NETWORK ASSET CONDITION ASSESSMENT AND REFURBISHMENT PLANNING

Similar documents
Performance target setting and prioritising electrical power system-level investment

Simplified reliability modelling as a basis for performance target setting and prioritising electrical power system-level investment

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

Lifetime Decisions. Investments can be planned, lifetime costs of equipment made transparent and decisions based on informed fact.

Alan Tait Managing Director Pragma Africa

Distribution Systems - Program 128

Example of Information for EOL Projects. American Municipal Power October 19, 2017

Electrical utility distribution network capital planning

Enhance Power Equipment Reliability with Predictive Maintenance Technologies

Exhibit to Agenda Item #1

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

WILEY A JOHN WILEY & SONS, INC., PUBLICATION

AEP Guidelines for Transmission Owner Identified Needs

INCREMENTAL CAPITAL ELIGIBLE PROJECTS DETAILS Capital Expenditure $3,931,290 ($3,530,841 in 2013) Background:

Presenter: Louis Pieterse (City Power) Author: Johanette van der Merwe (Eon Consulting) Co-Authors: Louis Pieterse (City Power); Kurt Dedekind (Eskom)

Supporting Document 03. Information to support our proposed base capital expenditure programme

Evaluating Your Electrical Distribution System

FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

POTOMAC ELECTRIC POWER COMPANY

Survey and Summary of Best Practices for Distribution Reliability Improvement. December 8, p.m. EST

Connection Study Requirements

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

THE IMPROVEMENTS TO PRESENT LOAD CURVE AND NETWORK CALCULATION

Asset Management and Maintenance in Transmission and Distribution Networks

SQUEEZING MARGINS: REDUCING COSTS WHILE BALANCING RISKS. G.A. Bloemhof, J. Knijp. KEMA T&D Power, the Netherlands

POWER QUALITY IN REGULATION OF DISTRIBUTION COMPANIES A FINNISH CASE

Influence of Distributed Power Generation from Renewable Energy Sources on Reliability of Distribution Networks

SUMMARY OF DISTRIBUTION BUSINESS

DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES

Smart Distribution Applications and Technologies - Program 124

Transmission Owner Asset Management

Pomona, CA May 24 25, 2016

ExISTING SubSTATION INfORmATIONON

Postprint. This is the accepted version of a paper presented at 2017 CIGRÉ SC B3 (Substations) Colloquium.

Challenges of Asset Management in Power Transmission Network

Improved transformer temperature monitoring. Increasing the availability, reliability, and reducing maintenance costs COLUMN ABSTRACT KEYWORDS

The Analysis of Renovation Criteria for Protective Relay in Power Substation

DISTRIBUTION OPERATIONS AND MAINTENANCE

OMDEC Solution Overview

Enhancing Utility Outage Management System (OMS) Performance

CIRED Workshop - Lyon, 7>8 June 2010 Paper 0004 ABSTRACT WHAT IS ISCM? INTRODUCTION WHY ISCM?

Grid Modernization Initiatives at ComEd

A computer-aided, reliability-centered maintenance strategy for power networks

Preferential Subjects for the 2010 Session

ITC Drives Performance with Asset Management

Evaluation of Systems Performances and Systems Reconfigurations

NFRRSTRUCTURES AGING POWER DELIVERY. Second Edition. Randall R. Schrieber. H. Lee Willis. CRC Press. Taylor & Francis Group

List of training courses on electrical power system for Cambodia, Laos, Vietnam and Thailand (CLVT) countries

Walk-through of long-term utility distribution plans: Part 1 - Traditional Distribution Planning

Reliability Assessment of a Power Grid with Customer Operated Chp Systems Using Monte Carlo Simulation

The Value of Customer Reliability to the Utility

Grid Solutions. ASSET PERFORMANCE MANAGEMENT for Electrical Substations

A PARTIAL RELATIONSHIP BETWEEN COSTS AND QUALITY AS A BASIS FOR SETTING REGULATION PARAMETERS OF SUPPLY CONTINUITY

Basic Reliability Analysis of Electrical Power Systems

Carry out routine inspection and service on high voltage indoor metal clad circuit breakers and bus

Ageing Management and Development of a Programme for Long Term Operation of Nuclear Power Plants

Platte River Power Authority. Ten-Year Transmission Plan ( )

Electricity Industry Act Electricity Distribution Licence Performance Reporting Handbook

Study Committee A3. High Voltage Equipment. Action Plan

Medium Voltage Service Maintenance and refurbishment

Residual Life assessment with DGA, Furan content in transformer oil and Degree of polymerization of solid insulation

Electric Distribution Reliability PUCO Staff

Making Decision of the Maintenance Priority of Power Distribution System using Time Varying Failure Rate and Interruption Cost

Substation Transformer Condition-Based Maintenance (CBM)

MITIGATION OF OPERATIONAL RISKS FOR THE 2010 FIFA SOCCER WORLD CUP

Electrical Networks Principles and Performance

SIMULATION METHOD FOR RELIABILITY ASSESSMENT OF ELECTRICAL DISTRIBUTION SYSTEMS

School of Electrical Engineering and Computer Science. Expansion: Analysis, and Formulation. Washington State University

Mapping Document for FAC-010-3

Reliability Centered Asset Management (RCAM)

NZQA registered unit standard version 4 Page 1 of 6. Carry out acceptance, commissioning and maintenance tests on power transformers

B Improvements on High Voltage Electrical Substations to face the new Brazilian Legislation. G. M. Bastos (*) R. C. Valente E.

Maintenance Optimization: A Critical Aspect of the Equipment Reliability Program

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TOGA Electrical Insulating Fluid Analysis. Improving performance and protecting assets.

DISTRIBUTION SYSTEM ASSET CONDITION ASSESSMENT UPDATE

Utility Licence Annual Technical Report

GE Grid Solutions ASSET LIFECYCLE FLEXIBLE SERVICES OPTIMIZING GRID ASSET MANAGEMENT MANAGEMENT STRATEGIES

Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL Billy E. Brown, Executive V.P.

IMPROVING HVDC SYSTEM RELIABILITY

FUNDAMENTAL ASPECTS OF INFORMATION PROCESSING TO SUPPORT ASSET MANAGEMENT

MySiteCondit ion ABB Ability TM Life Cycle Assessment for Elect rical Syst ems

Meter and billing auditing of commercial and industrial electricity customers in a Metro Municipal Electricity Utility

Substation Asset Methodology Framework

Living on borrowed time

Executive summary. by Vanya Ignatova and Chuck Hoeppner

Circuit Breaker Asset Management Using Intelligent Electronic Device (IED)- Based Health Monitoring

Information Document Protection System Information ID# R

Capacity Performance FAQ Response

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

INFORMATION SYSTEM SOLUTION FOR RELIABILITY BASED ANALYSIS AND DEVELOPMENT OF DISTRIBUTION NETWORKS

ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS

ABSORPTION FILTERS FAP SERIES

What Factors Determine How Much and How Often?

Improvement in Reliability Analysis using Distributed Generators

Managing System Performance

International ejournals

Standard Development Timeline

Electricity Industry Act Electricity Distribution Licence Performance Reporting Handbook

Transcription:

NETWORK ASSET CONDITION ASSESSMENT AND REFURBISHMENT PLANNING D J Vrey (Senior Eng, M.Ing, Pr.Eng, NETGroup South Africa) M E N du Preez (Managing Dir, M.Ing, Pr.Eng, NETGroup South Africa) H H van der Merwe (Senior Tech, N. Dip, NETGroup South Africa) Abstract. Ageing infrastructure is a major problem in the Electricity Supply Industry due to demand growth and performance requirements. It is further exacerbated by higher equipment loading and reluctance in replacement program, and can most probably be regarded as one of the major crippling factors within electrical utilities. Utilities acted as if equipment would last forever. This is changing, largely because it is becoming obvious that equipment eventually fails. By following a systematic approach, supported by a computerised system, utility engineers can make informed decisions regarding future strategies to extend the life of equipment through altered maintenance policies or de-rating, or to refurbish or replace equipment. Keyword Index Equipment age, condition assessment, reliability 1 Introduction Many electric distribution networks around the world are experiencing difficulty in meeting their customer service quality targets and stakeholder profit margins [6]. These problems are due to the fact that large portions of their systems consist of ageing infrastructure. A power system composing mostly old equipment near the end of its useful lifetime, configured in a layout that is itself quite old and not completely compatible with modern needs, produces reliability, maintenance and budgeting challenges. If these challenges are not anticipated and brought under control, they will eventually overwhelm even the most effective organization. Many traditional utilities seem incapable of proactively addressing this ubiquitous and looming problem. More than any other issue, ageing infrastructure illustrates the potential of asset managers to address critical transmission and distribution problems. First, it forces asset owners (executive management) to articulate clear goals in terms of budget, system performance and acceptable risk. It also requires an asset registry that tracks, at a minimum, the age of each piece of equipment in the field. Engineers can then perform detail technical analysis such as inspect, repair, extend life, replace and make system modifications. This analysis must take a multiyear approach, since ageing infrastructure cannot be addressed in a single budget cycle. If performance and risk targets cannot be met within budget constraints, asset owners must decide which target to relax [6]. 2 Asset Management Along with network performance improvement strategies, network refurbishment strategies form a major focus of Asset Management. Asset Management is the art of balancing cost, performance, and risk. 2.1 Asset Management Goals In its most general sense, asset management is a business approach designed to align the management of asset-related spending to corporate goals. The objective is to make all infrastructure-related decisions according to a set of stakeholder driven criteria. The payoff will be spending decisions capable of delivering the greatest stakeholder value from the investment. Asset management is thus a corporate strategy that seeks to balance performance, cost and risk. Achieving this balance requires the alignment of corporate goals, management decisions and technical decisions. The typical goals of asset management are to [4]: Balance cost, performance and risk, Align corporate objectives with spending decisions, and Create a multiyear asset plan based on a rigorous and data driven process. Along with the above goals utilities face the challenge of reducing cost and increasing levels of reliability. To manage this, financial instruments that link reliability to profits are becoming increasingly more common. Examples include performance-based rates and performance guarantees, more loosely referred to in this paper as performance or reliability target.

2.2 Performance Targets In their most general form, performance-based targets are regulatory statutes, referred to as performance based rates (PBR s), that rewards utilities for good reliability and penalize poor performance. Regulators use PBR s under rate cap situations to counteract the tendency of utilities to cut cost and allow reliability to suffer. Performance is usually based on average customer interruptions measures such as System Average Interruption Duration Index (SAIDI) and System Average Interruption Frequency Index (SAIFI). Reliability guarantees on the other hand are the simplest method of giving customers choice. Each customer chooses a performance contract. Expensive contracts guarantee high levels of performance while basic contracts guarantees modest levels of performance and the cheapest contracts do not provide guarantees. Customers experiencing reliability below guaranteed levels receive rebate checks or credits on their energy bill. Both these instruments relate directly to the topology of the system supplying customers, as well as the performance of individual component within the system. Network reliability assessment is well understood by asset investment planners and forms a key part of network planning. 3 Equipment Reliability & Ageing Good distribution planning ensures that money spent today has lasting value in future. Along with service-level voltage, reliability is a critical performance measure for distribution systems due to its high impact on cost and customer satisfaction. In addition, as mentioned above, Regulators are moving towards adopting reliability targets that utilities are expected to achieve. The primary performance measure of distribution asset planning is thus reliability, and the primary risk measure is the probability of not meeting reliability targets [3]. Reliability, in the context of this paper, refers to the frequency and duration of power outages, and the ability / capacity of the system to transmit energy while in service. Both these network attributes (outages / capacity) are influenced by the age and condition of network components. System reliability models typically use average equipment failure rates and nominal equipment ratings in prediction models. Although generally acceptable for capital planning, the use of average values has two drawbacks. First, average values cannot reflect the impact of relatively unreliable equipment and may overestimate the reliability of worst performing networks. Secondly, average values cannot reflect the impact of equipment condition. Component age and condition thus needs to be considered when predicting system performance. 3.1 Equipment Reliability as a Function of Age Component reliability parameters, such as failure rate (λ), Mean Time to Repair (MTTR), and Probability of Failure (P), are used to measure component behaviour in order to predict system performance. The reliability of a component in terms of component ageing is defined through the hazard rate curve which characterizes the operating life for a component. Figure 3-1 shows the increase in expected component failure as a function of age for a switch and distribution transformer. Failure Rate Failure Rate 1.00 0.80 0.60 0.40 0.20 0.00 1.00 0.80 0.60 0.40 0.20 0.00 Distribution Transformer 10 20 30 40 50 60 70 Time Switch 10 20 30 40 50 60 70 Time Figure 3-1: Equipment Hazard Rates Table 3-1: [5] further shows component failure rates for various power system components as a function of age. Table 3-1: Component Failure Rates Component λ new λ real λ old Substation Transformer.003.02.15 Distribution Transformer.0007.005.037 Overhead Line.042.2.96 Underground Cable.005.02.082 Circuit Breaker.0009.0066.049 Switch.007.05.37

3.2 Equipment Rating as a Function of Age Apart from reliability, the ageing of equipment further results in a reduced capacity or rating. Since the major nodes of deterioration and failure are often heat-related or other servicestress created causes, such as failures, one option available to an operator is to reduce the loading or to change the maintenance strategy in order to increase the expected lifetime of the equipment. Figure 3-2 shows a de-rating curve for a power transformer that has an expected 40-year lifetime and has already seen 30 years of service at designed load levels. Peak load can be no more than Percent of Nominal De-Rating that must be applied to provide expected 30-year remaining lifetime 120 100 80 60 40 20 0 0 10 20 30 40 50 60 Time Already in Service Figure 3-2: Transformer De-rating Curve Figure 3-3 shows the same power transformer under different maintenance policies [2]. Asset Value Initial Asset Value Remaining Values Policy 1 Policy 2 Time Incremental Asset Value Life Extension Figure 3-3: Transformer under different maintenance policies 4 Equipment Condition Assessment Traditionally utility managers, engineers and operators managed equipment lifetime and failure as if it were out beyond the planning horizon. Those failures that did occur were treated as anomalies, due to flaws, mistakes or just plain bad luck. This is changing, largely because it is becoming obvious that equipment does eventually fail. Figure 4-1: Equipment Condition A simple and practical approach to ensure that electrical infrastructure life expectancy is planned to meet future needs, is achieved by adopting a thorough asset condition assessment and refurbishment planning process. The main objectives of such a process include: The development of a systematic replacement or refurbishment program, driven by asset condition and age, and The assessment of the perceived performance (reliability) and thermal capability of assets. Both the above attributes impacts directly on Asset Management of Regulatory targets. 4.1 Condition Assessment Methodology A life extension or refurbishment program that will permit continued economical operation of electrical infrastructure must address both: Individual facilities as they approach design life, and Individual equipment on a system wide basis. Site specific assessment is conducted that provides a systematic across the board estimate of the remaining life of electrical facilities. The process is based on a number of tasks of which the main tasks include: The definition of the condition assessment methodology, Definition of utility standards, targets and criteria, Identification of equipment to be included in the investigation, Review and interpretation of historical information and reports related to the equipment under investigation,

Development of attributes, criteria and weighting factors for each equipment type, A physical visual inspection, The identification of critical equipment, earmarked for further investigation or replacement, The development of a multiyear refurbishment plan, and The development of predictive performance and capability measures. establishment of the criticality of equipment can be achieved through prior sensitivity analysis assessing the outcome of equipment scores related to the corporate objectives or goals or may be specified by the utility. 4.2.2 Equipment Assessment Attributes and Weight Once the equipment to be included in the condition asset condition assessment exercise has been selected, the basic attributes, criteria and associated weights are developed for each piece of equipment. Table 4-1 shows typical attributes and the associated maximum weight for each attribute of a power transformer. A scoring guideline is shown in Table 4-2. The totalling of weight result in a score which prioritises individual equipment related to the entire system. Table 4-1: Power Transformer Inspection Form Figure 4-2: Condition Assessment System 4.2 Condition Assessment System A technical condition assessment system has been developed by NETGroup that allows for the set-up of refurbishment projects in a structured manner. The system allows for the capturing of equipment condition information through mobile technology, followed by systematic evaluation and prioritisation of refurbishment projects and actions. The system is dynamic in nature in that it allows for projects to be set-up individually without the reconfiguration of database structures to specific utility needs. The following equipment structure is used: Equipment Type: (Power Transformer) - Attribute: (Condition of Tank) - Criterion: (Damaged / Good) - Weight: (0 to Max weight) 4.2.1 Equipment Definition Depending on the goals and objectives, different equipment types could be included in the assessment exercise. Equipment could be only substation related or may also include lines and cables. Substation equipment may further include only critical equipment and ignore less important equipment. The Attributes Weight Score Age (year of operation) 8 Oil type 1 Condition of tank 1 Condition of tap changer 2 Condition of Cooling 1 Condition of bushings 2 Condition of insulation 2 Transformer loading 3 Mechanical stress 3 Dielectric stress 2 Noise level 1 Gas in oil analysis 5 Oil analysis 6 Experience with unit 4 Table 4-2: Score Guideline Age (years of operation) Score Less than 1 0.00 1 10 0.05 11 25 0.20 26 29 0.40 30 35 0.60 36 40 0.80 Greater than 40 1.00

4.2.3 Data Collection and Technical Audit The information used for the study is usually obtained from the utility for review purposes, followed by discussion with key personnel. The technical audit comprises of an exercise where basic information about the installations are obtained and evaluated on site. A further phase allows for a design engineer to evaluate this basic information and to provide a technical perspective of the state, suitability of the design and maintainability of the equipment. Data collection and infrastructure visual inspections allows for: A systematic review of infrastructure that may have reached or exceeded their original design life, Identify systems, structures and equipment approaching wear-out or becoming obsolete, Prioritise replacement, refurbishment, and follow-up tasks, and Support the development of a capital program that will ensure economic network refurbishment. It must be noted that a preparation exercise to exhaust readily available information prior to the site visit is essential. 4.3 Condition Assessment Outcome The outcome of the asset condition assessment is primarily: The development of a systematic replacement or refurbishment program, driven by asset condition and age, and The assessment of the perceived performance (reliability) and thermal capability of involved assets. A key output from the assessment is a prioritised list of equipment condition and age profiles. As an example, a standard output from the condition assessment systems is a prioritised view of substation scores within a distribution network, such as shown in Figure 4-3. Substations with the highest score are predicted to have the oldest and worst performing equipment. Figure 4-3: Weighted Substation Scores 4.3.1 Prioritised Equipment Condition Through the evaluation of the prioritised list, engineers obtain actual information regarding specific equipment condition such as failed equipment components or conditions that might cause failures. This information is manipulated to identify strategic actions to rectify or mitigate possible violations [2]. These actions include: Maintain existing maintenance policy or change maintenance policy to ensure effective operation. This action is usually applicable to equipment regarded as being in normal condition, or Follow a strategy whereby equipment should be refurbished, or replaced. Normally this decision is based on age or further diagnostic tests. Options Continue as Before Overhaul Replace Delay in Action Present Policy Cost Equipment Model Input Cost of Failure Consequences Equipment Model Cost Reliability Expected Cost of Failure Expected Cost of Failure Reliability New Policy Net Present Value Figure 4-4: Strategic Option Selection 4.3.2 Equipment Age Profiles Age can be used for the longer-term planning or the strategic planning phase of the exercise and gives guidance to the number and location

of equipment approaching or exceeding its expected useful life. Although age in itself does not provide any conclusive information on the state of equipment or the need to refurbish or to replace, it does provide a good overview of the extent of the task at hand. Age profiles are used to highlight the following aspects: It provides insight into the state of the network, Identify replacement cost of assets older than a certain age, List and phase equipment to be refurbished or replaced in order to maintain an age of less than a specified value, and At what rate equipment age will increase if the current replacement or refurbishment rates are adhered to for the next 20 years. Figure 4-5: Transformer Age Profiles 4.3.3 Failure Rate Model As previously indicated, there exist a relation between equipment age / condition and its failure rate. The basis for predicting equipment failure rate lies in sufficient historical data. This allows for the use of regression-based equations to interpolate failure rates corresponding to the worst and best condition scores. An exponential model normally best describes the relationship between the normalized equipment condition and equipment failure rates [1]. A typical formula is shown in equation 4-1: λ ( x ) = Ae Bx + C (4-1) achieved by defining best, average and worst condition scores of 0, 0.5 and 1, corresponding to λ(0), λ(0.5) and λ(1). These equipment failure models are used as basis for network reliability assessment to predict network performance in relation to performance targets. 4.3.4 Capacity Model A further output from the condition assessment exercise involves the development of capacity models for critical equipment such as transformers and cables. These are only done for the equipment, probably less than 10%, which could not be classified as normal. The basic failure model for a transformer, shown in Figure 4-6 [7], assumes that there are a number of key parameters (such as dielectric, thermal or mechanical strength), that when exceeded, will lead to failure. The withstand strength of transformer will naturally decrease over its life due to various ageing processes, but may deteriorate faster than normal under the influence of agents of deterioration, e.g. moisture, or if some abnormal destructive deterioration process occurs. For the identified units, on-line diagnoses are carried out which might include magnetizing current, frequency response analysis, partial discharge and dielectric response measurements. Strength Fault occurs Failure with fault Failure without fault Ageing without fault Stress Ageing with fault new AGE old Figure 4-6: Transformer Failure Model Once analysed, similar strategies as shown in Figure 4-4 can be followed to extend the units life or recommend replacement. As an example, the unit might be de-rated to ensure that the expected useful life be reached. Where: λ = failure rate, x = condition score, Three data pairs are further required to solve for parameters A, B and C. This can be

5 Consolidated Refurbishment Plan The key success to the refurbishment plan lies in the integration of equipment refurbishment or replacement with the strategic network development or strengthening plan. The development plan forms part of an organisation s Asset Management strategy and should comply with the objectives and goals of the Asset Management strategy. The refurbishment plan is thus a key ingredient to the effectiveness of the Asset Management strategy, due to the fact that it directly influences network performance and capacity. Through the analysis of the results obtained from the equipment condition exercise, the planning engineer can develop a strategic refurbishment plan. The plan consists of equipment renewal and life extension programs and provides the following input to the network development plan: An equipment replacement schedule and associated cost estimates for both primary and auxiliary equipment, Recommendations with regard to equipment life extension strategies in terms of component refurbishment or changes in maintenance strategy, and Recommendations for equipment performance and capacity parameter adjustment for the use in load flow and reliability simulations. 6 CONCLUSION Reliability is a critical performance measure for distribution systems due to its high impact on cost and customer satisfaction. Substantial portions of electrical networks throughout the world consist of infrastructure approaching or exceeding their expected useful life. Equipment age and condition has a direct influence on network reliability. This paper has shown that through a systematic approach, supported by a computerised system, the condition and age of equipment can be assessed. Once filtered and prioritised, specific actions can be developed to extend the life of equipment through altered maintenance policies or de-rating, or refurbishment or replacement based on age or recommendations supported by diagnostic test. The paper has further shown that through the development of equipment failure and rating models, network performance prediction can be enhanced. These models provide improved insight to the actual network performance in relation to performance target, which in turn allows for more accurate identification of equipment responsible for target deviances. 7 REFERENCES 1. Brown R.E, Frimpong G, Willis H.L., Failure Rate Modeling Using Equipment Inspection Data, IEEE Transactions on Power Systems, VOL. 19, NO. 2, May 2004, 2. Anders G.J, Endrenyi J., Yung C., Riskbased Planner for Asset Management, IEEE Computer Applications in Power, October 2004, 3. Brown R.E., Hanson A.P., Willis H.L., Luedtke F.A., Born M.F., Assessing the Reliability of Distribution Systems, IEEE Computer Applications in Power, January 2001, 4. Brown R.E, Spare J.H., Asset Management, Risk and Distribution System Planning, IEEE Transactions on Power Systems, 2004, 5. Ross D.P., Welch G.V., Willis H.L., Sensitivity of System Reliability to Component Aging in Metropolitan, Urban and Rural Areas, IEEE Transactions on Power Systems, 2001, 6. Willis H.L., Welch G.V., Schrieber R.R., Aging Power Delivery Infrastructure, ISBN:0-8247-0539-4, 2001, 7. Guuinic P., Aubin J., CIGRE s Work on Power Transformers, Paper presented at the EPRI Substation Equipment Diagnostics Conference IX, February 18-21, 2001, New Orleans, Louisiana, USA.