Why THP Made Sense for TRA

Similar documents
Thermal Hydrolysis Comes to Texas!

Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant. February 2015

COMMISSION MEETING. April 18, Engineering and Construction Team. Piscataway WWTP Bio-Energy Commissioners Status Briefing

Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.

Thermal Hydrolysis The Next Generation

The TRA CRWS Master Plan. Past, Present, & Future of CRWS. Kaylee Dusek, EIT, Garver Matt Jalbert, PE, TRA

4/23/2012. Program development to Preliminary Design level by the Biosolids Program Manager. Thermal hydrolysis/digestion challenges and innovations

January 21, Presented by Lynne H. Moss, PE, BCEE

Solids Master Plan Briefing June 22, 2017

Sustainable Biosolids Management: Direct Energy Use Does Not Tell All

Application of the AGF (Anoxic Gas Flotation) Process

COMMISSION MEETING. June 21, Engineering and Construction Team. Piscataway WWTP Bio-Energy Commissioners Status Briefing

APPENDIX A. 1. Background. 1.1 Existing Facilities. Page 1

innovation & technology Water Digelis Turbo Boosting biogas production for greater energy recovery

Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project

WEF Residuals and Biosolids Conference 2017

Little Patuxent WRP 8 th Addition - Biosolids Processing Facilities Improvements

DC Water Class A EQ Biosolids

WWTP Side Stream Treatment of Nutrients Considerations for City of Raleigh s Bioenergy Recovery Project. Erika L. Bailey, PE, City of Raleigh

ES.1 Solids Master Planning Background and Goals

THERMAL HYDROLYSIS: DESIGN, COMMISSIONING AND LESSONS LEARNED THROUGH A HISTORY OF INSTALLATIONS GREG KNIGHT

Advanced Aerobic Digestion. ThermAer. Autothermal Thermophilic Aerobic Digestion. Biosolids Treatment. Thermal Process Systems ThermAer Process

January 25, Utility of the Future One City s Journey

Workshop on good practices and experience in sludge management

JTI Swedish Institute of Agricultural and Environmental Engineering

DC WATER CAPITAL IMPROVEMENT PROGRAM (CIP)

Maximizing Benefits from Renewable Energy at Blue Plains AWWTP RESIDUALS & BIOSOLIDS CONFERENCE 2010 SAVANNAH, GA

Center Sanitation District

Co-Digestion of food wastes at wastewater treatment plants. Alice Varkey, PEng Senior Engineer Mike Muffels, MSc PEng Senior Engineer June 2016

Dewatered Cake Lime Stabilization at the Ann Arbor WWTP

THERMAL HYDROLYSIS AND ENERGY REDUCTION IN BIOSOLIDS PROCESSING

The Biosolids Odor Reduction Roadmap (BORR): A Decision Tool to Reduce Cake Odors

Palmer Wastewater Treatment Plant 6.7 Alternative 7: Upgrade Existing Lagoons with New Percolation Bed

Thermal Process Systems. Quality Biosolids Through Advanced Technologies

EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT

Codigestion Case Studies Enhancing Energy Recovery From Sludge

Resources and Energy Management at IEUA s Regional Water Recycling Plant No. 1

HWEA Conference March 16, 2010 ThermAer : A New Day for ATAD Thermal Process Systems

Executive Summary. ES.1 Introduction

Thermophilic anaerobic digestion for increased biogas production and pathogen control

Sewage Sludge Treatment in Large Cities Using the Example of Berlin

Industrial Services.

Conducting Successful Energy Audits for Both Water and Wastewater Utilities By: Rich Atoulikian, HDR

WEF Residuals and Biosolids Conference 2017

PRODUCT OFFERING BIOSOLIDS MANAGEMENT & RESOURCE RECOVERY GROUP. Interested in smaller sludge volumes & enhanced ph?

PANEL DISCUSSION: PLANNING FOR SUSTAINABLE RESOURCE RECOVERY PROGRAMS

Chapter 2: Description of Treatment Facilities

Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant

Taking the Waste out of WAS: Sludge Pretreatment for Beneficial Uses

Municipal Wastewater Engineering

Solids Master Plan Briefing October 27, 2016

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010

Biosolids and Carbon Footprint

Harrisburg Advanced Wastewater Treatment Facility Biosolids Facilities Improvement Plan Existing Conditions Report. February 2017

intra Newsletter of the Trinity River Authority of Texas The future of biosolids

Excellence in Engineering Since 1946

ENERGY MANAGEMENT AT WWTP WITH BIOGAS UTILISATION

A -M WRF Solids Alternatives. Joint City Council Meeting

Operating Experience with Ostara Struvite Harvesting Process

THE INFLUENCE OF HEAT BALANCE ON THE ECONOMICS OF ADVANCED ANAEROBIC DIGESTION PROCESSES

Solids Processing Challenges at WSSC Western Branch Can An Innovative Technology Offer a Solution?

Solids Treatment and Management in a Changing Environment! Biosolids and Renewable Energy Specialty Workshop! May 12-13, 2015!

Sustainable Energy Management

Polishing Ponds. Biosolids Storage. Ammonia Removal. Digesters. Thickeners. Pretreatment. Final Clarifiers. Primary Clarifiers.

Technological options for fecal sludge treatment in urban areas: case study in Beijing

Prepared by the Operation of Municipal Wastewater Treatment Plants Task Force of the Water Environment Federation

SWIM-H2020 SM Regional Activities 14

Masses at Massillon: IFAS for Industrial Loads and Nutrient Removal

Sludge Workshop 3rd April 2017 Zagreb. Isabelle LEBLANC -

Converting Digester Gas to Steam and Electricity at the Blue Plains AWTF

HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN

Ohio Water Environment Association December 3, 2015 Biosolids Workshop. Southerly Renewable Energy Facility

Thermal Hydrolysis Processes. Reduces sludge volume. Improves sludge quality. Increases biogas production WATER TECHNOLOGIES

Study Session Wastewater Enterprise, Proposed Improvement Projects and Projected Funding Needs Update

Learning Wastewater Treatment

Bio Thelys batch thermal hydrolysis. Reduces sludge volume. Improves sludge quality. Increases biogas production WATER TECHNOLOGIES

TO: Public Works Commission FROM: Robyn Mattison, Jim Pardy, and Paul Zimmerman DATE: April 5, 2017 RE: Water Renewal Fund Capital Projects

City of Elk River Wastewater Treatment Facility Improvements. Achieving Wastewater Treatment Goals

Orange County Utilities ANNUAL BIOSOLIDS REPORT

Module- 35. Lec- 35. Dr. ShishirSinha Dept. of Chemical Engineering IIT Roorkee

Pre-RFP Meeting for Integrated Wastewater Treatment Plant Master Plan (MWWTP Master Plan) Presentation to Interested Parties. September 13, 2018

Lycoming County Water and Sewer Authority WWTP Mechanical Thickened Aerobic Digester Case Study

NEW YORK STATE: WASTEWATER DIGESTER POTENTIAL. June 6, 2016 George Bevington

Anaerobic Processing Principles & Technologies. Endeco

NAWT Septage Processing What are my disposal resources and how do they fit

EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION

Capital Improvement Plan Update:

SEEIT Scholarship: A Journey through the United Kingdom For Biosolids Processing Solutions

Table 1. Existing Anaerobic Digesters

ATHOS WET AIR OXIDATION PROCESS.

Without digestion tank

PHOSPHORUS RECOVERY FROM SEWAGE SLUDGE USING THE AQUACRITOX SUPERCRITICAL WATER OXIDATION PROCESS

SeRVice: Wastewater Treatment

Evaluation of Energy Recovery Options for Conversion of Aerobic Digesters to Anaerobic Digestion

Biogas Cogeneration System Sizing and Payback Based on Weekly Patterns of Anaerobic Digestion and Biosolids Dryer Operation

Wastewater treatment objecives

Anaerobic digestion = biogas process

Economic Elements LAND APPLICATION. Economic Elements. Economic Elements DEDICATED FACILITY TECHNOLOGIES

Anaerobic Digestion The New Frontier Ohio WEA Biosolids Specialty Workshop 11 December 2014 J. Hunter Long

Transcription:

Why THP Made Sense for TRA June 16, 2016

Central Regional Wastewater System Treatment Plant (CRWS) CRWS Solids Treatment Area 2

162-mgd ADF permitted and 125- mgd average daily flows Pre-THP Solids Process: Gravity thickening (Primary) DAFTs and GBTs (WAS) Blending Dewatering BFPs and Plate-and-frame press Lime stabilization CRWS Overview

TRA Solids Management Goals Produce Class A biosolids Minimize volume of biosolids Ensure redundancy and reliability Optimize use of existing structures Leverage potential markets for biosolids Maximize resource recovery

Solids Management Improvements 2011 Solids Master Plan recommendations Phase I: thickening and screening improvements Phase II: dewatering improvements Phase III: THP/digestion improvements Phase IV: additional digester and thickening for 2040 needs

Why THP made Sense for TRA Overall lowest life cycle cost Minimize volume of biosolids leaving the plant Minimize digester volume to build Produce Class A biosolids Optimize use of existing structures Leverage potential markets for biosolids in future Potential for resource recovery

Thermal Hydrolysis In Thermal Hydrolysis, sludge is heated and pressurized to make organic solids more readily biodegradable.. In other words, it s a pressure cooker. Before After

Thermal Hydrolysis Process (THP) Process gases (to digester) Raw sludge 14-18% DS REACTOR Recycled Steam 97 o C 1.5 hr PULPER 165 o C 6 bar 20 min homogenized sludge 11 bar hydrolyzed sludge steam 1.5-2 bar 102 o C 1.5 hr FLASH TANK to Digester 8-12% DS

Batch Testing Summary Testing conducted at Virginia Tech University Determined thermal hydrolysis would be an effective process for TRA 9 to 10% increase in VS destruction Ammonia production is not inhibitory, even at 42 o C, resulting in lower cooling costs Low odor product can be expected Almost 10% increase in solids concentration after dewatering Results are similar to previous testing for DC Water s Blue Plains WWTP

Proposed Solids Handling Process Primary Thickening Pre- Dewatering Biogas Dewatering Class A Land Application Solids Screening Thickening Thermal Hydrolysis Mesophilic Digestion Landfill Compost WAS Soil Amendment

Planned THP Facilities 3 thermal hydrolysis units and boiler system Heat exchangers and cooling towers 3 new digesters and digester building New pre-dewatering centrifuges, pumps, and polymer Rehab 2 existing digesters for blending/storage Chemical treatment for struvite prevention Dewatered biosolids storage and conveyance Gas pretreatment for boiler use and disposal Odor control

PHASE I Construct GT 7 Construct Primary Sludge Pump and Screening Station PS 15 (without screens) Install 2, 2-M Gravity Belt Thickeners Decommission Dissolved Air Flotation Thickeners Construct Odor Control Facility 15 New Decommission Demolish Rehabilitate Completed in Prior Phase

PHASE II Replace Elevator Rehab 3 existing BFPs Rehab lime silo roof Expand PS15, add screens Replace FP 3 with 2 new BFPs Odor control, electrical, OIP, bidding Demo Dissolved Air Flotation Thickeners New Decommission Demolish Rehabilitate Completed in Prior Phase

Project Implementation Phase I: low-bid contract in construction until spring 2016 Phase II: low-bid construction contract awarded August 2015 Phase III: final design in progress CMAR delivery method final completion expected December 2018 commissioning complete by July 2019 Phase IV: begin after Phase III complete

CMAR Procurement Overview Why Construction Manager at Risk (CMAR)? Design collaboration/quality Accelerated Schedule Cost Control Request for Qualifications Request for Proposals Contract Negotiation Board Approval First CMAR for TRA

Solids Phase III Progress CMAR contract Awarded at August 2015 Board Meeting GMP1 approved December 2015 GMP2 negotiations ended May 2016 Final completion potentially 2019 Commissioning completion 6 months after

Questions?