Workshop Brief Notes on: Construction of Pipe Roof and Support System

Similar documents
LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

13/05/2016. Introductions of Pipe Roof. Focuses. Application of Rectangular Shield Jacking

CC1602 Microtunneling

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Experts in tunneling with Tunnel Boring Machines

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

AGS(HK) Seminar - Tunnelling - Selected Topics Instrumentation for Tunnelling. Practical Aspects of Tunnelling Instrumentation

Performance review of a pipe jacking project in Hong Kong

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Tel: Neil: Tony: Website:

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

4th International Engineering and Construction Conference - July 28, 2006

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Multiple Large Diameter Microtunnels with Limited Ground Cover

COMPANY PROFILE. HARKE Capability Statement. Insideout

Temporary Works Excellence Award 2017 MTRC Contract 1128 SOV TO ADMIRALTY TUNNELS

Reinforced Concrete Microtunnelling Pipe Designed for Project Conditions and MTBM Machines

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

Replacement of the Existing Water Siphons between Brooklyn and Staten Island Siphon Project

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

Trenchless Technology

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

Ensuring Building Safety In An Urbanised Environment Singapore s Perspective. Ong See Ho Deputy CEO & Commissioner of Building Control

Selection of Proprietary Shoring Equipment

These challenges can only be mastered by a partner familiar with the complexity of building metros.

Cost Estimating Framework

HMA GROUP AUSTRALIA - NEW ZEALAND - INDONESIA - SOUTH AFRICA SINCE 1966

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

Introduction to Tunnel Construction

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

Appendix C Canadian Pacific Rail License of Entry Document

Concrete Pipe Jacking

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

Safe Work Method Statement (SWMS) for Painting projects

1. ORIGINAL CONSTRUCTION SEQUENCE PRESENTED IN THE APPROVED EIA REPORT

Multi-Institutional Academic Health Science & Research Center Evansville, IN

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

Trenchless Pipeline Crossings

WARNING DO NOT BID ON THIS PROJECT

UK POWER NETWORKS BATTERSEA CABLE TUNNEL: POWERING A RENAISSANCE AT BATTERSEA S ICONIC POWER STATION

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON

Microtunneling Drive for Mixed Layers in Singapore / Japan

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE

Scottish Water has recently commenced the first phase of construction on a 120m investment project designed

Singapore 11 November Uphill Excavator Peter Leyton and Peter Coppenhall

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

SECTION DUCTILE IRON PILES

Geotechnical control of a major railway project involving tunnel works in Hong Kong

PUMPING STATION CONSOLIDATION AND TRENCHLESS INSTALLATION CASE STUDY

Take Me to the Other Side:

Amendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility Installation by Jacking and Boring

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

Phase 2 Update. October 12, 2017

SECTION TRENCHLESS INSTALLATION

Ground Freezing for Tunnel, Shafts, and Adits

Construction OS&H Project planning and control for safe OS&H

ITEM 432 TUNNEL CONSTRUCTION


An introduction to. pipe jacking

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

Mayor and Council Tony Seibert, Drainage Engineer Waechter Creek Culvert Emergency Repair at Simpson Road Extension

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Maynard Akkerman CEO/President Akkerman 04/22/15

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject

Behaviour of Various Support Systems for Deep Excavations, Changi Airport Underground MRT Station

ILC ASIAN DRAFT SCHEDULE

Transbay Program Phase 2 Downtown Rail Extension (DTX) Tunnel Options Study Briefing

A. Section includes temporary excavation support and protection systems.

How we would build the proposed storm relief sewer

Pedestrian Tunnels The Mode of the Future. By Don Del Nero, PE, CDT

CHAPTER 17 - SPECIALIST CONSTRUCTION SYSTEMS

GEOTECHNICAL BASELINE REPORTS APPLYING THE GUIDELINES TO MICROTUNNELING

Undertrack Crossings and Pressure Pipelines

CIVIL BREADTH Exam Specifications

6 Preliminary Assessment of Construction Method and Constructability Issues

STATUS REPORT On the

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

Geotechnical & Structural Instrumentation

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING

Sheet Pile Retaining Walls Design and Construction in Brown Fields Environment

Small Diameter Rock TBM Tunneling in Baltimore

A case study of twin bored tunnelling under mixed-face soil - Bendemeer MRT station project (Downtown Line 3), Singapore

ASCE PIPELINES 2015 CONFERENCE. Recap/Highlights by Bill Chavez, PUG Vice-Chairman Baltimore, MD August 23-26, 2015

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

ACEI Design Excellence Awards Nomination Form

Transcription:

Workshop Brief Notes on: Construction of Pipe Roof and Support System Kim H. CHENG, BE (Hons, Monash),DHE( Delft),PE, FIEM, MIES, MISTT, FINDSTT,Tunnel Services,, C& V Summary: The notes herein illustrated the application of pipe roof/arch method of constructing circualr or rectangular/any shaped box culvert structures. These notes covered various considerations in the planning/design and construction of such works. The pipe roof/arch method involves the use of microtunnelling /jacking / other trenchless machine to install a series of interlocking steel pipes which formed a temporary support system, below which the final section of the box culvert structures is then mined and constructed.problems encountered and instrumentations issues were also mentioned. Date Dec 2010 Title Author /Speaker Pipe Roof/Arch consideration in the construction Mr Cheng Kim Hua Introduction. Consideration Planning and Design Construction Problems encountered Instrumentations and monitoring Conclusion 1 Page1

Introduction. 1) Pipe roof as alternatives to open cut and other method. Pipe roof method of construction can generally be suitable when a relatively short tunnel or culvert/underpass need to be installation in heavy traffic or where road /rail services cannot be interrupted and where settlement due to work are to be minimised. 2) Such method involve the construction of temporary works using interlocked steel pipes, installed by microtunnelling or pipe jacking,to form the temporary ground support inside which the permanent structure is constructed. 3) The workshop will be conducted by Mr Cheng Kim Hua, PE, BE(Hons) Monash, Dip Hydraulic Eng( IHE, The Nederland s) who have been in the trenchless line since 1989, and have been involved in many microtunnelling projects in S E Asia, India and the Middle East. Considerations 4) The cases for the need to consider pipe roof will include: a) Installing sections across roads, railway for underpass or drainage/sewer /other culvert b) Relatively large sections, sometimes as long as 19 m x 4.5m x 293 m (Ref 1:-Coller P 1994) e) Sensitive settlement issues, where cost of interruptions/repair are probative, or as mandated by Authorities such as near MRT or other services ( Singapore s LTA project 6 m x 4 x 53 m - undercrossing Major road, and above MRT Lines) 5) The other methods that may be considered include: a) Pipe ramming (where the pipes are rammed to form the support) or by auger microtunnelling Fig 3- pipe roof by Auger microtunnelling (Ref 4) c) Martha Railway, Atlanta Fig 1-pipe roof in Martha Railway, Atlanta (Ref 2) d) Singapore underpass 1993 Fig 2 Singapore Orchard Underpass( Ref 3) 2 b) Direct box culvert jacking/pushing (such 10 m x 4 m box section of services tunnel Singapore Power Grid, Jacking under Boston Railway, USA) Page2

Fig 4 - Jacked tunnel under Boston (Ref 5) A summary of method used in pipe roof/arch construction is given in ISTT (Guideline) (Ref 4). 6) The general soil parameters used in the design of the shaft and tunnel( pipe jacking ) and portal frame will include soil investigation, study of the project areas, and discussions with the client and authority 7) Generally the pipe roof is undertaken on a design and build basis, where by the appointed main contractor will appoint either specialise sub contractor for such task or have its own specialist design team, and assemble specialist trade such as pipe jacking to carry out the works, 8) Additional teams of specialist will include soil improvements, geotechnical measurement and monitoring teams 9) The client will appoint its own supervising team, and sometimes independent check. 10) The performance criteria will follow pipe jacking tolerances for jacking works, and structural tolerances for others sections.the monitoring /suspension. Alert levels for instrumentation works will be decided by site and design considerations, and agreed upon prior to work commencement. 3 Page3

Planning and Design 11) The soil parameters are mainly used to design the shafts for which to launch the pipe roof pipe jacking machine.typically: Fig 5 Soil profile (typical) -General soil profile of the pipe jacking / mined tunnel zone surrounding ground, stability of the excavated face and base stability during excavation; ii. Structural aspects such as the design of the pipe-roof and the structural steel frames supporting the piped-roof; iii. Soil improvements and types and extent of protection to existing services; iv. Other pertinent points related to method and operation included: the adoption of single or multiple sided( 3, 4) pipe roof, type and capabilities of jacking machine used, their maintenance of face pressure, excavation speed especially when encountered with obstructions such as sheet piles, timber pieces, skill of operators, details of pipe clutching and damages expected to be caused by excessive settlement, mitigation measures and others. v. Risk assessment and hazard analysis including alert and suspension levels for instrumentations such as inclinometers and settlement markers, tilt meter etc during construction stage Other calculations: a) Thrust wall design b) Jacking force calculations; 12) The design parameters is sampled as shown Fig 6 Design soil parameters c) Final drawing of culvert Fig 7-sample design drawings of culvert section 14) Design modelling: Use 2 D Plaxis -2D Plan strain model 13) The key considerations. Fig 8-2 D Plaxis Modelling The key design considerations can include factors such as: i. Geotechnical aspects, including soilstructure interaction between pipe-roof and 4 Page4

15) Typical section of the pipe roof is as shown Fig 9 - -typical section of pipe roof (3 sided) 5 Page5

Construction 16) Methodology The interlocking sections are sampled below: Fig 10- -interlocking steel pipe sample iv. Preparing guard Rail for jacking v. Setting TBM 17) Pipe jacking of individual pipe.typical work Fig 13-preapring and setting up Jacking Machine 18) The following pictures show the pipe jacking and pipe roof construction i. Slurry shield jacking layout Fig 10- typical layout for pipe jacking vi. Welding steel sections Fig 14- welding joint ii. shaft Constrction of jacking and receiving Fig 11- shaft construction Vii. ready for jacking iii. View of jacking machine Fig 15 ready for jacking Fig 12- jacking machine 6 Page6

viii. Break through at receiving shaft Fig 16- Break through envisaged /in tender drawings Others insurance cover, night or overtime work, mapping and service detection especially for shaft areas Etc Instrumentations and monitoring ix. Completed row Fig 17- completed row 20) The requirements of the authorities/client will determine primarily the extent of monitoring needed.considerations will include the frequency and extent of measurements- 21) Measurement areas will cover the crossing (road /rail settlement), water table, adjacent structures (movement, tilt) 22) Instruments will include inclinometers, settlement markers piezometer, tiltmeter, vibration meter Problems encountered 19) The problems encountered in any pipe roof works will likely to include: Problems Solution? Soil profile Choose more different from versatile machine, provided in tender use conservative or soil paramours investigation report 23) Reports to include alert/suspension levels, frequency and measurement/readings/interpretations /recommendations for additional instrumentation 24) Usually separate/independent specialist to carry out, sometimes done directly under the client s purview. Fig 18 shows typical mentoring plot 7 Excessive settlement/problem in jacking due to obstruction Encounter services of not Site solution, innovative, rescue operations well coordinated, use of man entry( as far as possible bigger than 760 mm OD) Alternative design to ensure conditions met( cover, alignment) Coordinated response, Conclusion Pipe roof/arch method of construction by pipe jacking generally are useful and effective solution to situations where the constraints of settlement, crossings and client's requirements cannot be met by other cheaper method such as open cut or other trenchless method. Page7

There are numerous issue to consider and as the work are normally contracted out on a design and build basis, the contractor will need to weight the risk and allow for specialist inputs to be always on the site, and during planning/design stage. With well coordinated efforts from all stakeholders, the pipe roof method can perform as planned, and has been successfully adopted since the 90 s. References 1- Coller, p, Abbot,D, 1994 Microtunnelling used for record braking pipe roofing project( Japan) North America Tunnelling 94 2- Attalla, A.L. and D.T. Islay, 1991. "Pipe Arch Horizontal Drift Method for MARTA's Transit Extension Under I-285," Proceedings of Rapid Excavation and Tunneling Conference, SME, Chapter 24, June, pp. 435-453. 3- Darling, P., 1993. "Jacking Under Singapore's Busiest Street, Pacific Rim Supplement to Tunnels & Tunnelling, summer, pp. 19-23. Jacking under Singapore s Busiest Street. 4- ISTT Guideline, TRC,SECTION 9- Associated Techniques 5- S. Taylor, D Penrice, Jacking Large Tunnel underneath active Rail Tracks 8 Page8