ST IMPLICATIONS IN THE CNGS PROJECT

Similar documents
EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics CERN TS DEPARTMENT

EUROPEAN LABORATORY FOR PARTICLE PHYSICS LABORATOIRE EUROPEEN POUR LA PHYSIQUE DES PARTICULES

Civil Engineering for the SHiP Facility

ILC ASIAN DRAFT SCHEDULE

Calculation of Water Activity in Point 7

Guy Crockford, BE/OP/LHC, CERN

THE CHALLENGES OF THE SOFTWARE SUPPORT FOR INDUSTRIAL CONTROLS CONTRACT.

1. CERN Accelerator Complex 2. Decay Ring Magnets 3. Costing

Finnish Underground Lab

CLIC Civil Engineering, Infrastructure and Siting Working Group, (CEIS) John Osborne Matthew Stuart CERN SMB-SE-FAS

2008 JINST 3 S The interface to the LHC machine. Chapter Beampipe Layout

CHAPTER 20 THE INTERNAL BEAM DUMPING SYSTEM

CHAPTER 10 EXPERIMENTAL AREAS

Status Report on the LHC machine Lyndon Evans

NuMI/LBNF Radiation Protection. Jim Hylen NBI September 2017

Finnish Underground Lab

An Experimental Area for Short Baseline Neutrino Physics on the CERN Neutrino Beam to Gran Sasso

LUCOEX Conference Oskarshamn, June F. Chauvet & al. CIGEO/

Market Survey. Technical Description. Supply of Long Austenitic Steel Shells for D2 Dipole Cold Masses

The Dismantling Project for the Large Electron Positron (LEP) Collider

RÍO AMOYÁ - LA ESPERANZA Hydroelectric Power Plant

PRELIMINARY VENTILATION AND COOLING DURING THE CONSTRUCTION OF THE BRENNER BASE TUNNEL

Conceptual Design Report

Tohoku Pacific Earthquake and the seismic damage to the NPSs

llilliiiillllllllilllllllllllllllllllllllil CERN AT, (CR, 94'36

The neutron Time-Of-Flight facility, n TOF, at CERN (I): Technical Description

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES

CLIC MEETING. 1 - ILC Frascati workshop 2 - Conventional Facilities & Siting. CFS Group of GDE J.L. Baldy

ScienceDirect. Application of a novel, vacuum-insulated solar collector for heating and cooling

Radiation and Enviromental studies for BDF

NLC Conventional Facilities

Technical Summary for the Tokamak Assembly Works- A0

Surface treatments for vacuum applications at CERN

Buildings Construction Procurement Strategy

Water Cooling for the LHC

UNDP / PAPP OFFICE BUILDING RAMALLAH HVAC WORKS


Systems for Neutrino Facilities. STFC Rutherford Appleton Laboratory

Report from the GDE director. Barry Barish Snowmass 14-Aug-05

Background information for Procurement Procedure F4E-OPE-301 (TB04)

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy

Short Term Programs for Civil Engineering Students (Diploma/Degree) Specialization: Lab Testing

Misan University - College of Engineering Civil Engineering Department

Production of High Power and Large-Area Negative Ion Beams for ITER

THE CRYOGENIC SYSTEM FOR THE LHC TEST STRING 2: DESIGN, COMMISSIONING AND OPERATION

Civil Construction: Buildings and Supply Systems

PoS(Vertex 2011)003. Cooling in HEP Vertex and Tracking Detectors. Hans Postema 1. Bart Verlaat

Status and Future of high-power Neutrino Target Stations. Jim Hylen (Fermilab) NuFACT August 2018

TECHNICAL NOTE RELATED TO THE MARKET SURVEY OF THE PF COILS COLD TEST FACILITY SUPPLIER

ELECTRON BEAM DUMP - ROOM DATA SHEET

Buildings Construction Procurement Strategy

An Update on the LBNF/DUNE Project

ESS Target Facility Design. John Haines for the ESS Target Project Team

2008 JINST 3 S Cryogenic system. Chapter Overview

2.15 Tokamak Seismic Analysis

New Plants Update November 2008

1. Requirements 2. MARS Simulation for Beam Dump 3. Beam Dump Cooling 4. Layout of Beam Dump & Muon Pit 5. Summary & Schedule

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018

J PARC neutrino Cryogenics system

Tohoku Pacific Earthquake and the seismic damage to the NPSs

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents MEDIUM VOLTAGE VAULT DESIGN... 2 DIVISION LIST OF FIGURES...

DIVISION MEDIUM VOLTAGE VAULT DESIGN Contents

ISOLDE AND N_TOF CONSOLIDATION

Energy consumption and savings potential of CLIC

CERN. maximizes uptime of the world s largest and most complex machine with Infor EAM CUSTOMER INNOVATION STUDY

Technical coordination of the MICE experiment

MCKAYS CREEK HYDRO-ELECTRIC POWER SCHEME ENHANCEMENT FEASIBILITY AND SCOPING REPORT PREPARED FOR SCHEME RECONSENTING

Technical Summary. Contract for Procurement of Piping and Fittings (IO/14/CFT/9560/ACS CP/1)

How we would build the proposed storm relief sewer

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways

Energy efficiency and saving potential analysis of the high intensity proton accelerator HIPA at PSI

A New Concept for Selective Mechanical Mining of Hard Rock

Appendix 2-3. Subway Design Standards and Construction Methods

Diaphragm wall Construction

CONSTRUCTION SPECIFICATION FOR TUNNELLING

Tsunami Countermeasures at Hamaoka Nuclear Power Station

Invitation to Tender

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

2017 CERN Water Consumption

Detector Solenoid and Iron Structure

Forensics by Freezing

Procedia Earth and Planetary Science 11 ( 2015 )

ELEVATING VAM RTO INLET CONCENTRATION THROUGH CMM BLENDING FOR POWER GENERATION

6 Preliminary Assessment of Construction Method and Constructability Issues

Michael R. Lockwood Construction Management National Museum of the Marine Corps Quantico, VA

Pipe Jacking. Japan Sewage Works Association

From Colonia Jardín to Cuatro Vientos

Interface LINAC ID 25 Risk Assessments ID 26, ID 27, ID 28 Mitigation of Risks

AN INNOVATIVE PUMPED-STORAGE PROJECT IN AN UNDERGROUND MINE. Ernst Zeller November 2017

Project Case Study. Motor City DCP. Project: District Cooling Plant, Motor City Start Date: 2007 Completion Date: 2010

ORC TURBOGENERATOR TYPE CHP - Organic Rankine Cycle Turbogenerator fed by thermal oil, for the combined production of electric energy and heat -

Status of ITER Buildings construction and next procurement steps

H. Underground Transmission System Design

Second Avenue Subway

Session 5 Shutdown schedule 2008/9 and Future shutdowns

Radiation Environment and Shielding Design Optimization at MEIC

INDUSTRIAL ACTIVITY AT CERN

Experts in tunneling with Tunnel Boring Machines

Market Survey. Technical Description Recuperation, Recycling and Treatment of Written-off Oil-Filled Electrical Transformers

Transcription:

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH ORGANISATION EUROPÉENNE POUR LA RECHERCHE NUCLÉAIRE CERN - ST Division CERN-ST-2000-012 February, 2000 ST IMPLICATIONS IN THE CNGS PROJECT M. Wilhelmsson Abstract The CNGS project concerns the construction of a neutrino beam facility (CNGS = CERN Neutrino beam to Gran Sasso). A 450 GeV proton beam will be extracted from the SPS accelerator. This proton beam will hit a target a few hundred metres downstream from the extraction point (BA4). In the debris of the proton beam we will find pions which continue down a 1000 m, evacuated tunnel and a fraction of which decay into a neutrino beam. After this decay tunnel (1.1 km), a 'hadron stop' will separate the neutrinos, after which they will resume their journey down to a detector pit, outside Rome (Gran Sasso). The CERN facility has a total length of approximately 3 km. The ST division has an important share in the construction work, both of the above-mentioned tunnels as well as of all other infrastructure services, and this work concerns most of the groups in the division. This report will outline the technical design of the facility and explain how we, in the ST division, are involved in the project. The CERN council approved the project on 17 December 1999 for a scheduled commissioning in 2005. Presented at the 3 rd ST Workshop Chamonix, France, January 25-28, 2000

1 INTRODUCTION The description of matter and force particles known as the Standard Model has been challenged by the perceived deficit of mass in our universe. A possible clue to this intriguing issue is the property of the neutrino (a fundamental, chargeless particle in the lepton family) and especially the question of whether the neutrino has mass. The answer to this question is, hopefully, one outcome of the CNGS project, a project hosted at CERN but funded mainly by INFN (Istituto Nazionale di Fisica Nucleare) and other national sources. If the neutrino has mass, it is likely to be out of reach of direct measurement. Therefore the key method is to search for neutrino oscillations, the transformation of one kind of neutrino into another, which can occur only for massive neutrinos. Experiments proposed in the INFN Gran Sasso Laboratory aim, with various methods, to detect and measure these oscillations. Apart from the CERN INFN effort, described in this report, research is in progress in other parts of the world on the subject, for example, - at the SuperKamiokande experiment in Japan, using a neutrino beam from the KEK accelerator outside Tokyo, where some experiences already has been reported, indicating positive results; - at Fermilab in the USA, where a facility is under construction that will send a neutrino beam to a detector 730 km away in à mine cavern (MINOS). The CNGS project was approved by the CERN Council on 17 December 1999. 2 GENERAL DESCRIPTION OF THE FACILITY For a complete description of the facility, see Ref. >1@. Figure 1: General layout of the CNGS facility. 2

The underground structure for the CNGS facility links to the existing SPS (BA4) structure. The five main parts of the facility are listed below and illustrated in Fig. 1: - proton-beam tunnel the beam-link with the SPS accelerator from an extraction point at TT40 (where the LHC-TI8 also reaches the SPS); - target chamber with associated services structure; - access gallery to the target chamber from the SPS (ECA 4); - decay tunnel; - 'hadron-stop' chamber with connecting link-tunnels to the LEP/LHC structure at octant 8-1, and associated muon monitoring detectors. The extraction point from SPS (LSS4) is, after the upgrade, used as proton injector for the LHC via the TI8. 110 m after the extraction point the 450 GeV proton beam branches off, and continues 830 m through 73 bending magnets where it hits a target. In the debris of the proton beam we will find pions (S), which continue down a 1000 m, evacuated tunnel and a fraction of which decay into a neutrino (Q) beam. This neutrino beam meets at the end of the facility a 'hadron stop', which filters the hadrons which have not decayed, and leaves the pure Q-beam on it s flight through earth down to the Gran Sasso experiment outside Rome. 3 SCHEDULE The present schedule, see Fig. 2, for the construction of the facility is for a first proton on target in April 2005, thus very close to the commissioning of the LHC. In order to meet this schedule, the civil engineering study had to start in advance of the formal approval, and the call for tender is now ready to be issued. The construction will start by the end of 2000. Figure 2: Installation schedule for the CNGS project. 3

4 SPECIFIC GROUP DESIGNS 4.1 Civil engineering construction The description of the civil engineering structure follows the five main parts listed above. 4.1.1 Proton-beam tunnel The tunnel, from the junction with TJ8, is 590 m long with a diameter of 3.10 m, except for a slight widening over the last 20 m. 4.1.2 Target chamber and ancillary structures (See Schematic top view of the structure in Annex 1) The target chamber itself is a 115 m long cylindrical cavern with a diameter of 6.50 m. It widens on one side for the junctions of proton-beam and access tunnels. Upstream from this junction towards the access gallery is a cavern with length 15 m and a diameter 9 m to house mainly ventilation equipment, as well as a 20 m long and 3.10 m wide storage chamber. Parallel to the target chamber, there is a 3.40 m diameter service tunnel for vacuum and ventilation installations. 4.1.3 Access tunnel The access tunnel from the SPS ECA4 to the target chamber area is 769 m long and 3.10 m in diameter. A 57 m deep shaft will be located 130 m along this tunnel for access with construction tools, e.g. TBM (Tunnel Boring Machine). 4.1.4 Decay tunnel The 994 m long decay tunnel runs between the target area and the hadron stop. The tunnel, bored to a diameter of 3.10 m, is lined with a 2.45 m steel pipe and the space between the pipe and the tunnel wall is filled with concrete. The steel pipe will be welded in 6 m sections so that it can contain a vacuum of 1 mbar. 4.1.5 Hadron-stop and muon-detector area (See schematic top view in Annex 1) The cavern that houses the hadron stop and the first muon detector is a 26 m long cylindrical cavern with a diameter of 6 m. A tunnel link from the LEP/LHC structure RE88 has a total length of 224 m and a diameter of 3.10 m. The second muon detector is located in a small cavern 67 m from the first on the same beam axis. A chamber for electronic and cooling equipment is situated 10 m perpendicular to the muon chamber; it is 20 m long and 3.10 m in diameter. 4.1.6 Sequence of civil engineering work The civil engineering work will most likely commence with the excavation of an access shaft and a suitable chamber at the foot of the access gallery. A TBM can from then onwards bore all of the underground structure, with a diameter of actual head of the TBM of about 3.5 m. The final dimensions will successively be excavated by roadheader, and finished by various types of concrete lining, construction-steel elements for the crane, flat floors with embedded drain pipes, and especially the non-shrink concrete filling around the decay-tunnel steel pipe and around the hadron stop. 4.2 Electrical-power distribution The main part of the facility (target and access areas as well as the proton-beam tunnel) is powered from the BA4, SPS. It is proposed to install an 18 kv cable from BA4 to an 18 kv/400 V transformer close to the target area, to minimize transfer losses and thus optimize cost. For the hadron-stop and muon-detector area, the power is distributed from the LEP stub tunnel RE88; as the power is modest, a 400 V link should be sufficient. The lighting and safety systems (emergency stops, 48 V supplies, anti-panic light and safe power) follow the same approved concepts as LEP200 installations, which basically will be continued over the LHC period. The cabling in the underground structure will be very carefully studied, as space is very limited in the narrow tunnels and galleries. 4

4.3 Heavy handling An overhead crane with a capacity of 10 t will be installed in the target chamber. The heavy-handling team will (as can be seen in the resource plan, see Annex 2) be in heavy demand during the installation period. 4.4 Access and machine-interlock system The CNGS underground structures are considered as 'CERN Primary Beam Area' and the equipment related to the safety of personnel and equipment must be implemented accordingly. Two access points will be available to the area, duly equipped with access control and interlock systems: - Access to the target chamber area from point 4 of the SPS. The access point is situated in the underground cavern ECA4. - Access to the hadron stop and the muon detector is provided through LEP/LHC structure RE88. Access to this area requires that both the neutrino and the LHC beams be switched off. 4.5 Fire detection system Although no fire detection system has for the time being been foreseen in the CNGS underground areas, it should not be excluded in the final concept. The difficulties, pointed out during the conceptual design, of the long distance between sampling points and the smoke detectors could possibly be overcome with a general implementation in the LHC underground structure. 4.6 Ventilation 4.6.1 Target chamber and service gallery The air for this area is treated by an AHU (Air Handling Unit) placed in the second level of the tunnel junction reserved for ventilation equipment. The unit operates entirely on recirculated air, except during access periods, to avoid any unwanted release of radioactive air to the outside atmosphere. With the experienced corrosion problem from the previous West Area Neutrino Facility, the dew point is chosen as very low. 4.6.2 Proton-beam tunnel The proton-beam tunnel is also supplied from a recirculating AHU located in the ventilation cavern. During access periods fresh air is also injected. 4.6.3 Access gallery The access gallery is ventilated by an AHU located in a surface building attached to BA4, named SUI4. This unit operates only during access periods. 4.6.4 Hadron-stop and muon-detector area This area is ventilated from sector 8-1 of the LHC tunnel. A duct and fans ensure that the air reaches the whole area as far as the muon chambers. The components for air handling will be designed to provide the conditions shown in Table 1. Table 1: Parameters for the ventilation of the different areas. Dry temperature Dew point Air flow rate Smoke extraction Target area and service gallery 19qC 15qC 16 000 m 3 /h Yes Proton-beam tunnel 19qC 10qC 12 000 m 3 /h Yes Access gallery 19qC 10qC 16 000 m 3 /h Yes Hadron-stop and muon-detector area 19qC 12qC 2 300 m 3 /h Yes 5

The smoke-removal equipment is designed for cold smoke at a maximum temperature of 100qC. Before access can be authorized after a run period, the fresh air ventilation will be started and the whole area aerated for a certain time. This air release is monitored in relation to radioactivity. 4.7 Cooling The cooling requirements for different purposes are shown in Table 2. Table 2: Parameters for cooling. Cooling load Temperature Water flow rate Target 50 kw 27/42qC 3 m 3 /h Proton-beam tunnel 2000 kw 27/42qC 115 m 3 /h Hadron stop 50 kw 27/42qC 3 m 3 /h Air-conditioning target area, service and access gallery 600 kw 6/12qC 86 m 3 h 4.7.1 Proton-beam tunnel and target chamber The primary cooling system at the SPS BA4 provides the cooling of the demineralized water for the proton-beam magnets by a separate cooling station in BA4. A small closed circuit, also of demineralized water, is provided for the equipment in the target chamber. The air-conditioning units in the ventilation cavern are supplied with chilled water from a refrigeration unit located, again, in BA4. The chilled-water pipes are installed in the access gallery. 4.7.2 Hadron stop The hadron stop is cooled by a closed demineralized-water circuit, for which the cooling station is preliminarily located in the LEP RE88. This cooling station is supplied from the LHC primary water in octant 8-1. 4.7.3 Fire extinguishing system In accordance with other underground structures, a fire extinguishing circuit is installed. The targetchamber area is supplied from the SPS primary water system, through the proton-beam tunnel, whereas the supply for the hadron-stop area comes from the LHC tunnel. 5 COST ESTIMATE The cost estimate for the construction of the CNGS is in the order of 71 MCHF. The breakdown of this sum and a careful analysis of manpower needed for the realization of the facility are shown in Annex 2. 6 CONCLUDING REMARKS The estimate for services related to our division counts for 48 MCHF, thus 67% of the total, which shows the importance of the performance within ST division for the success of the project. What cannot be seen in this report of the final design is the long list of alternatives needed to convince the management (and others) of the convergence and optimization of chosen solutions. As an example, at least three technical solutions were discussed, analysed and estimated, before the final steel-pipe design was chosen for the decay tunnel. After the exciting decision by CERN council on 17 December 1999 to approve the project, we can look back and see that the effort made by ST, and of course by others, has been fruitful. This is also a solid preparation for the engineering work, which now will continue. REFERENCES >1] R. Bailey et al., The CERN Neutrino beam to Gran Sasso (NGS), CERN 98 02 (1998). 6

ANNEX 1: CIVIL ENGINEERING DETAILS Figure 1: Target chamber and ancillary structures. Figure 2: Hadron-stop and muon-detector area. 7

ANNEX 2: RESOURCES FOR THE CNGS PROJECT Table 1: Cost and manpower estimate for the CNGS project. CNGS (manyears) Civil engineerin g Table 2: Manpower profile in ST for the CNGS project. Cooling & ventilation Safety alarms (ST) Heavy handling, transport Electricity Coordination (ST) year 1 2.9 0.7 0.1 0.3 4.0 year 2 3.3 0.8 1.1 0.1 0.3 5.6 year 3 2.5 0.8 0.5 1.1 0.8 0.2 5.9 year 4 2.0 0.8 0.5 0.8 0.4 0.2 4.7 year 5 0.1 0.3 0.2 0.1 0.1 0.8 Total Total 10.8 3.4 1.2 3.0 1.5 1.1 21 8