Annex C Cavity Closures

Similar documents
Cavity Barriers: Final Factual Report of the Experimental Programme

The experimental programme for this stage of the project has been undertaken in three phases:

BS :2005 test on a Kingspan Benchmark External Wall Insulation System

BRE Global Classification Report

Rainscreen Cladding Compliance Guide When specifying Celotex RS5000 in buildings above 18 metres

8414-1: A1:2017

BRE Global Classification Report

BRE Global Test Report

BRE Global Classification Report

BRE Global Client Report

TEST REPORT. Bushfire resistance test of an external wall system to BAL A40 in accordance with AS EWFA Report No:

Fire Testing Laboratory

PRODUCT SUSPENDED. Rainscreen Cladding Compliance Guide When specifying Celotex RS5000 in buildings above 18 metres

BS8414 Part 1: 2002 Test on a Phenolic Insulated Rainscreen system. Prepared for: Kingspan Insulation Ltd Pembridge Leominster Herefordshire HR6 9LA

BRE Global Test Report

BRE Global Test Report

BRE Global Ltd Watford, Herts WD25 9XX. d+b facades (UK) Ltd. The Packway, Larkhill, Salisbury, SP4 8PY. Customer Services

Refurbishment site guidance for solid-walled houses windows and doors

Precast Concrete Hollow Core Slabs in Fire. By Tom Lennon, Principal Consultant, BRE

Use of Coatings to Improve Fire Resistance of Wood

PROJECT NUMBER: ISSUE DATE: EXPIRY DATE: PAGE: FT March March of 28

BRE Global Test Report

combustibility behaviour of insulation products

calibrated gas flows from the room burner.

1. PREINSPECTION RESIDENTIAL ENERGY EFFICIENCY 7

Title: WF Report No: Prepared for: International Petroleum Products Ltd Bradwell Hall Bradwell-On-Sea Essex CMO 7HX. Date: 24 th August 2015

BRE Global Classification Report

CI/SfB (37.5) Xn6 Uniclass L416 May LOFT ACCESS TRAPS ...

TEST REPORT. Fire resistance load-bearing test of a 136mm thick Ozone Panels wall system tested in accordance with AS

Test Report: Fire resistance test in accordance with BS EN :1999 on a nonloadbearing. incorporating Scolmore Doubled Switched electrical sockets

Fire Test Report. Test Number 1243 Dated 22 September Prepared for:

Thermal Performance of Plasterboard Lined Steel Stud Walls

Originally Issued: 11/06/2017 Valid Through: 11/30/2018

Building Design Data

Sustainable Retrofit A fabric first approach. Mark Elton Technical expert panel member Energy Saving Trust

Building Typology Brochure England September 2014

Loss Prevention Standard

BRE Cardington Steel Framed Building Fire Tests

CASE STUDY OF THE SOUND REDUCTION OF VARIOUS RESIDENTIAL GLAZING TREATMENTS

CWCT CURTAIN WALL INSTALLATION HANDBOOK

Knowledge Objectives (3 of 3)

Interior FRT Wood. References of Previous Model Building Codes

Originally Issued: 08/03/2017 Revised: 02/01/2019 Valid Through: 08/31/2019

CALL TO TALK TO THE SAS TEAM

Contents. Timber framing to be installed in accordance with AS:1684 Metal framing to be installed in accordance with BCA Volume: 2

BERS Pro Plus 4.2 New Features and Modelling Changes. Holger Willrath Solar Logic October 2011

Originally Issued: 02/01/2019 Valid Through: 02/28/2020

A Handbook of thermal bridging details incorporating aircrete blocks

Executive summary. Fire Hazards of Exterior Wall Assemblies Containing Combustible Components v

BILL ROBINSON TIMBER DESIGN SERVICES SPECIALISING IN TIMBER AND TIMBER FRAME CONSTRUCTION SITE INSPECTIONS

EUROPEAN ORGANISATION FOR TECHNICAL APPROVALS

Fire Engineering, the BCA (NCC) & Bushfire Calculator. Keith Nicholls - Manager Product Testing and Assessments (Australia) Exova Group Limited

Exterior Wall Solutions Building Shell

Part E robustdetails. robustdetails. January 2017 Update Pack. Dear Colleague,

Report for CSR Hebel. Impact of various wall and floor construction options on 5 star compliance for two houses. by Tony Isaacs Consulting Pty Ltd

ASSESSMENT REPORT. EWFA Report No: Report Sponsor: 3M New Zealand 94 Apollo Drive, Rosedale Auckland, New Zealand

FIRE TESTING OF ROOMS WITH EXPOSED WOOD SURFACES IN ENCAPSULATED MASS TIMBER

BRE Global Assessment Report

Fire damper frequently asked questions for ASFP

**Section C and R ; change to read as follows:

The effect of Building Regulations (Part L1 2002) on existing dwellings

Loss Prevention Standard

LVH-A Series Intumescent Fire Dampers Alternative Mounted Systems 1, 2 & 4 hour Fire Rating

Insulbreak. Insulation. thermal break solution

Loft access doors. Loft access doors. 1 Call

Technical information & installation advice

How to build compliant SPANDREL PANELS. Guidance on building and installing spandrel panels for party walls above masonry

Good Morning everybody

Certificate No: EWWS165

Cl/SfB 1 (4-) RJ July Cempanel BUILDING BOARD CEMENT PARTICLE BOARD.

NUMERICAL-SIMULATION RESEARCH ON BUILDING-FACADE GEOMETRY AND ITS EFFECT ON FIRE PROPAGATION IN WOODEN FACADES

(Project Location) (your firm's name)

Burtin Polymer Laboratories 2 SwRI Project No e[1]

Title: WF Report No: Prepared for: Alstrong Enterprises India (PVT) Limited E-40/3, Okhla Industrial Area, New Delhi, India Date: 15 th June 2015

REPORT NUMBER: SAT-001A_Rev.2 ORIGINAL ISSUE DATE: April 7, 2015 REVISED DATE: July 21, 2015

Defining a Fabric Energy Efficiency Standard for zero carbon homes

Construction Studies Theory - Higher Level

BRE Global Test Report

FIRE TEST REPORT FP 5663

Assessment of the Fire Behaviour of Insulated Steel Deck Flat Roofs

REPORT NUMBER: SAT-005 ORIGINAL ISSUE DATE: September 14, 2012 REVISED DATE: N/A

Title: Do Unprotected Small Diameter Service Penetrations in Fire Rated Constructions Hasten Gypsum Plasterboard Failure?

ESR-2847 Reissued September 1, 2013 This report is subject to renewal September 1, 2015.

FIRE RESISTANCE TESTS OF BRICK VENEER / WOOD FRAME WALLS J. GREGG BORCHELT

Title: The Fire Resistance Performance of Modified Timber Based Panelled Doorsets. WF Assessment Report No: Issue 8.

R-Matte Plus-3: Insulation for the Building Envelope

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES. Chapter 10

P.O. Box ZN Bleiswijk Brandpuntlaan Zuid NZ Bleiswijk The Netherlands

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK ND AND 3 RD FIX FINISHES

BRE Global Assessment Report

DIVISION: THERMAL AND MOISTURE PROTECTION SECTION: THERMAL INSULATION REPORT HOLDER: THE DOW CHEMICAL COMPANY

June Non - Residential Refurbishment Internal lining walls

Connection Temperatures during the Mokrsko Fire Test J. Chlouba, F. Wald

1 Introduction The legal validity of this report can only be claimed on presentation of the complete report.

Design guide to separating distances during construction

SOUTH AFRICAN NATIONAL STANDARD

DRY CONSTRUCTION SYSTEMS

Construction Studies Theory - Higher Level

Communal 51 Ceiling Systems by Vogl

K15 Rainscreen Board. Insulation INSULATION FOR USE BEHIND RAINSCREEN CLADDING SYSTEMS

Transcription:

Annex C Cavity Closures Introduction The objective of this study was to investigate the effectiveness of different types of window frame constructions at mitigating the entry of fire into a timber frame cavity. The experimental scenario selected for this study was based upon a post flashover fire within an enclosure breaking out through a window opening, which is set within a timber frame cavity wall construction. The cavity wall construction was based upon the robust design details produced by DEFRA and DTLR in the Limiting thermal bridging and air leakage: Robust construction details for dwellings and similar buildings. 22 Edition. These design details are reproduced in Figure C1 and show a timber beading closing in the cavity around the window frame opening. Duplicate tests were therefore run with and without the timber beading for each frame type to assess the influence of this feature on the performance of each of these window frame types. Four, commercially supplied, window frame systems were identified by the project advisory group for consideration. These were: Aluminium frame systems PVCu frame systems Hardwood frame systems Softwood frame systems All the window frames were purchased from commercial suppliers. The window units were screw fitted into the test frame with 3 fixings on each side. Unglazed frames were used throughout this study as the investigation was concerned with the fire performance of the window framing system and not the failure time or mechanism of failure of the glazing units. Experimental Room enclosure The test room was constructed from a steel box-section frame, 2.4m square, lined with single sheets of 12 mm thick plasterboard. The front wall of the enclosure was 3 m in height and constructed as a timber frame stud wall, with a mm cavity, using the robust design details shown in Figure C1. A 1.2m x 1.m high window opening was incorporated into the front wall construction as shown in Figure C2. 62 Building Research Establishment Ltd 2

Figure C1. Robust Design Details Fuel Load The fire load was provided by a wooden crib consisting of 12 lengths of nominal mm x mm sawn softwood timber cut into 1.m lengths. The crib was laid in 12 layers with lengths per layer with a gap of mm between each length. The timber crib was positioned on a 1m 2 sheet of plasterboard, located 4mm above the floor of the enclosure, see Figure C2. 63 Building Research Establishment Ltd 2

Fibreboard strips, pre-soaked in white spirit, were inserted into the lower layer of the crib to assist in obtaining a simultaneous ignition of the crib. The nominal test duration was thirty minutes or until fire was observed in the cavity, whichever occurred first. Instrumentation Figure C2 shows a schematic of the instrumentation locations..mm diameter sheathed type K thermocouples were used to monitor the temperature within the cavity and the test room. Each cavity thermocouple was set at the mid depth of the cavity to monitor air temperature. A thermocouple was also located in the ceiling of the test room to monitor the room temperature. 1 Stud wall Cavity Space 2 Window & frame acting as cavity barrier Crib or burner Ventilation opening Thermocouple 8,9, Thermocouple 16,17 Thermocouple 18,19 Thermocouple 2 top of window head external face top of window head internal face top of test rig external face top of test crib Figure C2. Layout of thermocouple on test rig TC and - 4mm either side of the centre line above the window opening, 2 mm above the opening, TC12 and 13-4mm either side of the centre line above the window opening, mm above the opening, 64 Building Research Establishment Ltd 2

TC and 1 on the centre line above the window opening, mm and mm respectively, above the opening. Results The temperature-time curves recorded from each test are presented in Graphs 1 to 2. The results from each test are also summarised in Table C1 below. Table C1. Summary of Test Results No Frame type Entry time based on observation Entry time based on graphical data Cavity Breach Graph Reference (C) Photograph Reference (C) 1 PVCu with timber head 9sec (24mins sec) sec (23mins 3sec) Head of window frame 1 1,2 2 PVCu without timber head 34sec (mins 4sec) 32sec (mins 1sec) Head of Window frame 2 3 3 Aluminium With timber head 917sec (1mins 17sec) 82sec (13mins 4sec) Side of timber head, 4 Aluminium Without timber head 4sec (9mins) 446sec (7mins 26sec) Head of window frame 4 6 Hardwood with timber head 3sec (23mins 23sec) 3sec (23mins 23sec) Inside enclosure (see note 1) 7,8 6 Hardwood without timber head 1sec (19mins sec) 16sec (16mins 6sec) Inside enclosure (see note 1) 6 9, 7 Softwood with timber head 17sec (2mins 7sec) 1661sec (27mins 41sec) Inside enclosure (see note 1) 7,12 8 Softwood without timber head 88sec (mins 4sec) 88sec (mins4sec ) Inside enclosure (see note 1) 8 13 Note 1: post test inspection suggested that the window frame systems were still intact and that the breach may have been due to the failure of the joint detail between the enclosure and the window framework. Discussion and Recommendations From both the visual observations and temperature measurements, as shown in Table C1 that it can be seen that in all cases the fire entered the cavity within the thirty minute exposure period. It is therefore important to identify the failure mode for each type of window system as also given in Table C1. As can be seen from the note associated with Table C1 that the failure mechanism of the timber frame windows appears to be primarily a breach of integrity at the interface between the window frame and the enclosure, with the window frames remaining effectively intact when inspected after 6 Building Research Establishment Ltd 2

removal from the test frame. This finding suggests that, as has been seen throughout this work, the interface detail between the cavity closure and the primary substrate is critical to the overall performance of the system. This work has also shown that where the frame or primary structure has distorted or been consumed, such that the cavity has become exposed, the performance of the timber bead has provided some additional mitigation against fire spread within the cavity. Graphs ODPM Cavity Barriers Windows frame tests UPVC Frame with timber heads 7 6 Visual observation of breach of cavity 9 sec (24mins sec) 1 4 3 Graphical observation of breach of cavity sec (23mins 33 sec) 2 2 2 TC TC TC 12 TC 13 TC TC 1 Graph C1. Temperature versus time of thermocouple PVCu frames with timber heads. 66 Building Research Establishment Ltd 2

2 Visual observation of breach of cavity 34sec (mins 4sec) 2 Graphical Breach of cavity 32sec (mins 1sec) ODPM Cavity Barriers Windows frame tests PVCu Frames without timber heads 1 2 4 6 8 12 16 18 TC TC TC 12 TC 13 TC TC 1 Graph C2. Temperature versus time of thermocouple PVCu frames without timber heads. ODPM Cavity Barriers Windows frame tests Aluminium Frame with timber heads 16 12 8 6 4 2 Visual observation of breach of cavity 917sec (1mins 17 sec) Graphical observation of breach of cavity 82sec (13mins 4sec) 1 2 4 6 8 12 16 18 2 TC TC TC 12 TC 13 TC TC 1 Graph C3. Temperature versus time of thermocouple Aluminium frames with timber heads. 67 Building Research Establishment Ltd 2

ODPM Cavity Barriers Windows frame tests Aluminium Frame without timber heads 2 18 16 Visual observation of breach of cavity 4sec(9mins) 1 12 8 Graphical observation of breach of cavity 446sec (7mins 26sec) 6 4 2 2 4 6 8 12 TC TC TC 12 TC 13 TC TC 1 Graph C4. Temperature versus time of thermocouple Aluminium frame without timber heads. ODPM Cavity Barriers Windows frame tests Hardwood Frame with timber heads 9 8 7 Visual observation of breach of cavity 3 sec (23mins 23 sec) 1 6 4 3 Graphical observation of breach of cavity 3 sec (23mins 23 sec) 2 2 4 6 8 12 16 18 2 TC TC TC 12 TC 13 TC TC 1 Graph C. Temperature versus time of thermocouple Hardwood frame with timber heads. 68 Building Research Establishment Ltd 2

ODPM Cavity Barriers Windows frame tests Hardwood Frame without timber heads 2 2 Visual observation of breach of cavity 1 sec (19mins sec) Termination of test 17sec (19mins 7sec) 1 Graphical observation of breach of cavity 16 sec (16mins 6 sec) 2 4 6 8 12 16 18 2 TC TC TC 12 TC 13 TC TC 1 Graph C6. Temperature versus time of thermocouple Hardwood frame without timber heads. 2 ODPM Cavity Barriers Windows frame tests Softwood Frame with timber heads 1 2 Graphical observation of breach of cavity 1661 sec (27mins 41 sec) Visual observation of breach of cavity 17 sec (2mins 7 sec) 2 2 TC 6 TC 7 Graph C7. Temperature versus time of thermocouple softwood with timber heads. 69 Building Research Establishment Ltd 2

ODPM Cavity Barriers Windows frame tests Softwood Frame without timber heads 9 8 7 6 4 3 Visual observation of breach of cavity 88sec (mins 4sec) Graphical observation of breach of cavity 88sec (mins 4sec) 1 2 2 4 6 8 12 16 TC TC TC 12 TC 13 TC TC 1 Graph C8. Temperature versus time of thermocouple softwood without timber heads. Photographs PVCu with timber bead Photograph C1. Showing the break through of flames out of the enclosure 7 Building Research Establishment Ltd 2

Photograph C2. Showing post test damage. PVCu without timber bead Photograph C3. Showing distortion of the window frame. 71 Building Research Establishment Ltd 2

Aluminium with timber bead Photograph C4. Showing flaming entering the cavity. Photograph C. Showing post test damage. 72 Building Research Establishment Ltd 2

Aluminium without timber bead Photograph C6. Showing post test damage. Hardwood with timber bead Photograph C7. Showing flaming in the cavity above the window 73 Building Research Establishment Ltd 2

Photograph C8. Showing post test damage. Hardwood without timber bead Photograph C9. Showing flames entering the cavity. 74 Building Research Establishment Ltd 2

Photograph C. Showing post test damage. Softwood with timber bead Photograph C. Showing flames entering the cavity 7 Building Research Establishment Ltd 2

Photograph C12. Showing post test damage. Softwood without timber bead Photograph C13. Showing post test damage. 76 Building Research Establishment Ltd 2