Duracast Pressure Plate Installation Instructions

Similar documents
Series Outside glazed curtain wall. Installation instructions

Series Silicone structural glazed. Installation Instructions

Series Silicone structural glazed curtain wall. Installation instructions

SERIES 5600PG PREGLAZABLE CURTAINWALL

Installation Instructions

SERIES ET350 STRIP WINDOW SYSTEM

Note: Installation and Glazing Manuals are product specific. FOR REVIEW ONLY! FEBRUARY 2012

Flushglaze For Steel Tube Applications and Horizontal Panels. Façades Installation Guide

SERIES 487 CENTER GLAZED SLIDING DOOR WITH 1-1/2" TRIM

YOW 250 T Window System

YCW 250 I-Beam Curtain Wall System Installation Manual

Guardian Wall Panel Installation Manual

SECTION STAINLESS STEEL WALL PANELS

7000 Series Curtain Wall Information Specifications

1600 WALL SYSTEM 2 ESTIMATING/TAKE-OFF AND ORDERING GUIDE (16 Pages) E.C.# (09/09/13)

ESTIMATING/TAKE-OFF AND ORDERING GUIDE

SECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Summit tm Modular Railing System

Maximum thermal performance ISOLEREN INSULATED METAL PANELS INSTALLATION GUIDE

1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces.

INSTALLATION INSTRUCTIONS 2-1/2 x 7-5/16 for 1-5/16 Glass

Gensler 2014/06/16 Hertz Global Headquarters ISSUE FOR BUILDING PERMIT Estero, Florida SECTION

MS 360 SLIDING MALL FRONT INSTALLATION INSTRUCTION MANUAL

SECTION E INDEX CURTAINWALL FRAMING SYSTEMS

Trex Commercial Products page Decorative Metal Railing

SECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Monaco tm Modular Railing System

THERMAL ISOLATION CLIP

Architectural Wall Products Guide Specifications


Cardinal Commercial Products ALUMINUM STOREFRONT SYSTEM SERIES CF450 GUIDE SPECIFICATIONS SECTION ALUMINUM ENTRANCES AND STOREFRONT SYSTEMS

SECTION COMPOSITE WALL PANELS PART 1 GENERAL 1.01 SECTION INCLUDES

SIGNATURE SERIES UNIT WALL

Install & Maintenance Instructions

Division 8 Section "Flush Wood Doors" for louvers in wood doors. Division 15 Sections for louvers that are a part of mechanical equipment.

C. All anchors, brackets, and hardware attachments necessary to complete the specified structural assembly, when included within project scope.

General Window Installation Instructions

PROJECT LOCATION SECTION COPPER METAL PLATE WALL PANELS

DETAIL INSTRUCTION No. 1

SECTION ARCHITECTURAL GLASS HANDRAIL AND RAILINGS

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system.

SECTION LAGUNA SERIES TOP HUNG SLIDING DOOR SYSTEM

Guideline Specifications

SECTION ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

SECTION EXTERIOR GRILLS AND SCREENS

SECTION ALUMINUM WINDOWS

Tender No Section St. James - Assiniboia Centennial Pool Fitness Facility Addition Page 1

TerraClad TM General Specifications

RAMAPO COLLEGE OF NEW JERSEY PHASE II HOUSING REHABILITATION C 2012

YES SSG TU Vent Window System

SECTION METAL FRAMED SKYLIGHT. A. Engineering, preparation of fabrication drawings and structural calculations for the entire skylight system.

SECTION HANDRAILS AND RAILINGS. A. Section Cast-In-Place Concrete; coordination with substrate.

Page 1 of 5

Master Specifications for Microcotta November 2017

Installation Guidelines for all Quaker products with nail fins New construction nail fin installation with a drainable weather resistant barrier.

SECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Casino Modular Railing System

Repair Maintenance Hangar Phase II August 2010

HOTEL SPECIFICATION SECTION 08100

FL200 13/4 x41/2 GUIDE SPECIFICATION. Non-Thermal Storefront

PRESTON HEALTH SERVICES ARCHITECT'S NO MITCHELL-HOLLINGSWORTH NURSING & REHAB ADPH #B

Architectural Roof Products Guide Specifications

MPG Series 2250T Thermally Broken Aluminum Window

Design No. HI/BP PERIMETER FIRE BARRIER SYSTEM Hilti, Inc. ASTM E 2307 Table 1

SECTION ORNAMENTAL ALUMINUM RAILING

SECTION MANUAL FOUR FOLD DOORS MODEL 38 DECORATIVE PANEL DESIGN

K. ASTM F436- Standard Specification for Hardened Steel Washers; 2011.

SECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Glenlake Modular Railing System

SECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

SECTION ORNAMENTAL ALUMINUM RAILING

ReCote Finish System over Concrete

Corium Brick Rainscreen System Specifications

North Hanover Township School District North Hanover Township, New Jersey

SECTION ARCHITECTURAL GLASS HANDRAIL AND RAILINGS 3-Line Glass Rail Railing Spec

FIRESTOP JOINT SPRAY CFS-SP WB. 2mm (0.079") WET FILM ± 7.5 ± 5

SWING DOOR SPECIFICATION

TRUMAN STATE UNIVERSITY GREENWOOD SCHOOL WINDOW REPLACEMENT

DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION MORTAR AND MASONRY GROUT

SECTION CONCRETE FORMWORK AND ACCESSORIES

Expansion Joint Covers

SECTION COLD-FORMED METAL TRUSSES

Architectural Roof Products Guide Specifications

Architectural Roof and Wall Products Guide Specifications

ARCHITECTURAL WALL PANELS APPLIED OVER A SHEATHED STUDWALL BY MEANS OF A FIELD ASSEMBLED RAINSCREEN SYSTEM

ARCHITECTURAL WALL PANELS APPLIED OVER A SHEATHED STUDWALL BY MEANS OF A FIELD ASSEMBLED RAINSCREEN SYSTEM

Proudly Made in the U.S.A. 5-Year Warranty. Wayfinding Products

Project No: Pakenham Branch Library, Pakenham, Ontario Section January, 2017 Page 1 of 7

200 Singleton Drive Waxahachie, Texas T: F:

SPECIAL NOTES: EXCLUSIONS: THE FOLLOWING ITEMS ARE NOT SUPPLIED - SEE SEPARATE SAMPLES FOR GLASS MAKE UP.

A. Section includes conventionally glazed aluminum curtain walls installed as stick assemblies.

SECTION ALUMINUM WINDOWS

Exterior System installation instructions

Expansion Joint Covers (079513)

SECTION ALUMINUM ENTRANCES AND STOREFRONTS. A. Section Includes: Aluminum doors and window wall frames.

SECTION ALUMINUM CURTAIN WALL PART 1 - GENERAL

DIVISION 5 - STRUCTURAL STEEL AND IRON WORK

MARLIN WINDOWS, INC 3500 HC SERIES 3 3 8" SLIDING WINDOW PAGE 1

GENERAL SPECIFICATION FOR FIRE RATED APPLICATIONS

SECTION EMBEDDED CMU/SPLIT FACE ARCHITECTURAL PRECAST/SITECAST CONCRETE. A. Site Cast or Tilt-Up CMU/Split Face Concrete Panels.

Home Depot Page 1 of 5 HDPB Humacao, PR 10/19/09

Architectural Roof and Wall Products Guide Specifications

2002 Advanced Building Products, Inc., P.O. Box 98, Springvale, Maine TEL: ; FAX: ; WEBSITE:

METL-VISION WINDOW SYSTEM FOR HORIZONTAL WALL

Transcription:

July 2015 EFCO CORPORATION 7/2015 PART NO. YW45 1

TABLE OF CONTENTS SECTION S-5600 / S-5900 DURACAST PRESSURE PLATE PAGE I. General Notes and Guidelines. 3-4 II. Glazing Preparation & Installation... 5 III. Pressure Plate Installation... 6-10 IV. Vertical Splice Joints. 11 V. Exterior Cover Installation... 12 Minimizing Condensation Note: Please reference EFCO's "Understanding Condensation" brochure which can be obtained through your EFCO representative. Condensation will form on any surface when unfavorable conditions (interior temperature and relative humidity and exterior temperature) are present. When the formation of excessive condensation is a concern, it is highly recommended that a design professional is utilized to perform an analysis of the shop drawings to recommend the best possible installation methods. Please contact your EFCO representative for information on EFCO's Thermal Analysis Services. Many current installation practices lead to an increase in the possibility of the formation of condensation. Though not all inclusive, the list of examples below illustrates conditions under which condensation is likely to occur: 1. Bridging system thermal break with non-thermally broken metal flashing or lintels that are exposed to the exterior 2. System exposure to cold air cavities 3. Interior relative humidity levels not maintained at recommended levels, see EFCO s Understanding Condensation brochure 4. Inadequate separation between system and surrounding condition at perimeter 5. Product combinations during the shop drawing stage that result in bridging thermal breaks of one or all products involved Note: These installation instructions are a supplement to the approved final shop drawings and are to be used in conjunction with those drawings. EFCO CORPORATION 6/2012 PART NO. YW45 2

Section I: General Notes and Guidelines I. HANDLING / STORING / PROTECTING DURACAST - The following precautions are recommended to assure early acceptance of your products and workmanship. A. HANDLE CAREFULLY - Store with adequate separation between components so the material will not rub together. Store the material off the ground. Protect materials against weather elements and other construction trades. B. KEEP MATERIAL AWAY FROM WATER, MUD, AND SPRAY - Prevent cement, plaster, and other materials from contacting with and damaging the finish. Do not allow moisture to be trapped between the finished surface and the wrapping material. C. PROTECT MATERIALS AFTER ERECTION - Wrap or erect screens of plastic sheeting over material. Cement, plaster, terrazzo, and other alkaline materials are very harmful to the finish and are to be removed with soap and water before hardening. Under no circumstances should these materials be allowed to dry or permanent staining will occur. D. CUTTING OF DURACAST - Duracast can be cut with a standard miter saw using a carbide blade; however, the life of the blade life will be shortened significantly due to the high glass content of Duracast. For best results use a diamond tipped or concrete blade for extended blade life. II. GENERAL GUIDELINES - The following practices are recommended for all installations: A. REVIEW APPROVED SHOP DRAWINGS Become thoroughly familiar with the project. Shop drawings govern when conflicting information exists in these installation instructions. B. INSTALL ALL FRAMING MATERIAL PLUMB, LEVEL, AND TRUE Proper alignment and relationships to benchmarks and column centerlines, as established by the architectural drawings and the general contractor, must be maintained. C. The sequence of erection should be coordinated with the project superintendent to prevent delays and minimize the risk of material damage. Note: If preset anchors are required, coordinate and supervise anchor placement with the general contractor. D. Verify that all job site conditions and accompanying substrates receiving the installation are in accordance with the contract documents. If deviations occur, notification must be given IN WRITING to the general contractor and differences resolved before proceeding further with the installation in the questionable area. EFCO CORPORATION 6/2012 PART NO. YW45 3

SECTION I: GENERAL NOTES and GUIDELINES F. Follow EFCO framing installation and glazing instructions. G. Verify contents of all material shipments received upon their arrival. Verify quantity and correct finishes. NOTIFY EFCO IMMEDIATELY OF ANY DISCREPANCIES OR DAMAGE THAT MAY HAVE OCCURRED. H. Throughout these instructions the term SEALANT will appear. For the purposes of these instructions, sealant is to be defined as the following: SEALANT - A weather resistant, gunnable liquid filler which when cured provides a resilient, flexible (± 50% movement capability) air and water seal between similar and dissimilar materials. All sealant must meet ASTM C 920, CLASS 50. BUTYL SEALANT- A non-skinning, non-hardening material (NAAMM Reference Standard 5C-1). NOTE: All sealant must be compatible with all surfaces on which adhesion is required, including other sealant surfaces. All frame surfaces should be clean, dry, dust, and frost free. If a primer is required, it must be applied to clean surfaces. All perimeter substrates shall be clean and properly treated to receive sealant. This system is designed and has been tested to utilize butyl or silicone sealants at all internal joineries, i.e., joint plugs, gasket intersections, etc. Regardless of the sealant used, the customer should contact the sealant manufacturer to determine compatibility and adhesion. Follow sealant manufacturer's proper application procedures and quality assurance programs for weather sealing. Maintain caulk joints as shown in the approved shop drawings. Unless specified otherwise, most sealant manufacturers recommend a 3/8 minimum perimeter caulk joint. A 3/4 minimum joint is recommended at the head condition to accommodate thermal expansion and contraction. Anchoring surfaces of perimeter construction must be level and plumb within the adjustable limits of the head, jamb, and sill framing. EFCO CORPORATION 6/2012 PART NO. YW45 4

Section II: Glazing Prep. & Installation Note: All anchors must be FIXED before glazing installation begins. 5600 Series Outside Glazed Installation A. Seal and install Joint plugs per Installation Instruction Y302 - Section VI: Glazing Preparation. DO NOT install a Thermal Isolator as indicated in Steps 1A and 1B. B. Install Setting Blocks, Infill Glazing Material, Temporary Retainers, and Side Blocks per Installation Instruction Y302 - Section VII: Glazing Installation, Steps #3 thru #5. 5900 Series Outside Glazed Installation A. Seal and install Joint plugs per Installation Instruction Y350 - Sections VI: Joint Plug Application. B. Install Glazing Adaptors / Mullion Gaskets per Installation Instruction Y350 - Sections VII: Glazing Adaptors / Mullion Gaskets. C. Install Setting Blocks, Infill Glazing Material, and Anti-Walk Blocks ONLY per Installation Instruction Y350 - Sections VIII: Setting Blocks / Anti-Walk Blocks / Pressure Plate Gaskets. Follow the instructions in this document for the installation of the Pressure Plate. See Section III - Pressure Plate Installation EFCO CORPORATION 6/2012 PART NO. YW45 5

Section III: Pressure Plate Installation Note: All anchors must be FIXED before glazing installation begins. STEP #1 Perimeter Pressure Plate Preparation A. If not using a Perimeter Adaptor skip to Step #2 B. Align the Perimeter Adaptor the Pressure plate and install using a rubber mallet or hammer every 2 to 3 feet. The adaptor should be installed flush with each end of the pressure Plate. C. When installing the exterior gasket material as described in step #2, one gasket should be installed in the pressure plate and the second gasket installed in the Perimeter Adaptor. Install Perimeter adaptor with mallet every 2 to 3 feet. Align Perimeter adaptor to pressure plate. The Pressure Plate and Adaptor should both be flush at the each end. Install glazing gaskets per step #2. One gasket should be located in the adaptor and one in the pressure plate EFCO CORPORATION 6/2012 PART NO. YW45 6

Section III: Pressure Plate Installation Note: All anchors must be FIXED before glazing installation begins. STEP #2 Pressure Plate Preparation A. Remove exterior gasket material from the reel and allow to relax and shrink. B. Insert glazing gaskets into the pressure plates. For horizontals, gaskets should extend 1/4 beyond each end of the pressure plate. For vertical single story applications, gaskets should be flush with both ends of the pressure plate. For vertical multi-story applications, gaskets should extend 1 beyond the top end of the pressure plate and flush with the bottom end of the pressure plate. Horizontal Pressure Plate Vertical Pressure Plate Horizontal Pressure Plate Typical horizontal gasket extended ¼ each end. Typical horizontal gasket extended ¼ each end. Typical vertical gasket cut flush top and bottom. Vertical at multistory, gasket extended 1 at top only STEP #3 Joint Plug Face Sealing A. Apply sealant to the face of the joint plugs prior to installation of vertical and horizontal pressure plates. Apply sealant to face of all joint plugs EFCO CORPORATION 6/2012 PART NO. YW45 7

Section III: Pressure Plate Installation STEP #4 Install Pressure Plate A. First attach the vertical pressure plates and then the horizontal pressure plates into position using stainless steel hex washer head screws (refer to Table #1 for screw size based on Curtain Wall Series). Locate screws in the first complete pre-punched hole on each end of the pressure plate no more than 3.5 from the end. Refer to the final approved shop drawings for screw spacing. B. Torque screws to 80 inch-pounds. C. In cold Weather, first torque all pressure plate screws to 40 inchpounds. Once all four sides have been clamped down, torque all screws to 80 inch-pounds. D. When possible, work from the center outward on horizontals and from the sill upward on verticals. E. Glazier should always place screws in Pressure Plate End Incomplete Hole Hex washer head screw in first complete hole (see Table #1). pre-punched holes immediately above and below each horizontal. This will provide maximum control of pressure on mullion plugs that provide a critical sealing function. F. The pressure plate should extend 3 past any splice (see Section IV: Vertical Splice Joints). Table #1 Curtain Wall Series Screw Size & Type 5600 #13 x 5/8" S.S. Hex Washer Head Screw 5900 ¼" x 1" S.S. Hex Washer Head Screw Place screws in holes immediately above and below all horizontals EFCO CORPORATION 6/2012 PART NO. YW45 8

Section III: Pressure Plate Installation STEP #4 Install Pressure Plate (continued) F. For curtain wall systems that utilize vertical covers 1 in depth and over, attach a Roll Pin Support on the vertical at each horizontal. This will allow the application of a roll pen after cover installation to prevent slippage. G. For curtain wall systems that utilize horizontal covers 1 in depth and over, attach a Roll Pin Support at the mid-span of the horizontal. Roll Pin Support located at each horizontal when vertical cover depth 1 and over. Note: Orient horizontal pressure plates such that the weeps are located above the mullion tongue 3/16 x 1 weep slot centered 4 off each end of pressure plate. Clean fiberglass hairs from edges. (Optional Weep Holes: Drill (3) 5/16 Dia. weep holes side by side. Locate center of holes 5/32 above top of tongue.clear glass fray from holes with utility knife. Do before installing.) Note: Horizontal pressure plates are ¼ shorter than horizontal mullions. The glazier should center the horizontal pressure plate on the mullion before installation. EFCO CORPORATION 7/2015 PART NO. YW45 9

Section III: Pressure Plate Installation STEP #5 Seal Pressure Plate Ends A. Seal all joints between the vertical and horizontal pressure plates with sealant to provide a water and airtight joint. Seal joint between horizontal and vertical pressure plates. EFCO CORPORATION 6/2012 PART NO. YW45 10

Section IV: Vertical Splice Joints 5600 Series Outside Glazed Installation A. Vertical splices should be assembled per Y302 - Section VIII: Vertical Splice Joints including location of pressure plate and cover splice joint locations and overlaps. 5900 Series Outside Glazed Installation A. Vertical splices should be assembled per Y350 - Section V: Vertical Splice Joints including location of pressure plate and cover splice joint locations and overlaps. EFCO CORPORATION 6/2012 PART NO. YW45 11

Section V: Exterior Cover Installation 5600 Series Outside Glazed Installation A. Vertical and horizontal covers should be installed per Installation InstructionY302 - Section IX: Exterior Cover Installation. Note, if roll pins are required they should be located such that the pins engage the Roll Pin Supports applied in Section III, Step #3 of this instruction. 5900 Series Outside Glazed Installation A. Vertical and horizontal covers should be installed per Installation InstructionY350 - Section X: Exterior Cover Installation. Note, if roll pins are required they should be located such that the pins engage the Roll Pin Supports applied in Section III, Step #3 of this instruction. EFCO CORPORATION 6/2012 PART NO. YW45 12