Comments of National Grid to the New England States Committee on Electricity on the Coordinated Competitive Renewable Power Procurement Process

Similar documents
New England State and Federal Laws and Regulations and the Electric Power Sector

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS PUBLIC UTILITIES COMMISSION

Maine Power Express, LLC Response to Request for Comments December 28, 2016

TDI-NE Responses to 83D Questions December 28, b. Type of Organization (Public/Industry/Advocacy/Other)

Energy and Climate Report

REPORT TO THE MINNESOTA LEGISLATURE

2030 Power System Study Report to the New England Governors 2009 Economic Study: Scenario Analysis of Renewable Resource Development

Sierra Club Comments Draft Request for Proposals for Clean Energy and Transmission

NALCOR ENERGY. Comments on Draft Request for Proposals for Clean Energy and Transmission

August 31, 2015 PROCUREMENT OF RESOURCES PURSUANT TO PUBLIC ACT NOTICE OF PROCEEDINGS AND OPPORTUNITY FOR PUBLIC COMMENT

New England States Committee on Electricity

NESCOE Submission Regarding Transmission Needs Driven by State and Federal Public Policy Requirements. May 1, 2017

Community-Based Renewable Energy

December 28, Introduction

The Transformation of the New England Electric Grid and the Importance of Situational Awareness Tools

Coordinated Procurement Transmission in the Northeast

NESCOE Comments on the Draft 2017 Regional System Plan July 21, 2017

Renewable and Clean Energy Scenario Analysis and Mechanisms 2.0 Study

Rhode Island. Public Energy Partnership

20 Walnut Street, Suite 308, Wellesley, MA

ISO New England Regional Electricity Outlook

Peninsula Clean Energy could launch a CCE by Fall January October 2015 October 2015 February 2016 March 2016 October 2016

VIA ELECTRONIC DELIVERY March 27, 2015

Rhode Island Renewable Energy Standard. Annual RES Compliance Report for Compliance Year 2015

Massachusetts Renewable Energy Portfolio Standard (RPS) Program Status and Overview of Section 83 Long Term Contracts

Presentation to Lafayette City Council. Amy Dao Community Energy Manager Jan. 26, 2015

Comparison of Renewable Portfolio Standards (RPS) Programs in PJM States

New England Electricity Outlook

ICC Regulatory Framework for Renewable Energy Sources. Matthew L. Harvey Office of General Counsel Illinois Commerce Commission August 9, 2010

The State of Wind Energy in New England

EBC Energy Resources Program: Renewable Energy Procurement in Massachusetts and New England

To: NEPOOL From: NESCOE Date: April 7, 2017 Subject: Feedback to NEPOOL on Long-Term Achieve -style IMAPP proposals

New England Governors Renewable Energy Blueprint

The New England Clean Power Link A powerful wind and hydro partnership for Massachusetts

From Restructuring to Decarbonization: Operational and Market-Design Challenges in New England

Emerging Trends In North American Energy: Focusing On New England s Electricity Market

Targeted Deployment of Solar Generation using Advanced Inverters. J. VALENZUELA J. WOODARD J. SALSMAN National Grid USA

83D Q & A Set #8. Answer: Please see response to question 117.

WATER AND WIND QUÉBEC S CLEAN, RENEWABLE ENERGY RESOURCES

NORTHWESTERN ENERGY 2018 ELECTRICITY RESOURCE PROCUREMENT PLAN STRAWMAN 1

Recognizing the Value of Existing Hydropower June 25, 2009

Managing the Reliability of the Electric Grid While the Power Industry Undergoes Rapid Transformation

The Road to Better System Planning: ISO-New England s Revised Energy Efficiency Forecast

Renewable and Clean Energy Scenario Analysis and Mechanisms 2.0 Study. Phase I: Scenario Analysis Winter 2017

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA

Proposed Business Plan: CleanPowerSF Build-out of Local Renewable Energy Resources

Massachusetts Clean Energy Center Request for Proposals (RFP): Moon Island Engineering Design Consultant

Table 10.1 DRAFT IRP Action Plan

CHAPTER 1 EXECUTIVE SUMMARY

Interconnection of New Generation Facilities

COMMENTS OF CONSERVATION LAW FOUNDATION AND MASS ENERGY CONSUMERS ALLIANCE

New England States Committee on Electricity

NYISO s Integrating Public Policy Project

Renewable State of Mind: New York Releases the Clean Energy Standard

The Impacts of the Green Communities Act on the Massachusetts Economy:

Hawaii s 100% RPS and Vermont s New RPS

ISO New England Overview and Regional Update

Storage as a Transmission Asset Stakeholder Comment Template

New England Power Sector Overview

ISO New England s 2011 Natural Gas Study

SB 838: Oregon Renewable Energy Act Establishing an Oregon Renewable Energy Standard

Village of Morrisville Water & Light Department Integrated Resource Plan

SB 838: Oregon Renewable Energy Act Establishing an Oregon Renewable Energy Standard

Guam Power Authority. Renewable Energy. zzzzzzzzz. April 25, 2012

Electricity Options for Vermont

Response to NYISO Solicitation. of Transmission Needs Driven by Public Policy Requirements

Meeting Our Kyoto Obligation: Canada s Essential Implementation Steps in 2005

Carbon Free Boston Energy Advisory Working Group. Institute for Sustainable Energy, Boston University April 6, 2018

NASEO 2017 Northeast Regional Meeting Energy Storage Initiative. DOER Commissioner Judith Judson

Oregon Renewable Energy Resources

Exploring the Impacts of California s Renewable Portfolio Standard

Policy Direction for Alberta s Capacity Market Framework

Business Practice Manual for Distributed Generation Deliverability. Version

NSTAR Electric Company and Western Massachusetts Electric Company d/b/a Eversource

CONNECTION & COSTS. Mary Doswell Alternative Energy Solutions December 7 th, 2010

Impacts from Peak Load Reductions in Markets and Long-Range Planning

Business Practice Manual for The Transmission Planning Process

Commissioner Rob Klee, CT Department of Energy & Environmental Protection Massachusetts Electric Distribution Companies Narragansett Electric Company

Risks And Opportunities For PacifiCorp State Level Findings:

PROPOSAL OF INDEPENDENT POWER PRODUCERS OF NEW YORK, INC. FOR INTEGRATING CARBON PRICING INTO THE WHOLESALE ENERGY MARKET

This briefing provides the status of renewable generation in the ISO s generator interconnection queue as of August 1, Key highlights include:

A Forward Clean Energy Market for New England?

Regulatory Approach to Maintaining Local Security of Supply in Electricity

1. Is there a preference between MW and MWh? RPS need for San Diego Gas & Electric is based upon a percentage of retail sales, which is in MWh.


Regulatory Assistance Project Electric Resource Long-range Planning Survey 1 Compiled by CM LB

The New Illinois Energy Bill and What It Means for Solar Development Anthony Star Director

Dear Chairman Downing, Chairman Golden, and Members of the Committee:

City of Newton. Municipal Aggregation Plan. I. Key Features. II. Support for Renewable Energy. March 5, Draft. 1. A Greener Standard Offering

Commonwealth of Massachusetts Executive Office of Energy and Environmental Affairs and Department of Environmental Protection

Impact of Regional Greenhouse Gas Initiative and Renewable Portfolio Standards on Power System Planning

Regulatory Mechanisms to Ensure Fuel Adequacy U.S. DOE Electricity Advisory Committee

RESUME. Alvaro E. Pereira, Ph.D. Managing Consultant

The Commonwealth of Massachusetts

Rhode Island Power Sector Transformation Performance Incentive Mechanisms Straw Proposal

Carbon Free Energy with Storage

REDACTED THE STATE OF NEW HAMPSHIRE BEFORE THE NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION PREPARED TESTIMONY OF JAMES G. DALY

Renewables Portfolio Standards in the United States: A Status Update

What s the Deal? 21 st Century Energy. CBIA and CPES. New England States Committee on Electricity. October 8, 2014

(Non-legislative acts) REGULATIONS

Transcription:

Ian Springsteel Director, Regulatory Strategy U.S. Regulation and Pricing Oct. 2, 2012 Comments of National Grid to the New England States Committee on Electricity on the Coordinated Competitive Renewable Power Procurement Process National Grid 1 is pleased to offer these comments in response to the recent Comment Opportunity issued by NESCOE on August 10, 2012. National Grid is the electric distribution company ( EDC ) for approximately 3 million customers in Massachusetts, Rhode Island and New York states, and procures approximately 60,000 GWhs of electricity each year to serve their needs. National Grid is also a transmission owner in New England. New England Power ( NEP ) is National Grid s wholly-transmission operating subsidiary, which delivers electricity at wholesale to electric utilities and municipalities across New England. National Grid has extensive experience with the procurement of renewable energy across its service territories. In New England, National Grid purchased more than 150,000 renewable energy certificates (RECs) to meet its requirements under the Renewable Portfolio Standards of Massachusetts and Rhode Island in 2011 alone. In addition, the Company has entered into multiple long-term renewable energy contracts with renewable developers to fulfill statutory procurement requirements in these two states. Specifically, the Company has long-term contracts with renewable developers for more than 300 MW nameplate capacity of on-shore and off-shore wind, 1 The National Grid legal entities submitting these comments are Massachusetts Electric Company, Nantucket Electric Company, The Narragansett Electric Company and New England Power Company each d/b/a National Grid (collectively referred to as National Grid or Company ). Massachusetts Electric Company, Nantucket Electric Company and The Narragansett Electric Company are electric distribution companies and New England Power Company is the wholly-owned transmission operating subsidiary of National Grid.

landfill gas, anaerobic digester gas, hydroelectric and solar PV powered generation across the region. National Grid commends NESCOE for offering a robust draft work plan for the development of a regional procurement process. The process plan specific to the issuance of an RFP and contract negotiations appears well-scheduled and complete. Moreover, the discussion of the formation of the Procurement Team ( PT ), and the Legal Subteam, with opportunity for direct involvement of EDCs in the process, appears to be workable and sufficiently representative and respectful of the differences between states in their approach to renewable procurement. Nevertheless, the challenge of regional procurement lies less with a well-planned RFP process, and more with the coordination of both new and existing laws that have been enacted to effect such procurement on a state level. That is, while this proposal lays out a process for joint procurement, the requirement or obligation on each EDC or state procurement authority is determined at the state level. Without a direct link between such requirements -- with the clear cost recovery and balance sheet mitigation provisions such requirements allow -- and the NESCOE process, National Grid believes there will be little motivation for it or other EDCs to participate in the multistate process, despite the potential price and transmission planning benefits a regional procurement approach is likely to create. Many states are moving forward with their renewable energy policies in ways that could integrate with the proposed NESCOE process, but at present do not. National Grid notes that Massachusetts recently passed an Act Relative to Competitively Priced Electricity in the Commonwealth 2 which requires a new round of joint procurement by the Commonwealth s EDCs, beginning on January 1, 2013. The EDCs must issue two joint solicitations for long-term renewable energy contracts up to 4% of distribution load by December 31, 2016, which will be

shared proportionally among them based on load. In Rhode Island, the Company recently conducted a third round of four required solicitations for long-term renewable electricity contracts, under the Long Term Contracting Act, 3 which will likely result in approximately 75% of the 90 MW capacity requirement (counted at a 100% capacity factor) being under contract by summer of 2013, and the entire amount contracted by 2014. We would encourage NESCOE to work closely with the states to better detail and plan how the existing and new requirements in all the New England states might be integrated into the seemingly longer length process proposed in the work plan if the intent is indeed to integrate the two. This could initially take the form of a joint policy statement from NESCOE and various state energy offices and secretariats that would be responsible for representing their state in a joint procurement. Within such planning, it may be beneficial to identify procurement blocks that align with specific state policy mandates as they come to apply to the region s EDCs, and design the procurement to meet those specific needs. Doing so would also help define the preferred volumes, resources and products to be sought in the solicitation. In terms of the mechanics within any procurement that moves forward, some additional consideration of the timing of each state s or EDC s commitment within the process to participate in the process and enter into contracts may be warranted. In the case of a state or EDC that decides to pull out once final selections have been made, or faces a change in policy prior to a contract being fully approved, a protocol or set of procedures for renegotiating and potentially redistributing some contracts would ideally be established prior to the launch of any solicitation. A further challenge will be to coordinate such a procurement so that more complex transmission-dependent new renewables that require substantial lead time can benefit from such a 2 Chapter 209 of the Acts of 2012, An Act Relative to Competitively Priced Electricity in the Commonwealth. 3 R.I. Gen. Laws 39-26.1-1 et. seq.

central procurement approach. Transmission-dependent renewable supply will in some cases be the most cost-effective due to lower siting costs, better wind and economies of scale - but these projects take more time to plan and build than those that can access existing transmission capacity. The planning and construction of transmission infrastructure upgrades is a critical element to allowing many potential new generation sources to supply power to customers unimpeded and without threat of curtailment. To allow for the best transmission approach to be selected, National Grid believes it is important to seek bids from generation with transmission solutions, as well as determining costs through other regional planning processes, with clear visibility and unbundling of the prices for each scenario. The desire to receive and compare individual proposals inclusive of all generation and transmission investment costs expected by the potential developers is certainly understandable, and such an approach could provide valuable information. However, such an approach would not necessarily lead to the selection of the most cost-effective or reliable solutions for consumers. For example, under such an all-in costs solicitation, several individual proposals might be submitted for generation to be located in same geographical area of the system, with each proposal also including significant transmission infrastructure costs expected by each developer in order to satisfy only their individual project s particular needs. Assuming more than one of these resources might be needed, it would be worthwhile to explore through a more centralized and coordinated regional planning process that could determine whether some of these individual transmission needs could be eliminated, reduced, or more efficiently and reliably resolved. Rather than paying for several long radial lines to each particular resource, perhaps a system upgrade consisting of a single new transmission loop through that geographical location would be a better solution.

Thus, a procurement process which also allows renewable generation developers to focus and compete on their expected costs for the generation investment, and allows the associated transmission costs to be explored and analyzed through a more comprehensive and coordinated transmission planning process informed by the generation proposals, would produce the best outcome for the region and electric customers. Such determinations will likely require the participation of ISO-NE, and/or the transmission owner whose system is impacted. We would suggest that such participation from ISO-NE and the incumbent transmission owners be sought on the Procurement Team ( PT ), or in a dedicated advisory role to the PT. To that end, the selection of the most beneficial and cost-effective transmission solution consistent with submissions received from project developers and State requirements may be best addressed by requesting that ISO-NE undertake a more comprehensive study, (e.g., a Public Policy Transmission study). Of course, undertaking such a study may affect the timeframe for the overall process, and how it will link to specific state procurement requirements. To summarize, National Grid looks forward to additional information on the proposed procurement effort, and would welcome formal participation in any working groups that are established to craft this process. Further, National Grid encourages NESCOE to work with the states to more directly link the process to their renewable energy policy objectives and procurement requirements. Finally, the Company recommends a deliberate, planning-focused approach to indentifying transmission solutions to support desired new generation, and close involvement of ISO-NE, EDCs and transmission owners in the development of the procurement plan.