Quality Management (PQM01) Chapter 04 - Quality Control

Similar documents
Project Quality Management. For the PMP Exam using PMBOK

For the PMP Exam using PMBOK. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

PROJECT QUALITY MANAGEMENT. 1 Powered by POeT Solvers LImited

Quality. Monitoring & Controlling Processes. Planning. Processes. Executing Processes. Process. Knowledge Area. Monitoring &

Quality Management Chapter 14

A semaphore telegraph, optical telegraph, shutter telegraph chain, Chappe telegraph, or Napoleonic semaphore is a system of conveying information by

PMP Exam Preparation Workshop Project Quality Management

Projektledning och Projektmetodik, VBEF01. Kristian Widén Tekn. Doktor Avd. För Byggproduktion Inst. För Byggvetenskaper Lunds Universitet

Delivering Engineered Solutions

Lecture Notes on Statistical Quality Control

The Philosophy of TQM An Overview

PROJECT MANAGEMENT. Quality Management (QM) Course 7 Project Management Knowledge Areas (5) Risk Management (RM)

Project Management CTC-ITC 310 Spring 2018 Howard Rosenthal

Ch.8 Quality Management.

Learning Objectives. Defining Quality. Defining Quality 5 Ways. Manufacturing Quality vs. Service Quality. Cost of Quality. Chapter 5 Managing Quality

Malay (Rumi, Roman script)

CH (8) Hot Topics. Quality Management

Project Quality Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

CSU Project Management Certificate Program

Process Performance and Quality Chapter 6

Project Quality Management

Process Performance and Quality

Computer Science and Software Engineering University of Wisconsin - Platteville 3. Statistical Process Control

Quality Management in Construction Projects. Dr. Nabil El Sawalhi

Quality Management. Katarzyna Wasielewska-Michniewska, PhD Eng.

Online Student Guide Types of Control Charts

Application of statistical tools and techniques in Quality Management

Quality Control Introduction to Quality

Chapter 1. Introduction

LEAN PRODUCTION SYSTEM

FUNDAMENTALS OF QUALITY CONTROL AND IMPROVEMENT. Fourth Edition. AMITAVA MITRA Auburn University College of Business Auburn, Alabama.

SHORT ANSWER QUESTIONS (KEY) UNIT- I

Dimensions of product and service quality

Expert Reference Series of White Papers. Tools and Techniques Useful in Quality Planning, Assurance, and Control

İŞL 343 Üretim İşlemler Yönetimi Bahar Dönemi. Chapters 9-10 Management and Control of Quality. Melike Meterelliyoz Kuyzu

Operations Management

Ch.3 Quality Issues.

Presented by Renaldo de Jager 11-1

IIA-CIA-Part3 IIA. Certified Internal Auditor - Part 3, Business Analysis and Information Technology

Chapter 9 1. List and briefly explain the dimensions of product and service quality

Quality Assurance. Chapter 42

WHY QUALITY IS IMPORTANT? PRODUCT AND QUALITY COSTS OF POOR QUALITY COST OF ACHIEVING GOOD QUALITY. Prevention costs.

FUNDAMENTALS OF QUALITY CONTROL AND IMPROVEMENT

Principles of Operations Management: Concepts and Applications Topic Outline Principles of managing Operations (PMO)

Information Technology Project Management Fifth Edition

Project Quality Management

QUALITY CONTROL CHAPTER OUTLINE

CERTIFIED QUALITY IMPROVEMENT ASSOCIATE

Total Quality Management

Workshop 5. Managing Quality. Kate Hughes & John Whiteley

Quality Management EOE-072. It costs a lot to produce a bad product. Norman Augustine

IE 301 Industrial Engineering laboratory LAB No.5: The seven QC tools and Acceptance sampling Instructor: Assisant.Prof. Parichat Chuenwatanakul Lab

QUALITY MANAGEMENT DEFINITIONS AND CONCEPTS QUALITY MANAGEMENT TOOLS QA / QC PROCESS COMPUTERS AND PROJECT QUALITY

PART 5 Managing Growth in the Small Business

Quality Management. It costs a lot to produce a bad product. Norman Augustine

APICS PRINCIPLES OF OPERATIONS MANAGEMENT TOPIC OUTLINE CONCEPTS AND APPLICATIONS

Chapter 6 - Statistical Quality Control

Statistics Quality: Control - Statistical Process Control and Using Control Charts

International Association of Certified Practicing Engineers

1. What is a key difference between an Affinity Diagram and other tools?

Quality Tool to Achieve Excellence in Construction Projects. By Dr. Abdul Razzak Rumane 2018 by Rumane

An Introduction to Business Process Management

Seven Quality Control Tools

PROJECT QUALITY MANAGEMENT

Quality Control Charts

UNIT 2 QUALITY PHILOSOPHY

Developing and implementing statistical process control tools in a Jordanian company. R.H. Fouad* and Salman D. Al-Shobaki

Introduction to Quality Management. BPF 2123 Quality Management System

The materials required over the next two modules include:

CQE Sample Test #4. A. I and only. B. I and only. C. and only. D., and. 4. The equation below represents the

Continuous Improvement Toolkit

QUESTION 2 What conclusion is most correct about the Experimental Design shown here with the response in the far right column?

Quality and Strategy. Quality and Strategy 27/11/2014

Statistics and data analysis procedures can be divided into two general categories: quantitative techniques and graphical techniques.

Chapter 9A. Process Capability & SPC

Change the Process How to implement process improvement in your project

Total Quality Service. Unit 5

Quality Manual ISO 9001:2000

KillTest *KIJGT 3WCNKV[ $GVVGT 5GTXKEG Q&A NZZV ]]] QORRZKYZ IUS =K ULLKX LXKK [VJGZK YKX\OIK LUX UTK _KGX

Introduction to Total Quality Management

Internal Auditing and Control of Nonconforming Work

Acceptance sampling is an inspection procedure used to

Analysis of Software Quality Tools Samsung Galaxy Note 7 Recall Case

Cage Code First Edition. A guide to AQS continuous improvement expectations

Slide Chapter 17 Quality management

many quality problems remain invisible to consumers

International Journal on Textile Engineering and Processes, ISSN: , Vol 1, Issue 1, Jan2015

CP:

LCS International, Inc. PMP Review. Chapter 7 Planning Project Resources. Presented by David J. Lanners, MBA, PMP

2. List 5 processes of the Executing Process Group. (15)

1.20 Testing involves Using many products with same design to perform life tests to see how the design performs on average over a span of time.

Quality Engineering. Page 1. Grahame Baker. Medway School of Engineering QUALITY ENGINEERING QUALITY ENGINEERING

Fundamentals of Quality

Why Learn Statistics?

Seven Basic Tools of Quality Control: The Appropriate Techniques for Solving Quality Problems in the Organizations Neyestani, Behnam

Quality management in construction projects

Global Operations and Supply Chain Management Final Exam Notes

Total Quality Management

TOTAL QUALITY MANAGEMENT UNIT I INTRODUCTION

FMEA Failure Mode Effects Analysis. ASQ/APICS Joint Meeting May 10, 2017

Transcription:

Quality Management (PQM01) Chapter 04 - Quality Control

Slide 1

Slide 2 Involves monitoring specific project results to determine if they comply with relevant quality standards, and identifying ways to eliminate causes of unsatisfactory results. Performed throughout the project Results in ability to eliminate or reduce causes of unsatisfactory performance 2

Slide 3 Juran defines Quality Control as The process through which we measure quality performance, compare it with quality goals, and act on the difference. 3

Slide 4 Cost of Quality Conformance Nonconformance Prevention Planning Scrap Failure Appraisal Training Rework Auditing Testing Controlling Expediting Warranty Service Recalls v. 7.0 - Copyright and all rights reserved 4

Slide 5 7 Basic Quality Tools Also know as 7QC Tools. Used within PDCA cycle to solve quality problems. They are: Cause-and-effect diagrams Checksheets Histograms Flowcharts Pareto diagrams Control charts Scatter diagrams v. 7.0 - Copyright and all rights reserved 5

Slide 6 Key Concepts Prevention vs. Control Prevention Aims to stop an event or failure from ever occurring Control Attempts to limit the impact of a failure after it has happened 6

Slide 7 Key Concepts Attribute Sampling & Variable Sampling Attribute Sampling Asks the question, does the attribute exist and is binary in nature? Variable Sampling Addresses characteristics like how much and is numeric in nature 7

Slide 8 Key Concepts Special Causes vs. Random Causes Special Causes Unusual events Random/Common Causes Normal or expected variations 8

Slide 9 Key Concepts Tolerances & Control Limits Tolerances Range of acceptable results Control Limits Values that indicate if a process is in control 9

Slide 10 Trend Analysis Involves using mathematical techniques to forecast future outcomes based on historical results. Technical Performance how many errors or defects have been identified, how many remain to be corrected? Cost and Schedule Performance how many activities per period were completed with significant variances? 10

Slide 11 A Good Quality System Will Compare actuals to standards (inspection) Act when standards are not met Plan for improvements 11

Slide 12 Control Charts Graphic display of the results of a process over time Based on statistical probability Determine if a process is in control Verify the impact on a process when changes are made 12

Slide 13 Control Charts Key Terms A center line - designated with an x, which provides the average (x) of the process area. An upper line designating the upper control limit (UCL). 13

Slide 14 Control Charts Key Terms The lower line designating the lower control limit (LCL) Points outside of the UCL and LCL are indicative that the process is out of control and/or unstable 14

Slide 15 In Control When in control a process should not be adjusted UCL X LCL x x x x x x x x x x x What is out of control? x 3ơ 2ơ 1ơ -1ơ -2ơ -3ơ The rule of 7? 15

Slide 16 Variations Normal Common, random, naturally occurring Found throughout the entire system Accounts for 85% of variation (Deming) Management s responsibility to correct Requires investigation and elimination or incorporation 16

Slide 17 Variations Abnormal Assignable or special Specific to material, machinery, manpower, or method Accounts for only 15% of variation Location supervisor or worker should correct 17

Slide 18 SIPOC Sometimes called COPIS Tool that summarizes the inputs and outputs of one or more processes in table form. Acronym SIPOC stands for suppliers, inputs, process, outputs, and customers which form the columns of the table. First used in TQM programs. Used today in Six Sigma and Lean manufacturing. v. 7.0 - Copyright and all rights reserved 18

Slide 19 SIPOC Supplier Input Process Output Customer Requirements & Feedback Loop Requirements & Feedback Loop Requirements List Measurements List Requirements List Measurements List v. 7.0 - Copyright and all rights reserved 19

Slide 20 Pareto Diagrams A histogram, ordered by frequency of occurrence, that shows how many results were generated by type of category of identified cause. 60 50 40 30 20 10 0 1 2 3 4 5 6 20

Slide 21 Pareto Diagrams Can combine bar charts with Pareto Diagrams 40 100 30 Cumulative 75 Percentage 20 50 10 25 0 0 Improper Rotation Noise Wobble Pressure Axle Caulking Case Wobbles Other Number of Defective Cases Percentage of Defective Cases Car Problems 21

Slide 22 Statistical Sampling Terms Attribute Either accept or reject (% defective) Variable Anything measured (average measure) Producer s Risk (alpha) chance of rejecting a good lot. Type II error. 22

Slide 23 Statistical Sampling Terms Consumer s Risk (Beta) chance of accepting a bad lot. Type I error. Sampling Plan Sample size (n) and acceptance criteria ( c ) 23

Slide 24 Acceptance Sampling Process of evaluating a portion of the product in a lot for the purpose of accepting or rejecting the entire lot. Alternative to 0% or 100% inspection Single or multiple samples 24

Slide 25 Advantages of Acceptance Sampling Smaller inspection staff Less product damage Quicker decisions Less inspection errors Lower cost 25

Slide 26 Disadvantages of Acceptance Sampling Sampling risks Less information 26

Slide 27 Quality Circles 5-15 workers who meet on a frequent basis to identify, discuss and solve productivity and quality problems One member of the group acts as the liaison between management and the group 27

Slide 28 Quality Assurance Applying the planned systematic quality activities to ensure that the project employs all processes needed to meet requirements. Quality Control Monitoring specific project results to determine whether they comply with relevant quality standards, and identifying ways to eliminate causes of unsatisfactory performance 28

Slide 29 Quality Planning Perform Quality Assurance Continuous Improvement Perform Quality Control 29

Review Questions: 1. Which of the following statements concerning quality control is NOT true? A. Quality control involves monitoring specific project results to determine if they comply with relevant quality standards, and identifying ways to eliminate causes of unsatisfactory results B. Quality control is performed throughout the project C. Quality control results in the ability to eliminate or reduce causes of unsatisfactory performance D. None; all of the above are true 2. Which of the following best describes the preventive aspect of quality control? A. It attempts to limit the impact of a failure after it has happened B. It aims to stop an event or failure from ever occurring C. All of the above D. None of the above 3. What type of sampling asks the question "does the attribute exist", and is binary in nature? A. Attribute sampling B. Variable sampling C. Both of the above D. None of the above 4. When evaluating the causes of errors, what type explains outcomes that are naturally occurring? A. Type I errors B. Type II errors C. Random causes D. Special causes 5. What term is used to describe the range of acceptable results? A. Control limits B. Tolerances C. Special causes D. Random causes

6. Who describes quality control as the process through which we measure quality performance, compare it with quality goals, and act on the difference? A. Deming B. Crosby C. Juran D. Taguchi 7. What type of analysis involves using mathematical techniques to forecast future outcomes based on historical results? A. Technical analysis B. Trend analysis C. Performance analysis D. None of the above 8. What kind of performance evaluates how many errors or defects have been identified, or how many remain to be corrected? A. Technical performance B. Cost and schedule performance C. Technical analysis D. Trend analysis 9. Which of the following will a good quality control system do? A. Compare actuals to standards (inspection) B. Act when standards are not met C. Plan for improvements D. All of the above 10. Which of the following is used to describe a control chart? A. Based on statistical probability B. Determine if a process is in control C. Verify the impact on a process when changes are made D. All of the above 11. Which of the following is NOT a common name for the curve most often used to describe a variable that is unaffected by other variables? A. A normal distribution B. A bell curve C. A standard distribution D. A Gaussian distribution

12. Which of the following terms is often used to describe the mid-point of the distribution when examining a control chart? A. The mean B. X (with a line above it) C. The centerline D. All of the above 13. Which of the following terms is often used to describe the maximum allowable value for a control chart? A. Lower control limit B. Upper control limit C. Maximum value D. Top value 14. Which of the following is NOT a term used to describe variations that account for 85% of the error? A. Normal variation B. Standard variation C. Type II errors D. Abnormal variation 15. A graph ordered by frequency of occurrence that shows how many results were generated by type of category of identified cause is called what? A. A histogram B. A pareto diagram C. A trend chart D. A scatter diagram 16. Which of the following statistical sampling terms is used to describe a tested item that is either accepted or rejected? A. A variable B. A sample plan C. An attribute D. None of the above

17. What kind of risk is involved when you are worried that you might accept product that should be rejected? A. Producer risk B. Consumer risk C. Project risk D. Alpha risk 18. Which of the following is an advantage of acceptance sampling? A. Less product damage B. Quicker decisions C. Less inspection errors D. All of the above 19. Which of the following is NOT a characteristic of a quality circle? A. It is usually made up of 5-15 workers B. The team meets on a frequent basis to identify, discuss, and solve productivity and quality problems C. One member of the group acts as the liaison between management and the group D. All of the above are characteristics of a quality circle 20. Which of the following statements defines quality control? A. It is the application of planned systematic quality activities to ensure that the project employs all processes needed to meet requirements B. It is the monitoring of specific project results to determine whether they comply with relevant quality standards, and identifying ways to eliminate causes of unsatisfactory performance C. Both statements define quality control D. Neither statement defines quality control 21. In which of the following processes is continuous improvement most commonly categorized? A. Quality planning B. Perform quality assurance C. Perform quality control D. All of the above

Answer Key: 1. D Quality control involves monitoring specific project results to determine if they comply with relevant quality standards, and identifying ways to eliminate causes of unsatisfactory results. It is performed throughout the project and results in the ability to eliminate or reduce causes of unsatisfactory performance. 2. B Prevention, as a concept in quality management, is all about stopping an event or failure from ever occurring within the project. 3. A Attribute sampling and variable sampling are the two types of sampling techniques. Attribute sampling asks if the attribute exists at the desired level or value. It is a simple yes or no question. 4. C Random causes are inherent in nature and are difficult to predict. However, they account for only 85% of the errors. 5. B Tolerances describe the limits and what you are willing to tolerate or accept, in terms of the results. 6. C Juran describes quality control as the process through which we measure quality performance, compare it with quality goals, and act on the difference. 7. B Trend analysis takes past values and using mathematical techniques forecasts future outcomes based on historical trends. 8. A Technical performance is a purely quantitative method for measuring results. It focuses on how many defects have been identified and keeping track of how many remain to be corrected.

9. D By definition, according to Juran, a good quality control system will measure quality performance, compare it with quality goals, act on the difference, and plan for improvements. 10. D A control chart is based on statistical probability and is used to determine if a process is in control by establishing upper and lower control limits. It can also verify the impact on a process when changes are made. 11. C The curve that describes any independent variable with a nominal number of cases that is distributed in a balanced or normal fashion is called a normal distribution, a bell curve or a Gaussian distribution. 12. D It is most commonly referred to as the mean of the distribution; it can also be represented by an X with a line over it, or called the centerline of the distribution. 13. B Within a control chart, the tolerances are defined by an upper and lower control limit. These create the maximum and minimum allowable value. 14. D Abnormal variation, assignable, or special variations account for only 15% of differences and require the resource to take action. These are different than the normal or standard variation that is also referred to as a type II error. 15. B A pareto diagram is a bar chart representing occurrences of something, usually errors. It is typically organized from left to right with the most commonly occurring errors on the left. 16. C An attribute is a variable that has a yes or no answer. It can be binary in nature or it can be a target value that must be reached as a minimum. 17. B Consumer risk is sometimes referred to as a type I error and represents the likelihood of accepting a product that should be rejected.

18. D Acceptance sampling allows the organization to test only a small portion of the total products. This allows for less damage (e.g. fewer products tested), quicker decisions, and fewer errors. 19. D Quality circles are usually made up of 5-15 workers, require the team to meet on a frequent basis to identify, discuss, and solve productivity and quality problems. They often require that one member of the group acts as the liaison between management and the group. 20. B Quality control is the monitoring of specific project results to determine whether they comply with relevant quality standards, and identifying ways to eliminate causes of unsatisfactory performance. 21. B Continuous improvement is part of the perform quality assurance process.