COGPEM26 - SQA Unit Code FP3J 04 Hand over process engineering plant and equipment

Similar documents
COGPEM78 - SQA Unit Code FP6K 04 Monitor the performance and condition of instrument and control systems

COGPEM57 Determine the feasibility of repair of components from electrical plant and equipment

COGPEM51 - SQA Unit Code FP4K 04 Diagnose and determine the causes of faults in electrical plant and equipment

COGPEM14 Carry out planned maintenance procedures on electrical process plant and equipment

COGPEM20 Carry out planned maintenance procedures on instrument and control plant and equipment

COGPEM08 - SQA Unit Code FP6N 04 Carry out planned maintenance procedures on mechanical process plant and equipment

COGPEM42 - SQA Unit Code FP7A 04 Read and extract information from mechanical engineering drawings and specifications

COGPEM73 Determine the feasibility of repair of components from instrument and control systems

COGPEM48 - SQA Unit Code FP5P 04 Inspect mechanical plant and equipment

SFJCCBF3.1 (SQA Unit Code - HD6R 04) Develop and sustain effective working with staff from other agencies

COSVR712 - SQA Unit Code H6AS 04 Manage own professional development

COGSBP24 Control Efficient Transport Usage within Sustainable Business Practice

SFS6 Work effectively with other agencies

COSVR702 - SQA Unit Code H6AL 04 Plan work activities and resources to meet work requirements

EUSNCO309 - SQA Unit Code HG38 04 Monitor the installation process for Network Construction Operations

CFABAA SQA Unit Code FE17 04 Prepare, co-ordinate and monitor operational plans

SFSSCN4 Oversee the implementation of security measures

Overview COGESA4.10. Solve explosives process problems. This standard comprises the following elements:

SEMBIT SQA Unit Code F9HK 04 Applying failure modes and effects analysis (FMEA)

CFABAA122 SQA Unit Code FE18 04 Implement, monitor and maintain administrative services

SEMBIT SQA Unit F9J4 04 Carrying out measurement systems analysis (MSA)

[Unique Reference Number] Achieve effective working relationships with colleagues in bus/coach engineering and maintenance

SQA Unit Code H4R5 04 Maintain and develop your own knowledge, skills and competence

Overview COGESA2.12. Analyse and identify aggregated hazards and risks for explosives

SFJ CO5 SQA Unit Code H55W 04 Maintain the reliability and readiness of fire and rescue control operations and equipment

COGODO7(SQA Unit Code-F221 04) Carry out general cleaning operations

COGODO7 Carry out general cleaning operations

SEMBIT SQA Unit Code F9JK 04 Contributing to the application of measurement systems analysis (MSA)

COSVR705 - SQA Unit Code H6AP 04 Allocate and monitor the use of plant, equipment or machinery

SEMPMO223 - SQA Unit Code H04A 04 Recording and reporting inspection and test results

QUALIFICATION SPECIFICATION

FSPIO03 SQA Unit Code H5GN 04 Reconcile investment market transactions

SEMBIT SQA Unit Code F9HL 04 Applying flow process analysis

SEMBIT3-03 Applying workplace organisation techniques

SEMBIT SQA Unit Code F9J7 04 Carrying out set-up reduction techniques

PROSMD14 Assess, plan and control capital costs for development

SEMBIT SQA Unit Code F9HT 04 Applying set-up reduction techniques

SEMPMO102 - SQA Unit Code H03J 04 Developing and maintaining working relationships

SFJ CO9 SQA Unit Code H Drive, manoeuvre and redeploy fire and rescue vehicles

ECIPMD7 Monitor and review project risks

COSVR586(SQA Unit Code-H4X8 04) Resolve indeterminate situations

SEMBIT SQA Unit Code F9J2 04 Carrying out capability studies

SEMPMO108 - SQA Unit Code H03R 04 Carrying out shaping operations

SEMBIT SQA Unit Code F9K1 04 Producing a characteristic selection matrix

COSVR709 - SQA Unit Code H6AR 04 Control work against agreed quality standards

SEMPMO104 - SQA Unit Code H03L 04 Getting ready for manufacturing operations

COSVR210 Develop and maintain good working relationships

ASTHSS1 - SQA Unit Code F7EG 04 Make sure your own actions reduce risks to health and safety

SFSREM8 Maintain the performance of remote monitoring systems

COSCCOC02 (SQA Unit Code - HA3N 04) Prepare programmes and schedules of work in construction

COSVR71 SQA Unit Code HL77 04 Install mechanically fixed plasterboard

This standard deals with the following: 1. Measure out materials in specified quantities 2. Prepare materials for process operations

ASTCO3 Ensure that your own actions reduce risks to health and safety

This standard deals with the following:

SFL45 SQA Unit Code (HA66 04) Identify suitable collection and delivery points

COSBEDO02 - SQA Unit Code F50J 04 Maintain professional relationships and practice in built environment design

SKAA52 Support the work of your team and organisation

SEMBIT SQA Unit Code F9JA 04 Carrying out value stream sapping (VSM)

COSVR214 Allocate and monitor the use of plant, machinery or equipment

COSVR477 SQA Unit Code HM2F 04 Machinery and equipment maintenance

CFABAA312 - SQA Unit Code H46B 04 Organise and co-ordinate events

COSVR257 HL4M 04 Commission lightning conductor installation systems

SEMBIT SQA Unit Code F9JD 04 Contributing to carrying out lead time analysis

SFJ HI1. Plan, implement and manage the sharing of knowledge and. practice to inform innovation and improve service delivery

COSCSMO08 SQA Unit Code H99R 04 Evaluate sustainable resources and requirements for the whole life cycle of a construction project

SEMBIT SQA Unit Code F9J3 04 Carrying out flow process analysis

ECIPMD4 Manage agreed project changes

SKAALA52 Contribute to the work of your team

SKAC215 (SQA Unit Code - D1NP 04) Promote the conservation of the environment

ECIMPSM13 - SQA Unit Code FP7E 04 Test the performance and condition of mechanical plant and equipment

CCSAPAE1 Develop information systems to meet the needs of users

SKAD459 (SQA Unit Code - FG6G 04) Evaluate exercise and physical activity programmes

V COSVR??? Dynamic load and integrity testing of piles

SCDLDSS415 Develop and sustain effective working with staff from other agencies

COSVR728 - SQA Unit Code F3H7 04 Evaluate and select work methods

SFJ EFSM15 Develop teams and individuals to enhance work based performance

SFJHI1 - SQA Unit Code F33C 04 Plan, implement and manage the sharing of knowledge and good practice to inform innovation and improve service delivery

COSVR375 SQA Unit Code HL5P 04 Lay flexible pavement materials

Overview SFSSLP4. Control security incidents

SFJCH201 Plan, prepare and occupy static covert observation posts in an urban environment

Overview COGPIO4.9. Monitor and evaluate energy efficiency in processing industries operations

SEMMAN SQA Unit Code FR0T 04 Working efficiently and effectively in engineering

COSVR767 SQA Unit Code HG63 04 Prepare and mix earth plasters and earth renders

National Occupational Standards. Offshore Surveying and Positioning

COSVR296 Install supplementary steel frame finishings

SEMBIT SQA Unit Code F9JR 04 Contributing to the application of workplace organisation techniques

COSVR618 - SQA Unit Code FW1L 04 Finish dry lining walls or ceilings

SKAD214 (SQA Unit Code - FA4E 04) Support equality and diversity in active leisure and recreation

Overview COSVR777. Operate and control operations of road plant, machinery or equipment for planing or milling operations

COSVR133 - SQA Unit Code DY1W 04 Install raised access flooring systems

SKAC12 (SQA Unit Code - FA4F 04) Set up, take down and store activity equipment

Overview COSVR130. Install plasterboard linings

Overview. COSVR204 - SQA Unit Code HP7M 04. Contribute to stone cladding lifting procedures

SKAA319 Recruit, select and keep colleagues

COSVR221 - SQA Unit Code HM0W 04 Form drill holes or core in the structural fabric

COSVR221 (SQA Unit Code - H1P5 04) Form drill holes or core in the structural fabric

COSVR400 Operate powered units, tools or pedestrian plant, machinery or equipment

COSVR186 - SQA Unit Code FW1A 04 Remove existing wall cladding systems

COSVR166 (SQA Unit Code - FW1E 04) Cut and bend reinforcement steel to shape

SFJCB1 Gather and submit information that has the potential to support law enforcement objectives

Transcription:

Hand over process engineering plant and equipment Overview This unit is about your competence in completing safe and effective hand over of plant and equipment. It includes the hand over to others and your acceptance and confirmation of responsibility for the control of the plant and equipment. This unit is common to the Electrical, Mechanical and Instrument & Control disciplines. This unit deals with the following: 1 Hand over plant and equipment 2 Accept and confirm responsibility for the control of plant and equipment During this work you must take account of the relevant worksite operational requirements, procedures and safe working practices AS THEY APPLY TO YOU. Previous Version: Adapted from Unit C3.1 of Process Engineering Maintenance NOS version February 2004. This unit is a tailored version of an Electrical unit produced by the ECITB from the OSC Eng Engineering Competence Standards (ECS 7.03 & 7.02) which was originally designated MPS Elec 16. COGPEM26: 1

Performance criteria You must be able to: P1 work safely at all times, complying with health and safety and other relevant regulations and guidelines P2 confirm and define the condition of the engineering products or assets in accordance with specifications P3 clearly define and obtain agreement on the moment of transfer of responsibility P4 communicate hand over of control as specified P5 produce and maintain records of the hand over in accordance with organisational procedures P6 make sure that the information received at hand over is accurate, up-todate and complete P7 seek additional information if there are any areas of doubt or lack of clarity P8 provide proper support and co-ordination to those transferring control P9 confirm and record acceptance of responsibility and control in line with agreed procedures COGPEM26: 2

Knowledge and understanding You need to know and understand: K1 K2 K3 K4 K5 K6 you must have a working knowledge and understanding of what your responsibilities are in respect of Heath, Safety and Environment. This should include the limits of your personal responsibility, your legal responsibility for your own health and safety and the health and safety of others you must have a working knowledge of the relevant regulations and the safe working practices and procedures required within your work area you must have a working knowledge and understanding of the types of support through your working relationships that can be offered to those transferring control you must have a working knowledge and understanding of the hand over procedures for products or assets. This should include when the hand over should occur, how to confirm the precise moment of transfer, and why it is important to define the precise moment of transfer you must have a working knowledge and understanding of the record and documentation systems and procedures. This should include the level of detail on the condition of engineering products/assets as required by different parties, how to confirm that information received at hand over is accurate and complete, and what the types of situation are where additional information and clarification might be required you must have a working knowledge and understanding of your responsibilities with regard to the reporting lines and procedures in your working environment COGPEM26: 3

Additional Information Scope/range related to performance criteria 1 The level and extent of responsibility is limited to working within clearly defined specifications for hand over situations. In some cases, you may still be expected to refer to others for final authorisation, even though you remain responsible for identifying and implementing decisions 2 The type of products or assets could include: 2.1 Systems & sub-systems 2.2 Process equipment 2.3 New installations 3 The hand over procedures and environments may be under operational or non-operational conditions. A typical example of a hand over during operational conditions could be: 3.1 Shift changes on continuous process plants A typical example of hand over under non-operational conditions could be: 3.2 Between maintenance and operational teams at the end of an overhaul 3.3 Hand-over of a large on-going maintenance project 3.4 Hand over from in-house maintenance teams to outside specialists 3.5 Shift to shift 4 The parties to hand over to could include: 4.1 Clients 4.2 Production operations 4.3 Maintenance engineers 4.4 Line supervisors 5 The Complexity of hand-overs could include: 5.1 written 5.2 Oral 5.3 Test documentation COGPEM26: 4

Scope/range related to knowledge and understanding The Knowledge and Understanding levels expressed indicate the minimum level of knowledge and understanding sufficient to perform your role in a manner that would normally be associated with the minimum acceptable performance of a competent person undertaking your role. The expression working knowledge and understanding indicates you are able to: 1 Identify and apply relevant information, procedures and practices to your usual role in your expected working environments needing only occasional recourse to reference materials 2 Describe, in your own words, the principles underlying your working methods. This does not mean the ability to quote Chapter and verse. Rather you must know what supporting information is available, how and where to find it and from whom to seek further guidance and information confirm any additional required detail 3 Interpret and apply the information obtained to your role, your working practice and in your expected working environment COGPEM26: 5

Developed by Cogent Version number 1 Date approved May 2010 Indicative review date Validity Status Originating organisation May 2012 Current Tailored ECITB Original URN MPS Elec 16 Relevant occupations Suite Key words Engineering Professionals; Engineering and manufacturing technologies; Manufacturing technologies Process Engineering Maintenance hand over, confirm, accept, process, engineering, plant, equipment COGPEM26: 6