Pre-installation Manual CONCEPT 301 D/401 D/501 D

Similar documents
Pre-installation Manual. Plate Processor 68/85 Thermal

Pre-Installation Guide

Gerber M Series Site Requirements

Site Preparation Guide. Scodix Ultra Press and Scodix Ultra-Pro Press and Scodix Ultra Foil Station

Gerber. Scientific Products. Dear Gerber Sabre Customer:

Precision Range (All Models)

CRON HDI-920 Site Planning. Customer Responsibilities

Latex 3000 Printer series. Site Preparation Checklist

XPM 2. Reflow Soldering / Curing Systems. Site Preparation & Installation

Xerox Wide Format Stacker HS

RapID Raw Materials Verification System

TRS100 Rapid Assay System Pre-Installation Guide

XN24 for Package Production. Site Preparation Guide XN24

! CAUTION: Read and follow these instructions.

Symmetra PX 160 Classic Battery Cabinet

Pre-Delivery Instructions

Saphyr System Safety Guide for Saphyr P/N 60325

Gerber Scientific Products

E-Series Installing E-Series U Cabinet

Stack Parking Surface Mounted Stackers

MNL, SEL DIMENSIONS, SITE AW PLANNING GUIDE ARTWORK SIZE A SHEET 1 OF 1

EPS Receiving and Unpacking 06/

Powerware 9390 Integrated Accessory Cabinet IAC-D Configuration Installation and Operation Manual. For use with kva and kva UPS Models

RENA XPS-3000 Base. User Guide. SC2000 Media Transport System

TeraFrame HD Cabinet System Supplemental Installation Guide

booster EX2 / EX3 Operating Manual Extrusion Welder Weldy AG Galileo-Strasse 10 CH-6056 Kaegiswil / Switzerland TECHSPANGROUP

Symmetra PX kw 208 V. Receiving and Unpacking 08/2015.

Customer Responsibilities

Pre-Delivery Instructions

Installation Instructions

Installation and Operation Manual

This document provides the Pre-Installation Checklist for the ADVANTAGE Router 600.

Customer Responsibilities

MESH FLOOR HEATING SYSTEMS INSTALLATION INSTRUCTIONS

Galaxy VM kva 400 V Receiving and Unpacking 06/

Bedhead Service Systems. Instructions for Use. July 2016 ASF-18 (0)

EXPRESS5800/1080Xd. Installation Procedures

Low-profile, 11U high cabinets hold networking equipment, servers, and phone equipment.

Daker DK kva. Parallel installation quick start. Part. LE08927AA-09/15-01 GF

Agilent 7696A Sample Prep WorkBench

medixx Series Installation Guidelines medixx 50 medixx 60 medixx 70 Suitable for the following Siemens MRI Systems, or similar models:

Agilent Technologies 7620-AS Sample Changer Site Preparation Checklist Hardware Site Preparation Specification

nual k Excella E-1 Open Air Shaker N) manual New Brunswick Excella E-1 Open Air Shaker Operating manual

Site Preparation Guide for

Maintenance Bypass Breaker Cabinet Series Configuration 5. Installation and Operation Manual

INSTRUCTION MANUAL WARNING: BEFORE USING THE MACHINE READ THE INSTRUCTION MANUAL CAREFULLY!

Three-sided barrier compliant to DIN EN ISO Depending on location, design also as wind protection. Clear height (DH) Three-sided barrier

Site Preparation Guide. Stratasys J750 3D Printing System. DOC Rev. D1

ENel Sp. z o. o. - WROCŁAW DESIGN AND MANUFACTURE OF POWER ELECTRONIC DEVICES INVERTER WELDING MACHINE ENEL250A USER MANUAL DEALER:

OptoLum MegaLine RGBW Luminaire

Pre-installation Manual LightCELL Advanced Laser Machining Center

Instructions for Installation of Metal Clad Switchgear 38 kv, 150 BIL Outdoor Housings

3M Intelligent Return Classic and Sorter System SL. Architect/Contractor's Package

July P Wide Format Stacker User Guide

INSTRUCTION MANUAL Wardrobe lift 717

MEDIUM VOLTAGE SWITCHGEAR THE MODULAR CONCEPT

Created by EBCCW 00:06. X65 Locating module. User Documentation

Power Distribution Center. Model: SUDC208V42P

Maintenance Bypass Breaker Cabinet Series Configuration 2. Installation and Operation Manual

INSTALLATION GUIDE. 4-Post Lift. Model United States. United Arab Emirates. Egypt.

ProCut 2500 M, 2500 L, 3200 L, and 3200 XL

Installation Plan. Washer-extractor PW 6088 EL LP. en - AU M.-Nr

DR-6/DT-6 MEDIUM VOLTAGE RING MAIN UNIT. Lifting & Transport Instructions MEDIUM VOLTAGE SWITCHGEAR, BUILT TO LAST

Installation Instructions

SPIRIT. Water purifier. Complete User Manual

Pre Delivery & Installation Guide GX 480 GX 480 DT GX 480 APC GX 480 DT APC GX 600 GX 800 GX 1000

Manual Supplement. This supplement contains information necessary to ensure the accuracy of the above manual.

TECHCONNECT TC2 USBTP2 OWNERS MANUAL. TC2_USBTP2_manual_en.doc

T1000 Transformer INSTRUCTION SHEET. for Magnetic-Field Susceptibility Testing. Features

MV Product Specifications

1. Telecommunications mounting elements. 2. Backboards. 3. Telecommunications equipment racks and cabinets. 4. Grounding.

Quick-release pins swing the rack open from left to right to simplify installing and maintaining your equipment.

Table of contents. 1. Introduction

The Selections Checked Below Apply To This Equipment

VWR Zero Air Generator Models , Installation, Operation, and Maintenance Manual. Bulletin TI-ZAG3500-L1466

Installation plan. Tumble dryer. PT 8807 EL (Electrically heated) en - US Mat. NR / 02

Tepidus Wire Installation instructions for Electric Radiant Floor Heating INDEX

3M Intelligent Return Plus and Sorter System FX. Architect/Contractor Package

Installation Instructions Snow Melt Mats

Wenger Corporation 2011 Printed in USA 02/11 Part #185A462-01

Barrier. Delimitation. Water drainage

The power behind competitiveness. Delta Infrasuite Power Management. Power Distribution Cabinet. User Manual.

COMPACT FIRE PUMP SYSTEM LIFTING MANUAL LIFTING & MOVING INSTRUCTIONS

Section 7: Specifications

Conversion Station Model 812

You will probably need to perform this procedure in the loading dock area of the building. A fork lift or chain hoist may be needed.

Author to add specific customer activities or additional help, information, or guidance for the customer to follow prior to installation.

PRODUCT DATA kg

PRODUCT DATA kg / 2600 kg

V21 Parts & Service Manual All V21 Identified Equipment REV A 10/2013 P/N: GENERAL INFORMATION. V21 General Information G-1

CLARK PUBLIC UTILITIES TECHNICAL SPECIFICATIONS SINGLE-PHASE PADMOUNTED TRANSFORMERS

Series 8009A 9-Meter Earth Station Antenna. Site Preparation Manual

Heating cables in concrete Concrete > 3 cm

Installation. Smart-UPS VT in Parallel kva 380/400/415 V 208/220 V 200/208 V

1. Installation Preparatory work Equipotential bonding Floor installation Connection of several modules...

Installation Manual Type DDR DIN rail power supply Series DDR-120 Introduction

PRODUCT DATA kg / 2600 kg

LEISTER WELDMAX Mini-Hand Extruder

Stacker 1000 Operator Manual 701P98048

Installation Instructions. Overview. Important Notes. LINCTM Enclosure EDB-WPM-GRX-6-CE

Transcription:

Pre-installation Manual CONCEPT 301 D/401 D/501 D

Pre-installation Manual CONCEPT 301 D/401 D/501 D Concept 301 D T11416 Edition BA, January 2015 This book has part No 10077155

0-2 This manual is published by: Glunz & Jensen S.p.A. Via Alessandro Volta 28 20088 Rosate (MI) ITALY Tel.: +39 02 900 90 180 Fax: +39 02 900 90 149 Internet: www.degraf.glunz-jensen.com Copyright 2015 by Glunz & Jensen S.p.A. Pre-installation Manual - CONCEPT 301 D/401 D/501D 1504

Introduction 0-3 Part 0: Introduction Reservations This manual was written and illustrated using the best possible information available at the time of publication. Any differences between this manual and the unit reflect improvements introduced after the publication of the manual. Changes, technical inaccuracies and typographic errors will be corrected in subsequent editions. As a part of our policy of continuous improvement, we reserve the right to alter design and specifications without further notice. Pre-installation instructions The instructions in this Pre-installation Manual allow the customer and the Service Technician to prepare the installation site for the unit and for the installation itself. Never install the unit in explosive environments. It is the responsibility of the owner and operator/s of the unit that the installation is made in accordance with local regulations, and by engineers authorized to carry out plumbing and electrical installations. The manufacturer cannot be held responsible for any damage caused by incorrect installation of the unit. Only qualified Service Technicians are allowed to unpack and install the unit. When preparing the installation site please take into consideration that this unit is for restricted access locations only! Notes, cautions, and warnings! Throughout the manual warnings, cautions, and notes are written in bold like the example below: Electrical installation must conform to local regulations and guidelines. Symbol Meaning Explanation Note Caution Warning The operator should observe and/or act according to the information in order to obtain the best possible function of the unit. The operator must observe and/or act according to the information in order to avoid any mechanical or electrical damage to the unit. The operator must observe and/or act according to the information in order to avoid any personal injury. 1504 Pre-installation Manual - CONCEPT 301 D/401 D/501D

0-4 Introduction Table of contents Table of contents Part 0: Introduction... 0-3 Reservations...0-3 Pre-installation instructions...0-3 Notes, cautions, and warnings!.... 0-3 Part 1: Transportation... 1-1 When the unit arrives...1-1 Storing the unit before installation...1-1 The crate....1-1 Dimensions and weight....1-1 Checking the crate for damage....1-2 Handling the crate...1-2 Transporting the unit....1-3 Lifting the crate...1-3 Available width for transport...1-3 Part 2: Installation requirements... 2-1 Environmental requirements...2-1 Accessories to be provided by customer for connections...2-1 Installation kit...2-1 Space requirements...2-2 Free space around the unit...2-2 Unit dimensions and connection locations....2-3 Electrical requirements...2-4 Main power connection....2-4 Main power outlet...2-4 Power supply cable...2-4 Electrical specifications....2-4 Fuses...2-4 Power consumption...2-4 Part 3: Pre-installation checklist... 3-1 Pre-installation Manual - CONCEPT 301 D/401 D/501D 1504

Transportation When the unit arrives 1-1 Part 1: Transportation When the unit arrives Storing the unit before installation The crated unit will usually be delivered some time before the arrival of the Service Technician. In which case you should prepare an appropriate place indoors to store the crated unit. The crate Dimensions and weight L W H T33126 301 401 501 Width (W) 1910 mm (75.2") 2270 mm (89.4") 2680 mm (105.5") Length (L) 1488 mm (58.6") 1748 mm (68.8") 1838 mm (72.4") Height (H) 1447 mm (57.0") Weight, crated (± 5%) app. 760 kg (1675 lb) app. 900 kg (1985 lb) app. 1100 kg (2425 lb) Weight, unit app. 560 kg (1235 lb) app. 650 kg (1433 lb) app. 750 kg (1654 lb) 1504 Pre-installation Manual - CONCEPT 301 D/401 D/501D

1-2 Transportation The crate Checking the crate for damage Check if the crate is damaged at the time of delivery. Take note of the damage before you allow the Service Technician to unpack the unit. Provide a detailed description or take a photograph of the damage. Report any damage to the crate to the transport company. Handling the crate The icons on the crate indicate how to handle the crate during transport and storage: Ensure that the side indicated by the arrows is always up Handle the crate with care. Never expose the crate to water, or place it in a highhumidity area. Do not stack the crates. Do not tilt the crate. Pre-installation Manual - CONCEPT 301 D/401 D/501D 1504

Transportation Transporting the unit 1-3 Transporting the unit Lifting the crate The unit is supplied in a wooden crate. The unit is very heavy equipment. To lift the crate a fork-lift truck is required. T33127 Available width for transport Depending on the width of the door(s) through which the unit has to be transported to the installation site, the Service Technician may have to perform the actions described in the table below. If width of the door is Then 301 401 501 > 1550 mm No action is required as the crated unit can be transported immediately to the installation site. 1550-1400 mm The Service Technician has to unpack the unit. > 1800 mm No action is required as the crated unit can be transported immediately to the installation site. 1800-1700 mm The Service Technician has to unpack the unit. > 1890 mm No action is required as the crated unit can be transported immediately to the installation site. 1890-1750 mm The Service Technician has to unpack the unit. 1504 Pre-installation Manual - CONCEPT 301 D/401 D/501D

1-4 Transportation Transporting the unit Pre-installation Manual - CONCEPT 301 D/401 D/501D 1504

Installation requirements Environmental requirements 2-1 Part 2: Installation requirements This unit must be installed in restricted access locations only. Check the delivery route to the installation location for necessary clearance and remove all obstructions. Environmental requirements Provide a heating and ventilating system capable of maintaining room temperature between 17 and 28 C (63 and 82 F) and relative humidity on max. 80%. For heat emission see "Power consumption" on the page 2-4. Accessories to be provided by customer for connections Customer has to provide power cable according to the requirements on page 2-4. Hoses for exhausts are delivered with the unit. Installation kit Installation kit is included with the unit. It comprise the parts necessary to make the installation. See Service Manual for installation part list. 1504 Pre-installation Manual - CONCEPT 301 D/401 D/501D

FLOOR 2-2 Installation requirements Space requirements Space requirements Free space around the unit Decide where the unit shall be placed and make sure that the free space around the unit makes servicing and work possible. The recommended minimum free space around the unit is: 1200 mm (47.2") in front of the unit, 500 mm (19.7") at the back of the unit, 200 mm (7.9") on the left side of the unit, 800 mm (31.5") on the right side of the unit. 500 mm ( 1 9. 7 ") 800 mm( 31.5" ) 200 m m (7. 9 ") 12 00 m m (47. 2 ") T33279 Pre-installation Manual - CONCEPT 301 D/401 D/501D 1504

Installation requirements Space requirements 2-3 Unit dimensions and connection locations W L H exhausts ø80 power supply T33280 301 401 501 Width (W) 1750 mm (68.9") 2080 mm (81.9") 2500 mm (98.4") Length (L) 1320 mm (52.0") 1600 mm (63.0") 1650 mm (65.0") Height (H) 1130 mm (44.5") Exhaust Exhausts must be connected to the appropriate location (directly to the outside or to the building exhaust installation). Make sure that the airflow is correct and minimum exhaust capacity is 100 m 3 /h. 1504 Pre-installation Manual - CONCEPT 301 D/401 D/501D

2-4 Installation requirements Electrical requirements Electrical requirements Electrical installation must conform to local regulations and guidelines. Main power connection The main power connection must be made to the main connector located at the back of the unit. Main power outlet Provide a main power outlet close to the installation site. The table below indicates the applicable power supply types. Power supply cable The power supply table below shows recommended power supply cable for unit. The conductors in the power supply cable must be of copper. When deciding what type of cable to use take into account the mechanical resistance (operator may step onto cable). Provide for additional cable protection, e.g. cable covers, if cable is exposed to heavier transport such as fork-lift trucks etc. The unit is Class 1 equipment. Therefore, the unit must be connected to earth to avoid electrical shocks. Electrical specifications Installation requirements for power supply EUR US Supply/fuse 3W+N+PE,400VAC 3 x 8 Amps, 50-60 Hz 3W + PE, 230 VAC 3 x 14 Amps, 50-60 Hz Recommended cable type Min. 5 x 2.5 mm 2 type H07RN-F Min. 4 x 10 AWG, UL62 listed type S, SJ, SJO or SJT All Voltage tolerance ± 10% Fuses The fuses must have a breaking capacity of min. 100kA. If using automatic circuit breakers make sure that they are Type D. Power consumption Power consumption at All 230/400 VAC operation 5,000 W Pre-installation Manual - CONCEPT 301 D/401 D/501D 1504

Pre-installation checklist 3-1 Part 3: Pre-installation checklist Please ask the customer to answer the following questions in order to ensure a trouble-free installation of the unit. Send this completed pre-installation checklist to your regional service coordinator. 1. Delivery of the crate and transport to the installation site YES NO A. Is there a place indoor where the crated unit can be stored temporarily? B. Is there a fork-lift truck or any other lifting device available? C. Can the crate be transported directly to the installation site? See minimum width specifications on page 1-3. D. Is it sufficient to unpack the unit before it is transported to the installation site? See minimum width specifications on page 1-3. E. Are there other factors (stairs, elevators, corners, obstacles, etc.) which should be taken into account when transporting the crate or unit? If so, explain:............ 2. Power supply YES NO A. Make a note of the present supply specifications: No. of Phases... Voltage... V Fused by... Amps Neutral Wire?... Earth Wire?... Frequency... Hz B. Has a connection box been provided to connect the unit to the mains? C. Is the customer aware that he/she should provide (or order) power cable necessary to connect the unit to the mains? D. Is there a house electrician available? E. Are there any known problems in the building where the unit will be installed? If so, explain:............... 1504 Pre-installation Manual - CONCEPT 301 D/401 D/501D

3-2 Pre-installation checklist 3. Connections YES NO A. Capacity of air condition/ventilation adequate with regard to power consumption as specified on page 2-4? B. Is there an exhaust system available? C. Can hoses (ø80) be connected to the exhaust system? D. Availability of warm water for cleaning of the unit? 4. Comments and questions............ 5. Disposition of the various supplies and equipment on the installation site Pre-installation Manual - CONCEPT 301 D/401 D/501D 1504