PEFA assessment cycle overview 10 steps for planning, managing, and using PEFA

Similar documents
PEFA assessment cycle overview 10 steps for planning, managing, and using PEFA

Good Practices in Applying the PFM Performance Measurement Framework. Guidance for Assessment Planners and Managers

I. Context. 1 In January 2011 the PFM PMF was modified by the revision of 3 indicators (PI-2, PI-3, and PI-19), in order to take in account

Concept note: ISPA Quality Assurance Protocols August 22, 2016

Guidelines for the Diagnostic Trade Integration Study (DTIS) and DTIS Update (DTISU) under EIF Phase Two

MSG oversight of the EITI reporting cycle

TERMS OF REFERENCE. Evaluation of the Independent Science and Partnership Council (ISPC) May Background Rationale and Context

RDA Secretary General Recruitment

ADMINISTRATION OF QUALITY ASSURANCE PROCESSES

Supreme Audit Institutions Performance Measurement Framework

The Assessment Process. Asian Development Bank Workshop October 2014 PEFA Secretariat

Pillar II. Institutional Framework and Management Capacity

Supreme Audit Institutions Performance Measurement Framework

Standard Operating Procedures for timely preparation and implementation of management responses to evaluations commissioned by the Evaluation Office

Terms of Reference. Projects Outputs Evaluation

RESEARCH SUPPORT SERVICES FRAMEWORK. Streamlining the management and governance of R&D studies in the NHS

QUICK GUIDE TO INTEGRATING PUBLIC-PRIVATE DIALOGUE SCOPING MISSION. Investment Climate l World Bank Group. In partnership with

6. Cross-Cutting Issues Indicators

TERMS OF REFERENCE. Location

End-Phase Project Evaluation Guidance Note. For EIF Tier I and Tier II-funded projects

Workplace Travel Planning Guide

ASEAN-AUSTRALIA DEVELOPMENT COOPERATION PROGRAM (AADCP) PHASE II

OCHA s Management Response Plan (MRP) to Internally-mandated Evaluation of the OCHA s Role in Civil-Military Coordination Date: 15 May 2013

INTERNATIONAL INSTITUTE FOR DEMOCRACY AND ELECTORAL ASSISTANCE TENDER NOTICE

UN-HABITAT ENTERPRISE RISK MANAGEMENT IMPLEMENTATION GUIDELINES

TERMS OF REFERENCE. Independent Evaluation of the ILO Action Plan for Gender Equality

INDIVIDUAL CONSULTANT PROCUREMENT NOTICE / TERMS OF REFERENCE

Policy Development Guidelines. Produced by the Local Government Natural Resource Management Project

TERMS OF REFERENCE 1. BACKGROUND ECCSA. Demand Study for the Ethiopian Chamber of Commerce and Sectoral Associations (ECCSA) 1.1 Assignment background

UNODC Evaluation Policy Independent Evaluation Unit

INDIVIDUAL CONSULTANT PROCUREMENT NOTICE

TIPS PREPARING AN EVALUATION STATEMENT OF WORK ABOUT TIPS

INDIVIDUAL CONSULTANT PROCUREMENT NOTICE For an individual consultant and/or individual consultant assigned by consulting firms/institutions

FAO actions to implement the IASC Transformative Agenda (December 2012)

Educational Sessions for Strategic Property Planning

Independent Formative Evaluation of the World Health Organization

QUICK GUIDE TO INTEGRATING PUBLIC-PRIVATE DIALOGUE 2STAKEHOLDER MAPPING FOR ENGAGEMENT. Investment Climate l World Bank Group. In partnership with

Evaluation policy PURPOSE

Terms of reference. Recruitment of a consultant for the Functional Assessment of Public Administration Structure in Cabo Verde

Terms of Reference (TOR)

BOARD CHARTER JUNE Energy Action Limited ABN

A Guide for Standard Setting Organisations

Related manuals Health & Safety Part 1 Section 1; H&S Part 1 Section 2; H&S Part 1 Section 3 ; Part 2 Section 1; Corporate Services Part 5 Section 1

Sixtieth session of the Trade and Development Board Geneva, 24 September 2013

Strategic Evaluations I. GUIDANCE FOR PROCESS & CONTENT

ENHANCED INTEGRATED FRAMEWORK. Concept Note. Sustainability of EIF Tier 1 projects to support National Implementation Arrangements (NIAs)

Framework for the Establishment of DST-NRF Centres of Excellence Managed by the Research Chairs and Centres of Excellence (RCCE) Version 2.1.

Executing Organisations: SOCADIDO - Soroti Catholic Diocese Integrated Development Organisation Hoffnungszeichen Sign of Hope e.v.

EU Rural Networks Strategic Framework and governance bodies

S23 - Hallmarks of a Strong Audit Function Lilian Fong and Marta O'Shea

UNECE International PPP Centre of Excellence. Defining PPP Excellence: Meeting of the PPP Specialist Centres

ERM: Risk Maps and Registers. Performing an ISO Risk Assessment

Ref: SADC/2/3/3 Vacancy No 2 of 2017 SOUTHERN AFRICAN DEVELOPMENT COMMUNITY VACANCY ANNOUNCEMENT

Call for Applications: Chair of the International Auditing and Assurance Standards Board (IAASB)

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/102

PARTNERSHIP FOR MARKET READINESS (PMR) IMPLICATIONS OF THE PARIS AGREEMENT ON PMR ACTIVITIES Workshop Summary Monday 25 April, 2016 Lima, Peru

QQI Consultation on: Quality Assurance Guidelines and Criteria for Voluntary Providers of Further Education and Training V.01

Risk Oversight Committee - Terms of Reference

Mid-term Project Evaluation Guidance Note For EIF TIER 1 Funded Projects: Support to National Implementation Arrangements

AFM Corporate Governance Code

LEGAL AID BOARD BOARD EVALUATION FINAL REPORT

CIVIL SOCIETY PARTICIPATION IN THE EITI

MODEL AFFIRMATIVE ACTION PLAN INTRODUCTORY STATEMENT

TERMS OF REFERENCE Bangkok, Thailand with possible travel to countries in Asia Pacific.

Critical milestones towards a coherent, efficient, and inclusive follow-up and review of the 2030 Agenda at the global level COVER NOTE:

Frequently Asked Questions: UN-SWAP Evaluation Performance Indicator Reporting

LLOYDS BANKING GROUP AUDIT COMMITTEE TERMS OF REFERENCE (LLOYDS BANKING GROUP PLC, LLOYDS BANK PLC, BANK OF SCOTLAND PLC & HBOS PLC)

Audit, Risk & Compliance Committee. Charter

Developing an EITI work plan

FOREST EUROPE Structures, Procedures and Work Modalities

Intergovernmental Committee for Physical Education and Sport Extraordinary Session and Joint Meeting with the Permanent Consultative Council (PCC)

LIJUN INTERNATIONAL PHARMACEUTICAL (HOLDING) CO., LTD. (the "Company") (Incorporated in the Cayman Islands with limited liability) (Stock Code: 2005)

TERMS OF REFERENCE. For. The Design of a Monitoring & Evaluation System to track the Progress of the CARIFORUM-EU EPA Implementation

GUIDANCE NOTE: DEVELOPING A RESULTS

Preface. Chairman. Dr. Anwar Nasution

December 19, Call for Applications: Chair of the International Auditing and Assurance Standards Board (IAASB)

Introduction. Identify and Empower the Evaluation Manager. The Evaluation Manager s Role

M i n i s t e r i a l R e v i e w T r a c k e r P a g e 1

An Excel Based Analytical Tool for Undertaking an Internal PEFA Review or for Scoring a PEFA Analysis at the National or Sub- National Levels

TERMS OF REFERENCE. For a Bi-lingual Local Project Coordinator. To support stakeholder engagement and research on financial inclusion in Benin

THE VIETNAM PARTNERSHIP GROUP ON AID EFFECTIVENESS

Joint Assessment of National Health Strategies and Plans

AGRICULTURE. A global framework for action in a changing climate April 2017 FAO HQ, Rome, Italy

NATIONAL EXPORT STRATEGY

Supporting countries for HRH development: from dialogue to action

Terms of Reference (TOR)

REPORT 2015/128 INTERNAL AUDIT DIVISION. Audit of the Field Personnel Specialist Support Service in the Department of Field Support

The PEFA Performance Measurement Framework

ENTERPRISE RISK MANAGEMENT

ENHANCED BLACK CARBON AND METHANE EMISSIONS REDUCTIONS AN ARCTIC COUNCIL FRAMEWORK FOR ACTION

MID-TERM REVIEW OF TRANSPARENCY INTERNATIONAL S 2020 STRATEGY

CONTRACT FOR STAKEHOLDER ENGAGEMENT AND COMMUNICATIONS SUPPORT FOR THE INTEGRATED URBAN DEVELOPMENT FRAMEWORK (IUDF)

TEMPORARY JOB OPENING ANNOUNCEMENT

SAI Performance Measurement Framework Implementation strategy

Global Financing Facility in Support of Every Woman Every Child Country Platforms

Corporate Governance. Information Request List Family- or Founder-Owned Unlisted Companies. Commitment to Corporate Governance

Open Government Data Assessment Report Template


Measuring Our Performance Action plan

Guidance Note: Corporate Governance - Audit Committee. March Ce document est aussi disponible en français.

Transcription:

PEFA assessment cycle overview 10 steps for planning, managing, and using PEFA How to use this guidance Experience gained from more than 500 PEFA assessments demonstrates clearly that a well-planned and systematic process is crucial to efficient and timely completion of a comprehensive, evidence-based PEFA. This guide explains the basic phases and steps in a standard PEFA assessment process. It provides a chronological checklist of what to do and when to do it. Tips are provided on where to get further information and the important matters to consider in each step. It is aimed at all users who are involved, or expecting to be involved, in a PEFA assessment. The diagram PEFA in 10 steps provides a visual overview of the entire PEFA cycle. It provides an indicative timeframe for the four phases of planning, field work, reporting and PFM reform action. The companion table 10 steps for planning, implementing, and using PEFA expands on the diagram. For each step it identifies the key tasks, highlights the main issues, identifies who should be responsible and the indicative timeframe. The table also provides advice on where to get guidance needed for each step or task. The timeline included in the table measures the time period using as focal point the date that fieldwork (F) commences. The reason that the field work is the focal point for the timeline is that it is usually the most resources intensive part of the PEFA process and needs to be performed efficiently for both the assessment and the people who will be consulted during the fieldwork. The period before fieldwork (F-x) covers all of the planning and preparatory activities. The period after the fieldwork (F+x) relate to what happens with the information once it has been collected, including preparation of the PEFA report, and the next steps after the report has been completed. The timeline for a PEFA assessment depends on country circumstances, but most assessments take about 10 months from the initial dialogue on the need for a PEFA assessment (Step 1) to the final report and publication (Step 8). More detailed information on the 10 Steps can be found in Volume 1 of the PEFA Handbook: Planning, managing and using PEFA. 1

2

10 steps for planning, managing and using PEFA P L A N N I N G Steps Key Tasks Main Issues Responsibility Indicative 1 Dialogue on the need for a PEFA assessment 2 Develop the Concept 1.1 Initiate a dialogue on the need for a PEFA assessment 1.2 Establish an Oversight Team (OT) i, 1.3 Identify resource requirements and funding source 1.4 Appoint the assessment manager (AM) 1.5 Appoint a government liaison officer for the assessment. 2.1 Prepare draft of CN/ToR Discussions should focus on: o the purpose, scope, and coverage o type of assessment o timing o resources and o proposed funding source May be part of broader public administration reform dialogue May be internal discussion within government or between government and international organizations and civil society The OT s role is to govern the process and oversee the PEFA assessment The OT should include all main stakeholders; OT members identify and agree: o key responsibilities o approach to assessment Requirements will depend on the scope of the assessment Need to identify expertise required Calculate staffing and consultancy costs Estimate other costs including travel, translation, administrative support etc. AM is responsible for day to day management of assessment process Government appoints a liaison officer who is the focal point of, or main contact for, the assessment team, whether it is a self-assessment or external assessment CN/ToR specifies: Development Partners Development Partners Development Partners F-6 PEFA Handbook Volume 1: PEFA ; Additional guidance and assistance as required. F-6 F-6 OT F-5 Government F-5 AM; F-4 CN/TOR guidelines and template in 3

Steps Key Tasks Main Issues Responsibility Indicative Note/Terms of Reference (CN/TOR) 3 Prepare for the assessment o Objectives ii, scope iii and coverage of the assessment o Size iv of the assessment team (number), its composition (staff, international and local consultants) and required expertise (minimum requirements in terms of skills, local knowledge), training requirements, budget, sourcing, and timetable v o Approach and methodology o Management and oversight o QA arrangements Government approval of the CN/ToR (see 2.3) is important for ensuring government s commitment and ownership 2.2 Peer review The Concept Note (CN) is shared with the government if they are not already part of the assessment team Four peer-reviewers should be requested to review the CN/TOR and the report vi (see PEFA CHECK requirements), including Government representatives and the Allow at least 2 weeks for review. This is an essential step for the report to qualify for the process quality endorsement, PEFA check (explained in the PEFA Handbook) 2.3 Finalize CN/ToR. Revise CN/TOR to address peer-reviewers comments OT, then government, approve final CN/ToR Submit approved CN/ToR to 3.1 Mobilize the assessment team (AT) vii. AM will identify, assemble and mobilize the AT The assessment team leader (TL) leads the assessment work and coordinates the assessment AT Development partners Peer Reviewers, OT, Government assessment TL and as appropriate government or PEFA Handbook Volume 1: PEFA F-4 PEFA CHECK guidelines and templates included in PEFA Handbook Volume 1, Annex 1.8 F-3 CN/TOR guidelines in PEFA Handbook Volume 1: PEFA F-2 PEFA Handbook Volume 1: PEFA 4

B F I E L D W 4 Launch and introductory training. Steps Key Tasks Main Issues Responsibility Indicative 3.2 Identify data requirements and data sources viii 3.3 Prepare field work schedule/agenda. 3.4 Specify reporting requirements 4.1 High level briefing to senior officials. 4.2 Introductory launch training AM and assessment team leader (TL) will clarify roles and responsibilities of team members, how the team will function, communicate and coordinate within and outside the team Identify data requirements and sources for indicator set and PEFA report; o Reviewing published/unpublished data prior to the field work can save significant time and resources AM issues an initial data request to relevant officials Announce planned field visit and agree agenda and meeting schedule with host country and organizations. Issue letter confirming arrangements Prepare data bases and templates for retention and storage of information required/collected Includes periodic briefings, briefing notes to the OT, at end of fieldwork, discussion of final report with OT (and senior government officials) Senior government officials and members of the OT may prefer a separate briefing on key aspects of PEFA and the assessment. The AT may provide this briefing at the start of the fieldwork The launch informs stakeholders including government officials, members of the OT and partners, of the purpose, scope and partner AT Government representatives AM in consultation with government officials and partners AT OT Lead agency AT, Senior government officials AT, Government officials, F-1 PEFA Handbook Volume 1 PEFA includes data request to host country. PEFA Volume 2: Fieldguide includes guidance on data requirements, calculations and data sources. F-1 PEFA Volume 1: Process includes template and draft letter for mission schedule F-1 F model training workshop material 5

O R K Steps Key Tasks Main Issues Responsibility Indicative 5 Data collection and analysis 5.1 In-country data collection 5.2 Data analysis and initial scoring 5.3 Field mission exit presentation (initial findings and data gaps) assessment methodology and relevant features of the PEFA framework A formal launch provides the opportunity to explain PEFA and how the assessment will be performed. It is important that people responsible for providing data and others involved in the assessment know what is required and why Length of training can vary from 1 to 2 days Data collection begins in Step 3, and continues with the in-country field work Assessors should ensure there is sufficient data to address all aspects of scoring requirements, calculations and required data tables Data will be captured from documents and interviews with key stakeholders including members of the OT, other government officials, partners and civil society organizations As data is collected assessors begin the process of analyzing data and, based on this evidence, scoring of indicators and dimensions It is also important to validate and crossreference information received Sometimes the AT makes a presentation to the OT and senior government officials and partners at the conclusion of the field work to: o Present initial scores and findings o Identify any outstanding data requirements partners AM AT AT, OT, Senior government officials F included in PEFA Handbook Volume 1 PEFA Handbook Volume 2 The Fieldguide specifies data requirement, calculations and data sources. PEFA Handbook Volume 2 The Fieldguide includes additional definitions, interpretation and measurement guidance PEFA Handbook Volume 1 includes draft outline of a PEFA field work exit presentation. 6

Steps Key Tasks Main Issues Responsibility Indicative 6 Draft assessment report preparation 7 Review, validation, and refinement 6.1 Prepare draft PEFA report. 7.1 Submit draft PEFA report for peer review Following the field work, the AT commences preparation of draft the PEFA report and scores for dimensions and indicators, including the narrative content contained in Chapters 3 and 4 The data analysis is combined into a draft report, using the prescribed PEFA format outlined in the PEFA 2016 Framework document and the PEFA Handbook. More detailed analysis of the implications of results for pillars, high level outcomes and internal control elements usually takes place after basic scoring and narrative explanations are well advanced The draft PEFA report is shared with at least four peer reviewers for comments o Reviewers should include representatives of the government assessed, the and at least two PFM independent institutions o At least three weeks should be allowed for peer reviewers to provide comments AT F+2 PEFA Handbook Volume 3: The PEFA Report sets out the detailed structure of the PEFA report, guidelines and report template. Peer reviewers (including government and PEFA secretariat) F+2 PEFA Handbook Volume 1: The PEFA includes a peerreview standard checklist. 7.2 Response to peer review (peer review comments matrix) 7.3 Revised draft submitted to peer reviewers for followup review Draft report is refined in response to comments and a separate matrix of peer review comments and assessment team response is prepared Following the initial review some assessments have a validation workshop at this point where the government and other stakeholders provide comments to the draft report Submit revised draft assessment report and separate matrix of comments to peer-reviewers o Allow at least 2 weeks for a follow-up review Peer-reviewers F+3 PEFA Handbook Volume 1: The PEFA includes a template for a peer review comments matrix. 7

Steps Key Tasks Main Issues Responsibility Indicative 8 Final report and publication 8.1 Presentation of final draft PEFA report to Government. Once the refinements have been made to the draft report, the latter is finalized and provided to the government for acceptance A briefing is usually arranged with the OT, senior government officials and partners This may involve a workshop for a wider audience AT, partners F+4 PEFA Handbook Volume 3: The PEFA Report which includes template and guidelines. D P F M R E F O R 8.2 Submit final report to (PEFA Check) 8.3 Government approves the final report 8.4 Publication of the final report. 9 Reform dialogue 9.1 Appoint a technical team (TT) to prepare reform plan and/or PFM action plan. 9.2 Undertake consultations within AM initiates request for the PEFA check Subject to meeting requirements the PEFA Secretariat issues the PEFA Check PEFA Secretariat Government approves final report Government F+4 Acceptance of the final report is usually followed by public release and often a dissemination event involving interested organizations and officials If authorized by government, the will publish the report on its website o Authorization can be done by an e-mail o The final report is usually published on a government website and on the PEFA website in quick succession TT is appointed by the government Its role is to facilitate dialogue and prepare a PFM reform strategy and/or action plan Government considers a range of factors in deciding priorities including other relevant information (such as other diagnostics, political, economic and environmental factors) Draft reform plan should identify required actions, capacity needs and costs The dialogue should involve consultations with senior government officials, partners and other key stakeholders PEFA Secretariat, partners (where relevant) Government and/or partners TT F+4 PEFA Handbook Volume 1: The PEFA, sets out the PEFA Check guidelines F+4 will upload the PEFA report on its website following government approval to publish. Country specific PEFA Handbook Volume 1 The Process 8

M A C T I O N Steps Key Tasks Main Issues Responsibility Indicative 10 Monitoring and follow-up government and with other stakeholders. 9.3 Prepare draft PFM reform strategy or PFM action plan 9.4 Review and approve final PFM reform plan or action plan. 10.1 Monitor PFM reform progress over time using PEFA. 10.2 Review and refine actions The dialogue should: o discuss the PEFA report findings as well as other relevant information including other diagnostics and current reform initiatives and o focus on the need for a comprehensive and integrated strategy and reform program, and how such a reform program agenda could be financed and implemented Following the dialogue the TT will prepare a draft PFM reform strategy, action plan or similar document for submission to the government for approval Following consideration and any amendments, the government should approve the PFM reform action plan. At this time the government should also identify its priorities as well as a mechanism for monitoring implementation (see Step 10) The government (through the MoF or other central agency) can use PEFA indicators and dimensions to measure PFM reform progress over time The government should appoint someone to be responsible for monitoring implementation of the action plan and reporting back Regular reports to the head of the TT should be prepared by those responsible for implementing reforms (in accordance with the action plan). The head of the TT (or other responsible officer) should prepare regular updates (e.g. quarterly or half-yearly) for the government. Develop proposed follow-up activities including subsequent PEFA assessments TT PEFA Handbook Volume 1 The Process Government Government - MOF Reform plan action officers; TT Country specific PEFA Handbook PEFA Website 9

i OT members would be drawn from the leading government entity in the assessment (e.g. MOF, NAO), other government agencies involved, non-government stakeholders such as the Audit General office, Parliament, etc. and partners ii The objectives for the assessment should reference the application of the 31 indicators and the structure of the PEFA report as described in the PEFA 2016 framework document. The reasons for not using a specific indicator should be clearly explained (see page 7, PEFA 2016 document, insert link). To be considered a PEFA assessment, the report needs to include at least two-thirds of the indicators. Partial use of the PEFA framework is discouraged although it is appropriate to use particular indicators or dimensions in the government internal monitoring and evaluation system. In the case of a successive assessment the requirement to measure and document performance changes over time should be clearly stated and explained in the CN (see PEFA 2016, Annex 1, page 107). The CN should specify that the team must explain all factors that impact a change in rating, indicator by indicator; identify the performance change and ensure that readers can track the change from the previous assessment. iii The levels of government to be assessed should be clearly defined on the basis of the structure of general government, for example, central government, subnational government, sample of subnational governments, etc.. iv The size of the AT, person days and average costs depend on the scope and nature of the assessment, and the size of a country. Precise resource requirements will vary from country to country. There is no standard budget. v A PEFA assessment should be planned and carried out within as short time as possible otherwise, it loses relevance, however, the timetable should contain flexibility to accommodate unforeseeable complications and provide time to fill information gaps after the initial comments are received from the reviewers. vii It is recommended that the assessment team leader is an experienced PFM practitioner and ideally has received training in the relevant PEFA methodology and has previous PEFA assessment experience. viii In establishing information requirements it is important that definitions are clear, for example, SNG is distinguished from de-concentrated central government entities; domestic arrears, extra-budgetary funds, and classification of parastatals. The use of correct definitions facilitates tracking performance changes over time. Guidance on information requirements can be obtained from the PEFA Handbook. 10