An introduction to. pipe jacking

Similar documents
Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

Experts in tunneling with Tunnel Boring Machines

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

DISTRIBUTED BY EMPIRE INFRASTRUCTURE PTY LTD

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

PERFECT PIPE THE REVOLUTION CONTINUES

Concrete Pipe Jacking

Pipe Jacking Association An introduction to pipe jacking and microtunnelling

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

SECTION A1 EXCAVATION AND BACKFILL GENERAL

Horizontal Directional Drilling

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

APPENDIX: C. Stormwater and Wastewater Construction Specification. Tauranga City Council

Superior GRP pipes for today s sewer challenges

GRP JACKING PIPES FOR MICRO-TUNNELING

Cured-in-Place Pipe (CIPP) for Pressure Pipe. Presented by: Mike Moore

WASTEWATER & STORM WATER COLLECTION AND REMOVAL

Current Status of Sewer Network Renovation in Europe and the Activities of CEN

Brief Discussion on Application of Guided Boring Non-excavation Technology in Repair of Sewage Pipes Mei-Di SHAN1,a,*, Feng ZHOU2,b

Pipe Jacking. Japan Sewage Works Association

Reliable GRP pipe systems for potable water supply

HEKAPLAST. PE-HD twin wall cable ducts and cable protection pipes for underground installation. Corrugated and Twin Wall Pipes of Plastics

Construction OS&H Project planning and control for safe OS&H

DESIGN OF SEWER SYSTEMS

Trenchless Pipeline Crossings

Report on Trenching Operations

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

Concrete Pipe Jacking

4th International Engineering and Construction Conference - July 28, 2006

Landscaping and Fencing

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON

SKSC Civils (pty) LTD. Brilliance Technology Quality - Innovation

CIPP Cured-in-Place Pipeline CIPP. cured-in-place pipe. trenchless pipe rehabilitation

Glass-fibre reinforced polyester (GRP) pipe systems PRODUCT GUIDE

Below ground System of pipework required to carry waste fluids from building to disposal site.

We have enough water if we manage it well

JUST THE FACTS CONCRETE PIPE VS. HDPE

Loshan pipe manufacturing Co. LOSHAN PROFILE

Amendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility Installation by Jacking and Boring

Trenchless Technology

PipeLine. 7 Times in Europe - Air Cushion Siphon of h Pipes Rehabilitates Sewage System, DE. November 2011

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Pipe Bursting Services. pipe bursting. services

Employment Intensive Infrastructure Program (EIIP) in Lebanon ANNEX 2

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

OUR OBJECTIVE: TO PROVIDE EDUCATION ON AN ALTERNATIVE TO TRADITIONAL CONCRETE FORMWORK FOR WALLS

ITEM NO SLIPLINING SANITARY SEWERS

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

SECTION STORM DRAIN

The History of Spiral Wound Pipe Technology In Australia s Pipe Renewal Industry

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

Requirements for Measuring and Pricing of Structural Concrete

International Aramoon Corp. Pipe Inspection and Rehabilitation By: Faiz Al-Elweet. SAWEA Al-Khobar KSA February 24, 2010

Weholite LIGHTWEIGHT PIPE SYSTEM

17/03/2017 CONTENTS. Real Cases Studies in the Region for Pipelines Inspection & Rehabilitation. Introduction CONTENTS. Introduction / Cont.

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

Construction (Design & Management) Regulations 2015 Briefing Note

Tel: Neil: Tony: Website:

Reinforced Concrete Microtunnelling Pipe Designed for Project Conditions and MTBM Machines

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

Item 460 Corrugated Metal Pipe

Highway Maintenance & Civil Engineering Contractor. irvinegrenson.co.uk

Tunnel. Immersed Tunnels

TAMDID PIPES GRP MANHOLE BROCHURE

With over 40 years experience, SDI-unistride

ISO/TS TECHNICAL SPECIFICATION

The Weak Links in the Wastewater Collection System: Manholes and Access Devices. Antonio V Almeida, PE CMOM 2014 Austin Texas August 19, 2014

h Sewer Pipe Systems

Lateral Thinking The Key To Meeting Sewer Infiltration Reduction Targets & Lowering Operating Costs

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018

SECTION TRENCHING

INTORODUCTION BRIDGE:

The Pilot Pipe method is a very simple method for trenchless installation of supply lines. It is done in several steps:

DIVISION 3 PAVEMENT (FLEXIBLE AND RIGID) CONSTRUCTION SPECIFICATIONS

SECTION FACILITY SANITARY SEWERS

CHAPTER 5 SUPPLEMENTAL DATA

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

LATEST DEVELOPMENTS INCREASE THE CAPABILITIES OF SPIRAL WOUND LINERS

Design Data 4M. Jacking Concrete Pipe

TABLE OF CONTENTS

This unofficial translation of. Ministerial Decision No 421/1998. was downloaded from METS is not the copyright owner.

AN INNOVATIVE APPROACH TO SMALL BRIDGE REHABILITATION. Peter Marchant ITS Pipetech Pty Ltd, NSW Australia

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Cost Estimate Summary Site Prep Supervision Works Cost Risk OB Works + Risk + OB Total Union Street / Laburnum Row Junction 12,353 5,147 73,006

Project: King Abdulaziz International Airport KAIA 2

11.1 INTRODUCTION Objectives Key References Interpretation GENERAL CONDITIONS DESIGN...

Geopolymer Mortar System for Structural Rehabilitation/Repair of Sewer and Storm Infrastructure

Khalid SINCE 1997 TECHNICAL MANUAL 2017 GRP MANHOLE LINER & ACCESSORIES

TECHNICAL SPECIFICATION

Transcription:

An introduction to pipe jacking

The pipe jacking technique The major applications for pipe jacking and microtunneling include new sewerage and drainage construction, sewer replacement and lining, gas and water mains, oil pipelines, electricity and telecommunications cable installation, and culverts. Special applications include the installation of rectangular or circular sections for pedestrian subways, road underpasses and bridge abutments. The technique can be used to negotiate obstacles such as motorways, railways, rivers, canals, buildings and airfields in the path of pipe laying projects; to minimize the surface disruption frequently associated with open cut pipe laying methods in urban areas; or simply to provide a permanent underground tunnel construction. Pipe jacking is primarily used as an alternative to open cut excavations or other tunneling methods. Significant lengths are attainable at larger diameters using mechanized techniques. Reference should be made to Tables 4c and 4d for specific recommendations. Construction methods are available to cope with both cohesive and non-cohesive soils in dry or water bearing conditions. Excavation techniques are also available for jacking through rock or mixed ground conditions, including cobbles and boulders. 1

Advantages and disadvantage: Trenchless method Decreasing cost of surface repair Decrease Time of project ( Trenchless method is very faster than open trench) Crossing under the river and other structures Less interface with infrastructures Less disturbance in Traffic Increasing pollutions Environmental advantages Ability to work under water More Safety Earth moving is reduced to minimum Construction work in all weather 2

Pipe jacking, generally referred to in the smaller diameters as microtunneling, is a technique for installing underground pipelines, ducts and culverts. Powerful hydraulic jacks are used to push specially designed pipes through the ground behind a shield at the same time as excavation is taking place within the shield. The method provides a flexible, structural, watertight, finished pipeline as the tunnel is excavated. There is no theoretical limit to the length of individual pipe jacks although practical engineering considerations and economics may impose restrictions. Drives of several hundred meters either in a straight line or to a radius or a series of radii are readily achievable. A number of excavation systems are available including manual, mechanical and remote control. Pipes in the range 150mm to 3000mm, can be installed by employing the appropriate system. Construction tolerances are comparable with other tunneling methods, and the pipe jacking method generally requires less overbreak than segmental tunnels and provides ground support and reduces potential ground movement. Mechanical excavation methods are similar to those employed in other forms of tunneling. Shields, excavation and face support can be provided for a wide variety of ground conditions. 3

In order to install a pipeline using this technique, thrust and reception pits are constructed, usually at manhole positions. The dimensions and construction of a thrust pit vary according to the specific requirements of any drive with economics being a key factor. Pit sizes will vary according to the excavation methods employed, although these can be reduced if required by special circumstances. A thrust wall is constructed to provide a reaction against which to jack. To ensure that the jacking forces are distributed around the circumference of a pipe being jacked, a thrust ring is used to transfer the loads. The jacks are interconnected hydraulically to ensure that the thrust from each is the same. A reception pit of sufficient size for removal of the jacking shield is normally required at the completed end of each drive. The initial alignment of the pipe jack is obtained by accurately positioning guide rails within the thrust pit on which the pipes are laid. To maintain accuracy of alignment during pipe jacking, it is necessary to use a steerable shield, which must be frequently checked for line and level from a fixed reference. For short or simple pipe jacks, these checks can be carried out using traditional surveying equipment. Rapid excavation and remote control techniques require sophisticated electronic guidance systems using a combination of lasers and screen based computer techniques. 4

5

Safety Benefits Pipe jacking is an inherently safer method of working than open trench construction or traditional segmental tunneling. When considering the risks associated with deep, large section, open excavations, Health and Safety Executive guidance suggests these risks should be reduced if appropriate using trenchless technology to avoid the need to excavate the trench in the first place. Given gang size differences between the techniques and the resulting reduction in man-hours, opportunities for accidents to occur are less with pipe jacking. There is also significant reduction in the risk of injury as a result of utility strikes and interface with the public. Environmental Benefits There are substantial environmental benefits to be gained by the use of pipe jacking techniques when compared with the traditional open trench approach. Typically the trenchless method will reduce the quantities of incoming and outgoing materials, with a consequent reduction in tipping of spoil and quarrying of imported stone fill. This in turn leads to reduced vehicle movements and subsequently less associated disruption. In many cases use of pipe jacking techniques instead of open trenching will contribute positively towards workplace safety, the interface with the general public, and the local and wider environment. Technical Benefits Technical benefits associated with pipe jacking are: Inherent strength of lining Smooth internal finish giving good flow characteristics No requirement for secondary lining Considerably less joints than a segmental tunnel Prevention of ground water ingress by use of pipes with sealed flexible joints Provision of invert channels in larger pipes to contain the dry weather flow of a sewer in a combined system Less risk of settlement Minimal surface disruption Minimal reinstatement Reduced requirement for utilities diversions in urban areas 6

Pipe Jacking Project of Kayson Hamedan Sewerage Project by Pipe Jacking Method Client: Hamedan Province Water & Wastewater Company Financed by: Islamic Development Bank Location: Hamedan, Iran Contract Period: 36 Months Partner: Mushrif of Kuwait Key Statistics Reception & drive shafts: 64 Manholes: 64 1200 mm diameter pipes: 5329 meters 1400 mm diameter pipes: 1564 meters Excavation: 60,000 cubic meters Concrete: 8,000 cubic meters Formwork: 12,000 square meters Tehran, Khaje Abdullah Ave. Client: Tehran Water & Wastewater Company Ministry of Power Financed by: Ministry of Power Location: Tehran, Iran Contract Period: 12 Months Key Statistics Drive shafts: 34 Manholes: 33 1400 mm diameter pipes: 552 meters 1600 mm diameter pipes: 2170 meters 1800 mm diameter pipes: 1180meters Excavation: 10,620 cubic meters Concrete: 8,814 cubic meters Formwork: 5,810 square meters Tehran, Region 2, 5 and 9 of Tehran Client: Tehran Water & Wastewater Company Ministry of Power Financed by: Ministry of Power Location: Tehran, Iran Contract Period: 20 Months Key Statistics Drive shafts: 39 Manholes: 39 1600 mm diameter pipes: 4283 meters 1800 mm diameter pipes: 612 meters Excavation: 9,632 cubic meters Concrete: 2,880 cubic meters Formwork: 9,410 square meters 7

Polymer Concrete Pipes Polymer concrete is a high strength, corrosion resistant concrete product which is created when thermosetting polyester resin is used to bond the highest quality of quartz aggregates under strictly controlled temperature and moisture conditions. The polyester resin, which acts as the bonding agent, after curing, gives the pipes the additional positive properties of elasticity, fracture and corrosion resistance. No water or cement is used in the manufacture of polymer concrete products. Polymer concrete products are corrosion-resistant during usage for flows with a PH range of 1.0 to 12.0. The glass-reinforced-plastic (GRP) couplings are made to connect plain end pipes quickly and easily and provide the added benefit of leak-proof joints, thus making polymer concrete pipes the natural choice for use in demanding municipal and industrial sewage management systems. It should be pointed out that the object of establishing PCPMC Co. in Iran are as follows: a)approach to Sustainable Development in water and wastewater industry of Iran b)production of environment friendly and recyclable pipes for wastewater industries c)production of corrosion resistant and durable pipes for sewage transportation d)improving Science and Technology in the field of Composites and polymer Concrete Materials and Products 8

Design and construction methods Prior to embarking on a detailed construction design and method analysis, the client s engineer will generally have ascertained the basic design parameters to meet the requirements of the scheme. For a sewerage system these are likely to include: Hydraulic requirements Preferred route Depth Gradient Following an assessment of engineering, environmental and cost parameters, pipe jack excavation method and shaft construction will also be governed by a number of factors which include: Ground conditions Details of existing services and underground structures Location of manholes and working areas Lengths required Diameters of pipeline Economics Ground conditions will play a major role in determining the type of shaft to be constructed, the pipe jack excavation method and any ground support systems to be used. Each of these may have limitations in terms of either the diameter or length of drive. The interface between these variables, together with physical considerations, such as the location of manholes and the size of working areas, will provide an optimum solution or range of solutions which can then be appraised on the basis of cost and value engineering. 9

10

Telephone: (+9821) 88072501-9 / Fax: (+9821) 88072500 Email: info@kayson-ir.com / Website: www.kayson-ir.com Head Office Address: Iranzamin Bldg., 2288 Iranzamin Ave., Shahrak Qods, Tehran 1465613763, Iran Designed and published by Kayson company