ODOT Design & Construction Requirements for MSE Walls

Similar documents
MSE Walls Problems and Solutions

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 867 TEMPORARY WIRE FACED MECHANICALLY STABILIZED EARTH WALL.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 840 MECHANICALLY STABILIZED EARTH WALL. January 19, 2007

MagnumStone Specifications Gravity

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 840 MECHANICALLY STABILIZED EARTH WALL. July 18, 2014

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

SPECIFICATION FOR MAGNUMSTONE GEOGRID REINFORCED Mechanically Stabilized Earth (MSE) SYSTEM

SPECIFICATION FOR CORNERSTONE GEOGRID REINFORCED SEGMENTAL RETAINING WALL SYSTEM

ENGINEERING DIRECTIVE

SECTION SEGMENTAL CONCRETE UNIT MASONRY RETAINING WALL MAXIMUM HEIGHT OF 5-0 HIGH

Earth Retaining Structures and Systems Submittal Checklist. Part One: Materials and Material Properties

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

CHAPTER 11: WALLS.

Hydraulic Updates. History of 603/604

Chapter 3 - Excavation

SECTION CONCRETE SEGMENTAL RETAINING WALL SYSTEM

T-WALL.

207 TEMPORARY SEDIMENT AND EROSION CONTROLS

ANSWERS TO QUESTIONS RECEIVED THROUGH 1:00 PM ON MAY 24, 2018:

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Description. This work shall consist of furnishing materials and placement of modular block wall constructed in accordance with

Best Practices for Design and Construction of MSE Walls

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

Chapter 1 INTRODUCTION

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 9/17/18)

SECTION Segmental Concrete Unit Masonry Retaining Wall Height Over 5-0 High

Special Provision No. 599S22 March 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS)

PROPOSED SEGMENTAL RETAINING WALLS ARGONAUT RETAIL VILLAGE - PHASE I PENSACOLA, FLORIDA

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

Michigan State University Construction Standards SEGMENTAL CONCRETE RETAINING WALLS PAGE SECTION SEGMENTAL CONCRETE RETAINING WALLS

2.1 Backfill - General

SECTION SEGMENTAL RETAINING WALL

2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Designer Supplement: AS-2-15 Approach Slab Installation January 16, 2015

T-WALL Retaining Wall System

Reinforced Soil Slopes (RSS)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS

Uwall UNIVERSAL CONSTRUCTION MANUAL

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following:

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

SECTION CONCRETE SEGMENTAL RETAINING WALL SYSTEM

SECTION TRENCHING

Geotechnical Specification and Construction Update

Notes for Erection of Evergreen Maxi Wall Retaining Walls

SECTION CONCRETE SEGMENTAL RETAINING WALL SYSTEM BIG BLOCK / WETCAST

Section 401. PIPE CULVERTS

Final Estimates Level 2

DECEMBER 5, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $5,000,000) Bids

SECTION BUILDING EARTHWORK

SECTION CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CONSTRUCTION MANUAL 2.5 x 5 UNITS

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

LANDSCAPE RETAINING WALLS

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

Bureau of Materials Materials Approval Procedures

SECTION MECHANICALLY STABILIZED EARTH 1.01 SUMMARY

Tensar MesaTM Retaining Wall System Initial Report August Reporting on Work Plan 2001-S-9 Category ll Experimental Project

ATTACHMENT 50-1: PERFORMANCE AND MEASUREMENT TABLE

SECTION MECHANICALLY STABILIZED EARTH RETAINING WALLS

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CYPRESS Stone Geogrid Reinforced Retaining Wall Installation Specification SECTION CONCRETE SEGMENTAL RETAINING WALL PART 1 GENERAL

SECTION SPECIFICATION FOR MECHANICALLY STABILIZED EARTH TWO STAGE WALL SYSTEM

Maine Turnpike Authority

SECTION LIMESTONE SEGMENTAL RETAINING WALLS

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

T-WALL & STONE STRONG

Redi Rock Specification and Installation Manual

Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO

Inspector s Manual for Mechanically Stabilized Earth Walls

GEOSYTHETIC SLOPE SPEC-V0704rev.doc STANDARD SPECIAL PROVISION FOR GEOSYNTHETIC REINFORCED SLOPE CONSTRUCTION

REGIONAL CONSTRUCTION STANDARDS

StormPod Arch Installation Guide

Strengthened Soil Wall Construction Manual

Section G1. Design of Cast-In-Place Box Conduits

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

Draft. Not Yet Approved SECTION 10.1 GENERAL SCOPE DEFINITIONS

DIVISION 4100 SITEWORK

UNIFIED FACILITIES GUIDE SPECIFICATIONS

Table of Contents 5.1 GENERAL Overview Investigation and Engineering Information

CUYAHOGA COUNTY, OHIO ADDENDUM NUMBER 1, APRIL 25, 2018 FOR THE CITY OF BRECKSVILLE,

SPECIAL SPECIFICATION 4xxx Thermoplastic Pipe

SAMPLE CONSTRUCTION AND MATERIAL SPECIFICATIONS FOR THE ULTRABLOCK GRAVITY WALL SYSTEM

A.2.a Random Riprap... Table

MassBloc Permeable Instant Wall System

SECTION 303 CULVERTS

Wall Modular Block Mechanically Stabilized Earth, Item S.

HYDROLOGIC RESTORATION OF THE CASH CREEK BASIN IN TATE'S HELL STATE FOREST

CHAPTER 2. Restricted Residential ½ Street** Design Speed 25 MPH 25 MPH 25 MPH 25 MPH 40 MPH 50 MPH 55 MPH

Anchorplex retaining wall construction guide

FEBRUARY 13, 2019 AT 2:00 P.M. (EASTERN) (Estimated Cost: $9,000,000.00) Bids. Kokosing Construction Company, Inc. $8,623,609.96

CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO

Monumental Blok. Pallet Overview. Compatible caps. Notes. code 3521 (a) 3522 (b) 3523 (c) texture Chiseled. Specifications per pallet.

Gravity Wall. A force to be reckoned with... Gravity (SRW) segmental retaining wall systems are structures

Transcription:

ODOT Design & Construction Requirements for MSE Walls Peter Narsavage, P.E. Foundation Engineering Coordinator Ohio Department of Transportation Office of Structural Engineering 2006 Ohio Transportation Engineering Conference

A brief history ODOT has used MSE walls since the 1980 s. In 2004, responsibility for MSE wall construction was assigned to State Construction Geotechnical Engineer. Through 2004 and 2005, problems with MSE wall construction were investigated by OCA and OSE. Slide 2

A brief history OSE started preliminary development of a long-term MSE wall inspection program. ODOT begins to develop a new supplemental specification for MSE walls. Roundtable with contractors and suppliers scheduled for December, 20, 2005. Slide 3

A brief history December 7, 2005, District 6 shut down a three-lane collector-distributor road along I-270 in northeast Columbus because of an MSE wall problem. Drainage appears to be the cause. December 20, 2005, ODOT began a preliminary inspection program of all MSE walls built by ODOT. Inspections are completed within a month. Slide 4

Problems Sand leaking from joints Settlement of panels Uncontrolled drainage Deteriorating panels Slide 5

Sand leaking from slip joint Slide 6

Sand pile under vertical joint Slide 7

Settlement of panels Slide 8

Erosion along MSE wall Slide 9

Void beneath slab Joint separation Slide 10

Final resting place of MSE wall fill Slide 11

Another bridge with erosion along MSE wall

Water probably flowed through horizontal joint Slide 13

Deteriorating panel Slide 14

More deteriorating panels Slide 15

Preliminary inspection program Districts inspected each MSE wall. Completed inspections by Jan 20, 2006 339 Walls 30 percent have sand leaking from joints 32 percent have vegetation in joints 19 percent have cracked panels 11 percent have bowed or bulging walls 13 percent have some erosion 9 percent have problems with drainage system Slide 16

Sealing joints Slide 17

MSE wall inspection program OSE will use the information from the preliminary inspections to develop an inspection program. The program will be similar to the bridge inspection program, in that it will include: An inventory An inspection cycle An inspection manual Training and inspector qualification Slide 18

Design changes for MSE walls Implemented in July 2006 revisions to BDM Preference for straight MSE wall alignments Abutments supported on spread footings only under certain conditions Consider drainage around MSE walls Avoid utilities through or underneath MSE walls Slide 19

Preference of wall geometry at bridges 1. Straight walls 2a. Walls turned back up to 45 degrees (change of wall alignment = 135 to 179 ) 2b. Walls turned back with large radius 3. Walls turned back at 46 to 90 degrees Do not use acute corners! Slide 20

Straight MSE wall Slide 21

MSE wall turned back 45 degrees Slide 22

MSE wall turned back with curve Slide 23

MSE wall turned back 90 degrees Slide 24

Avoid acute corners! Slide 25

Avoid acute corners and minimize obstructions Don t do this. Slide 26

Do you think this backfill is well compacted? Slide 27

Bridge abutments at MSE walls If MSE wall is on bedrock, use spread footings to support bridge abutment. If MSE wall is on soil, consider possible settlement of the MSE wall Use piles if the bridge is a continuous multi-span structure or if the bridge is constructed part width in phases. If the bridge is single-span and not constructed part width, either spread footings or piles may be used to support the bridge abutment. Slide 28

Bridge abutments at MSE walls For piling minimum of 3-6 from the back face of the facing panels to centerline of the front row pile Should avoid this situation Slide 29

Bridge abutments at MSE walls For spread footing minimum of 3 from the back face of the facing panels to the front face of the footing and minimum of 5 from back face to centerline of bearings Slide 30

Drainage around MSE walls Control of roadway drainage is critical around MSE walls. The major problems with MSE walls have been related to the loss of drainage control. Provide barrier with a catch basin to collect the drainage. Locate catch basin 25 past the limit of the MSE wall soil reinforcement, where possible. Continue barrier 10 past catch basin. Use a minimum 30 approach slab for structures with MSE walls at the abutments. Slide 31

Utilities and MSE walls Avoid utilities through or underneath MSE walls. When it can t be avoided, encase the utility in a protective conduit that extends 10 beyond the limits of the select granular backfill. Pipe culverts through MSE walls should be avoided. Water and sewer lines within 10 of an MSE wall shall also be encased. X Slide 32

Other new MSE wall requirements Obstructions, such as piles, utilities, catch basins, etc. need to be shown on the plan, elevation, and typical sections for the MSE wall drawings. 45 degree slope of Select Granular Backfill 1 undercut with geotextile fabric and Item 203, Granular Material, Type C Bottom 3 of SGB meets gradation requirements for Item 304 Slide 33

Other new MSE wall requirements Select Granular Backfill 45 º Slope Retained soil 3 SGB, Item 304 Geotextile Fabric 1 Item 203, Granular Material Type C Slide 34

Undercuts No separate undercut and backfill pay item If undercut beyond the standard 1 is required Show undercut as additional wall excavation. Backfill with Item 203, Granular Material, Type C or D. Geotextile fabric for foundation preparation remains 1 below the bottom of the leveling pad. Slide 35

Undercuts Select Granular Backfill 1 Granular Material included with Foundation Preparation. Geotextile Fabric 3 SGB, Item 304 Item 203 Granular Material, Type C Additional Granular Material requires Item 203 pay item. Slide 36

Supplemental Specification 840 Approved July 2006 One specification that covers all accredited MSE wall systems for permanent MSE walls Added definitions Added material requirements Adjusted tolerances on facing panels and wall construction Greatly expanded construction section Created separate pay items for wall components Slide 37

SS 840 Definitions Defines and standardizes terminology MSE Wall System Soil Reinforcement Facing Panels Connection Device MSE Wall System Supplier Accredited MSE Wall System Precaster Slide 38

SS 840 Material requirements For the joint cover, require A woven, monofilament geotextile 90% UV stability after 500 hours Minimum width of 24 inches For Select Granular Backfill, require direct shear testing on material passing No. 10 sieve. φ 34º For foundation preparation, require a woven monofilament geotextile at the base of the undercut Slide 39

SS 840 Facing panels Precaster must be certified in accordance with Supplement 1073 Slide 40

SS 840 Facing panels Maximum panel size is 5 x 5 feet Gives sizes of chips or spalls, and width of cracks that are cause for panel rejection Slide 41

SS 840 Construction Increased from 2 to 8 pages. Preconstruction meeting is required. Foundation Preparation Compaction testing of foundation required. Department reviews foundation to verify bearing capacity. Usually performed by geotechnical consultant under consultant services. After acceptance, geotextile and 1 of granular material placed and compacted. Slide 42

SS 840 Construction Leveling pad is 6 x 24 Leveling pad must be within 1/8 of elevation and cannot vary more than 1/8 in 10. Facing panels cannot extend more than 6 beyond the end of the leveling pad at steps. Slide 43

SS 840 Construction Extensive wall erection details, such as Limit on shim size to start first row of panels Panels can t extend past the leveling pad transversely. Joints must be between ½ to 1 wide. Joint cover fabric must not be exposed. Excavation in front of the wall must be backfilled as soon as possible. Vertical and horizontal tolerances checked repeatedly. Slide 44

Flashlight test to see if joint cover fabric is exposed Slide 45

SS 840 Construction SGB placed and compacted in a manner that places the soil reinforcement in tension. Each 8 lift of SGB placed by starting 3 from facing panels and moving away from panels The lift compacted in same manner. Slide 46

SS 840 Construction SGB within 3 of facing panel is then placed and compacted. The compaction of each lift is tested. The compaction of every fifth lift is checked by ODOT. Slide 47

SS 840 Construction Concrete Sealing Exterior surfaces sealed with epoxyurethane sealer according to CMS 512. Do not damage joint cover fabric when preparing surface. On-site assistance from supplier is required. Designer Note recommends 5 days for projects with less than 4 walls. Slide 48

SS 840 New pay items Mechanically Stabilized Earth Wall Wall Excavation Foundation Preparation Select Granular Backfill Porous Backfill with Filter Fabric Drainage Pipe Concrete Coping On-Site Assistance SGB Inspection and Compaction Testing SF CY SY CY CY FT FT Days Lump Sum Slide 49

Additional MSE wall pay items 203 Items Embankment Granular Material, Types B, C, and D Included with wall quantities Item 503, Cofferdams, Cribs, and Sheeting Generally only for walls not at bridges, since the bridge plans will usually already include this item. Slide 50

Implementation of SS 840 ODOT is implementing SS 840 on all projects not already awarded, either by revising plans or preparing addenda. If retrofitting plans to fit SS 840, some changes are not required 45 degree slope for SGB is not required, since this will affect the limits for wall quantities. Do not need to move piling or footing, since this will extend bridge. Slide 51