Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619

Similar documents
Field Accuracy of Temperature Measurements in TAB Work Andrew P. Nolfo, PE

SECTION AIR TERMINAL UNITS

B. ASHRAE 1991 HVAC Applications Handbook: Chapter 34--Testing, Adjusting and Balancing.

Commissioning Case Study: University of Iowa s Bowen Science Building HVAC Modernization Project Course Number: CXENERGY1630

RETRO-COMMISSIONING: AN OWNER S LOOK AT THE TRUE COSTS AND RETURN ON INVESTMENT. Adam Renzi, PE

NEBBinar: Managing Building Performance through Commissioning. March 28, 2013

THE IMPORTANCE OF EQUIPMENT ACCESSIBILITY IN BUILDINGS

Karl Helmink, P.E., CEM Retrocommissioning Manager University of Illinois. Retrocommissioning Saving the Planet One Building at a Time

1.02 Related Sections A. Section Heating, Ventilation and Air Conditioning (HVAC). C. Section Pneumatic and Electric Control HVAC.

NEBBinar: Technical Commissioning: The most effective commissioning process for new buildings. March 5, 2014

Preparing a Cx Plan. Technical vs. Process Commissioning TECHNICAL FEATURE

Teague Research Center

Factor. For a building owner concerned with operating costs, the clear- How it Affects Operating Cost

2008 Questions & Solutions Engineering, Inc.

Performance Monitoring for Efficiency

Building Codes for Energy Efficiency and Cx. Randall Higa Codes and Standards Program Manager Southern California Edison

SECTION TESTING, ADJUSTING, AND BALANCING FOR HVAC. B. Testing, adjustment, and balancing of refrigerating systems.

Seminar 4 Energy Performance of Active Chilled Beam Installations

2. The requirements of Sections 502, 503, 504 and 505. In addition, commercial buildings shall comply with either Section 506.2, or

Existing Building Cx: Processes & Results A Cultural Journey. Barry Abramson Senior Vice President Servidyne

Retro-Commissioning for Existing Facilities

A. The purpose of this section is to specify Division 23 responsibilities in the commissioning process.

SECTION AIR DISTRIBUTION

SECTION TESTING, ADJUSTING AND BALANCING (TAB) OF HEATING, VENTILATING & AIR CONDITIONING (HVAC) SYSTEMS

Energy Efficiency in Building Active Design Part II

Reducing Hospital Energy Use and Maintaining Savings. Glen Anderson, PE

Converting CAV to VAV in Florida: What does this really mean?

Georgetown University New Science Center

FACILITIES MANAGEMENT

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

Energy Modeling Tools Solutions for Creating an Intelligent Building

LEED Commissioning and Actual Energy Use. John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering

GATES-HILLMAN CENTERS

Commissioning Lighting Control Systems

Commissioning & Retro-Commissioning Meet Energy Code

HVAC SYSTEM SCHEMATIC DESIGN

Banyan Air Service November 18, 2011 AVE Aviation and Commerce Center Building 1 Miami, FL

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.

Building Envelope Commissioning and Building Diagnostic Test: Case Studies Course Number: CXENERGY1506

Commissioning at NYP. Joseph Lorino, PE, LEED Corporate Director April 1, 2014

Retrocommissioning Investigation Report

Owner/Operator Involvement in Cx Cx to Facilitate Owner Training & Turnover. Kent Barber, PE Managing Principal KBA

Chilled Beams. The new system of choice?

Monitoring-Based Commissioning: A Case Study in Higher Education. Janelle H. Griffin, PE, CCP, LEED AP

The baseline building system for compliance with Senate Bill 668 is defined by Appendix G,

Smart Labs: Building Next Generation Labs While Maintaining Safety and Comfort

Fundamentals of Acoustics

Using System Curves to Avoid Problems in VAV Systems

County of Yolo Development Services Building Inspection Division

HVAC SYSTEM DESIGN PROCESS

Textile Air Dispersion Systems

Capital Projects Group Testing, Adjusting and Balancing Specification

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/06/2013 BUILDING SURVEY DATE

Underf loor For Schools

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

MODULE #6 COMMISSIONING, VALIDATION, CERTIFICATIONS

PARK PLACE CASE STUDY VANCOUVER. Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68%

Variable Air Volume (VAV) For Laboratories

HVAC SYSTEM DESIGN PROCESS

Not Just a Lot of Hot Air!

PROJECT TITLE PROJECT NO.: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

Grunenwald Science and Technology Building

CONTINUOUS COMMISSIONING OF SALT LAKE COMMUNITY COLLEGE SOUTH CITY CAMPUS

ARE YOU READY TO OPERATE? Designing ORs to meet new technological advancements

Commissioning: The Most Important Component of LEED. Rick Miller, PE, LEED AP. RNM Engineering, Inc. San Luis Obispo, CA

How LEED & The Retro-Commissioning Credits Produce Energy Savings. James Vallort Vice President Environmental Systems Design, Inc.

Optimizing Energy Use in a HealthCare Setting. Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning

Energy Efficiency Opportunities in the OR

Strategies for Persistence: Measurement and Verification. Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions

Absolute Energy Raters Commissioning Plan Outline Template

Engineering Update JANUARY VOLUME 9 THIS PACKAGE INCLUDES A COLLECTION OF ARTICLES FROM VOLUME 9 OF THE JANUARY 2013 ENGINEERING UPDATE.

Persistence Tracking in a Retro-commissioning Program

Sound & Vibration Commissioning STUART MCGREGOR, PE ENGINEERING DYNAMICS, INC.

Bid Package 15A Mechanical

Next Connecticut Energy Code

MBCx: The Next Wave of Energy Savings in Utility Incentive Programs

Interdisciplinary Science and Engineering Building

Interdisciplinary Science and Engineering Building

Mechanical Product Overview

Capital Projects Group Air Terminal Units Specification

COMcheck Software Version Envelope Compliance Certificate

Executive Summary. Sample Company. BETA Engineers, P.C. 36 W. Main Street Mechanicsburg, PA PHONE: FAX:

AVOIDING 2015 MINNESOTA ENERGY CODE VIOLATIONS

COMMERCIAL LOAD ESTIMATING. Load Estimating Level 3: Block and Zone Loads. Technical Development Program

St. Monica Food Pantry Testing, Adjusting, & Balancing for HVAC sys-tek No

Sustainability and Energy Use

Janice Reedus, Director of Business & Auxiliary Services Campus Center Building A, Room Houbolt Road Joliet, IL 60431

Codes, Standards & Guidelines, Oh My! Michael Chelednik, AIA Sr. Airport Terminal Architect URS

What Contractors Need to Know about LEED Commissioning & IAQ Management

What s My Baseline? ASHRAE

DUKE UNIVERSITY CONSTRUCTION STANDARDS

Retro-Commissioning in Hospitals

AIR FLOW HOOD TACHOMETERS

Implementing Low-Cost Energy Savings Projects & Conducting Energy Audits

Modular Active Chilled Beams

A. All drawings and general provisions of the contract, including all other Division 01 and general and supplementary conditions.

Capital Projects Group Mechanical Work Commissioning Specification

WELD COUNTY SOUTHWEST BUILDING HVAC EVALUATION 4209 COUNTY ROAD 24 ½, FIRESTONE, COLORADO August 4, 2017

Promulgation Details for 1 RCNY

The Ed Roberts Campus

Transcription:

AABC Commissioning Group AIA Provider Number 50111116 Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 Jim Hall, PE, TBE, CxA Systems Management & Balancing, Inc. April 13, 2016

Credit(s) earned on completion of this course will be reported to AIA CES for AIA members. Certificates of Completion for both AIA members and non-aia members are available upon request. This course is registered with AIA CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

Copyright Materials This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation without written permission of the speaker is prohibited. Systems Management & Balancing, Inc. 2012

Course Description This practical information-packed session explains many of the key test and balance issues from precise specifications, to duct leakage testing, to pump- and fan-curve considerations that if properly addressed in cooperation with an independent TAB firm can ensure that any project goes smoothly.

Learning Objectives At the end of the this course, participants will be able to: 1. Understand the proper use, application, and limitations of the TAB instrumentation. 2. Understand what is accurate, useful and meaningful data that is obtained in the field vs. laboratory data for use on their project. 3. Gain an understanding of HVAC systems and the TAB/measurement process; how can systems be set up to allow for proper data collection. 4. Promote a project team approach to address schedule challenges, design alternatives as it relates to balancing device locations, equipment usage and HVAC system operation.

Learning Laboratories The TAB Agency is fortunate.every project is a potential Learning Laboratory Lessons learned need to be shared

Specification Challenges One of the most beneficial and productive parts of the Cx process is a specification and drawing review. Utilize common sense; what is the goal or intent? Review system functionality; Are balancing dampers & valves strategically placed? Is there proper access to equipment/systems? If the CxA is utilizing the project specifications to establish PFC s and FPT s make sure they are applicable. (Who performs their own PFC s?)

Specification Challenges: TAB Data Understand what is meaningful data. Just because the specification calls for a measurement, that does not mean it is relevant or useful. For example; Wet-bulb temperatures a single point measurement is not extremely accurate and a steady state load needs to be introduced. Is this data really needed? Will this data provide a benefit to the owner? The coil should be ARI certified. Try to think of how data will be obtained and what data will be required before requesting the data: Will the requested data be accurate, repeatable and meaningful?

Specification Challenges: Measurement Tolerances Avoid ±5% or 0% to +10% tolerances Adds cost, but not necessarily value. May not be feasible, depending on the system and its components. 0% to +10%; Is this realistic for how the system operates? Reserve tight tolerances for special applications, not comfort cooling/heating. Keep in mind, that in Labs and ORs, the main criteria for airflow is ACH and room pressurization. Typically the room envelope dictates the amount of airflow required to maintain proper pressurization. The TAB equipment manufacturer s tolerances sometimes are greater than the specification tolerances.

Specification Challenges Calibration of TAB instrumentation per manufacturer s recommendations. (As a note, most require calibration every 2 years.)

Specification Challenges: Marking Damper Positions Verify that all balancing damper handles are exposed and visible on externally insulated ductwork. Marking the external duct insulation is not accurate/helpful.

Specification Challenges: Marking Valve Positions If valve handles required to be marked, make sure the specified and installed valve has provisions for marking. Recording the valve position in the TAB report should suffice in most situations.

Specification Challenges: Insulation Requirements Make sure damper handles are exposed on externally wrapped ductwork Utilize test port extensions on balancing valves and all test ports

Specification Challenges: Controls Make sure that access to the control system is made available to the TAB agency and CxA. This includes any required hardware and software. This seems to be a regional issue, not a manufacturer s issue.

Specification Challenges: Seasonal Testing Make sure that the Seasonal Testing required is affected by the season. Utilize the DDC system for trending data. Typically airflows and water flows are tested at maximum flow conditions and the season does not affect the test data.

Specification Challenges: Sheaves Sheave changes are NOT automatically the responsibility of the mechanical contractor or TAB agency. It is difficult to define who is responsible -- Manufacturer, contractor, engineer? How many are required? At bid time, sheaves are an unknown cost and unknown quantity. Sheave changes for fans should be included as an allowance in the project or handled as a cost plus change order.

Specification Challenges: Domestic Water Systems Plumbing pumps, fire pumps, steam condensate pumps: Typically cannot be accurately tested without a constant, established water flow.

Specification Challenges: Domestic Water Systems Domestic Hot Water Recirculation System A non-invasive procedure is recommended. A balancing valve is still required to allow for proportioning of the domestic hot water recirculation system. Consider installing temperature sensors on the domestic hot water recirculation loop that can report the temperatures to the DDC system.

Project Document Challenges Help promote identifying each piece of equipment (fans, AHUs, HPs, VAVs, etc.) with a unique tag.

Airflow Measurement & The Flow Hood The flow hood is a proportioning device. Know the limitations of the flow hood and how it should be used.

Airflow Measurement & The Flow Hood Flow Hood Measurement

Airflow Measurement & Fan Curves Fan curves AMCA Tested Produced under laboratory conditions Free inlet Straight discharge Ideal traverse plane Multiple speeds-extrapolated data Standard temperature & pressure (STP) Normal manufacturing tolerances Know the limitations of fan curves

Airflow Measurement & Fan Curves ASHRAE Journal Article, November 2005

Airflow Measurement: Traverse Locations & Alternatives The preferred airflow measurement method is a duct traverse. Ideal traverse plane: For round duct, AABC, AMCA & ASHRAE all identify the ideal traverse plane as 2 ½ diameters from condition (discharge, elbow, etc.) for up to 2500 fpm. Add 1 diameter for each additional 100 fpm. For rectangular duct, E L = (4a*b/π) 0.5, where a & b are the duct dimensions.

Example: Airflow Measurement: Traverse Locations & Alternatives 10,000 cfm, 30 x 20 duct, 2400 fpm E L = (4a*b/π) 0.5 =27.6 2 ½ * 27.6 = 69.1 69.1 (~ 6 ) straight duct required Alternatives to Traverse (if a traverse is not possible): Face velocity reading of filters, coils, etc. Summation of airflows at individual outlets Summation of calibrated VAV boxes as read at the DDC computer

Airflow Measurement: Equipment Considerations Can outdoor air be measured to AHU? Is there enough ductwork for a proper traverse? Does unit configuration allow for proper measurement? Roof Top Units Can outdoor airflow be measured? Static pressure profile of RTU is not practical unless factory ports are installed.

Supply Grills & Airflow Never rely on face dampers for air balancing. Face dampers add static to a system, but do not help divert airflow in the system Sometimes go closed or open due to system pressure Can be noisy, the occupant can adjust, & they get dirty on exhaust systems

Airflow Measurement: Airflow Monitoring Stations Requires calibration and maintenance Requires filtered air Will the AFMS work properly in the installed location? Is the velocity profile acceptable? Will the AFMS work at minimum airflow, but function improperly at maximum airflow or vice-versa? Will the control damper create turbulence and measurement issues?

Design Requirements: 800 gpm @ 68 9 Impeller, 20 hp motor, 5BC,1750 rpm (Point 1) Field Measurements: Shutoff ΔP = 73 (Point 2) Operating ΔP = 70.0 Results: Actual: 700 gpm w/9 imp 12.5% below design Flat Pump Curve Hard to interpolate. Utilize measured flows at terminals or branches to determine pump total. Water Flow Measurement: Pump Curves

Water Flow Measurement: Pump Curves Design Requirements: 800 gpm@ 68 10-3/8 Impeller, 20 hp motor, 4E, 1750 rpm Field Measurements: Shutoff ΔP = 104 Operating ΔP = 72 Results: Actual: 775 gpm w/10-3/8 imp 3.1% below design Steep Pump Curve Immediate Resolution.

Pump Flow Measurement Provide test ports/pump taps at the pumps (Extend outside of insulation). Provide a flow measuring device at the pump Fixed orifice type device preferred, use Multi- Purpose Valves with caution.

Water Flow Measuring Stations: Sizing Flow measuring stations need to be sized to allow for a measurable and useful pressure drop. Sized for water flow quantity and not pipe size The use of Multi-Purpose Valves for total pump flow measurement is typically not accurate Typically sized line size and not for flow quantity (oversized) Location is not ideal, need 5 pipe diameters before and after the valve.

Water Flow Measuring Stations: Strainer Effect ¾ Balancing Valve 50% Open ¾ Balancing Valve 25% Open

Water Flow Measuring Stations: Strainer Effect

Water Flow Measurement: Automatic Flow Limiting Devices These devices do not eliminate water balancing. Ideal for fan coil units, unit ventilators, heat pumps, VAV reheat coils and areas where access to valves is limited (actual pressure readings might not be obtained for each autoflow). Factory-installed piping kits frequently do not provide access to the ports!!!

Water Flow Measurement: Factory-Piped Balancing Valves

Water Flow Measurement: AFLD Installation

Access Challenges Proper clearance and access must be provided to all dampers, valves, equipment, etc. Sheetrock ceilings, architectural features, etc. Locate devices in the corridors outside of OR s, classrooms, etc. Access to outlets, dampers, etc. in theatre type seating areas. How will this be accomplished? AHU is typically not in operation when scaffolding is installed.

Scheduling Challenges There needs to be enough time allowed in the schedule for the TAB & Cx work to be completed. All work must be complete for TAB work to commence. Clean air filters installed. All strainers cleaned and start-up strainers removed. All balancing dampers installed and 100% open. All manual balancing valves and flow measuring stations installed and 100% open. Temperature Controls complete and functional.

Scheduling Challenges Remember that TAB work is completed by system, not by area. Very seldom does the HVAC system match the Phasing or Scheduled Areas. Make sure that the Owner & Architect understand the possibility that the TAB work might be performed after occupancy. Variable volume systems (air and water) can have provisions to balance partial HVAC systems. Constant volume systems can pose major complications if they overlap several areas/phases. Hydronic systems need to be carefully considered for scheduling issues.

TAB Reports Typically a final TAB report is NOT available at time of commencement of the Cx FPT s. Have an experienced, responsible engineer review the report. It is not just about matching numbers. It is reviewing system performance and employing engineering judgment. Don t hesitate to call the TAB agency to review the report together or ask questions. Keep in mind that there is no benefit to the TAB Agency (owner s benefit) to report problems or deficiencies, it is a responsibility. Be cautious of the pristine TAB report.

This concludes The American Institute of Architects Continuing Education Systems Course Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619 Jim Hall, PE, TBE, CxA Systems Management & Balancing, Inc. 925 SE Olson Drive Waukee, IA 50263 515-987-2825