ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING

Similar documents
Technical Specifications (In-Cash Procurement)

Technical Summary for the Tokamak Assembly Works- A0

Status of Design and R&D Activities for ITER Thermal Shield

ITER Assembly Opportunities

Call for Nomination. Vacuum Vessel Assembly Welding

Technical Summary. 1. Purpose

Technical Summary. Purpose. ITER_D_RZ5S7J v2.1

Engineering Support in the Areas of Vacuum, Cryogenics and Instrumentation for ITER Magnet Feeders and Vacuum System. Technical Specification

Status of Design and Research & Development for ITER Sector Sub-assembly Tools

Vacuum Vessel In-Service Inspection_Phase 2 (WP3+WP6): Summary of Technical Specifications

Summary Technical Specification Building 13 - Metrology Laboratory

Call for Nomination Documents IDM UID W37G6V. VERSION CREATED ON / VERSION / STATUS 20 Feb 2018 / 1.1 / Approved EXTERNAL REFERENCE / VERSION

Key Features and Progress of the KSTAR Tokamak Engineering

Technical Summary. Contract for Procurement of Piping and Fittings (IO/14/CFT/9560/ACS CP/1)

Design Progress and Analysis for ITER Thermal Shield

R & D of the Fabrication Technology for ITER Magnet Supports

Summary Technical Specification. In-vessel Survey Development

Technical Summary for TCC0 Global overview of the scope for TCC0 contract

The Heat Rejection System of the ITER Reactor

Preliminary Design of ITER Component Cooling Water System and Heat Rejection System

ITER Organization. Françoise Flament. Head of Procurement Arrangements & Contracts Division. Journée ITER/CEA 01/12/2010. Page 1

ITER Vacuum Vessel Status and Procurement

Technical Specification for Qualification of magnet assembly procedures

Cryostat transport Call for nomination

Argonne Engineering Professionals Seminar Series September 30, 2009 Argonne National Laboratory Argonne, IL

FIRST OF A KIND PIPE-IN-PIPE SPOOL DESIGN AND FABRICATION TECHNOLOGY FOR ITER-BURIED COOLING WATER SYSTEM

ITER Organization - Scientific Internships- 2016

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL

Technical Specification for Engineering Support on Instrumentation, TF Coils and Magnet Supports

Mechanical Requirements for Stainless Steel & Non-Ferrous Fasteners

Integrated System Level Simulation and Analysis of DEMO with Apros. Sami Kiviluoto

FABRICATION DESIGN AND CODE REQUIREMENTS FOR THE ITER VACUUM VESSEL

EU considerations on Design and Qualification of Plasma Facing Components for ITER

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

ITER Organization. Procurement Process Industrial Strategy Business Opportunities

Contents EN 14015:2004 (E) page

Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany

Division 11 - Equipment Section 11401

Stainless Steel Aeration Equipment Specification

Corrosion Resistant Bolting for Use in the Petroleum and Natural Gas Industries

Call for Nomination Documents IDM UID VCGCG5. VERSION CREATED ON / VERSION / STATUS 07 Sep 2017 / 1.1 / Approved EXTERNAL REFERENCE / VERSION

Technical Specification for Fabrication, Testing & Supply of Back plate assembly mock-up

Current Status of the KSTAR TF Superconducting Magnet Development

Film PEEK and Kapton. Rod / Tube PEEK, OFE Copper, and 304 Stainless Steel

Section 906. STRUCTURAL STEEL

STANDARD SPECIFICATION FOR ALUMINUM FRAMING FOR RAILROAD PASSENGER SHELTERS

Cable supply, Electrical and I&C Installation Works

Certification, Testing, Approval and R&D work on the Absorber Safety

Process Specification for the Heat Treatment of Nickel Alloys

SECTION ALTERNATING TREAD STEEL STAIRS

SECTION MISCELLANEOUS METALS

3M Electromagnetic Compatible Products

3ème RV Business du Nucléaire Civil en PACA. ITER Organization Future Call for Tenders

Corrosion Resistant Bolting for Use in the Petroleum and Natural Gas Industries

--> Buy True-PDF --> Auto-delivered in 0~10 minutes. GB/T Translated English of Chinese Standard: GB/T

ATI 601 ATI 601. Technical Data Sheet. Nickel-base Alloy INTRODUCTION PRODUCT FORMS SPECIFICATIONS & CERTIFICATES (UNS N06601)

DETAIL SPECIFICATION SHEET NUT, TUBE, BULKHEAD AND UNIVERSAL FITTING

SECTION STEEL WINDOWS UL Labeled Fire-Rated Fixed Lite (950) Use Tools / Options / View / Hidden Text to view hidden notes and edit.

Series Supply of Cryogenic Venturi Flowmeters for the ITER Project

SECTION EXPANSION CONTROL

The ITER Blanket System Design Challenge

Overview of Coatings and Surface Treatments

Technical summary - supply and install racks and other associated equipment in the warehouse of the logistics

Product specification TiNOX energy

1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces.

SECTION EXPANSION CONTROL

HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

Hot Cell Complex Building Engineering Contract (REVISED)

SECTION EXPANSION CONTROL

CONSTRUCTION SPECIFICATION FOR METAL TRAFFIC BARRIERS AND METAL RAILINGS FOR STRUCTURES

What Are Metal Standards and Why Are They Important?

METAL FABRICATION..1 General Conditions and Division 1 shall govern Work of this section.

ITER_D_PP4SYZ. Engineering Validation and Design Justification of Diagnostic Components. Technical Specifications

SECTION EXPANSION CONTROL

ITER Status & Opportunities. Meeting with CONFINDUSTRIA Piemonte Torino, November 16 th 2015 Benjamin Perier

Radiation Resistant Insulation Systems for the ITER Toroidal Field Coils

FUSION FOR ENERGY The European Joint Undertaking for ITER and the Development of Fusion Energy

SPECIFICATIONS - DETAILED PROVISIONS Section Stainless Steel Sluice Gates C O N T E N T S

Call for Expertise TECHNICAL SPECIFICATION. Expert Services Contract. Procurement Technical and Administration Support

Status Report and Documentation of DCLL Design

Daytona Beach Pier Building Renovation Jun 2010

Development of a Large-scale Monoblock Divertor Mock-up for Fusion Experimental Reactors in JAERI

Section includes plate heat transfer panels as detailed in drawings listed in Section 1.1 Related Documents.

Fusion: the fundamental principle

Fabricate and Install metal alternating tread stair assemblies in accordance with the requirements set forth in this section.

Technology Development for the Construction of ITER Superconducting Magnet System

Electroplating. Copyright 2016 Industrial Metallurgists, LLC

ACTIVATION, DECAY HEAT, AND WASTE DISPOSAL ANALYSES FOR THE ARIES-AT POWER PLANT

A. Compatibility: Products shall be suitable for piping service fluids, materials, working pressures, and temperatures.

SECTION DETENTION WINDOW SCREENS. 1. Detention screens for interior and exterior installations at exterior windows in existing buildings.

SECTION ALTERNATING TREAD STEEL STAIRS

Comparison of BS and BS EN for steel materials

SECTION STEEL WINDOWS UL Labeled Fire-Rated Fixed Lite (950) Use Tools / Options / View / Hidden Text to view hidden notes and edit.

Overview on Decade Development of Plasma-Facing Components at ASIPP

Section 4. Annex to IAEA Request for Proposal STATEMENT OF WORK. Primary/Secondary cooling water Heat Exchangers

Safety Classification of Mechanical Components for Fusion Application

SECTION WALL AND DOOR PROTECTION

PROCESS CHECK REPORT

DEMO Concept Development and Assessment of Relevant Technologies

SECTION STRUCTURAL METAL FRAMING

Transcription:

Route de Vinon-sur-Verdon - CS 90 046-13067 St Paul Lez Durance Cedex - France ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING CALL FOR NOMINATION Ref. IO/CFN/14/11176/PMT SUMMARY OF TECHNICAL SPECIFICATIONS 1 Purpose The purpose of this Build-to-Print Contract is to 1) procure the raw material, 2) perform necessary fabrication processes (cutting, machining, and polishing) 3) silver plating of the shielding plates and 4) packaging and delivery of the Additional Neutron Shielding (ANS) for the ITER Vacuum Vessel Thermal Shield (VVTS). 2 Background The International Thermo-nuclear Experimental Reactor (ITER) is a large-scale scientific experiment with the goal of demonstrating that it is possible to produce commercial energy from fusion. A major component in the ITER Tokamak is the Thermal Shield (TS). The TS system will provide an effective optically opaque barrier for thermal loads being transferred from warm components to the superconducting coils and structures that operate at 4.5K. Thermal loads include: 1) thermal radiation and conduction during plasma operating state, 2) thermal radiation and conduction during Vacuum Vessel (VV) baking and 3) nuclear heating to the TF coils (which must not exceed 14kW). Estimates of the nuclear heating using models incorporating the latest information on vacuum vessel, blanket and diverter designs indicate that the heating could be as high as 21kW during a 500MW pulse. The addition of neutron absorbing material to the thermal shield will provide the necessary nuclear shielding to reduce the TF coil heating. The Additional Neutron Shielding (ANS) will be constructed of numerous plates, with gaps of 3-5mm between the plates. The total number of plates will reach approximately 720 pieces (plus spares) with the total approximate weight 8 metric tons. Each shielding plate will be attached to the inboard of the VVTS by two stud-bolts. A copper spacer will be inserted between the ANS and VVTS to improve the conduction cooling between the ANS and the TS panel and provide clearance to the TS cooling tubes.

3 Scope of Work 3.1 Scope of the Supply The typical ANS assembly consists of neutron absorbing plates, copper spacers, threaded studs, hex nuts and washers, see Figure 3-1. The scope of basic supply includes the procurement and/or fabrication and delivery of the items listed in Table 3-1. Figure 3-1: ANS Detail Assembly Table 3-1: Supplied Items per 40 VVTS Inboard Sub-Assembly Sector Item Drawing/ Reference Quality class Safety class Specific requirements class.* Quantity/ 40 Sector ANS Plate 033771/XX 1 Not Applicable Not Applicable 80 Cu Spacer 033771/XX 1 Not Applicable Not Applicable 80 Studs M20 033771/13 1 Not Applicable Not Applicable 160 Washers 033771/14 1 Not Applicable Not Applicable 160 Nuts M20 033771/15 1 Not Applicable Not Applicable 160 *Nuclear pressure equipment, pressure equipment. Page 2 of 5

3.2 Extent of the Supply The following is a list of the general activities and tasks to be performed by the Supplier within the frame of the Supply Contract. Quality Control/Assurance Project Controls Procurement of raw material Manufacturing activities Packaging and Delivery 4 Manufacturing Requirements 4.1 Vacuum Thermal Shield components function in a vacuum environment. Care must be taken in manufacturing processes to ensure no contaminants are introduced into surfaces which may be difficult to remove later and which might result in degraded vacuum performance. 4.2 Dimensional Inspection At every important manufacturing stage, each ANS component shall be dimensionally inspected and the measurements documented. Results are to be compared with drawings. If necessary, remedial action is to be proposed to the IO prior to implementing a solution. 4.3 Material Requirements The material shall be gadolinium inserted chromium-nickel stainless steel plate, 316NU-78 or equivalent material containing a minimum boron equivalent of 6.2%. In general the material shall conform to ASME and ASTM standards. Before the start of production for full required quantity of material, a trial qualification program shall be performed with the goal of confirming the main requirements of the specification. The trial production of a limited quantity of plates (with equal thickness of production plates) shall be made and all the plates shall be qualified in accordance with qualification program agreed between Supplier and IO. The qualification test to be performed shall include (at a minimum) chemical composition, Charpy impact, KIC and tensile testing. Testing shall be performed at room temperature and cryogenic temperature (~70-80K). The results of testing shall be documented in accordance with approved documentation requirements. 4.3 Special Processes Requirements Silver Plating A critical parameter for the successful operation of the ANS plates is emissivity. The chosen method of reducing the emissivity and therefor the heat load to the superconducting surfaces of the magnet structure is silver plating. The candidate Suppliers shall have the experience to implement/oversee a silver plating program. The key processes of the silver coating are as follows: 1) Electrolysis cleaning removes contaminants other than oxide, hydroxide, and base metal from the surfaces of work pieces by placing the work pieces on the cathode. Page 3 of 5

2) Etching is the process used to remove oxide film, rust, scales or other forms of hydroxide from the surface of the work pieces. 3) Activation is the process of activating the surface by neutralizing the residual components and then removing any thin oxide film which may have appeared during the pretreatment process. 4) Nickel strike is the process of plating the material with nickel while removing the strong oxide film from the stainless steel. 5) Nickel plating is the process of forming an excellent, strong, and glossy plating layer by conducting nickel plating on the rough plating layer resulting from the nickel strike. 6) Silver plating is the process of forming a silver plating layer on the nickel plating layer. 7) Chromate treatment is the process of maintaining the original silver color from being affected by a contaminated environment or by fingerprints. The supplier will be required to submit a detailed plating procedure to the IO for approval. A test of the silver plating process shall be performed prior to plating the full production quantity. The supplier shall have the experience and capability to implement a quality control program to check: thickness of plating, adhesion, porosity and emissivity. 5 Timetable The tentative timetable is below. The final timetable with respect to delivery will be developed to coincide with VVTS deliveries. Call for Nominations December 2014 Call for Tender February 2015 Contract Placement May 2015 Batch #1 (sectors 5 & 6) estimated delivery January 2016 Batch #2 (sectors 1, 2, 3 & 4) estimated delivery April 2016 Batch #3 (sectors 7, 8 & 9) estimated delivery January 2017 6 Experience Requirements The ITER Organization is looking for suppliers which experience is based on the following criteria: Manufacturing capabilities: o understanding of the manufacturing requirements o experience with an appropriate procurement plan for material and associated inspection/testing o knowledge/experience of surface preparation/treatment and silver plating requirements and an appropriate execution plan o presence of required machining equipment o sufficient equipment and facility to meet the requirements as related to the scope of work (vacuum components, protection of silver plating, etc.) Experience with silver plating process and production of vacuum components Page 4 of 5

During the selection phase, ITER Organization reserves the right to contact some or all of each nominated company s references to ask if: (1) the nominated company delivered a quality product which was compliant with the customer s requirements; (2) the company s performance conformed with the terms and conditions of its contract, including the delivery schedule; and (3) the company was reasonable and cooperative during performance and committed to customer satisfaction. ITER Organization may choose to visit customer references and may also use other sources of information. 7 Candidature Candidature is open to all companies participating either individually or in a grouping (consortium) which is established in an ITER Member State. A consortium may be a permanent, legally-established grouping or a grouping, which has been constituted informally for a specific tender procedure. All members of a consortium (i.e. the leader and all other members) are jointly and severally liable to the ITER Organization. The consortium groupings shall be presented at the tender submission stage. The consortium cannot be modified later without the approval of the ITER Organization. Page 5 of 5