Low Voltage Switchgear Construction Checklist (under 500 kva)

Similar documents
Unit Substation Transformer Construction Checklist (under 500 kva)

FIELD TEST AND OPERATIONAL CHECK SECTION A. Refer to Section 16010, Electrical General Requirements.

SECTION to 5000 AMPERE PLUG-IN AND FEEDER BUSWAYS - SPECTRA. A. Low-Voltage Plug-in Busway to 5000 ampere, 600 VAC

PROJECT TITLE PROJECT NO.: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

Project Procedure 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /19/2011 PAGE 1 OF 4 FACILITY LIGHTING SYSTEMS INSTALLATION

SWITCH GEAR SERVICE AND MAINTAINNANCE SAFETY MEASURES AND REQUIREMENTS

SECTION BUSWAYS

SECTION BASIC ELECTRICAL REQUIREMENTS

XAP Series Busduct Storage, Installation, and Maintenance

A. Section includes busway and fittings including plug-in units.

SECTION CONVECTORS

POWER TRANSFORMER INSTALLATION

1 29SEP03 ALL General update with miscellaneous changes in entire document.

SECTION FUEL-FIRED UNIT HEATERS

B. Provide liquid-filled secondary substation transformers as indicated on drawings.

SECTION LOW-VOLTAGE TRANSFORMERS

SUGGESTED SPECIFICATION for Low Voltage (600V) Generator Paralleling Switchboard

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

ELECTRICAL INSPECTION BULLETIN (Effective )

SECTION ENCLOSED BUS ASSEMBLIES

SECTION SECONDARY UNIT SUBSTATIONS SECONDARY LESS THAN 1000 V

SECTION SECONDARY UNIT SUBSTATIONS

PRIMARY UNIT SUBSTATIONS SECONDARY 1000 V AND ABOVE SECTION SECTION

OAKDALE CHILLED WATER PLANT CAPACITY UPGRADES UI PROJECT INSTALL CHILLERS SECTION COMMISSIONING

Houston First Corporation Package 1 SECTION MEDIUM VOLTAGE FUSED SWITCH INTERRUPTER

A. This Section includes the following types of dry-type transformers rated 600 V and less, with capacities up to 1000 kva:

SECTION AIR TERMINAL UNITS

BUS DUCT INSTALLATION

University of Delaware

SECTION HVAC AIR CLEANING DEVICES

SECTION REQUIREMENTS FOR ELECTRICAL INSTALLATIONS

This section applies to the requirements for electrical Inspection, calibration, and testing.

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS

ADDENDUM NO. 1 BID AND CONTRACT DOCUMENTS FOR. BID No. 2019PW299

Statement of Work. Single Phase Power Up Service Single Phase Power-UP. Implementation Services. Table of Contents. 1.0 Executive Summary

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM GENERATION EQUIPMENT

A. Hazardous Areas: Hazardous areas as defined by the NEC as Class I, Division 1, Group D, or Class I, Division 2, Group D hazardous are as follows:

SECTION MOTOR CONTROL CENTER

Installation, Inspection and Maintenance of Dry Type Transformers

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF POWER SUPPLY EQUIPMENT

SPECIFICATION FOR SIMPLEX SWITCHBOARDS

SECTION GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL

NEUTRAL GROUNDING TRANSFORMERS INSTALLATION AND MAINTENANCE INSTRUCTIONS

Point Eight Power, Inc. Switchgear Specification Low Voltage UL 1558 Metal-Enclosed Switchgear

A. Provide a complete Distribution Panelboard system as indicated on the drawings, and as specified herein.

Equipment Specifications Low Voltage. Active Harmonic Filter

University of Delaware

SECTION AIR-TO-AIR ENERGY RECOVERY EQUIPMENT

SECTION ENCLOSED BUS ASSEMBLIES

Candidate NICET ID No.: NICET ENGINEERING TECHNICIAN CERTIFICATION Experience Application, Part II: Verifier Data. (Please print legibly or type)

SECTION AUTOMATIC TRANSFER SWITCH

SECTION PACKAGED, SUBMERSIBLE, DRAINAGE PUMP UNITS

Ground Fault Protection. Medium Voltage Artificial Neutrals

16300 HIGH VOLTAGE DISTRIBUTION

SECTION PACKAGED, SUBMERSIBLE SEWERAGE PUMP UNITS

1995 Metric CSJ SPECIAL SPECIFICATION ITEM Fiber Optic Dynamic Lane Control Sign

SERIES 800 / 810 SPECIFICATION 15KV & 25KV PADMOUNTED LIQUID-INSULATED VACUUM LOAD INTERRUPTER ASSEMBLIES

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

MRI Chiller Installation Guidelines

SECTION METAL-ENCLOSED BUS MEDIUM VOLTAGE

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number

The Medical Center Company Electrical System Installation Requirements

SECTION PROJECT CLOSEOUT

SIEMENS. Instructions. Outdoor Metal Clad Switchgear. Installation Assembly OGM&SGM SG kV and 15kV. www. ElectricalPartManuals.

SECTION SECONDARY UNIT SUBSTATIONS

Maintenance Bypass Breaker Cabinet Series Configuration 2. Installation and Operation Manual

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY DISTRIBUTION ENGINEERING NETWORK SYSTEMS SECTION

Architect s Project Number of 5 Decentralized HVAC Equipment District Master Specs 2013 Edition

TENOCHCA HALL - FAN COIL UNITS, RESTROOM AND FINISH RENOVATION PROJECT NO

- 1 - InfraStruXure InRow SC Assembly and Start-Up. Installation Service

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT

B. Accept materials on site in original factory packaging, labeled with manufacturer s identification.

MIRUS International Inc.

COUNTY OF RIVERSIDE BUILDING AND SAFETY DEPARTMENT PHOTOVOLTAIC PERMITTING GUIDELINES

SECTION 512A ELECTRICAL. A. Electrical materials, installation, testing and miscellaneous.

37-SDMS-01 REV. 03 SPECIFICATIONS FOR

SECTION INFLUENT EQUALIZATION TANK PUMPS

1.07 SUPPLEMENTS PRODUCTS (NOT USED) EXECUTION (NOT USED) END OF SECTION

SPECIFICATIONS - DETAILED PROVISIONS Section General Electrical Requirements C O N T E N T S

1. Telecommunications mounting elements. 2. Backboards. 3. Telecommunications equipment racks and cabinets. 4. Grounding.

NLCTA Electromagnet Equipment Lockout Procedure

Maintenance Bypass Breaker Cabinet Series Configuration 5. Installation and Operation Manual

SECTION LOW-VOLTAGE SWITCHGEAR

LOW-VOLTAGE SERVICE ENTRANCE SWITCHBOARDS SECTION D

SECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Pan System

SECTION GROUNDING

Installation and Operation Manual

WL Switchgear. Instruction and Installation Guide. 11-C Rev. 4. usa.siemens.com/switchgear

SECTION COMMISSIONING

SECTION COMMISSIONING

UBC Technical Guidelines Division Edition ELECTRICAL Page 1 of 1. Installation Methods and Requirements

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

DUPLEX INSTALLATION. Customer provides single service lateral attachment point in trough.

Powerware 9390 Integrated Accessory Cabinet IAC-D Configuration Installation and Operation Manual. For use with kva and kva UPS Models

MATERIAL AND WORKMANSHIP

NRC INSPECTION MANUAL

Program management and contract administration of the work per section 4.0

ELECTRIC METERING GENERAL

Capital Projects Group Transfer Switch Specification

Transcription:

Low Voltage Switchgear Checklist (under 500 kva) Project: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This construction checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed. List attached. Electrical Contractor Date General Contractor Date checklist items are to be completed as part of startup & initial checkout, preparatory to performing test procedures. This checklist does not take the place of the manufacturer s recommended checkout and startup procedures or report. If this form is not used for documenting, one of similar rigor shall be used. Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off. Approvals. This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below. Commissioning Authority Date Owner s Representative Date Low Voltage Switchgear Checklist Page 1 of 5

Switchgear Information Equipment Tag Location System (Circle one) Power or Lighting 208-120 or 480-277 Normal or Emergency Manufacturer Model Number Serial Number Short Circuit Capacity Volts/Phase Rating Main Bus Amperage Service Area Other Associated Checklists Transformer Other Other Requested documentation submitted Rec d Comments Manufacturer s cut sheets Installation and startup manual and plan O&M manuals Factory test results Sequences and control strategies Warranty Certificate Switchgear Enclosure/Cabinetry Check if Acceptable; Provide comment if unacceptable NA Comment Equipment installed per manufacturer s instructions and Equipment installed agrees with shop drawings and Verify mounting, location and clearances are per plans and Low Voltage Switchgear Checklist Page 2 of 5

Inspect for physical, electrical and mechanical condition of equipment and cabinet - no damage evident Inspect panels and doors for proper fit and alignment Equipment labels permanently affixed Panel is clean and clear of dust or dirt Verify the application of manufacturer recommended torque values applied to bolted connections Verify correct circuit breaker sizes and types per the and manufacturer s drawings Seismic anchoring installed and functional where applicable (nonshort circuiting) Verify that all manufacturer control wiring between shipping splits is properly connected per manufacturer s drawings and Inspect insulators, barriers and shields for damage or contamination Verify that ground bus is properly bonded to enclosure, enclosure is grounded and resistance to ground meets grounding Verify three or four wire configuration Metering transformer nameplate matches specified and approved transformer Transformer installed per manufacturer s instruction, plans and Inspect metering transformer cables and connections for defects or physical damage Verify metering transformer connections are correct per the single line Verify all grounding and shorting connections for the metering transformer are in place Verify correct fusing for the metering transformer primary and secondary Verify the metering transformer taps are in accordance with the manufacturer s nameplate and Verify the vents and air inlets are free and unobstructed. Clean air filters installed (if required) Megger test of bus phase to phase and phase to ground. Test voltage per manufacturer s recommendations Hi-potential test of bus phase to phase and phase to ground. Test voltage per manufacturer s recommendations Main Circuit Breaker Installed per manufacturer s instructions, plans and Verify all maintenance and service clearances are maintained Verify no physical damage Verify voltage and current rating of circuit breaker are per plans and Low Voltage Switchgear Checklist Page 3 of 5

Confirm correct application of manufacturer s recommended lubricant Verify that primary and secondary contact wipe dimensions are correct Verify breakers are mounted securely and operates smoothly Verify wire is properly installed and suitable size for breaker Check cell fit and element alignment Check racking mechanism Megger test of circuit breaker phase to phase and phase to ground. Test voltage per manufacturer s recommendations Inspect shutter operation Verify that vacuum contact wipe dimensions are correct Hi-potential test of circuit breaker phase to phase and phase to ground. Test voltage per manufacturer s recommendations Feeder Circuit Breakers Installed per manufacturer s instructions, plans and Verify all maintenance and service clearances are maintained Verify no physical damage Verify voltage and current rating of circuit breaker are per plans and Confirm correct application of manufacturer s recommended lubricant Verify that primary and secondary contact wipe dimensions are correct Verify breakers are mounted securely and operates smoothly Verify wire is properly installed and suitable size for breaker Check cell fit and element alignment Check racking mechanism Inspect shutter operation Verify that vacuum contact wipe dimensions are correct Megger test of circuit breaker phase to phase and phase to ground. Test voltage per manufacturer s recommendations Hi-potential test of circuit breaker phase to phase and phase to ground. Test voltage per manufacturer s recommendations Operational Checks Check if Acceptable; Provide comment if unacceptable NA Comment Control power energized to switchgear line-up A full listing of all relay settings per the coordination study is provided and relays are programmed / set and tested Low Voltage Switchgear Checklist Page 4 of 5

Electrically operated circuit breakers exercised in manual mode (electrically operated in test position and fully engaged position without main bus voltage applied) All incoming cables are terminated and ABC phasing is correct. Terminations are torqued, checked, stress cones are properly grounded and exposed energized surfaces are insulated Specified sequences of operation and operating schedules have been provided with all variations documented Specified point-to-point checks have been completed and documentation record submitted for this system Low Voltage Switchgear Checklist Page 5 of 5