STRUCTURE AND BRIDGE DIVISION

Similar documents
STRUCTURE AND BRIDGE DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDA VIRGINIA DEPARTMENT OF TRANSPORATION

Bridge Preservation Beyond the Short Term

STRUCTURE AND BRIDGE DIVISION

STRUCTURE AND BRIDGE DIVISION

MANUAL OF THE STRUCTURE AND BRIDGE DIVISION

STRUCTURE AND BRIDGE DIVISION

VDOT S BRIDGE PRESERVATION PROGRAM. Virginia Concrete Conference, 2012 RICHMOND, VA. March 9, 2012

Bridge Preservation and MAP-21. Bert Hartman, Oregon DOT

Federal Highway Administration s Role in Bridge Preservation. Anwar S. Ahmad 1

LOCATION AND DESIGN DIVISION

VIRGINIA'S PREVENTIVE MAINTENANCE CHALLENGES AND INNOVATION. Rodolfo F. Maruri 1

STRUCTURE AND BRIDGE DIVISION

PUBLIC INFORMATION MEETING June 24, 2015

LOCATION AND DESIGN DIVISION

Bridge Preventative Maintenance.Act now before this happens to you! Keith Cooper, P.E. Local Bridge Program Manager

STRUCTURE AND BRIDGE DIVISION

MAINTENANCE AND REPAIR TABLE OF CONTENTS CHAPTER 32

VIRGINIA DEPARTMENT OF TRANSPORTATION MATERIALS DIVISION MEMORANDUM. Charles A. Babish, PE State Materials Engineer Approved:

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017

MASTER AGREEMENT FOR BRIDGE DESIGN SERVICES SCOPE OF WORK

National Bridge Inspection Program Risk-based, Data-driven FHWA Oversight

How to Review SI&A Data

VDOT s Experience with Reinforced Concrete and Metal Culverts

System Preservation in Louisiana

ALTERNATIVE PROJECT DELIVERY DIVISION

STRUCTURE AND BRIDGE DIVISION

TRAFFIC ENGINEERING DIVISION

2016 STRUCTURE INSPECTION APPRAISAL REPORT. Prepared For: THE CORPORATION OF THE TOWNSHIP OF AMARANTH COUNTY OF DUFFERIN

APPROACHES AND BRIDGE OVER TYE RIVER (RTE. 29 NBL) RFP QUESTIONS AND ANSWERS-REVISION 2

MANUAL OF THE STRUCTURE AND BRIDGE DIVISION

Procedure No: (SP) Effective: August 28, 2002 Responsible Office: Division of Finance and Forecasting INFRASTRUCTURE CAPITALIZATION PROCEDURE

NEW JERSEY DEPARTMENT OF TRANSPORTATION MEMORANDUM

I-64 Capacity Improvements Segment I Financial Plan Annual Update

JOINTS TABLE OF CONTENTS CHAPTER 14

PCL Definitions for the Local Program J01 3R Policy J04 3P Policy J06 Local Bridges and Township Bridge Program Bridge Work Activities

ESTIMATED QUANTITIES SHEET CHECK LIST

Project NCHRP Proposed AASHTO Guide for Bridge Preservation Actions

MANUAL OF THE STRUCTURE AND BRIDGE DIVISION

BRIDGE STANDARD PLANS AND SPECIAL DETAILS ADAM LANCASTER, P.E. FEB. 27, 2018

MANUAL OF THE STRUCTURE AND BRIDGE DIVISION

PennDOT District 11 Bridge Asset Management. Louis J. Ruzzi, P.E. District 11-0 (Pittsburgh Area) Bridge Engineer

Midwest Bridge Preservation Partnership. Session 3 Preservation Actions, Policies, Needs, & Measures

VDOT s Strategic Approach to Bridge Management and Maintenance

CHAPTER 2B - PHASE I, INITIAL ROADWAY INVESTIGATION & PRELIMINARY FIELD INSPECTION

LIFE CYCLE COSTS OF BRIDGES: GALVANIZED STEEL vs. CONCRETE

CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - CONCRETE REMOVAL

COMMONWEALTH OF VIRGINIA DEPARTMENT OF TRANSPORTATION CONSTRUCTION DIRECTIVE MEMORANDUM

MANUAL OF THE STRUCTURE AND BRIDGE DIVISION

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR

STRUCTURE AND BRIDGE DIVISION

SOUTHEAST TEXAS CONTINUING EDUCATION BRIDGE INSPECTION, MAINTENANCE AND REPAIR

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation

State of New Jersey NEW JERSEY DEPARTMENT OF TRANSPORTATION 1035 PARKWAY AVENUE P.O. Box 600 TRENTON, NEW JERSEY

Presenter: Contributing Authors: Guy C. Nelson PE, SE TEG Engineering, LLC Structural Engineer

MATERIALS DIVISION MEMORANDUM SIGNATURE:

Chapter 1 INTRODUCTION

The FHWA Long-Term Bridge Performance Program

LOCATION AND DESIGN DIVISION

ODOT Bridge and Pavement Funding Allocation Business Process. Bruce Johnson 11 th IBSMC, Mesa Arizona 4/24/17

STRUCTURE AND BRIDGE DIVISION

State-Aid Bridge News July 20, 2004

BRIDGE PREVENTIVE MAINTENANCE STRATEGY FOR ERIE-NIAGARA LOCAL BRIDGE OWNERS

Baseline Document Change Announcement

Northeast Bridge Preservation Partnership Meeting

AGENDA AGENDA. Route 15/29 SBL Bridge Superstructure Replacement & Widening. NOVA District. Bridge Views SCOPE. Existing Structure.

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

West Virginia s First ABC Deck Replacement Project Bill Manuel & Johann Aakre HNTB Corporation

VTCA CONFERENCE Structure and Bridge Update. Kendal R. Walus, PE State Structure and Bridge Engineer. April 13, 2018

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

2010 STATE BRIDGE ENGINEERS QUESTIONNAIRE

STATE OF NEW HAMPSHIRE DEPARTMENT OF TRANSPORTATION LOAD RATING REPORT GENERAL SULLIVAN BRIDGE - DOVER 200/023 OVER THE LITTLE BAY

ATTACHMENT 50-1: PERFORMANCE AND MEASUREMENT TABLE

TRAFFIC ENGINEERING DIVISION INSTRUCTIONAL & INFORMATIONAL MEMORANDUM

Moving Ahead for Progress in the 21 st Century Act MAP-21

TxDOT Superheavy Bridge Report Requirements. Bridge Division

Scott Neubauer. Bridge Maintenance and Inspection Engineer Office of Bridges and Structures Iowa DOT

Corrosion Resistant Reinforcing Steel (CRR)

Future Programmatic Beyond 01/06/2020 Sorted By District (Subject to Departmental Changes)

Consultant: Client: MINISTRY OF EXTERNAL AFFAIRS NEW DELHI IRCON INFRASTRUCTURE & SERVICES LIMITED DIMENSION DETAILS OF RCC SUPERSTRUCTURE.

VIRGINIA DEPARTMENT OF TRANSPORTATION Documents Required to be Signed and Sealed

Highway Bridge Structure Components

Life Cycle Cost Analysis Pavement Options May 2002 Materials Division / Virginia Transportation Research Council TABLE OF CONTENTS

I-64 Capacity Improvements Segment II Financial Plan Annual Update October 30, 2017

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

Baseline Document Change Announcement

BRANT - NORFOLK TOWNLINE ROAD

Specification Changes and Their Effect on Plans. Bridge Construction Issues. BRG VTC April, 2010

April 19, 2017 Vicente Valeza, P.E. NOVA District Senior Structural Engineer (703)

Bridge Economy and Life Cycle Costs of Steel & Concrete Bridges

State of Good Repair (SGR) Program Bridge Prioritization Formula. Structure and Bridge Division

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E.

State of Good Repair (SGR) Program Bridge Prioritization Formula. Structure and Bridge Division

Bridge Preservation: Thin epoxy overlays

Bridge Engineering. Demetrios E. Tonias, RE. President HMC Group Ltd. Me Graw Hill. Jim J. Zhao, P.E. President Frederick Engineering Consultants, LLC

Project Overview. Wilson Boulevard over Route 50 Bridge Rehabilitation. Get Involved. Public Information Meeting. Contact Information

Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction

NJDOT Bridge Preservation and Asset Management Strategies. Gerald P. Oliveto, P.E. Roger Estivalletti

Use of BS 5400: Part 4: 1990

TRANSVERSE SECTION TABLE OF CONTENTS CHAPTER 9

Transcription:

VIRGINIA DEPARTMENT OF TRANSPORTATION STRUCTURE AND BRIDGE DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Bridge Project/Plan Authorization and Approval Authority SPECIFIC SUBJECT: NUMBER: Date: October 24, 2011 SUPERSEDES: IIM-S&B-19.9 DIVISION ADMINISTRATOR APPROVAL: /original signed/ Kendal R. Walus, P.E. State Structure and Bridge Engineer Approved: October 24, 2011 EFFECTIVE DATE Changes are shaded. This memorandum is effective for bridge projects advertised after July 1, 2011. PURPOSE This IIM is to provide guidance on the design and plan authorization authority based on the two tiered project development which is being implemented on July 1, 2011. The two tiers are as follows: Tier 1 = All projects < $5M (UPC) Construction Cost and that are not Federal Oversight. Non-federal oversight bridge maintenance projects that are limited to the following activities may exceed the $5M level: Bridge painting Bridge deck patching Bridge deck overlays and sealing Bridge Joints Bridge deck cleaning and washing For other bridge maintenance projects with a Construction Cost above $5M (UPC), the District Bridge Engineer may request that the project be designated Tier 1 thru the District Project Development Engineer.

Sheet 2 of 8 Tier 2 = all projects > $5M (UPC) Construction Cost (except as noted above), all projects designated as Design Build at the Scoping Stage, and any project that has Federal Oversight Tier 1 Bridge Projects (No Central Office Oversight) Project will be developed in the District following established VDOT policies, guidelines, procedures and standards to ensure consistency throughout the Commonwealth. The Districts will have full approval authority for these projects, with the oversight authority being determined at the project scoping, except that Federal authorizations and funding verifications must be obtained from Central Office Programming Division by the District Planning and Investment Manager (PIM). There will be no Central Office involvement in the project approval process except when there are deviations from AASHTO minimum standards, VDOT S&B modifications to AASHTO, VDOT S&B geometrics as shown in the Manual of the Structure and Bridge Division; environmental issues, R/W authorization; and submissions to the Commonwealth Transportation Board. AASHTO Bridge and VDOT S&B deviations shall be resolved by following established S&B design exception or waiver policies. Tier 2 Bridge Projects (Central Office Oversight) Projects shall follow all existing policies, procedures and processes, and shall include Central Office reviews and approvals during the various stages of the project development process. PROJECT ASSIGNMENT AUTHORIZATION Tier 1 bridge project assignments will be the responsibility of the District Structure and Bridge Engineer. Tier 2 bridge project assignments will be the responsibility of the Assistant State Structure and Bridge Engineer responsible for the Design Engineering Program in coordination with the District Structure and Bridge Engineer in which the project resides. Close coordination of project assignments shall occur between the Central Office and District Bridge Staff to ensure that a defined office is assigned responsibility for each project.

Sheet 3 of 8 PRELIMINARY PLAN APPROVAL The S&B Division Central Office/District will perform reviews and provide approval of all Stage I Preliminary Plan submissions developed by in-house staff and consultants. The preliminary plan approval authority is as shown in the following table: Tier 1 Projects Tier 2 Projects Preliminary Plan Approval Authority Plan Type Approval Authority District Structure & Bridge Engineer Assistant State Structure & Bridge Engineer (Design Engineering Program Area) and FHWA where required, with input from Non-conventional designs and/or Bridge construction costs > $25M (bridge cost only) Design Build Projects, PPP Projects and Locally Administered Projects District Structure and Bridge Engineer State Structure & Bridge Engineer and FHWA where required As indicated in the Design-Build Manual, the PPTA Implementation Manual and Guidelines, and the Locally Administered Projects (LAP) Manual Preliminary plans for new construction and total bridge replacements shall show the layout, substructure type, superstructure typical section, any unusual or distinctive feature(s) and sequence of construction (where required). The format should consist of a bridge plan title sheet and interior bridge plan sheets as needed. Preliminary plans must be accompanied by comparative estimates for the proposed layout as well as for any alternative layouts that were considered. For new and total replacement bridge projects, a preliminary Stage I report shall be developed. This report shall be posted in ipm after the Stage I plans have been approved. No final design shall begin until the preliminary plan layout has been approved by the assigned approval authority. If a hydraulic study is required, the preliminary plan layout shall not be approved until the analysis has been received. Major revisions to the span layout (i.e. a change from a two span to a three span concept) or design (i.e. a change from a fully integral abutment to a conventional abutment) concepts after preliminary plan approval will require a resubmission for authorization to proceed with the new concepts.

Sheet 4 of 8 PREPARATION OF PLANS Any new bridge requiring a special design superstructure or substructure, or any repair, alteration, deck/superstructure replacement, or widening performed on an existing bridge which, in any way, affects the structural capacity or integrity of the structure must have design and/or detail plans developed showing the proposed work. Geometrics shown in the Manual of the Structure and Bridge Division, Volume V Part 2, Chapter 6, shall be used on all structures unless a design exception/waiver from these standards is authorized in writing by the State Structure and Bridge Engineer. Minimum bridge widths can be exceeded subject to the approval of the assigned approval authority. All structure plans are to be prepared in accordance with approved AASHTO Bridge Design Specifications, VDOT Modifications and the Manuals of the Structure and Bridge Division. Plan numbers are assigned by the Central Office Structure and Bridge Division File Room. All bridge/drainage ("B" and "D" designation) structure plans (and sketches) shall have a plan number assigned and an As-Built plan completed and recorded in accordance with S&B Division policy. This also applies to repair plans involving structural modifications. Tier 1 Bridge Projects (No Central Office Oversight) Depending on the type of work being performed, Tier 1 bridge projects may be accomplished by utilizing 8 ½ x 11 detail sheets inserted into the contract assembly or by the use of full size drawings. Tier 1 Bridge projects utilizing 8 ½ x 11 detail sheets may include, but are not limited to, the following types of structural work: a) Small drainage structures or other engineered entities with or without road improvements, such as precast concrete box culverts, structural plate arches, 3- sided concrete rigid frames, retaining walls, sinkhole remediations, etc. b) Bridge rail/parapet repairs c) Bridge repair/preventative maintenance (Regional/District wide) d) Bridge painting operations e) Minor bridge structural repairs, e.g. heat straightening beams/girders f) Bridge deck overlays and sealing g) Bridge deck cleaning and washing h) Bridge concrete Gunite repairs i) Manufactured superstructure (truss) j) Bridge scour countermeasures or remedial measures k) Culvert repairs l) Bridge debris removal

m) Bridge slope repairs Instructional & Informational Memorandum Sheet 5 of 8 Tier 1 Bridge projects utilizing full size plans may include, but are not limited to the following types of structural work: a) Bridge Only Projects with minimal roadway approach work b) Special design bridges and structures c) Bridges or structures using standard drawings for superstructure and substructure elements (e.g., Retaining Walls, Steel Beam/Timber Deck (SS-8), C-I-P Slab Spans) All Tier 2 Bridge projects shall use full size plan sheets. FHWA REVIEW/APPROVAL: Projects in the following categories are to be sent to FHWA for review: Interstate projects estimated to have a construction cost (exclusive of construction engineering and contingencies) > $1.0 million. Interstate Preventive Maintenance Projects estimated to have a construction cost > $5.0 million. The following bridge activities have been defined as Preventive Maintenance : o Seal or replace leaking joints reconstruction of joint areas during joint replacement or elimination of deck joints. o Deck Overlays: Thin bonded overlays, rigid overlays and asphalt overlays with waterproof membranes. o Spot and zone painting/coating of structural steel to include bearings for prestressed concrete members. o Painting/coating of structural steel. o Cathodic Protection (CP) Systems for Bridge Decks, substructure elements and superstructure elements other than decks. o Electrochemical chloride extraction treatment for deck and substructure elements. o Scour countermeasures installation o Removing large debris from channels o Retrofit of fracture critical members o Retrofit of fatigue prone details o Concrete deck repairs in conjunction with installation of deck overlays, CP systems, or ECE treatment. o Substructure concrete repairs in conjunction with installation of CP systems, ECE treatment, or galvanic anodes. o Application of sealants, coatings, and membranes for surface protection of the concrete. o Bridge cleaning and/or washing services. (Decks, joints, drains, substructure horizontal elements and superstructure) o Place concrete mat along the flow line of steel pipe culverts.

Sheet 6 of 8 Note: When eligible substructure work and/or painting/coating of ends of girders under joint locations that are leaking, it is required to seal the joints. The District may request a waiver from the State Structure and Bridge Engineer to delay sealing the joints for a period not to exceed one year. Projects on the National Highway System (other than Interstate) estimated to have a construction cost (exclusive of construction engineering and contingencies) > $25.0 million. See the following link for NHS general information: http://www.fhwa.dot.gov/planning/nhs// See the following FHWA website that defines NHS Routes in Virginia: http://www.fhwa.dot.gov/planning/nhs//maps/va/index.htm Projects not meeting the three criteria mentioned above, but have been identified by FHWA as requiring Federal Oversight. USE OF STANDARD PLANS AND STANDARD DETAILS Maximum use is to be made of the standards and details in the various Manuals of the Structure and Bridge Division, Volume V-series. These details can easily be modified to fit a particular structure with minimum drafting needed. FINAL PLAN APPROVAL The S&B Division/Districts will provide review and recommendation for approval for all final plan submissions developed by both the in-house staff and consultant community in accordance with the table shown on the next page.

Sheet 7 of 8 Tier 1 Projects Tier 2 Projects Plan Type Final Plan Approval Authority Approval Authority District Structure & Bridge Engineer Assistant State Structure & Bridge Engineer (Design Engineering Program Area) and FHWA where required, with input from District Structure and Bridge Engineer Non-conventional designs and/or Bridge construction costs > $25M (bridge cost only) Design Build Projects, PPP Projects and Locally Administered Projects Assistant State Structure & Bridge Engineer (Design Engineering Program Area) and FHWA where required, with input from District Structure and Bridge Engineer As indicated in the Design-Build Manual, the PPTA Implementation Manual and Guidelines, and the Locally Administered Projects (LAP) Manual. FINAL PLAN SUBMISSION Completed bridge plan drawings in.dgn and.pdf format shall be archived in accordance with established file documentation policy. Separate plan sets shall be completed for each structure, unless the plan set includes an adjacent twin structure. At Final Plan Submission, the bridge plans are required to be 100% complete. After plan submission to the Scheduling and Contract Division, no changes relating to plan quality, constructability and bidability shall to be made without the approval of the Scheduling and Contract Division. RECOMMEND FOR APPROVAL AUTHORITY For Tier 1 bridge projects, the District Project Development Engineer recommends For Approval, and as such, will append his/her signature and date to the title sheet of completed projects per Manual of the Structure and Bridge Division, Volume V Part 2. For Tier 2 bridge projects, the State Structure and Bridge Engineer recommends For Approval and as such will append his/her signature and date to the title sheet of completed projects per Manual of the Structure and Bridge Division, Volume V Part 2.

Sheet 8 of 8 CC: Chief Engineer Assistant State Structure and Bridge Engineers District Structure and Bridge Engineers Central Office Structure and Bridge Program Managers FHWA Virginia Bridge Division Engineer State Location and Design Engineer