Appendix E8. Open Pit Loss and Dilution

Similar documents
Long Term Planning for Open Pit Mines

QUARTERLY PRODUCTION REPORT: KANMANTOO PRODUCTION AHEAD OF YTD GUIDANCE

GOLD RESOURCE CORPORATION UPDATES PROVEN & PROBABLE RESERVES, BOOSTING GLOBAL TONNES BY 16%, GOLD OUNCES BY 18% AND SILVER OUNCES BY 14%

Optimal Selection of Selective Mining Unit (SMU) Size

APPENDIX 4-D KSM MINE PLAN

Increasing Net Present Value by a Third at an Operating Sublevel Cave Mine Using Draw Strategy Optimisation. Presented by Alex Campbell

A simple and accurate method for Ore Reserve estimation and Mineral Resource depletion in caving mines. Alex Campbell

Morrison Copper/Gold/Moly (Silver) Project

Bisha Mining Share Company

HUCKLEBERRY MINES LTD. An Overview

QUARTERLY REPORT IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII PERIOD ENDING 31 MARCH 2016

INTRODUCTION SUMMARY. misclassification, resulting in increased ore recovery.

Application of Modern Geostatistics for Mine Planning

Estimation of Open Cut Mining Recovery and Mining Dilution. Summary. Introduction. Estimation Techniques. AusIMM JORC Code Edition.

What is Enterprise Optimisation?

Figure 1: Schematic block-diagram of the project test work

Long-Hole Stope Evaluation. Operating procedures. Introduction. 1. Approach of the model. 2. Notification. 3. Worksheets

Maiden Ore Reserve for Camel Creek JV

Waste Liberation: Improving mill feed from a miner s perspective. Bob McCarthy, SRK Consulting Dr. Bern Klein, University of British Columbia

QUARTERLY REPORT IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII PERIOD ENDING 31 DECEMBER 2017

Phase VII Expansion Waste Rock and Overburden Management Plan

On-Line Mine Improving mining economy through on-line mineral analysis

IN-PIT CRUSHING AND CONVEYING MINE PLANNING AND OPERATIONS Skillings Mining Review, June 1, 1985 by: Independent Mining Consultants, Inc.

Blast Dynamics POWER DECK OPTIMIZATION POWER DECK COMPANY MAY, 2004 PREPARED BY: improving productivity wi th the use of efficient blast designs

QUARTERLY REPORT IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII PERIOD ENDING 30 JUNE 2016

For personal use only

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum

Axehandle Pit Feasibility Study and Mining Reserve

Resource Efficient Mining Processes of Tomorrow

Evaluation of Grade Engineering using Enterprise Optimization. Michael Scott, Nick Redwood

IMPACT OF IN-PIT CRUSHING AND CONVEYING ON PIT SHELL OPTIMIZATION. Marc Johnson, Regional Manager - South America

ASX ANNOUNCEMENT 26 February 2013 ASX Code: BDR. MAIDEN DUCKHEAD HANGINGWALL LODE RESOURCE 584, g/t for 71,000 oz gold

For personal use only

MINING DILUTION: VARIABLE VERSUS FIXED FACTOR

Olympias: Highlights Q Phase 1 Retreatment. Acquired from European Goldfields in February. EIA approved. Phase 1 Retreatment began

OTJIKOTO GOLD MINE INTRODUCTION AND PROGRESS UPDATE MAY 2014

Mine Development and Operations Plan Area 2 Stage 3 Pit Design Change

Enterprise Optimization for Mining Businesses. Presented at the SME national Convention. February 27, 2013

8 January UPGRADED ORE RESERVE and EXTENDED MINELIFE MOLYHIL TUNGSTEN PROJECT

Health and Safety. Update: No LTI at Prestea Open Pits. 5.65M man hours worked with no LTI

ASX Release Prominent Hill 2012 Annual Mineral Resources and Ore Reserves Statement

SUITE WEST HASTINGS STREET VANCOUVER, BC V6C 2W2 CANADA TEL: FAX:

Release Notes. Datamine NPV Scheduler Products Version 4.26 Public Release

Copper Mountain Announces Robust Preliminary Economic Assessment Results for New Ingerbelle

Patrick Mukonki May and Augustin Muhota Kawinda

Southern Cross Goldfields Ltd

ASX ANNOUNCEMENT 13 December 2011 ASX Code: BDR TUCANO GOLD PROJECT CONSTRUCTION AND MINING UPDATE

Geostatistical Simulation of Optimum Mining Elevations for Nickel Laterite Deposits

Drilling, metallurgical test work and a new resource model add 21% to oxide gold reserves

For personal use only

INV METALS ANNOUNCES ROBUST PRELIMINARY FEASIBILITY STUDY AT LOMA LARGA

Kumtor Gold Company 2018

NEWS RELEASE. Post Tax NPV 10%) Post Tax IRR (100% equity) 17.6% Probable Reserves Project Life (based on Probable Reserves)

Thalanga Project Ore Reserve and Mineral Resource Statement (as at 1 December 2017)

Evaluation of Bench Height Selection for Limestone Resource Optimization A Case Study. N K Sharma, R Mazumder, D K Panda, A K Dubey

SECOND QUARTER REPORT 15 JULY 2014

QUARTERLY REPORT IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII PERIOD ENDING 31 MARCH 2018

Saracen Mineral Holdings Limited ACN

2007 MINERAL RESOURCE & ORE RESERVE EXPLANTATORY NOTES

African Barrick Gold. Buzwagi Site Overview. November 2014

For personal use only

Quality, Diverse Group of Mining Assets. February 2018

For personal use only

Prominent Hill 2011 Annual Mineral Resource and Ore Reserve Statement

Garden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces

QUARTERLY REPORT IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII PERIOD ENDING 30 SEPTEMBER 2017

Indonesia s Next World Class Mining Company

Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study

Gallowai-Bul River Mine Scoping Study

Forward Looking Statement

QUARTERLY REPORT for the period ending 30 September 2017

Outotec OreMet Optimizer

Density Neglected but Essential

Minara Resources Limited Investor Relations Presentation October Peter Johnston Managing Director and CEO

AMUR MINERALS CORPORATION (AIM: AMC) Independent Review of Cost Estimates $1.78 Per Pound Nickel Cost to Deliver to Rail Station

For personal use only

Underground Ore Reserve growth at Prominent Hill extends mine life to 2030

Sierra Metals Updates Mineral Resource and Reserve Estimate for Bolivar Mine, Mexico

NEW MINERAL RESOURCE ESTIMATE ADDS 281 MILLION TONNES OF HIGH-GRADE INFERRED RESOURCES TO THE HUGO NORTH COPPER-GOLD DEPOSIT IN MONGOLIA

Innovative technologies for operations resulting in: increased productivity reduction in operating costs improvements in long term sustainability

QUARTERLY REPORT IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII PERIOD ENDING 30 SEPTEMBER 2018

REPORT. Pre-feasibility Block Cave Mine Design - Iron Cap Deposit REPORT ON. May 31, 2012

Krasny project JORC resources update: oz of gold at 1,200 USD/oz gold price

Ravenswood Expansion Project Update

MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES

GEOVIA GEMS Course Catalog Africa

2016 Mineral Resource Tritton Tenement Package

Ore Dilution Estimation Model in Tanzania Southern Highland Zone: A Case of New Luika Gold Mine

Papua New Guinea Mineral resources and ore reserves

Thalanga Operations Ore Reserve and Mineral Resource Statement

For personal use only

Global Asset Optimisation

Rambler Updates the Reserve and Resource Estimates At its Ming Copper Gold Mine

Open Cut Coal Solutions

smart(er) management of technical risk:

Confidence in Carrapateena project grows

BUREAU OF MINERAL RESOURCES, GEOLOGY AND GEOPHYSICS

For personal use only

NEWS RELEASE December 11, 2018 Trading Symbols: TSX: AMM; NYSE American: AAU

For personal use only

Transcription:

Appendix E8 Open Pit Loss and Dilution

Memo From: Jesse Aarsen To: Tracey Meintjes, Jim Gray Date: April 29, 2012 Re: KSM - 2012 PFS Loss and dilution calculations 1. Introduction The KSM project is a large open pit copper-gold porphyry deposit. The ore-body is continuous within the cut-off grade shell. The pits will be mined with large shovels and trucks at an ore mining rate of 120,000 tonnes/day feeding the mill. Typical of large porphyries the large equipment and high mining rates, selective mining methods will not be possible. Blasthole sampling will be used to determine the waste/ore boundaries and the digging limits for the shovels. Blasting will create dilution along waste/ore boundaries and as the material is being loaded to the trucks some ore will be lost to the waste (mining loss) and some waste will be added to the ore (dilution). In some seasons, material will stick or freeze to the inside of the truck boxes and create carry-back. The truck boxes must be cleaned out regularly and if they are hauling in ore, this haul-back material will be wasted (mining loss). Also in some cases a load of ore may be misdirected to the waste dump (mining loss). In order to properly calculate the reserve files for scheduling purposes, mining losses and dilution must be taken into account. 2. 3D Block model and whole block dilution The 3D block model (3DBM) for KSM was built by RMI with 25mx25mx15m block sizes and called ksmp15.dat. MMTS has added some calculated items to the 3DBM. Each block has a calculated recovered grade based on the interpolated grades from RMI and the specified recovery formulae. An NSR value is then calculated from the recovered grades and includes Net Smelter Prices for each metal from the Smelter schedule. The resultant NSR value therefore represents the net $/tonne value of the block after all offsite costs have been taken into consideration, smelter charges and on-site plant recovery. The NSR calculation and smelter terms can be found in the Design Basis Memorandum. The NSR value is used as a cut-off item for breakeven ore/waste selection. Each block in the model has a volume of 9,375 m 3 and weighs approximately 26,000 tonnes. The plant feed will require around 4 ½ blocks per day which is an appropriate selective mining unit for this size of shovel. The interpolation of the metal grades to the 3DBM, averages the composites to a single value for each metal. This smoothing is in effect a numeric dilution where higher composite values are averaged down but conversely lower values are averaged up. Because of the continuous/smooth nature of the mineralization, it is assumed this smoothing down and up averages out around the cutoff grade. During operations, Ore Control System (OCS) from blasthole sampling will be done on a 8.5m spacing to determine cutoff boundaries for shovel dig limits. These smaller ore/waste blocks will be too small to separate with the large shovels, especially after the material has been displaced by blasting. Therefore the dilution from isolated blasthole blocks will be handled as whole block dilution in the 3DBM. The OCS will define smaller ore/waste zones but these will be smoothed into larger units which the shovels can selectively mine to. These larger units from the OCS are better represented by the 3DBM size blocks and will define contacts between ore and waste. These contact boundaries are approximated by the 3DBM as the smallest sized units the shovels can selectively mine. The 3DBM blocks can therefore be used to define how much contact dilution needs to be accounted for. MMMemo KSM Loss and Dilution 2012 Apr 29.docx Page 1

3. Contact Loss and dilution The mining reserves used for scheduling are calculated from grades in the 3D block model using detailed pit designs and the appropriate mining recoveries and dilutions applied. The recoveries and dilutions convert the in-situ ore tonnages into a ROM delivered tonnage to the mill. The ROM delivered tonnes is what the mill will actually see and therefore they are used to determine the appropriate production schedule. There are three main parts to recovery and dilution (as listed above). They are: a) Dilution of waste into ore where separate ore and waste blasts are not possible b) Loss of ore into waste where separate ore and waste blasts are not possible c) General mining losses due to handling (haul back in truck boxes, stockpile floor losses, etc) Mining Dilution The Minesight routine gndiln.dat (GNDLN) is run to calculate the number of waste blocks which surround an ore block on each bench (blocks on the benches above and below are not considered). Whole block dilution covers most of the effects of the material above and below and this evaluation considers the effects of recovery and dilution as the shovel extracts ore advancing across the bench face. On a particular bench, each block in the 3D block model is surrounded by 8 other blocks but only 4 of these blocks can be considered as contact blocks. Therefore the maximum number of waste contact blocks for an ore block on a bench can be 4. When the Minesight procedure is run, it calculates the number of waste contact blocks and stores the value into XTR04 item. At the pre-feasibility stage, only measured and indicated blocks can be classified as ore blocks. An NSR cut-off is also used to classify ore blocks and these cut-offs for the different pits are as follows: Mitchell $9.57 Sulphurets $10.17 Kerr $9.61 A visual illustration of the concept is shown below. The numerical definition following ORE represents the amount of waste contact blocks: ORE1 ORE1 ORE1 ORE1 ORE1 ORE ORE ORE ORE ORE Figure 1 - Separate ore and waste blasts Page 2

In this case, with a maximum of 1 waste block contact for each ORE1 block contact, the ore and waste can be separated quite easily with very little dilution from neighbouring blocks. Waste ORE2 ORE1 ORE2 Waste Waste ORE2 ORE1 ORE2 Waste Figure 2 - Ore blocks with 1 or 2 waste contact edges In this case some dilution will happen for the ORE2 blocks (blocks that have 2 waste contacts). Waste Waste Waste Waste ORE4 Waste Waste Waste Waste Figure 3 - Ore block surrounded by waste This is an example of a singular ore block with 4 waste contacts. Dilution will be high in this case. Waste ORE3 ORE2 ORE3 Waste Figure 4 - Ore blocks with 2 or 3 waste contacts Another example where dilution will be higher because of more waste contact blocks per ore block. Page 3

A sample bench plan for Mitchell pit is shown below that displays the ore blocks above cutoff grade and the number of waste contact blocks per ore block. The ultimate pit outline is shown with the green line. It can be seen that the orebody in Mitchell is quite continuous and that most of the ore blocks have only 1 or 2 waste contacts. Figure 5 - Mitchell 690 bench with ore blocks greater than cutoff grade A sample bench plan from Sulphurets is shown below: Figure 6 - Sulphurets 1245 bench with ore blocks greater than cutoff grade Page 4

A sample bench plan from Kerr is shown below. Figure 7 - Kerr 1575 bench with ore blocks greater than cutoff grade It is assumed that ore blocks with only 1 waste contact have a minimum mining dilution and almost 100% mining recovery because they can be mined in separate blasts. Ore blocks with 2, 3 or 4 waste contacts will incur dilution and a lower mining recovery because they are less likely to be blasted or mined separately from the surrounding waste blocks. In order to quantify the amount of dilution for the blocks that have 2, 3 or 4 waste contacts, the following description is used: The 80 tonne class dippers on the proposed shovels attempt to separate the ore and waste after a blast (when there is a mixed blast). The selectivity along the contact is influenced by over digging and under digging by the operator and also by mixing from the blast throw. The bucket size is approximately 30m 3, with an approximate lip width of 6m. Therefore the bucket size is about 2.5m deep x 2m high. Assuming that the operator digs along the edge of a contact block with a +/- 2 dipper depths (including the mixing effect) into the contact face, and half the time this is dilution and half the time its mining loss, the amount of diluted material along each edge of a block is as follows: (2X2.5m x 25m x 15m x 2.77) = 937.5 BCM x 2.77 = 2,597 tonnes 2 Each block has an approximate 26,000 tonnes. For blocks with 2, 3 or 4 waste contact edges the following dilution applies: 2 edge blocks = 2 x 2,597 tonnes = 5,194 tonnes (20% of total block) 3 edge blocks = 3 x 2,597 tonnes = 7,791 tonnes (30% of total block) 4 edge blocks = 4 x 2,597 tonnes = 10,388 tonnes (40% of total block) Page 5

After the GNDLN is run on the LG shells generated for each area using the appropriate waste/ore cutoff grade, a pitres report is run that separates the ore blocks by number of waste contact edges and calculates the total tonnage. A summary for each pit is shown below: Table 1 Mitchell pit dilution (mdil.rpt) M685 Block Diluted Tonnes ROM kt Dilution Added (kt) 1 edge 61,389 0% 0 2 edges 34,035 20% 6,807 3 edges 3,951 30% 1,185 4 edges 430 40% 172 Total (kt) 99,805 8,164 % of orebody with contact edges (10.1%) Dilution % Mitchell total reserves (kt) 991,337 0.82% Table 2 Sulphurets pit dilution (sdil.rpt) Sulphurets (PIT13) Block Diluted Tonnes ROM kt Dilution Added (kt) 1 edge 63,372 0% 0 2 edges 46,706 20% 9,341 3 edges 6,942 30% 2,083 4 edges 1,332 40% 533 Total (kt) 118,352 11,957 % of orebody with contact edges (38.5%) Dilution % Sulphurets total reserves (kt) 307,552 3.89% Table 3 Kerr pit dilution (kdil.rpt) Kerr (PIT13) Block Diluted Tonnes ROM kt Dilution Added (kt) 1 edge 55,702 0% 0 2 edges 31,815 20% 6,363 3 edges 3,992 30% 1,198 4 edges 268 40% 107 Total (kt) 91,777 7,668 % of orebody with contact edges (37.6%) Dilution % Kerr total reserves (kt) 242,782 3.16% It can be seen that a much higher percentage of the ore in the Sulphurets and Kerr areas have waste contact edges than in Mitchell (approximately 37%-39% compared to approximately 10%). Dilution grades are estimated by determining the grades of the envelope of waste contacts with the ore blocks. For the KSM project the waste blocks with NSR greater than $5/tonne and less than the cut-off grade where chosen. Inside each pit limit a reserve report is run separating out the waste blocks that Page 6

satisfy the criteria and the average grades are reported. Shown below is a table summarizing the results. Mining Loss Table 4 Dilution grades by pit 5<NSR<9.57 5<NSR<10.17 5<NSR<9.61 Mitchell Sulphurets Kerr NSR ($/t) 7.55 8.19 7.60 CUIDW (%) 0.043 0.056 0.106 AUIDW (g/t) 0.229 0.333 0.141 RCU (%) 0.021 0.028 0.069 RAU (g/t) 0.136 0.160 0.077 AGIDW g/t) 1.45 0.59 0.78 MOIDW ppm) 59.4 19.0 0 RAG (g/t) 0.67 0.18 0.24 RMO (ppm) 20.6 3.3 0 Mining losses must also be taken into consideration. As mentioned above, these can include carryback material and misdirected loads. Assuming for 4 months of the year, an estimated 10% of the truck boxes will have a build up of frozen ore. This material will have to be cleaned out regularly (say each day) using a backhoe. It is assumed the cleaned out, frozen ore will not be able to be salvaged as it will be a small amount and it will likely be highly diluted if it is set down on the ground and picked back up again. Therefore this ore will be counted as a mining loss for the purpose of reserve reporting. An estimation of the percentage is shown in the calculation below: 120 days * 40 trucks * 10% * 345 tonnes = 0.38% 43,200,000 tonnes/yr The lack of visual distinction between the waste and ore will result in misdirected loads as happens in all mines. The frequency of misdirected loads will be reduced by utilizing a fleet management system combined with GPS based or field staked ore/waste dig limits from the Ore control system. Nevertheless, misdirected loads will still happen. An allowance of 1% of misdirected ore loads to the RSF dumps is included. The last type of mining loss is contact block loss and is similar to dilution in the shovel loading face. Just as waste is included in the ore and counted as dilution, some ore will be lost along the edges to the surrounding waste blocks. The same methodology used for the dilution calculations can be applied for the mining loss calculations; therefore this type of mining loss is equal to the dilution. Total mining loss = Carry-back loss + misdirected loads + contact block loss (same as dilution) Page 7

A table showing the summary of loss and dilution for each area is shown below: Table 5 Total Summary of Loss and Dilution by pit area Pit Handling Loss Contact block Loss Total Loss Dilution Mitchell 1.38% 0.82% 2.2% 0.8% Sulphurets 1.38% 3.89% 5.3% 3.9% Kerr 1.38% 3.16% 4.5% 3.2% Page 8