic location in relation to both AUHOR: the global maritime Armando Caputo trade and the large deepwater oil and gas pro- echnical Director, Grupo Brasfond duction fields. he shipyard can process 160,000 mt (180,000 U.S. short tons) of steel per year, in an area of 1,620,000 sq m (17,400,000 sq ft), from which 130,000 sq m (1,400,000 sq ft) are covered areas used to process, cut and paint the steel. he area also contains a dry dock that is 400 m (1,312 ft) long and 76 m (250 ft) wide and 14 m (46 ft) deep. he dry dock is served by two Goliath Cranes with capacities of 1,500 kn each, with four additional support cranes, two of which have a capacity of 500 kn and two with 350 kn. he south outfitting quay is 730 m (2,400 ft) long and is served by another two 35 t cranes. he north quay, which extends 680 m (2,230 ft), is used for construction and repair of offshore platforms. he scale of such a manufacturing facility places the shipyard in the top group of fourth-generation shipyards with Asian plants, now at the forefront of the worldwide shipbuilding industry. Atlântico Sul Shipyard is in the Industrial Port Complex of Suape in Ipojuca, in the northeastern state of Pernambuco. he Complex of Suape connects to main navigation routes and to 160 ports worldwide. Its location is advantageous in relation to the big oil and natural gas production regions, such as the Brazilian upi oil field, Gulf of Mexico and Coast of West Africa. Brasfond Contract Brasfond s contract included the foundations and retaining walls for the following structures: he retaining wall of a de-waterable dry dock. A large expanse of quay wall plus cranage to provide a deep berth for merchant ships. All ancillary support facilities and administrative buildings. he mega block areas. his term refers to construction methodology in which eight large sections of ships are welded together inside the dock thus reducing overall construction time. 8 DP FOUNDAIONS FALL 2010

All these works presented geotechnical challenges. he ground profile across the site was generally made up of loose granular fill material overlying sandy silt/silty sand that in turn, was underlain by claystone and sandstone at approximately 25-35 m (82-115 ft) below ground level. he layer of silty sand directly below the fill was either dense to very dense or, in places, weak sandstone up to 6 m (20 ft) thick. his weak rock layer was clearly not formed by normal sedimentary rock processes and Figure 2: ypical soil profile Figure 1: Overview of Brasfond s works appeared to be a natural cementation of the sand grains as a consequence of the lixiviation (leaching) of the acids from decomposition of organic materials giving the sandy soil the brown color. he material below this sandstone layer was generally a medium dense state, varying from sands to clayey sandy silts. In some localized areas the sandy silt/silty sand directly above the deep sandstone was replaced by soft to firm silty clays up to 13 m (43 ft) thick. hese soft clays are believed to be the location of an old river channel. he site has high ground water relating closely to sea level that indicated the generally high permeability of the soils. Principal Challenges he main design and construction challenges at Suape were: Construction through and/or excavation of an upper sandstone layer that required mobilizing the correct equipment during construction, clearly identified in the design package. he presence of soft clay at depth meant there was little passive support for the wall below floor level during temporary stages of construction. Considering that the dry dock (once the dock floor was in place) would support the upper wall, the wall below the floor had to function as a cut-off wall to reduce the volume of water flowing into the drainage system and underside of the dock floor. It was important to consider that the wall was also designed to resist the vertical loads from the big Goliath cranes (up to 15,000 kn) running on it. he quay wall depth had to be increased after its construction as a consequence of the changes in the dredge level imposed by Port Authorities of Suape. he initial basic design concept for the 400 m (1,312 ft) long x 76 m (250 ft) wide x 14 m (46 ft) deep dry dock wall was to use steel sheet piling. Because of the erratic soil profile, the client decided to make a preliminary test on the drivability of the sheet piles to check the efficacy of the solution. hese tests proved that the energy needed to drive the sheet piles was so large, due to the presence of a sandstone layer between layers of sand and clay, that it would be necessary to drill a pre-hole with an auger to avoid significant deformations. his drilling would have increased the cost and time schedule with no guarantee of success. he final design concept was to use a diaphragm wall without tiebacks. Due to the great bending moments involved, a -shape 60 cm (2 ft) thick wall was designed with support at the top and one at the bottom (counterfort wall). he depth of the -shape diaphragm wall ranged between 18 m (59 ft) and 30 m (98 ft), always reaching bedrock. he large difference in depth was due to a layer of soft clay created by what was likely an old river channel. he diaphragm was installed by a clam-shell 3.20 m (10.5 ft) long x 0.60 m (2 ft) wide mounted in crawler cranes of 70 t. Crawler cranes up to 100 t were used to place the reinforcement cage. he 3 estimated volume of each -panel was approximately 100 m (3,531 cu ft). he basic concept of the dry dock floor design included: A sub-floor drainage system to prevent the buildup of hydrostatic pressure; the water reaching this drainage system had to be pumped away to the sea continuously to keep the dock dry. A pressure relief system so that the floor would neither lift nor suffer damage in the event of pressure build up due to the malfunction of the drainage system. Consideration of the heavy loads involved when the dock was either flooded or when the mega blocks were being assembled over the floor slab with the dock when dry. he foundation solution for the floor was bored piles drilled with bentonite slurry, 0.9 m (2.95 ft) diameter for a service load of 5,000 kn. he design criteria indicated that piles be bored to bedrock. In the dry dock area, the depths ranged between 10 m (33 ft) to 20 m (66 ft) below the floor slab level. he significant difference in the bedrock level was very similar both in terms of depths and characteristics to what was detected in the diaphragm wall perimeter. Because of the great difference in the depth of the piles, Brasfond proposed to undertake three static pile load tests in areas where the bedrock level was different to confirm the service loads being adopted. he client accepted. DP FOUNDAIONS FALL 2010 9

Figure 3: Overview of the dry dock o save time, all the piles below the slab were installed before the dry dock excavation, so it was very important to be sure that the pile cut-off level was preserved and the reinforcement cage was placed in the right position. he piles were installed by hydraulic rigs up to 260 knm torque with verticality and depth monitoring systems. he Overview of the dry dock (Figure 3) shows a general view and a cross section of the dry dock as well as the mega block paved area below. Another important part of the dry dock work was the excavation to concrete the floor slab. Figure 5: Cofferdam A cofferdam was necessary to excavate and concrete the last part of the slab, which was closer to sea. A plastic diaphragm wall, 0.6 m (2 ft) wide with an average depth of 25 m (82 ft) was designed and executed up to bedrock, to protect the dock. After completing the slab and installing the dock gate, the fill and the plastic wall were demolished to allow the final contact of the dry dock with the sea. Quay Design he designer s first option was to use steel sheet piles. Because of the soft soil in this region, the problem was the depth that the sheet piles had to reach to take the vertical load. o establish that the piles had sufficient load bearing capacity they would have had to be driven to refusal, and the depth at which this could be achieved was unpredictable. Figure 4: Dock floor execution his work was done in steps as follows: a) Concreting the reinforcement beam over the diaphragm wall and the mega block paved area b) xcavating the dry dock up to 3 m (10 ft) below ground level c) Installing the dewatering system inside and outside the dock area d) xcavation of the soil in the central part of the floor up to the final level leaving a berm along the wall e) Cutting off the pile heads, installing the drainage system, placing the reinforcement steel and concreting the central part of the floor slab, repeated until the floor slab was complete f) After the concrete was cured, excavating the berm up to the diaphragm wall and final level he excavation methodology proceeded with the condition that the diaphragm wall would be monitored in real time by inclinometers and strain-gauges. Figures 6: Quay platform after increasing depth 10 DP FOUNDAIONS FALL 2010

U O F P D N DAIONS IN DFI S I U Deep Foundations Institute 326 Lafayette Avenue Hawthorne, NJ 07506 USA 973-423-4030 Fax 973-423-4031 PRSORD SANDARD U.S. POSAG PAID PHILADLPHIA, PA PRMI NO. 102 OPA Winner: Atlântico Sul Shipyard on the coast of Brazil

he final decision was to use a diaphragm wall, with depths ranging between 22 m (72 ft) up to 30 m (98 ft), tied with a group of inclined root piles to resist the bending moment (pile trestle) and bored piles to take vertical loads, as shown below. he assumption was that the dredging in front of the quay would be carried out after constructing the quay structure, and the proposed dredged depth was -12 m (-39 ft). When the diaphragm wall was completed, the Port Authorities decided that the dredged depth had to be increased to -15 m (-49 ft). After analyzing the impact carefully, the designers thought it necessary to increase the depth of the diaphragm wall. Because it was already constructed, the solution was to create a spaced curtain (non-tangent/non-overlapping) of bored piles as close as possible to the wall to resist the bending moment induced by the new dredged depth, as shown below. Inclinometers and strain-gauges were installed in the wall and it was closely monitored during dredging. Construction underway for the dock floor Mega Block Area and Ancillary Facilities his area surrounding the dry dock was designed to resist the weight of the mega blocks constructed to facilitate ship assembly. he large steel blocks are built outside the dry dock in giant pieces and moved into the dry dock by the Goliath cranes. his procedure SRVICS Diaphragm Wall Plastic Diaphragm Wall Bored Piles CFA Piles Root Piles Jet Grouting Columns QUANIIS 88,327 m² / 950,744 square feet 5,468 m² / 58,857 square feet 5,484 ɸ / 102,824 m / 337,349 linear ft 4,845 ɸ / 94,342 m / 309,521 linear ft 1,283 ɸ / 32,258 m / 105,833 linear ft 2,106 ɸ / 23,800 m / 78,084 linear ft Piles rising from the dock floor minimizes the construction time for ships inside the dock and, in turn, maximizes ship production. he basic concept of the design was a slab with piles. Due to the heterogeneous soil condition in the area, the designer sometimes used bored piles and in other cases Continuous Flight Auger (CFA) piles. Initially, the client thought of installing pre-cast piles for these foundations, and again we conducted a drivability test. he results turned out to be negative, due to a dense upper sand layer that broke the pre-cast elements when they were driven into ground. Once more, it seemed necessary to pre-hole in order to install these. We tested an alternative solution, CFA piles, conducting several static load tests with excellent results. We tested an alternative solution, CFA piles. Consequently, the general solution was CFA piles except in areas where we found the deeper soft clay layer. In these areas, the designer used root piles, 0.4 m (1.3 ft) and 0.5 m (1.6 ft) in diameter, up to 30 m (98 ft) long. Conclusion Some lessons learned from this project were: It was extremely important that the client, the designer and the foundation contractor interacted to find the best solution, quickly and inside the clients budget. Due to a good soil investigation and the close monitoring during the execution, we overcame all the underground challenges, minimizing overall construction risks. he foundation design was optimized as a consequence of the static load tests that were conducted before the start of the job. Due to the short time available to fulfill the contracts for ship assembly, construction of the shipyard was concurrent with the construction of the first ship. his is clearly reflected in the total time taken to complete the foundations of the shipyard, 24 months, in comparison to the completion of the first ship, 32 months. DP FOUNDAIONS FALL 2010 11