the power is in our hands

Similar documents
Lower Churchill Project

1. the Infeed Option which is the Muskrat Falls Generating Station and Labrador-Island Link HVdc project; and 2. the Isolated Island Option.

Questions and Answers Electricity Demand and Supply in NL

PLANNING FOR TODAY, TOMORROW, AND THE FUTURE. P. 1

Independent Supply Decision Review

CIMFP Exhibit P Page 1 Commission of Inquiry Respecting the Muskrat Falls Project. Muskrat Falls Project Timeline

Questions and Answers Contracts and Procurement Process for the Muskrat Falls Project

Report on Two Generation Expansion Alternatives for the Island Interconnected Electrical System

4 Transmission Planning Criteria, AC Integration Studies, and NERC Standards

Muskrat Falls Project Update. June 23, 2017

Maritime Link Appendix 5.01 Page 1 of 84. Review of the Muskrat Falls and Labrador Island HVdc Link and the Isolated Island Options

HOLYROOD THERMAL GENERATING STATION REQUIREMENTS 2011 TO 2020

Attachment 2 mentions the retirement of the Holyrood Thermal Generating Station

Our Energy Resources: What s the Plan? Andy Fisher Faculty of Engineering January 2009

Making Best Use of the Lower Churchill:

Lower Churchill Project Gilbert Bennett, Vice President St. John s Board of Trade - May 22, 2013

NOVEMBER 5, International Conference on Ocean Energy

Environmental Management on a Mega Project. NewLEEF Oct

NALCOR ENERGY. Comments on Draft Request for Proposals for Clean Energy and Transmission

Newfoundland and Labrador Board of Commissioners of Public Utilities. Muskrat Falls Review. Public Presentation. Winston Adams

The Project. Federal Regulatory Approvals and Involvement

Electricity Demand Forecast: Do We Need the Power? NOVEMBER 2012

CA NLH NLH General Rate Application Page 1 of 3

Overview of the Environmental Management System for HVac/HVdc Transmission Line Construction Lower Churchill Power Project.

Update on Muskrat Falls Project Community Liaison Committee March 25, 2014

Holyrood Condition Assessment Technical Conference October 13, 2011

Review of BC Hydro s Alternatives Assessment Methodology

Muskrat Falls Project Independent Engineer Report & Project Overview April 15, 2014

Ms. Cheryl Blundon Director Corporate Services & Board Secretary

Analysis of Proposed Development of the Maritime Link and Associated Energy from Muskrat Falls Relative to Alternatives

Lower Churchill Project. NEIA AGM March 18, 2014

FutureMetrics LLC 8 Airport Road Bethel, ME 04217, USA

2018 Integrated Resource Plan Executive Summary

5 Muskrat Falls Project

Atlantic Link: An Update. June 6, 2017

Muskrat Falls Opportunities to Reduce Risk and Enhance Benefits

Labrador-Island Transmission Link

Muskrat Falls Projects

The Manitoba Hydro-Electric Board

The Lower Churchill Project

Regulatory Issues and Smart Grid Transmission Solutions

REQUESTS FOR INFORMATION THE NEWFOUNDLAND AND LABRADOR PUBLIC UTILITIES BOARD. GRK-NLH-1 to GRK-NLH-52

The Hydro Province. *Manitoba Hydro is the licensee of the Trademark and Official Mark.

Government FISCAL PLAN CLIMATE LEADERSHIP PLAN

2 Hydrology Studies. 2.1 Introduction

July 15, 2016 Director Corporate Services & Board Secretary

The New England Clean Power Link A powerful wind and hydro partnership for Massachusetts

Terasen Gas (Vancouver Island) Inc. Evidence In Response to VIEC CPCN Application for the VIGP

Wind-Hydrogen-Diesel Energy Project. Greg Jones Manager, Business Development September 15, 2010

Director Corporate Services & Board Secretary

LOWER CHURCHILL PROJECT COST ESTIMATE PROGRESSSION 1998 TO 2011

LONG-TERM SOLUTIONS FOR NEW YORK S CLEAN ENERGY FUTURE

at BC Hydro Presentation to PNUCC Randy Reimann, Director of Energy Planning

Research Projects as of March 27, 2018

Economic Impact Analysis of Iron Ore Mining Industry in Labrador

Electricity Power System Planning

Ministerial Statement To The House of Assembly. Dr. The Hon. E. Grant Gibbons, JP, MP Minister of Economic Development

Performance of Hydro's Generating Units.

Director Corporate Services & Board Secretary

TasNetworks Transformation Roadmap 2025

A summary Yukon Energy s 2016 Resource Plan

hydro November 15, 2018

2030 Power System Study Report to the New England Governors 2009 Economic Study: Scenario Analysis of Renewable Resource Development

ISO New England Overview and Regional Update

New England States Committee on Electricity

The Optimal Approach to Firming Windpower

2016 Integrated Resource Plan Executive Summary

Labrador-Island Transmission Link

Emera Investor Presentation. November 2008

Our symbol is an energy wave.

Director Corporate Services & Board Secretary

[R]enewables 24/7 EXECUTIVE SUMMARY

Integrated Resource Plan NOVEMBER EXECUTIVE SUMMARY

Planning the Interconnection of Islands to the Mainland Grid via Submarine Cables

APPENDIX 9.2 Description of SPLASH Model

Connecting New Generation in New Zealand. Len Gould Customer Services Manager Transpower New Zealand Ltd

2005 Integrated Electricity Plan

Briefing paper Mini Grids

NEWFOUNDLAND AND LABRADOR HYDRO

Muskrat Falls Project

AEA - Kodiak Electric Association Terror Lake Hydroelectric Facility Expansion

BC HYDRO S LONG-TERM PLAN PRESENTATION TO THE COLUMBIA BASIN REGIONAL ADVISORY COMMITTEE

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

Nation-building in the 21st Century: The Case for the Lower Churchill Hydro Development

WATER AND WIND QUÉBEC S CLEAN, RENEWABLE ENERGY RESOURCES

Ontario s Energy Action Plan

PUB NLH 600 Island Interconnected System Supply Issues and Power Outages Page 1 of 5

Newfoundland Power Inc. Energy Plan Submission February 28, 2006

BC HYDRO DRAFT INTEGRATED RESOURCE PLAN 2012

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid

Lines of Communication. Our New Approach to Consultation - Have Your Say

Greenhouse Gases and Water Use Planning

12/05/2016. Future Transmission Grids. Peter Vaessen. MSc in High Voltage and Power Engineering

BRIEFING TO THE INCOMING MINISTER

SRP RESOURCES AND STEWARDSHIP FOR A SUSTAINABLE FUTURE FISCAL YEAR 2010

Yukon Electricity Conservation and Demand Management Potential Review (CPR 2011)

Yukon Electricity Conservation and Demand Management Potential Review (CPR 2011)

CHAPTER 3: RESOURCE STRATEGY

Integrated Resource Plan

Carbon Pricing Plan. Prince Edward Island submission to Environment and Climate Change Canada on Carbon Pricing

Transcription:

the power is in our hands Financial Analysis of the Options MHI performed a number of sensitivities or stress tests on Muskrat Falls, including changes in fuel prices, capital costs, interest rates and the potential for carbon pricing. After reviewing these potential changes and the impact on the overall costs, MHI concluded that Muskrat Falls is still the preferred option. MHI concluded: The results of the CPW review indicate a strong preference in favour of the Interconnected Island (Muskrat Falls) option over the Isolated Island (Holyrood) option. The result of the CPW analysis indicates a preference for the Interconnected Island (Muskrat Falls) option of $2.4 billion over the Isolated Island (Holyrood) option. With the assumptions and inputs provided by Nalcor to MHI, the Interconnected Island (Muskrat Falls) option remains the least cost option to meet the needs for capacity and energy to supply the forecasted load in Newfoundland and Labrador until 2067. Also, any uncommitted energy from Muskrat Falls would allow Nalcor to more easily address any large future load additions to the Island of Newfoundland or Labrador. A Cumulative Present Worth analysis was performed on each of the large scale wind development scenarios and compared against the existing Nalcor CPW metrics for the Muskrat Falls Interconnected and Isolated Island options. The wind and battery scenario is the most costly option, while the wind and thermal backup CT option is less, but is still more costly than the Isolated Island option. The CPW result table from this assessment is shown in Table 1. Table 1: Cumula ve Present Worth of Studied s About the Project MHI s Final Recommendation Given the analysis that MHI has conducted based on the data and reports provided by Nalcor, MHI recommends that Nalcor pursue the Interconnected Island (Muskrat Falls) Did You Know? Cumula ve Present Worth (Billions in 2012) CPW Cost Component Interconnected Isolated Island Fixed Charges Opera ng Costs Fuel Costs Backup CT Fuel Costs Power Purchases Total.32.26 $1.32 $6.47 $8.37 $2.56.75 $6.71 $10.78 Source: Review of the Wind Study for the Isolated Island of Newfoundland, MHI October 2012 Thermal Ba ery $7.27 $1.29.87 $1.67 $11.86 $14.61 $1.18.87 $17.43 Muskrat Falls means long-term stable electricity rates for generations. If we continue to rely on the Holyrood plant and significant amounts of oil to generate our electricity, consumers will pay higher rates for electricity. Muskrat Falls will not only meet our domestic energy needs, but be a revenue generator for our province long into the future. At peak production, the Holyrood plant burns approximately 18,000 barrels of oil each day to meet the electricity needs on the island. With Muskrat Falls, Newfoundland and Labrador will be powered by 98% clean, renewable energy and become a leader in carbon reduction standards. The development of Muskrat Falls will avoid approximately 96 million tonnes of emissions by 2065. During each year of construction, there will be an average of 1,500 jobs in the province across 70 occupations. There will be peak employment during construction of approximately 3,100 people. Through jobs and business contracts, Newfoundlanders and Labradorians will earn $1.9 billion from Muskrat Falls construction. Muskrat Falls will almost completely eliminate our reliance on oil and provide a clean, renewable energy source. The development of Muskrat Falls will set the stage for Newfoundland and Labrador to manage its own energy and economic future without relying on others to meet our power needs. Muskrat Falls option as the least cost alternative to meet future generation requirements to meet the expected electrical load in Newfoundland and Labrador. Muskrat Falls will transform our province from an economy dependent on non-renewable resources to an economy built on renewable, sustainable energy resources. Project construction will generate approximately $290 million in tax revenues for the provincial government. Approximately $500 million in income to business and labour will be earned by Labradorians and Labradorbased businesses. Learn more about Muskrat Falls web: phone: e-mail: twitter: www.powerinourhands.ca 1-888-576-5454 info@powerinourhands.ca twitter.com/mffacts The demand for electricity in Newfoundland and Labrador is increasing. Our economy is growing and residential and business electricity use continues to rise steadily. The development of Muskrat Falls on the lower Churchill River in Labrador has been proposed as the best option for meeting the province s future power needs and providing homes and businesses with stable, affordable electricity rates into the future. Churchill Falls* The Muskrat Falls project will consist of: A generating facility, consisting of two dams and a powerhouse that will generate 824 megawatts of clean, renewable electricity. A 1,100 km transmission line from Muskrat Falls in Labrador to Soldiers Pond on the Avalon Peninsula. A 35 km subsea cable crossing the Strait of Belle Isle from Forteau Point in Labrador to Shoal Cove on the island. A 180 km subsea Maritime Transmission Link connecting Newfoundland and Labrador in a new way to markets in North America. Granite Canal* House of Assembly Debate The Government of Newfoundland and Labrador is seeking to hold a special debate in the House of Assembly this fall on its proposal to develop Muskrat Falls. Government believes it is important to provide you as citizens, and your elected representatives, with the opportunity to be fully engaged and learn more about Muskrat Falls before the province makes the final decision on whether or not to proceed with this development. project and the reasons Nalcor Energy has concluded that Muskrat Falls is the lowest-cost option for meeting our energy needs. This fact sheet contains a description of the proposed development as well as a summary of key information from the recent independent review of the project by Manitoba Hydro International. Government is providing this information to every household in Newfoundland and Labrador. Our aim is to help you understand the This is our province s opportunity to have an open and informed discussion about our energy future and the merits of Muskrat Falls. Government s commitment to the people of our province is that the decision we make at the end of the day will be one that is truly in the best interest of Newfoundlanders and Labradorians. It is the government s intention to debate this project the way the Voisey s Bay project was debated a decade ago. The main difference is that, in this case, we hired independent, world-renowned experts to put our own analysis to the test.

Independent Reviews Nalcor is our province s energy corporation, owned by the people of Newfoundland and Labrador. Nalcor is responsible for forecasting our province s energy needs and finding the lowest-cost means of meeting those needs. In November 2010, Nalcor determined that Newfoundland and Labrador will need a new source of electricity generation to meet the growing needs of the province s homes and businesses. Nalcor s initial review of the alternatives indicated that developing Muskrat Falls would be the lowest-cost option to meet the growing demand. Nalcor recommended the commissioning of the detailed engineering and financial analyses required to confirm if that were the case. Government then directed Nalcor to move forward with these in-depth analyses in preparation to make a final decision. To protect the best interests of Newfoundlanders and Labradorians, government then took the additional step of subjecting all of Nalcor s work to an independent, thirdparty review by Manitoba Hydro International (MHI), a recognized global leader in hydro developments. MHI had already gained significant knowledge of Newfoundland and Labrador s energy situation and the Muskrat Falls proposal from a previous review it was hired to conduct for the Board of Commissioners of Public Utilities in July 2011. In undertaking its thorough review of Nalcor s work, MHI conducted technical and economic analyses of four scenarios: 1) an isolated island option, involving thermal generation of electricity at Holyrood, supplemented by small hydro, wind and other thermal. 2) a wind and thermal scenario, which is also an isolated island option, but with large-scale wind power supplemented by thermal generation. 3) a wind and battery scenario, which is also an isolated island option, but with batteries enabling large-scale wind power to replace some thermal generation. 4) an interconnected option, involving Muskrat Falls development. At the same time, government commissioned Ziff Energy to review the costs of a fifth option using natural gas to generate electricity. Ziff determined that this option was neither economical nor realistic. They concluded: the low and variable volumes of gas required to produce power at Holyrood would be a challenging economic barrier to securing long-term firm LNG (liquefied natural gas) supply (Newfoundland and Labrador LNG Viability and Analysis, Ziff Energy) due to the low annualized volumes of gas required for Island Power Generation and the high capital cost of developing and transporting Grand Banks Gas, the unit cost of the gas landed at the generation plant gate is uneconomic (Grand Banks Natural Gas as an Island Electric Generation Option, Ziff Energy) To conduct its review of the other four options, MHI assembled its own team of specialists with expertise in load forecasting, risk analysis, hydroelectric generation, High Voltage direct current (HVdc) transmission engineering, electricity system planning and financial analysis. MHI subjected the four scenarios to a Cumulative Present Worth (CPW) analysis, which is the global industry standard for comparing development alternatives. A CPW analysis compares the alternatives by weighing all future costs, including capital costs, operating and maintenance costs, fuel costs and power purchase agreements. The option that is shown to have the lowest CPW over the project life will have the lowest cost and is therefore the preferred option. That approach works when comparing energy options. For Muskrat Falls, adding capital costs to other costs over the life of the project enables you to calculate the CPW and compare it to the CPW for other options comparing apples to apples. In its review of the Muskrat Falls proposal, MHI also judged Nalcor s project management and execution practices, its general utility practices, and the degree of skill, care and due diligence Nalcor demonstrated in the work that it performed in advising the government on Muskrat Falls. And here is what they concluded: MHI has found Nalcor s work to be skilled, well-founded, and in accordance with industry practices. You can obtain a copy of MHI s technical analyses in full at www.powerinourhands.ca, by calling 1-888-576-5454, or by visiting Government Service Centres and public libraries.

MHI s Endorsement of Nalcor and Muskrat Falls In October 2012, Manitoba Hydro International issued its final analysis of Nalcor Energy, the Muskrat Falls proposal and other electricity generation options for Newfoundland and Labrador. This is what MHI has concluded: MHI has found Nalcor s work to be skilled, well-founded, and in accordance with industry practices. The result of the CPW analysis indicates a preference for the Interconnected Island (Muskrat Falls) option of $2.4 billion over the Isolated Island (Holyrood) option. Both options have increased substantially in cost due to escalation and scope change from prior estimates released in November 2010. But all things considered, the Muskrat Falls option continues to have the lower cost. MHI therefore supports Nalcor s finding that the Interconnected Island (Muskrat Falls) option is the least-cost option of the two. Below are brief explanations of some of MHI s detailed findings. 1) Isolated Island (Holyrood) option In reviewing the Isolated Island (Holyrood) option, MHI confirmed Nalcor s assessments and conclusions about the role of the Holyrood Thermal Generating Station, the use of wind farms, the deployment of turbines, and the use of small hydroelectric plants. Holyrood Thermal Generating Station: MHI found that actual vendor costs were included in the estimates and fuel prices were updated to reflect the 2012 estimates by PIRA, a global leader in setting energy price forecasts. The studies completed on the pollution control equipment and life extension were appropriate for Nalcor to use. Wind Farms: MHI has reviewed the costs associated with the fixed charges and operating expenses and find them reasonable as inputs into the CPW analysis Simple and Combined Cycle Combustion Turbines: MHI finds that the methodology used to develop revised estimates for CT and CCCT thermal generating plants were reasonable and reflects state of the art industry practices for a project at the Decision Gate 3 level. Small Hydro Plants: The revised costs for the small-hydro plants Island Pond and Portland Creek are suitable as an estimate for input into Decision Gate 3. The revised costs for Round Pond are a reasonable estimate suitable for input into Decision Gate 3. 2) Wind and Thermal option and 3) Wind and Battery option The Wind and Battery scenario is the most costly option, What is a Decision Gate? The decision gate process is the standard in many industrial sectors. A decision gate is simply a point in the process when everyone pauses to assess the progress to date before deciding whether to move forward to the next phase. Muskrat Falls is now at Decision Gate 3, the critical point when the judgment is made to proceed or not. while the Wind and Thermal option is a more reasonable cost, but is still more costly than the Muskrat Falls and thermal Isolated Island options. (Review of the Wind Study for the Isolated Island of Newfoundland, MHI, October 2012) Based on these screening level study findings and the risks inherent in such a massive wind development, MHI does not recommend that the wind options beyond a 10% penetration level be pursued at this time. The wind power scenarios do not provide the same value for the $11.86 or $17.43 billion costed over the study period. MHI finds that large-scale wind development, as a replacement for Holyrood Thermal Generating Station is not a least cost option and does not represent good utility practice at this time. (Review of the Wind Study for the Isolated Island of Newfoundland, MHI, October 2012) 4) Interconnected Island (Muskrat Falls) option In reviewing the Interconnected (Muskrat Falls) option, MHI confirmed Nalcor s assessments and conclusions regarding six different elements of the plan. Load forecasting is needed to determine how much power is required at peak times to meet the demand. MHI s report concludes: MHI finds that the Load Forecast for the Interconnected Island (Muskrat Falls) option is well founded and appropriate as an input into the Decision Gate 3 process. The Muskrat Falls project involves the use of AC (alternating current) and high-voltage DC (direct current) power at various points along the path, and conversion between the two. MHI assessed Nalcor s AC integration plan and made the following conclusions: The review of the (AC) integration studies related to the Interconnected Island option indicate that Nalcor is in compliance with good utility practices and that there is an opportunity during detailed design to optimize final configurations that may enhance system reliability.

Regarding HVdc Converter Stations, MHI concluded: An assessment of the technical work completed by Nalcor and its consultants on the HVdc converter stations, electrode lines, and associated station equipment showed the work was reasonable as an input to the Decision Gate 3 process. Regarding Transmission Systems, MHI concluded: Nalcor, as part of the detailed design post Decision Gate 3, is aware that increased reliability is needed in the Long Range Mountains and other regions in Labrador subject to extreme wind and icing conditions and has taken actions to upgrade portions of the line. Nalcor, from its own analysis of the climatic loading study and information acquired from experience in the region, has specified a transmission line design criteria that exceeds the ice loading requirements experienced in Newfoundland and Labrador over the past 50 years. MHI continues to support selecting a 1:150 year climatic return period due to the criticality of the HVdc transmission line to the Newfoundland/Labrador electrical system. Selecting a higher return period means planning to withstand a more-rare and more-extreme climatic event. The return period standard is a measure of reliability. A standard of 1:150 means you would only experience a weather event once in 150 years that would affect the reliability of the line. With respect to ice loads, the transmission system exceeds the recommended 1:150 standard for reliability. In MHI s opinion, Nalcor has undertaken a diligent and appropriate approach to design the transmission line to withstand the many unique and severe climatic loading regions along its line length. Regarding the Strait of Belle Isle Crossing, MHI found that Nalcor s concept design definition and concept for the Straits crossing to be well founded and viable. MHI noted that there is a likelihood that the costs could decrease and that the crossing can be completed as planned within the allotted time frame. Regarding the Muskrat Falls Generating Station, MHI reviewed the costs, schedules and design work for the generating station and concluded: The proposed schedule is appropriate and consistent with best utility practices. Based on the amount of engineering completed and the number of tenders for which estimates have been provided by potential suppliers, MHI considers the Decision Gate 3 cost estimate to be an AACE Class 3 estimate and thus would be considered reasonable for a Decision Gate 3 project sanction. The Labrador transmission assets have also been appropriately designed, scheduled, with a cost estimate consistent with good utility practice.

the power is in our hands Financial Analysis of the Options MHI performed a number of sensitivities or stress tests on Muskrat Falls, including changes in fuel prices, capital costs, interest rates and the potential for carbon pricing. After reviewing these potential changes and the impact on the overall costs, MHI concluded that Muskrat Falls is still the preferred option. MHI concluded: The results of the CPW review indicate a strong preference in favour of the Interconnected Island (Muskrat Falls) option over the Isolated Island (Holyrood) option. The result of the CPW analysis indicates a preference for the Interconnected Island (Muskrat Falls) option of $2.4 billion over the Isolated Island (Holyrood) option. With the assumptions and inputs provided by Nalcor to MHI, the Interconnected Island (Muskrat Falls) option remains the least cost option to meet the needs for capacity and energy to supply the forecasted load in Newfoundland and Labrador until 2067. Also, any uncommitted energy from Muskrat Falls would allow Nalcor to more easily address any large future load additions to the Island of Newfoundland or Labrador. A Cumulative Present Worth analysis was performed on each of the large scale wind development scenarios and compared against the existing Nalcor CPW metrics for the Muskrat Falls Interconnected and Isolated Island options. The wind and battery scenario is the most costly option, while the wind and thermal backup CT option is less, but is still more costly than the Isolated Island option. The CPW result table from this assessment is shown in Table 1. Table 1: Cumula ve Present Worth of Studied s About the Project MHI s Final Recommendation Given the analysis that MHI has conducted based on the data and reports provided by Nalcor, MHI recommends that Nalcor pursue the Interconnected Island (Muskrat Falls) Did You Know? Cumula ve Present Worth (Billions in 2012) CPW Cost Component Interconnected Isolated Island Fixed Charges Opera ng Costs Fuel Costs Backup CT Fuel Costs Power Purchases Total.32.26 $1.32 $6.47 $8.37 $2.56.75 $6.71 $10.78 Source: Review of the Wind Study for the Isolated Island of Newfoundland, MHI October 2012 Thermal Ba ery $7.27 $1.29.87 $1.67 $11.86 $14.61 $1.18.87 $17.43 Muskrat Falls means long-term stable electricity rates for generations. If we continue to rely on the Holyrood plant and significant amounts of oil to generate our electricity, consumers will pay higher rates for electricity. Muskrat Falls will not only meet our domestic energy needs, but be a revenue generator for our province long into the future. At peak production, the Holyrood plant burns approximately 18,000 barrels of oil each day to meet the electricity needs on the island. With Muskrat Falls, Newfoundland and Labrador will be powered by 98% clean, renewable energy and become a leader in carbon reduction standards. The development of Muskrat Falls will avoid approximately 96 million tonnes of emissions by 2065. During each year of construction, there will be an average of 1,500 jobs in the province across 70 occupations. There will be peak employment during construction of approximately 3,100 people. Through jobs and business contracts, Newfoundlanders and Labradorians will earn $1.9 billion from Muskrat Falls construction. Muskrat Falls will almost completely eliminate our reliance on oil and provide a clean, renewable energy source. The development of Muskrat Falls will set the stage for Newfoundland and Labrador to manage its own energy and economic future without relying on others to meet our power needs. Muskrat Falls option as the least cost alternative to meet future generation requirements to meet the expected electrical load in Newfoundland and Labrador. Muskrat Falls will transform our province from an economy dependent on non-renewable resources to an economy built on renewable, sustainable energy resources. Project construction will generate approximately $290 million in tax revenues for the provincial government. Approximately $500 million in income to business and labour will be earned by Labradorians and Labradorbased businesses. Learn more about Muskrat Falls web: phone: e-mail: twitter: www.powerinourhands.ca 1-888-576-5454 info@powerinourhands.ca twitter.com/mffacts The demand for electricity in Newfoundland and Labrador is increasing. Our economy is growing and residential and business electricity use continues to rise steadily. The development of Muskrat Falls on the lower Churchill River in Labrador has been proposed as the best option for meeting the province s future power needs and providing homes and businesses with stable, affordable electricity rates into the future. Churchill Falls* The Muskrat Falls project will consist of: A generating facility, consisting of two dams and a powerhouse that will generate 824 megawatts of clean, renewable electricity. A 1,100 km transmission line from Muskrat Falls in Labrador to Soldiers Pond on the Avalon Peninsula. A 35 km subsea cable crossing the Strait of Belle Isle from Forteau Point in Labrador to Shoal Cove on the island. A 180 km subsea Maritime Transmission Link connecting Newfoundland and Labrador in a new way to markets in North America. Granite Canal* House of Assembly Debate The Government of Newfoundland and Labrador is seeking to hold a special debate in the House of Assembly this fall on its proposal to develop Muskrat Falls. Government believes it is important to provide you as citizens, and your elected representatives, with the opportunity to be fully engaged and learn more about Muskrat Falls before the province makes the final decision on whether or not to proceed with this development. project and the reasons Nalcor Energy has concluded that Muskrat Falls is the lowest-cost option for meeting our energy needs. This fact sheet contains a description of the proposed development as well as a summary of key information from the recent independent review of the project by Manitoba Hydro International. Government is providing this information to every household in Newfoundland and Labrador. Our aim is to help you understand the This is our province s opportunity to have an open and informed discussion about our energy future and the merits of Muskrat Falls. Government s commitment to the people of our province is that the decision we make at the end of the day will be one that is truly in the best interest of Newfoundlanders and Labradorians. It is the government s intention to debate this project the way the Voisey s Bay project was debated a decade ago. The main difference is that, in this case, we hired independent, world-renowned experts to put our own analysis to the test.

the power is in our hands Financial Analysis of the Options MHI performed a number of sensitivities or stress tests on Muskrat Falls, including changes in fuel prices, capital costs, interest rates and the potential for carbon pricing. After reviewing these potential changes and the impact on the overall costs, MHI concluded that Muskrat Falls is still the preferred option. MHI concluded: The results of the CPW review indicate a strong preference in favour of the Interconnected Island (Muskrat Falls) option over the Isolated Island (Holyrood) option. The result of the CPW analysis indicates a preference for the Interconnected Island (Muskrat Falls) option of $2.4 billion over the Isolated Island (Holyrood) option. With the assumptions and inputs provided by Nalcor to MHI, the Interconnected Island (Muskrat Falls) option remains the least cost option to meet the needs for capacity and energy to supply the forecasted load in Newfoundland and Labrador until 2067. Also, any uncommitted energy from Muskrat Falls would allow Nalcor to more easily address any large future load additions to the Island of Newfoundland or Labrador. A Cumulative Present Worth analysis was performed on each of the large scale wind development scenarios and compared against the existing Nalcor CPW metrics for the Muskrat Falls Interconnected and Isolated Island options. The wind and battery scenario is the most costly option, while the wind and thermal backup CT option is less, but is still more costly than the Isolated Island option. The CPW result table from this assessment is shown in Table 1. Table 1: Cumula ve Present Worth of Studied s About the Project MHI s Final Recommendation Given the analysis that MHI has conducted based on the data and reports provided by Nalcor, MHI recommends that Nalcor pursue the Interconnected Island (Muskrat Falls) Did You Know? Cumula ve Present Worth (Billions in 2012) CPW Cost Component Interconnected Isolated Island Fixed Charges Opera ng Costs Fuel Costs Backup CT Fuel Costs Power Purchases Total.32.26 $1.32 $6.47 $8.37 $2.56.75 $6.71 $10.78 Source: Review of the Wind Study for the Isolated Island of Newfoundland, MHI October 2012 Thermal Ba ery $7.27 $1.29.87 $1.67 $11.86 $14.61 $1.18.87 $17.43 Muskrat Falls means long-term stable electricity rates for generations. If we continue to rely on the Holyrood plant and significant amounts of oil to generate our electricity, consumers will pay higher rates for electricity. Muskrat Falls will not only meet our domestic energy needs, but be a revenue generator for our province long into the future. At peak production, the Holyrood plant burns approximately 18,000 barrels of oil each day to meet the electricity needs on the island. With Muskrat Falls, Newfoundland and Labrador will be powered by 98% clean, renewable energy and become a leader in carbon reduction standards. The development of Muskrat Falls will avoid approximately 96 million tonnes of emissions by 2065. During each year of construction, there will be an average of 1,500 jobs in the province across 70 occupations. There will be peak employment during construction of approximately 3,100 people. Through jobs and business contracts, Newfoundlanders and Labradorians will earn $1.9 billion from Muskrat Falls construction. Muskrat Falls will almost completely eliminate our reliance on oil and provide a clean, renewable energy source. The development of Muskrat Falls will set the stage for Newfoundland and Labrador to manage its own energy and economic future without relying on others to meet our power needs. Muskrat Falls option as the least cost alternative to meet future generation requirements to meet the expected electrical load in Newfoundland and Labrador. Muskrat Falls will transform our province from an economy dependent on non-renewable resources to an economy built on renewable, sustainable energy resources. Project construction will generate approximately $290 million in tax revenues for the provincial government. Approximately $500 million in income to business and labour will be earned by Labradorians and Labradorbased businesses. Learn more about Muskrat Falls web: phone: e-mail: twitter: www.powerinourhands.ca 1-888-576-5454 info@powerinourhands.ca twitter.com/mf_facts The demand for electricity in Newfoundland and Labrador is increasing. Our economy is growing and residential and business electricity use continues to rise steadily. The development of Muskrat Falls on the lower Churchill River in Labrador has been proposed as the best option for meeting the province s future power needs and providing homes and businesses with stable, affordable electricity rates into the future. Churchill Falls* The Muskrat Falls project will consist of: A generating facility, consisting of two dams and a powerhouse that will generate 824 megawatts of clean, renewable electricity. A 1,100 km transmission line from Muskrat Falls in Labrador to Soldiers Pond on the Avalon Peninsula. A 35 km subsea cable crossing the Strait of Belle Isle from Forteau Point in Labrador to Shoal Cove on the island. A 180 km subsea Maritime Transmission Link connecting Newfoundland and Labrador in a new way to markets in North America. Granite Canal* House of Assembly Debate The Government of Newfoundland and Labrador is seeking to hold a special debate in the House of Assembly this fall on its proposal to develop Muskrat Falls. Government believes it is important to provide you as citizens, and your elected representatives, with the opportunity to be fully engaged and learn more about Muskrat Falls before the province makes the final decision on whether or not to proceed with this development. project and the reasons Nalcor Energy has concluded that Muskrat Falls is the lowest-cost option for meeting our energy needs. This fact sheet contains a description of the proposed development as well as a summary of key information from the recent independent review of the project by Manitoba Hydro International. Government is providing this information to every household in Newfoundland and Labrador. Our aim is to help you understand the This is our province s opportunity to have an open and informed discussion about our energy future and the merits of Muskrat Falls. Government s commitment to the people of our province is that the decision we make at the end of the day will be one that is truly in the best interest of Newfoundlanders and Labradorians. It is the government s intention to debate this project the way the Voisey s Bay project was debated a decade ago. The main difference is that, in this case, we hired independent, world-renowned experts to put our own analysis to the test.