DG Investment Planning Analysis with Renewable Integration and Considering Emission Costs

Similar documents
Impacts of Operational Variability and Uncertainty on Distributed Generation Investment Planning: A Comprehensive Sensitivity Analysis

Optimal Scheduling Strategy in Insular Grids Considering Significant Share of Renewables

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

Impacts of Optimal Energy Storage Deployment and Network Reconfiguration on Renewable Integration Level in Distribution Systems

Optimizing distributed generation parameters through economic feasibility assessment

Optimal Behavior of Demand Response Aggregators in Providing Balancing and Ancillary Services in Renewable-Based Power Systems

AN ANALYTICAL METHOD TO ASSESS THE IMPACT OF DISTRIBUTED GENERATION AND ENERGY STORAGE ON RELIABILITY OF SUPPLY

ACTIVE DISTRIBUTION NETWORK PLANNING BASED ON A HYBRID GENETIC ALGORITHM-NONLINEAR PROGRAMMING METHOD

La regulación del incierto futuro de los sistemas eléctricos

A NOVEL OF PRIMARY DISTRIBUTION NETWORKS WITH MULTIPLE DISTRIBUTED GENERATOR PLACEMENT FOR LOSS REDUCTION

A Heuristic Approach for Economic Dispatch Problem in Insular Power Systems

Transmission and Wind Power Investment Luis Baringo, Student Member, IEEE, and Antonio J. Conejo, Fellow, IEEE

Managing Risk in Electric Distribution Networks

Multi-Agent System for Renewable Based Microgrid Restoration

Optimization of Wind-Pumped Storage Hydro Power System

2014 Grid of the Future Symposium

Optimal Placement of Distributed Generator in Distribution System using Fuzzy Composition

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012

Power Scheduling for Renewable Energy Connected to the grid

2016 Probabilistic Assessment. December 5, 2016 Southwest Power Pool

Generation Expansion Planning Considering Renewable Energies

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Robust Supply Function Bidding in Electricity Markets With Renewables

Flexible power generation and interconnection capacity needs of the Italian power system using PLEXOS LT plan.

Distributed Generation Penetration Impact on Distribution Networks Loss

Keywords - Distributed generation, Demand response program, Demand side management, Multi-objective particle swarm optimization.

Monte-Carlo Optimization Framework for Assessing Electricity Generation Portfolios

Robust Optimization Based Economic Dispatch for Managing System Ramp Requirement

RES Revolution! How the Sun and the Wind changed the Italian Electricity Market

RELIABILITY AND SECURITY ISSUES OF MODERN ELECTRIC POWER SYSTEMS WITH HIGH PENETRATION OF RENEWABLE ENERGY SOURCES

Methodology for calculating subsidies to renewables

The Future of Electricity: A Market with Costs of Zero? Marginal

EXTRACTION OF 9,163 REAL LV NETWORK MODELS FROM DNO GIS DATABASE TO ASSESS OVERVOLTAGE FROM PV AND CONSEQUENT MITIGATION MEASURES

Multi Objective Evolutionary Programming Based Optimal Placement of Distributed Generators

Solar, Wind and Market Power in the New Zealand Electricity Market (and hydro lake dynamics) Mina Bahrami Gholami and Stephen Poletti

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

World Scientific Research Journal (WSRJ) ISSN: Research on Intelligent Microgrid and its Reliable Grid Connection

Assessing the impact of micro generation in radial low voltage distribution networks taking into consideration the uncertainty

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008

The Future of Electricity: A Market with Costs of Zero? Marginal

Nuclear-renewable hybrid energy systems for non-electric applications

Toward Full Integration of Demand-Side Resources in Joint Forward Energy/Reserve Electricity Markets

A contribution from the MIT-Portugal Program: Sustainable Energy Systems

Ultra high wind penetration in simple wind-diesel power systems in Cape Verde

Proposed Work Plan for Seventh Plan Development. October 2, 2014 GRAC Tom Eckman

EVALUATING INVESTMENT DEFERRAL BY INCORPORATING DISTRIBUTED GENERATION IN DISTRIBUTION NETWORK PLANNING

Charles D. Corbin & Gregor P. Henze

I. INTRODUCTION

A Multi-Objective Method to Design Demand Response Strategies for Power Systems including Wind Power Generation

MISO Energy Storage Study DRAFT Scope

Moving Ontario to a 100% renewable electricity grid: system operation for renewable integration

TECHNICAL AND ECONOMIC ANALYSIS OF THE EUROPEAN ELECTRICITY SYSTEM WITH 60% RES EDF R&D

CONTRIBUTION OF ENERGY STORAGE AND DEMAND-SIDE RESPONSE TO SECURITY OF DISTRIBUTION NETWORKS

ANALYSIS OF THE IMPACT OF BATTERY STORAGE ON POWER DISTRIBUTION SYSTEMS

Bi-level two-stage stochastic SCUC for ISO day-ahead scheduling considering uncertain wind power and demand response

Planning the Interconnection of Islands to the Mainland Grid via Submarine Cables

The Influence of Demand Resource Response Time in Balancing Wind and Load

Background: ERCOT studies in 80 s and 90 s using NARP (N Area Reliability Program): o Small model in which each node represented a major load center

360 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 25, NO. 1, FEBRUARY 2010

National Council on Electricity Policy Annual Meeting & Workshop Denver, CO. May 8, Jeff Bladen Executive Director Market Development

Overcoming Grid Integration Challenges of Variable Generation

Loss Minimization and Voltage Profile Improvement with Network Reconfiguration and Distributed Generation V Usha Rani 1, J Sridevi 2

Craig L. Hart Consultant Energy Exemplar Africa (Pty) Ltd South Africa

Energy Uplift (Operating Reserves)

Robust and Decentralized Operations for Managing Renewable Generation and Demand Response in Large-Scale Distribution Systems

Economic Power Capacity Design of Distributed Energy Resources for Reliable Community Microgrids

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Solar Photovoltaic Volumetric Incentive Program 2015 Report to the Legislative Assembly

Flexibility from the Demand Side

Calculation of Demand Curve Parameters

Ancillary Service Markets

[R]enewables 24/7 EXECUTIVE SUMMARY

Keegan Moyer Byron Woertz Bradley Nickell. TEPPC RTEP Update October 5 th, 2012 SPSC/CREPC/RPF Meeting

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Transmission Expansion Planning of Systems With Increasing Wind Power Integration

Joint ICTP-IAEA Workshop on Vulnerability of Energy Systems to Climate Change and Extreme Events April 2010

Bulk Power System Integration of Variable Generation - Program 173

Zero Net Carbon Portfolio Analysis

To Study the Adequacy Assessment of Chitradurga distribution substation using MCS

PREPARED FOR: ARIZONA PUBLIC SERVICE Updated Solar PV Value Report

Transmission Infrastructure Investment Requirements in the Future European Low-Carbon Electricity System

Study on the value of flexibility in the management and design basis of distribution networks in France

Bulk Power System Integration of Variable Generation - Program 173

Review of energy storage allocation in power distribution networks: applications, methods and future research

FLEXIBILITY HOW TO CONTRIBUTE TO THE STABILITY OF THE GRID THANKS TO THE FLEXIBILITY OF YOUR PRODUCTION PROCESSES?

Storage as a Transmission Asset:

Integration of Photovoltaic Generation in a Microgrid: Spinning Reserve Analysis

Flexibility in the Swiss Electricity Markets. Jan Abrell Energieforschungsgespräche Disentis 2019,

OPTIMAL DESIGN OF DISTRIBUTED ENERGY RESOURCE SYSTEMS UNDER LARGE-SCALE UNCERTAINTIES IN ENERGY DEMANDS BASED ON DECISION-MAKING THEORY

PGE s 2013 Integrated Resource Plan

Electricity Charging Seminar Level Playing Field

MULTIFUNCTIONAL BATTERY ENERGY STORAGE SYSTEMS IN ISOLATED NETWORKS WITH WIND GENERATION

SYSTEMS ANALYSIS FOR ENERGY SYSTEMS USING AN INTEGRATED MODEL OF GIS AND TECHNOLOGY MODELS

MISO PJM Cross-Border Planning

Integrating High Levels of Variable Renewable Energy Sources

For example, the California PUC recently required all IOU s to submit DRP s detailing the circuit level impacts of DER on the distribution system.

ENABLING EMBEDDED GENERATION

Strategies for energy efficiency improvement in residential and office buildings: their role at building and country scale

Examining the Viability of Energy-Only Markets with High Renewable Penetrations

Levelized Cost of New Generation Resources in the Annual Energy Outlook 2012

Transcription:

DG Investment Planning Analysis with Renewable Integration and Considering Emission Costs Desta Zahlay Fitiwi, Sérgio F. Santos, Abebe W. Bizuayehu, Miadreza Shafie-khah, João P. S. Catalão Univ. Beira Interior, Covilhã, Portugal, and INESC-ID, Inst. Super Tecn., Univ. Lisbon, Lisbon, Portugal dzf@ubi.pt; sdfsantos@gmail.com; buzeabebe@gmail.com; miadreza@ubi.pt; catalao@ubi.pt Miguel Asensio, Javier Contreras Univ. Castilla La Mancha, Ciudad Real, Spain Miguel.Asensio@uclm.es; Javier.Contreras@uclm.es Abstract The prospect of distributed generation investment planning (DGIP) is especially relevant in insular networks because of a number of reasons such as energy security, emissions and renewable integration targets. In this context, this paper presents a DGIP model that considers various DG types, including renewables. The planning process involves an economic analysis considering the costs of emissions, reliability and other relevant cost components. In addition, a comprehensive sensitivity analysis is carried out in order to investigate the effect of variability and uncertainty of model parameters on DG investment decisions. The ultimate goal is to identify the parameters that significantly influence the decision-making process and to quantify their degree of influence. The results show that uncertainty has a meaningful impact on DG investment decisions. In fact, the degree of influence varies from one parameter to another. However, in general, ignoring or inadequately considering uncertainty and variability in model parameters has a quantifiable cost. The analyses made in this paper can be very useful to identify the most relevant model parameters that need special attention in planning practices. Keywords Distributed generation; investment planning; distribution network systems; uncertainty. NOMENCLATURE i) Sets and Indices Ω Set of DG types Ω Set of DG alternatives of the same type Ω Set of planning stages (t = 1, 2 T) Ω, Ω Set of snapshots and scenarios, respectively Ω Set of load blocks Ω Set of substations ii) Parameters,, Weights for balancing the cost terms Interest rate Maximum available budget for investment in stage t (Euros) DG penetration limit factor (%), Lifetime of DG type p and alternative k (years), Investment cost of DG type p and alternative k (Euros),,, Maintenance cost of new or existing DG type p and alternative k (Euros),,, Operation cost of new or existing DG type p and alternative k ( /MWh) Weight associated to snapshot w Probability of scenario s,, Demand for each snapshot w, scenario s and stage t (MW) Investment limit at stage t (Euros),, CO2 price for each snapshot w, scenario s and time stage t ( /tons),,, Emission rate of new or existing generator type p and alternative k (tons/mwh),,, Price of purchased electricity ( /MWh) for each substation ss, scenario s, snapshot w and time t iii) Variables Total investment cost Total operation, maintenance and reliability costs Total emission costs Investment cost of DG, Annual maintenance cost of new or existing DG, Operation cost of new or existing DG Cost of unserved power,, Binary investment variable associated to DG type p and alternative k,, Binary indicator variable of utilization of existing generator p and alternative k,,,,,,,,, Power generated by new or existing generation type p, alternative k for each snapshot w, scenario s and stage t,, Unserved power for each snapshot w, scenario s and stage t 2,2 Emission cost of new or existing DG at stage t,,, Purchased power at each substation ss, for each scenario s, snapshot w and time stage t Cost of purchased energy at time stage t I. INTRODUCTION Nowadays, there is a global trend towards integrating more distributed generation (DG) sources (in particular, renewable energy sources such as wind and solar) in distribution networks (DN) [1]. This is driven by the compounded effect of several techno-economic and environmental factors. The scale of DG integrated in power DN systems is steadily increasing. This trend is likely to continue in the years to come due to the advent of emerging solutions such as active management of distribution networks [2], [3], which are expected to alleviate existing technical limitations and facilitate smooth integration of DG s. The electricity demand covered by energy coming from DG (renewable energy sources, in particular) will gradually increase. 978-1-4799-8569-2/15/$31.00 2015 IEEE

Hence, such energy sources will play an important role in distribution systems. However, it should be noted that many DG sources (for example, the renewable energy sources such as solar and wind) are intermittent in nature. Hence, they introduce a significant operational variability and uncertainty to the system. In addition, there are several other parameters which are subject to a high level of uncertainty. The combination of all these relevant issues makes the operation and planning process more complicated. This will definitely require effective methods and tools in order to realize an optimal integration of DG. The prospect of DG investment planning (DGIP) is especially relevant in insular networks because of a number of reasons such as energy security, environmental and economic factors, as well as renewable integration targets. Therefore, tapping available energy resources (wind, solar, hydro, geothermal, etc.) is inevitable not only to meet an increasing demand for electricity but also to fulfill environmental constraints and renewable energy source (RES) integration targets set forth either globally or locally through Government initiatives. Framed in this context, this paper presents a DGIP model that considers various types of DG (including renewables). The planning process involves an economic analysis considering the cost of emissions, reliability and other relevant cost terms. In addition, our paper carries out a comprehensive sensitivity analysis in order to investigate the effect of variability and uncertainty of model parameters on DG investment decisions. The ultimate goal is to identify the parameters that notably influence the decision-making process and quantify their degree of influence. To perform the analyses, the DGIP problem is formulated as a multi-stage and multi-scenario optimization model, which minimizes the expected net present value of investment, operation and maintenance, reliability and emission costs, while respecting a number of technical and economic constraints. In addition, to ensure tractability, the entire problem is kept as a mixed integer linear programming (MILP) optimization. In general, the work here focuses on the problem arising from cost-effective integration of DG in insular network systems considering various sources of variability and uncertainty. II. LITERATURE REVIEW Distribution network systems are expected to undergo broad-range transformations in the near future so that current limitations of integrating DG (especially renewables) will be effectively addressed. As a result, the highly needed benefits of such DG, extensively discussed in [1] and [4], can be optimally exploited. In this regard, previous works on investment planning of DG in DN, such as [5] and [6], highlight the multi-faceted benefits of DGIP. In particular, the work in [6] demonstrate that investment in DG is an attractive distribution planning option for adding flexibility to an expansion plan, mainly by deferring network reinforcements. Other wide-range benefits of DG have been extensively discussed in [7] [11]. In fact, the integration of DG in distribution systems also has some challenges [12] [14]. For example, if DG s are not properly planned and operated, they can pose technical problems in the system. However, these are expected to be adequately mitigated in active DN [6]. From a modeling perspective, DGIP in previous works is carried out either jointly with distribution network expansion planning [15] [21] or independently [5], [6], [22], [23]. Either way, the decision variables of the optimization encompass the type of DG, its capacity and location, as well as the time of investment when a dynamic planning scheme is adopted as in [5], [15], [16], [19] [23]. Since DG includes intermittent energy sources, the planning model should adequately take account of the uncertainty and the variability of such sources, including that of the electricity demand. In this respect, uncertainties in load [5], [6], [15], [16], [19] [22], electricity price [5], [6], [15], [16], [22], wind power output [16], [22], solar power output [22], fuel price [22], demand growth [5], [6], and failures in DG [17] are among several sources of uncertainties, which have been given some attention in distribution planning works in the literature. As it can be observed, dealing with the variability, but not uncertainty, pertaining to electricity demand seems to be considered in many works in the literature (often by dividing load duration curve into 3 to 5 demand levels), while the others are largely ignored or represented in an overly simplified manner. III. PROBLEM FORMULATION The work here focuses on investigating how sensitive DG investment decisions are with respect to various uncertain parameters. This is relevant for identifying the parameters that influence most the investment solution to design a DGIP model that adequately accounts for the variability and the uncertainty of the most relevant parameters. Eventually, this helps to ensure an optimal integration of DG in network systems. Note that this can be carried out with or without a network. The former obviously considers the entire network system but the latter assumes that electricity demand is aggregated and connected to a hypothetical node, which all generators are assumed to be connected to. The main difference lies in the network losses, which are only accounted for when considering the network. However, since DN s span over a small geographical area, the feeders and the distribution lines are usually short. Therefore, in properly designed DN s, power losses are negligible; and hence, they are not expected to significantly change DG investment planning outcomes. This argument has been experimentally proven by running the case study in [16] with and without a network, in which the results of the DG investment planning in both cases are similar. A DGIP problem is naturally dynamic because the solution has to explicitly provide the necessary information regarding when DG investments are needed. Regarding the planning horizon and decision stages, considering the dynamic nature of the problem, a more realistic approach could be to formulate the problem with multiple decision stages (i.e. multi-year decision framework) while accounting for all possible future scenarios. However, to ensure tractability, the numbers of stages and scenarios are usually limited.

In this work, the DGIP problem is formulated as a multistage and multi-scenario optimization model within a given planning window (horizon). This modeling framework assumes that there are n probable future storylines (or scenarios) each associated with a probability of realization that stochastically represents relevant sources of uncertainties. A. Objective Function The DGIP model is formulated as a MILP optimization problem, whose objective function is to minimize the weighted sum of net present value (NPV) of three cost terms as in (1). The first term in (1) represents the NPV of DG investment costs, constituting conventional and various RESs, under the assumption of perpetual investment planning horizon [24]. In other words, the investment cost is amortized in annual installments throughout the lifetime of the installed DG, as is done in [16]. Note that, in this paper, the three weights, and in (1) are assumed to be the same and equal to 1. The cost terms in (1) are expressed as: Ω 1 Ω 1, 1, 1 2 2 Ω 1 2 2 1 1.1 1.2 1.3. The second term, expressed as in (1.2), corresponds to the sum of total NPV of (i) operation, maintenance and reliability (OMR) costs throughout the planning stage, and (ii) the OMR costs incurred after the last planning stage. Note that the costs in (ii) rely on the OMR costs of the last planning stage and a perpetual investment planning horizon is assumed when spreading these costs after the last planning stage. The last term in (1), expressed as in (1.3), corresponds to the sum of NPV of emission costs in the system throughout the planning stages and those incurred after the last planning stage under the same assumptions as in the case of OMR costs. The NPV of the total costs is then given by the sum of amortized investment costs in DG, constituting conventional and various renewable energy sources (1.4), expected maintenance and operation cost of new (1.5), (1.7) and existing (1.6), (1.8) DG, as well as the expected cost of reliability that is captured by penalizing unserved power as in (1.9). In addition, the expected cost of emission and energy purchased from the grid (if any) are also included in the objective function (see equations (1.10) through (1.12)). Note that in insular networks, the latter is zero since there is no functional market or such networks are not connected to the grid, as it is the case with the system considered in this paper for the case study. The individual cost terms in (1.1) through (1.3) are expressed as: 1, 1, 1, Ω Ω,,,, 1.4,,, 1.5 Ω Ω,,, 1.6 Ω Ω Ω Ω 8760, Ω Ω Ω 8760, Ω Ω Ω Ω 8760,,,, Ω 2 8760 Ω Ω 2 8760 Ω,, Ω Ω Ω Ω,, Ω Ω,,,,,,,,,, 8760,,,,,, Ω Ω 1.7 1.8 1.9,,,, 1.10,,,, 1.11 1.12 where equation (1.4) represents the total investment costs weighted by the capital recovery factor,,. Note that,,, is defined to be zero, and the formulation in (1.4) ensures that the investment cost of each DG is considered only once in the summation. Equations (1.5) and (1.6) stand for the annual maintenance costs of candidate and existing DG, respectively. These cost components are multiplied by the corresponding binary variables to determine whether each DG is being utilized or not. Note that the binary investment variable is also used for this purpose. This is because there is no economic explanation or justification as to why a given component (DG, in our case) cannot be utilized immediately after an investment is made on this asset. Therefore, there is no need to add another binary variable for a new asset to indicate its utilization, as in some previous works [16]. For existing generators, binary variables are introduced for indicating their respective utilizations. B. Constraints 1) Load balance constraints: The sum of total generation, purchased and unserved power should be equal to the demand for each scenario, snapshot and time stage as in (2).,,,,,,,,,,,,,,, 2 Ω

2) Investment limits: In real problems, financial constraints always exist; therefore, the maximum allowable budget for investments in DG in a given year is limited by (3).,,, Ω Ω,, 3 3) Generation capacity limits: Constraints (4) and (5) represent the minimum and the maximum capacity limits of existing and candidate generators, respectively. Note that the binary variables also appear here and multiply the minimum and maximum generation capacities of a given generator. This is to make sure that the power generation variable is zero when the generator remains either unutilized or unselected for investment. For technical reasons, the power that can be purchased from the transmission grid could have minimum and maximum limits. This is enforced by (6).,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, 4,,,,, 5 6 4) Unserved power limits: This constraint is given by (7). 0,,,, 7 5) DG penetration level limit: Mainly due to technical reasons, there can be a maximum penetration level of DG integration (or, equivalently saying, the maximum percentage of demand covered by renewable DG power). This is ensured by adding the constraints in (8).,,,,,,,,,, 8 6) Logical constraints: Logically, an investment made at time stage t cannot be reversed or divested in the subsequent time stages; hence, the asset should be available for utilization immediately after the investment is made. Such constraints can be realized using (9).,,,, 9 IV. CASE STUDY, RESULTS AND DISCUSSION A. Data Used for the Case Study and Assumptions The DGIP problem is coded in GAMS 24.0 and solved using CPLEX 12.0. The system considered in the study is a distribution network of Azores Island, which has a peak demand of 70 MW and existing generators as shown in Table I. In this system, various DG types with capacities ranging from 1 to 30 MW are considered as candidates for investment (see in Table I). These fall into small to medium-scale DG categories according to common capacity-based classification of DG. The installation and maintenance cost figures of each DG considered in the case study are shown in Table I. The hourly series of wind (WD) and solar photovoltaic (PV) power production for one year are obtained from various locations in the island. B. Scenario Definition Table II shows three evolutions of demand growth, denoted as Low, Medium and High, each having equal probability of realization. Similarly, emission price is represented by three equally probable storylines (scenarios), as shown in this table. Out of these individual scenarios, assuming the two uncertain parameters are independent, we can have nine different combinations. These form a new set of scenarios used in the simulations. With this as a base-case, sensitivity analyses are carried out to study the impact of several system parameters other than these, which involve some degree of uncertainty, on DG investment decisions. C. Sensitivity of DG Investments with Variations of Model System Parameters 1) Interest rate: The evolution of interest rate remains uncertain, and, thus, it is subject to changes at any time in the future. To see its effect on DG investment decisions, it is changed by holding other parameters at their base case values. Generally, investments in DG fall as the interest rate increases. This is shown in Fig. 1, where decreasing trends of investments in DG (renewables, in particular) can be clearly seen. TABLE I. a) Existing generators No. Generator type, p DATA FOR EXISTING AND CANDIDATE GENERATORS Alternative, k Installed capacity (MW) OC p,k ( /MWh) IC p,k MC p,k ER p,k (tons of CO 2/MWh) 1 Hydro Hydro 4.07 7 NA 0.38 0.0121 2 Geothermal GEOT 24 5 NA 1.20 0.0165 3 HFO-T* HFO 98 145.4 NA 0.01 0.5600 4 Wind WD 0 10 17 NA 0.80 0.0276 b) Candidate generators 1 Solar PV 1 1 40 3.00 0.06 0.0584 2 Solar PV 2 1.5 40 3.83 0.08 0.0584 3 Solar PV 3 2 40 4.55 0.09 0.0584 4 Solar PV 4 2.5 40 5.20 0.10 0.0584 5 Solar PV 5 3 40 5.80 0.12 0.0584 6 Solar PV 6 4 40 6.89 0.14 0.0584 7 Solar PV 7 6 40 8.79 0.17 0.0584 8 Solar PV 8 10 40 11.94 0.24 0.0584 9 Wind WD 1 1 17 2.64 0.05 0.0276 10 Wind WD 2 2 17 4.00 0.08 0.0276 11 Wind WD 3 5 17 6.93 0.14 0.0276 12 Wind WD 4 10 17 10.51 0.21 0.0276 13 CGT** CGT 1 30 145.4 27.00 0.01 0.5600 14 Biomass BM 1 20 20 80.00 3.00 0.0276 * Heavy fuel oil turbine, ** Combustion gas turbine Not applicable TABLE II. DEMAND GROWTH AND EMISSION PRICE SCENARIOS Demand growth scenarios Emission price scenarios ( /ton of CO 2) Stages Low Medium High Low Medium High T0 0% 0% 0% 5 5 5 T1 2% 5% 10% 7 35 90 T2 5% 10% 20% 10 50 115 T3 7% 15% 30% 20 70 150

Their share in the total energy produced also follows a similar trend. This is in line with financial theory, which states that higher interest rates deter investments because this raises the expected rate of return of an investment, which does not incentivize investments. As an example, an interest rate of 0.02 results in investments for all DG candidates of wind and solar types except for PV1 and PV2 (see Table I); whereas, for an interest rate of 0.12, the investments made only include PV7, PV8 and all wind type DG s. The huge difference here highlights how sensitive the investment decisions can be with respect to the interest rate. 2) DG penetration level factor: This factor is another relevant parameter that affects DG investment decisions. Intuitively, one may ponder that the higher this value is, the higher the incentive for integrating more renewables, and, therefore, the higher DG investments will be. However, this holds only up to a certain threshold, beyond which there seems to be few or minimal new investments made. Fig. 2 clearly reflects this phenomenon. In the case study presented in this paper, the threshold value for the penetration level seems to be 40%. Below this level, investments made in DG steadily increase with the penetration level, from almost no investments at 10% to seven investments at 40%. However, this is not the case for higher penetration levels. Even if the penetration level is set beyond 40%, no new investments are justified. As can be seen in Fig. 2, the impact of DG penetration level on emissions and expected system costs is also significant. As expected, the increase in DG investments is offset by a higher decrease in operation and emission costs, leading to decreasing trends of expected system cost and total emissions with increasing penetration level. However, beyond 40%, the rate of changes in both curves is insignificant. Alternatively, Fig. 3 shows the variation of DG investments with the DG penetration level factor. The results in this figure also strengthen the fact that DG investments show some variations with an increasing level of this factor. The level of emissions gets lower as the DG penetration factor is increased up to a certain level (around 40%), beyond which the change is insignificant. This is indicative of increasing investments in DG up to this level. In addition, this is in line with the previous statement. 3) Fuel prices and electricity tariffs: The impact of fuel prices and electricity tariffs of renewable generators are also analyzed by varying the levels of these parameters. The results of this sensitivity analysis are summarized in Table III. As seen in this table, DG investment decisions are very sensitive to fuel prices. For example, when the fuel price is considered to be 30% lower than that of the base case, it becomes less attractive to invest in DG (especially in solar PV). However, a 30% higher fuel price results in more investments in PVs. In addition to fuel prices, electricity tariffs also play a significant role in the decision-making process, particularly in the context of DG investment planning. In general terms, the price of electricity generated from wind or solar DG highly depends on the initial level of capital invested on such DG technologies. Once the investments are made, operation costs are normally very low. Nowadays, the capital costs of main components pertaining to these technologies are continuously falling, with a learning rate of more than 20% per annum. This trend will most likely be sustained [25], resulting in a dramatically lower final cost of electricity (tariff) generated from such resources. In this work, the effects of variations in PV energy tariff on DG investments are also investigated. As shown in Table III, when solar PV generators are considered to be as competitive as wind power generators, i.e. with a tariff of 20 /MWh, more investments in solar PV are made compared to the base case. On the other hand, if the electricity tariff of energy coming from PV turns out to be twice that of the base case ( 80/MWh), the number of investments made in solar PV declines. However, this is not likely to happen given the current learning rate of solar PV technology. Share of wind and solar energy for the whole horizon 0% 2% 4% 6% 8% 10% 12% 14% Discount rate Fig. 1. Impact of discount rate on DG investments and energy production from wind and solar. Total costs, Investment cost Fig. 2. Variations of emissions, investment and expected system costs with DG penetration level factor. Average CO 2 Emissions (thousands of tons) 27% 26% 26% 25% 25% 24% 24% 23% 23% 350 300 250 200 150 100 50 0 160 110 60 Objective function value Investment cost Average, do-nothing Average, φ = 20% Average, φ = 30% Average, φ = 35% Average, φ = 50% Wind and solar energy share Total investment 500 450 400 350 300 250 200 150 100 50 0 0% 20% 40% 60% 80% Maximum share of renewable power at a given hour 200 150 100 T0 T1 T2 T3 Planning stages Fig. 3. Variation of DG investments with penetration level and their effect on total CO 2 emissions. 50 0 Total investment Emissions (thousands of tons)

TABLE III. IMPACT OF FUEL PRICE AND DG TARIFFS ON DG INVESTMENT DECISIONS TABLE IV. IMPACT OF WIND AND SOLAR PV POWER OUTPUT UNCERTAINTY ON DG INVESTMENT DECISIONS Investment in wind and solar DG Total expected cost Total expected emissions (x1000 tons of CO 2) Changes in PV Changes in fuel price energy tariff Stages +0% -30% +30% -50% +100% T1 PV7, PV8, WD1, PV8, WD1, WD1, PV7, PV8, WD2, WD1, WD2, WD2, WD1, WD2, WD3, WD2, WD3, WD3, WD3, WD4 WD4 WD3, WD4 WD4 WD4 T2 PV7 - PV6 - PV8 T3 PV6 PV8 PV4, PV5 PV6 378 326 425 372 386 268.8 296.4 254.1 263.1 296.4 4) Wind and Solar Power Output Uncertainty: To analyze the effect of uncertainty in wind and solar power outputs, two scenarios are created for each. One scenario is taken to be above the average (roughly 30% higher than that of the base case), while the other one is taken below the average (approximately 30% lower than that of the base case) in each case. The results of the analysis are summarized in Table IV. It can be observed that when the B-wind scenario is considered, the number of investments in wind DG become lower than that of the base case (see Table II). This is because of the lower yield of wind resource. In contrast, more investments are made in wind DG when the A-wind scenario is considered. The sensitivity of investments in PV with respect to the uncertainty of PV outputs is even higher, as can be seen in Table IV. V. CONCLUSIONS This paper has presented comprehensive experimental analyses to determine the sensitivity of DG investments with variations of several uncertain parameters, in order to investigate the effect of variability and uncertainty in model parameters on DG investment decisions. The aim of such analyses was to identify parameters that have the highest degree of influence on DG investments. This can help planners to devise new methodologies and tools that best represent the most relevant sources of variability and uncertainty. The results of our analyses generally showed that both uncertainty and variability had a meaningful influence on DG investment decisions. In fact, the degree of influence varied from one parameter to another. However, in general, ignoring or inadequately considering uncertainty and variability in model parameters had a quantifiable cost. The analyses made in this paper could be very useful for other researchers working in similar fields to identify the most relevant model parameters that need special attention in planning practices. ACKNOWLEDGMENT This work was supported by FEDER funds (EU) through COMPETE, by Portuguese funds through FCT, under Projects FCOMP-01-0124-FEDER-020282 (Ref. PTDC/EEA- EEL/118519/2010) and UID/CEC/50021/2013, and by funds from the EU 7th Framework Programme FP7/2007-2013 under grant agreement no. 309048. Wind and Power output solar PV DG scenarios Below average (B) Wind Above average (A) Below average (B) Solar Above average (A) Time stages Investment Objective T1 T2 T3 cost value PV8,WD2, WD3,WD4 PV7-44.810 412.413 PV8, WD1,WD2, WD3,WD4 - - 38.462 339.000 PV8, WD1,WD2, WD3,WD4 - - 38.462 373.000 PV8, WD1,WD2, WD3,WD4 PV7 PV6 46.995 360.478 REFERENCES [1] R. Poudineh and T. Jamasb, Distributed generation, storage, demand response and energy efficiency as alternatives to grid capacity enhancement, Energy Policy, vol. 67, pp. 222 231, Apr. 2014. [2] C. L. T. Borges and V. F. Martins, Multistage expansion planning for active distribution networks under demand and Distributed Generation uncertainties, Int. J. Electr. Power Energy Syst., vol. 36, no. 1, pp. 107 116, Mar. 2012. [3] J. A. P. Lopes, N. Hatziargyriou, J. Mutale, P. Djapic, and N. Jenkins, Integrating distributed generation into electric power systems: A review of drivers, challenges and opportunities, Electr. Power Syst. Res., vol. 77, no. 9, pp. 1189 1203, Jul. 2007. [4] A. Yadav and L. Srivastava, Optimal placement of distributed generation: An overview and key issues, in 2014 International Conference on Power Signals Control and Computations (EPSCICON), 2014, pp. 1 6. [5] M. E. Samper and A. Vargas, Investment Decisions in Distribution Networks Under Uncertainty With Distributed Generation - Part I: Model Formulation, IEEE Trans. Power Syst., vol. 28, no. 3, pp. 2331 2340, Aug. 2013. [6] M. E. Samper and A. Vargas, Investment Decisions in Distribution Networks Under Uncertainty With Distributed Generation - Part II: Implementation and Results, IEEE Trans. Power Syst., vol. 28, no. 3, pp. 2341 2351, Aug. 2013. [7] A. Piccolo and P. Siano, Evaluating the Impact of Network Investment Deferral on Distributed Generation Expansion, IEEE Trans. Power Syst., vol. 24, no. 3, pp. 1559 1567, Aug. 2009. [8] T. Niknam, S. I. Taheri, J. Aghaei, S. Tabatabaei, and M. Nayeripour, A modified honey bee mating optimization algorithm for multiobjective placement of renewable energy resources, Appl. Energy, vol. 88, no. 12, pp. 4817 4830, Dec. 2011. [9] H. Hedayati, S. A. Nabaviniaki, and A. Akbarimajd, A Method for Placement of DG Units in Distribution Networks, IEEE Trans. Power Deliv., vol. 23, no. 3, pp. 1620 1628, Jul. 2008. [10] C. L. T. Borges and D. M. Falcão, Optimal distributed generation allocation for reliability, losses, and voltage improvement, Int. J. Electr. Power Energy Syst., vol. 28, no. 6, pp. 413 420, Jul. 2006. [11] M. A. Abdullah, A. P. Agalgaonkar, and K. M. Muttaqi, Assessment of energy supply and continuity of service in distribution network with renewable distributed generation, Appl. Energy, vol. 113, pp. 1015 1026, Jan. 2014. [12] J. Liu, W. Zhang, R. Zhou, and J. Zhong, Impacts of distributed renewable energy generations on smart grid operation and dispatch, in 2012 IEEE Power and Energy Society General Meeting, 2012, pp. 1 5. [13] F. Katiraei and J. R. Agüero, Solar PV Integration Challenges, IEEE Power Energy Mag., vol. 9, no. 3, pp. 62 71, May 2011. [14] S. Eftekharnejad, V. Vittal, G. T. Heydt, B. Keel, and J. Loehr, Impact of increased penetration of photovoltaic generation on power systems, IEEE Trans. Power Syst., vol. 28, no. 2, pp. 893 901, May 2013. [15] M. Shivaie, M. T. Ameli, M. S. Sepasian, P. D. Weinsier, and V. Vahidinasab, A multistage framework for reliability-based distribution expansion planning considering distributed generations by A self-adaptive global-based harmony search algorithm, Reliab. Eng. Syst. Saf., Mar. 2015. [16] G. Muñoz-Delgado, J. Contreras, and J. M. Arroyo, Joint Expansion Planning of Distributed Generation and Distribution Networks, IEEE Trans. Power Syst., vol. PP, no. 99, pp. 1 12, 2014. [17] Ž. N. Popović, V. D. Kerleta, and D. S. Popović, Hybrid simulated annealing and mixed integer linear programming algorithm for optimal planning of radial distribution networks with distributed generation, Electr. Power Syst. Res., vol. 108, pp. 211 222, Mar. 2014. [18] M.-C. Alvarez-Herault, N. N Doye, C. Gandioli, N. Hadjsaid, and P. Tixador, Meshed distribution network vs reinforcement to increase the distributed generation connection, Sustain. Energy Grids Netw., vol. 1, pp. 20 27, Mar. 2015. [19] M. Jalali, K. Zare, and M. T. Hagh, A multi-stage MINLP-based model for sub-transmission system expansion planning considering the placement of DG units, Int. J. Electr. Power Energy Syst., vol. 63, pp. 8 16, Dec. 2014. [20] H. Shayeghi and A. Bagheri, Dynamic sub-transmission system expansion planning incorporating distributed generation using hybrid DCGA and LP technique, Int. J. Electr. Power Energy Syst., vol. 48, pp. 111 122, Jun. 2013. [21] M. Sedghi, M. Aliakbar-Golkar, and M.-R. Haghifam, Distribution network expansion considering distributed generation and storage units using modified PSO algorithm, Int. J. Electr. Power Energy Syst., vol. 52, pp. 221 230, Nov. 2013. [22] M. Sadeghi and M. Kalantar, Multi types DG expansion dynamic planning in distribution system under stochastic conditions using Covariance Matrix Adaptation Evolutionary Strategy and Monte-Carlo simulation, Energy Convers. Manag., vol. 87, pp. 455 471, Nov. 2014. [23] M. Ahmadigorji and N. Amjady, A new evolutionary solution method for dynamic expansion planning of DG-integrated primary distribution networks, Energy Convers. Manag., vol. 82, pp. 61 70, Jun. 2014. [24] L. Blank and A. Tarquin, Engineering Economy, 7 edition. New York: McGraw- Hill Science/Engineering/Math, 2011. [25] M. Bazilian, et al., Re-considering the economics of photovoltaic power, Renew. Energy, vol. 53, pp. 329 338, May 2013.