. NOTES ON THE TEST OF A BUTT-WELD IN A 24in. x Min. x 1001b. ROLLED STEEL JOIST

Similar documents
METROPOLITAN. O & M Procedure No: E UTILITIES DISTRICT I. GENERAL

1 Exam Prep Placing Reinforcing Bars Tabs and Highlights

Welding Job Readiness Arc Welding Information Sheet Welding Equipment

SPECIFICATIONS FOR THE CONSTRUCTION OF NEW PASSENGER EQUIPMENT CARS PREFACE

THE FIRST ARC-WELDED IN EUROPE

NAME 345 Welding Technology Lecture 03 (Welding Joint Design)

APPENDIX J PROFICIENCY CHECKLISTS

The System Slotted Deflection Track (pat# 5,913,788)

4/19/2018. The heat generated for welding comes from an arc

APPENDIX B. LOAD FRAME. This Appendix will describe the philosophy in the design and operation of the loading system.

VARIOUS TYPES OF SLABS

A few tips to be sure that rolling windtowers becomes a profitable business. (Pictures and Video are courtesy of EWP Sweden)

PART 5 WELDING. 5.1 General 5.2 Preparation 5.3 Dimensions of welds 5.4 Materials 5.5 Aluminium alloys 5.6 Welding details 5.

A Practical Design Guide for Welded Connections Part 1 Basic Concepts and Weld Symbols

THE BRACE CONNECTION THE BOLTED OPTION FIGURE 1 MODEL SHOWING THE BOILER AND THE STRUCTURAL SUPPORT SYSTEM (BOILER BUILDING)

NODIA AND COMPANY. GATE SOLVED PAPER Civil Engineering Design of Steel Structure. Copyright By NODIA & COMPANY

CYCLIC BEHAVIOR OF AN INNOVATIVE STEEL SHEAR WALL SYSTEM

Chapter 8 Fatigue Strength and Endurance

Shear tests of hollow flange channel beams with stiffened web openings

BOAST. West Coast. Set to open this spring, the tallest building on the West Coast resists wind and seismic drifts with massive braces.

LPI 56 Technical Guide

FATIGUE FAILURES IN INDUSTRY CASE STUDIES

BUREAU OF INDIAN STANDARDS. Draft Indian Standard

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL

ANALYSIS AND COMPARISON... Continued /rom preceding page

4 Casting Bed. Concrete Forms. Reinforcing. Splices. Prestressing. Elongation. Prestressing System. Initial Tensioning of Straight Strands

Square butt joint (joint without preparation)

Simple Complex Simple Complex

Design for welding: Design recommendations

Design of Semi gravity Retaining Walls

SECTION PRE-ENGINEERED COLD-FORMED METAL ROOF AND FLOOR TRUSSES

1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns.

IJSRD - International Journal for Scientific Research & Development Vol. 4, Issue 05, 2016 ISSN (online):

REINFORCED CONCRETE STRUCTURE COURSE STR 302A CL0SED BOOK EXAM THIRD YEAR CIVIL FIRST TERM YEAR TYPES OF SLABS

SHEAR AND BUCKLING STRENGTHENING OF STEEL BRIDGE GIRDER USING SMALL-DIAMETER CFRP STRANDS

ASSIGNMENT 1 ANALYSIS OF PRESTRESS AND BENDING STRESS BFS 40303

Route 360 Inverted T-beams. Carin Roberts-Wollmann Virginia Tech Tommy Cousins Clemson University Fatmir Menkulasi Louisiana Tech

SECTION COMPOSITE METAL DECKING

JOB BB0414 PORTER RD. HWY. 112/71B WIDENING & INTCHNG. IMPVTS. (S) AUGUST 10, 2016

National Physical Laboratory Hampton Road Teddington Middlesex United Kingdom TW11 0LW

Manitoba Welder Practical Examination STRUCTURAL LEVEL 2

SECTION COLD-FORMED METAL TRUSSES

SECTION 1208 CHAIN LINK FENCING DESCRIPTION

Item 448 Structural Field Welding

Code No: R Set No. 1

CHAPTER 4 EXPERIMENTAL ANALYSIS FOR A 2 IN, SCHEDULE 10 PIPE

1. Structural Steel Sections Structural steel sections can be classified into various groups according to their shapes.

7. Stud Welding. 7.1 Scope. 7.2 General Requirements

Specification for the Fabrication of Tower Structures

INSPECTION OF FIELD WELDING

ME 207 Material Science I

Contents EN :2008+A1:2011 (E) Page

Item 442 Metal for Structures

NEW COMPOSITE CONSTRUCTION OF HYBRID BEAMS COMBINING STEEL INVERTED T-SECTION AND RC FLANGE

Contents. Tables. Notation xii Latin upper case letters Latin lower case letters Greek upper case letters Greek lower case letters. Foreword.

Structural Training - Part 1:

Section 906. STRUCTURAL STEEL

Inspection of Steel Girder Bridges

Development of New H-Section Steel Shape with Inner Rib, J-grip H, and Its Application to Steel Concrete Composite Diaphragm Wall

Stress-Laminated / Steel T-Beam Bridge System

ITEM 442 METAL FOR STRUCTURES

CHAPTER 3 BEHAVIOUR OF FERROCEMENT HOLLOW SLABS

DUCTILITY REQUIREMENTS FOR BUILDINGS

Sabah Shawkat Cabinet of Structural Engineering 2017

By Gorbel Inc. The Best in the Business is Better Than Ever!

CHAPTER III DYNAMIC BEHAVIOR OF A LABORATORY SPECIMEN

Investigating the Use of Spliced Swimmer Bars as Shear Reinforcement in Reinforced Concrete Beams

Code No: R Set No. 1

1. Poor attitude toward any of the other students, instructors, or judges. 2. Failure to use personal protective equipment (PPE).

Flexure and Serviceability Limit State

ITEM 461 STRUCTURAL PLATE STRUCTURES. Galvanized steel plates shall conform to AASHTO M167 and aluminum plates shall conform to AASHTO M219.

Transactions on Engineering Sciences vol 2, 1993 WIT Press, ISSN

CORROSION ENGINEERING SPECIFICATION FOR INSTALLATION SPECIFICATION FOR STEEL VESSELS TO BE LINED WITH ACID PROOF BRICK

ITEM 448 STRUCTURAL FIELD WELDING

SigmaJoint. The Ultimate Joint J. Armouring & Load Transfer Systems. Metallic Leave-In-Place Contraction & Day Joints for INDUSTRIAL CONCRETE FLOORS

POST AND FRAME STRUCTURES (Pole Barns)

Module 4 Design for Assembly

10-COLUMNS: 10.1 Introduction.

TESTING OF MANUAL ARC WELDERS Issue No 5 Date Issued 1/9/69

SECTION COLD-FORMED METAL FRAMING

VALLIAMMAI ENGINEERING COLLEGE

The Use of Bolted U-Link Swimmer Bars in the Reinforced Concrete Beams

Design of Column Base Plates

b) provide evidence of his qualifications and practical experience in welding.

UNIT IVCOMPOSITE CONSTRUCTION PART A

BUREAU OF INDIAN STANDARDS Draft Indian Standard

Metal-plate connections loaded in combined bending and tension

INSTALLATION MANUAL FOR MODULAR EXPANSION JOINT (LG SYSTEM)

OUR COMPANY OUR WARRANTY OUR GUARANTEE

Multideck 146. Contents

Design of offshore structures Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras

Lateral System Analysis and Confirmation Design November 15, 2004

AASHTO/AWS D1.5M/D1.5:2008. Table of Contents

SECTION COLD-FORMED METAL FRAMING

Case Study in Steel adapted from Structural Design Guide, Hoffman, Gouwens, Gustafson & Rice., 2 nd ed.

USE OF SALE CHARTS IN DETERMINING MOMENT AND SHEAR

Fundamentals of Structural Design Part of Steel Structures

TYPICAL PHYSICAL STRENGTH PROPERTIES OF PRO TILE

Interior Hangers. Application

SECTION MANUAL FOUR FOLD DOORS MODEL 38 DECORATIVE PANEL DESIGN

Transcription:

BUTT-WELD ROLLED STEEL JOIST. I t 9. NOTES ON THE TEST OF A BUTT-WELD IN A 24in. x Min. x 1001b. ROLLED STEEL JOIST By Mr. H. E. Grove. Practically the whole of the author's welding experience has been confined to medium and light steel sections; that is, on steel materials not exceeding in. in thickness. Most of the results of this work have been communicated to this Institute, but up to now there has been no opportunity for indicating how butt-welds in heavy sections behave when the material is loaded beyond the yield point. At the present moment an electrically welded steel building is in course of erection at the Metropolitan GasCompany's West Melbourne Works, and incorporated in its structure are two lines of steel beams each about 95 feet long, continuous over three spans. One line is a plain 24 in. x 7i in. x too lb. rolled joist, while the other has plated flanges. Each line of beam has three joints designed to make the section continuous throughout its length. The joints are four feet away from the supports in the outer spans, so that the bending moment is about one-third of the safe B.M. of the section. The shear, however, of 22 tons at the joint, approaches the maximum anywhere on the beam. The mode of making these joints was very carefully dis- ca, sed, and a good deal of time was spent in trying to perfect a splice-cover joint which would have an efficiency of too per cent. All the while the various designs were being laid down, the feeling persisted in our minds that a plain butt-weld would probably do all that was required, and accordingly we decided to make and test a full size specimen of butt-welded beam before finalising design procedure. There being no testing machine available in Melb ourne that could test a beam of this size, we had to devise some method that would give us the information. So we placed a too-ton hydraulic jack between the specimen and two other beams of the same section all laid flat on the floor. At each end of the beams two It in. bolts with heavy channel straps bound the ends of the beams together, giving a span of seventeen feet. The jack was placed at mid span, and the joint was two feet away from the centre line of the jack. Two 3/8 in. web stiffeners were welded into the joist on each side where the jack was placed to prevent the web crumpling at that point. The ram diameter was 74 in., and a hydraulic gauge reading up to 4500 lbs. per sq. inch was fitted. The beam withstood this maximum gauge reading without distortion, and the beam was flogged all over the weld with a 1 4 lb.

I20 VICTORIAN INSTITUTE OF ENGINEERS. hammer, showing no sign of failure. The load at this stage was 186,000 lbs., minus ram friction. The pressure was then dropped and the gauge taken out. The load was now increased and the beam distorted, indicating that the stress in the flange at the load had exceeded the yield point. The joint, again flogged, indicated no sign of failure. The maximum indicated shear was 41.5 tons, nearly twice the shear to be imposed. The maximum indicated stress in the tension flange of the beam at the joint was 15.08 tons per sq. inch, nearly six times the stress which will actually occur at the joint in the building. The actual stress corresponding to the readings on the index of the ram pressure gauge are from six to ten per cent. less on account of ram friction. But, since the beam actually yielded under the load, it is clear that the above stresses were slightly exceeded, the yield point being somewhat in excess of the elastic limit which is at least half the ultimate tensile strength. The 24 in. x 74 in. x 100 lb. R.S.J. has a web thickness of 9/16 in., and the flanges taper from about in. at the toe to 14 in. thick at the centre. The joint was prepared by bevelling the abutting ends of the flanges to 6o deg. from the horizontal, leaving a vee of 6o deg. between. The webs were bevelled on each side to a point leaving a vee on each side of 6o deg. A butt-joint requires more care in its making than does a lap joint, or a joint with cover straps, owing to the contraction stresses that occur, and for that reason a welded butt-joint should never be made between two members rigidly fixed at their outer ends. In the test specimen care was taken to observe this point, and also to make the weld in the same manner as it would be made at erection. The web was welded vertically, and the flanges were welded from above. At erection it is necessary, in 'a butt-weld of this nature, to obviate overhead welding, and the bottom flange is bevelled so that the trough, formed by the vee, can be welded from above. As the characteristics of the weld metal are a little inferior to the mild steel sections, it is necessary to compensate for this by adding an excess of metal. Our practice is to add' at least 25 per cent. more metal in the joint, and to bring the weld well over the edges of the parent metal. We value the last run of metal chiefly for its annealing effect. After lining up the members. leaving i/i6 in. space between them, the joint is first tack-welded together, and then a light run of metal is deposited on the two sections to mark

BUTT-WELD ROLLED STEEL JOIST. I 2 I the limits of the weld. This serves to apply heat gently 'to the metal, and is a guide to the welder when finishing the weld, for fusing into this run on completion prevents undercutting on the parent metal. The next step is to deposit a Iight run into the bottom of the vee, and when this is complete the slag covering is thoroughly removed with hammer and chisel. We do not fill the vee in from side to side, as would seem the obvious thing to do, but one face is built up by carrying a single run to the outer edge. After the slag has been thoroughly cleaned off with hammer and chisel, the weld metal is hammered with the ball peen of the hammer; this stretches the metal which has begun tocontract on itself. A light run of metal is next deposited in the new bottom to the vee, and, after cleaning from slag, the other face is built up, cleaned and hammered. As the vee gets smaller, so the two opposing faces are fused and "knitted" into each other. This building up continued until the metal was I in. higher than the face of the "parent" metal, and the welding was continued over and tapering down to the first light limiting runs laid down. This gave a width of a in. all round. The last run was not hammered. Altogether 256 feet of No. Io and 20 feet of No. 8 electrodes were used in the test joint which took I3 hours to weld. The gratifying feature about this work is the certainty with which joints of loo per cent. efficiency can be made; in fact, it is necessary to take care that too lavish a use of the electrode is not made. The PRESIDENT said Mr. Grove had submitted a fund of information. No one in the State had a better knowledge of electric welding than Mr. Grove, who had carried out some of the biggest works here. He had shown that even the biggest structural material could be safely welded -electrically. The thanks of the Institute were due to Mr. Grove for giving so freely of his brains and experience. Mr. A. LEWIS said Mr. Grove had shown very interesting examples of welding. He asked if, for the purpose of boiler welding, the weld would be water-tight. Mr. GROVE said it would be both oil tight and watertight. Mr. LEWIS said he had had experience of the weld metal being porous, and had been compelled to have recourse to caulking. Mr. GROVE said they had undertaken an oil tank, which was very difficult to make perfectly tight. But they had no

I22 VICTORIAN INSTITUTE OF ENGINEERS. fear of the result. It was a question of the absolute cleaning of the metal at each layer, and the proper heating. At first they had such difficulties, but there came a time when they did not happen. It was necessary to watch the shrinkage in welding. Welding, and designing for welding, would be the simplest thing in the world if there were ho expansion and contraction. That was a matter that no text book could teach. They did small portions at a time and tried to equalise it. Mr. WM. CHAS. ROWE said he appreciated the cleaning of the surface of the metal, but he did not understand the pulling of the metal. Mr. GROVE said the trouble in a welded joint was its inevitable contraction. In a big V joint there was contraction stress in the weld metal; and they had to try and compensate for that by stretching the metal by hammering. A steel joist with one flange plate on it would curve. They tried to anticipate as far as possible the amount of the curve, and before welding they would bend the joist in the opposite direction. Before the plate was put on they bent the beam, and when released it would come back straight. The contraction stresses thus were much reduced. Mr. R. J. BENNIE moved a hearty vote of thanks to Messrs. A. B. Robison, A. Lewis and H. E. Grove for their valuable papers. They had supplied some very valuable information. The information in connection with the Queensland Sugar Mills was very interesting. He was familiar with the work outlined by Mr. Grove. It presented many interesting problems. It was part of a work of construction upon which they hoped in a few months to present a joint paper. Mr. WM. CHAS. RowE, in seconding the vote of thanks, said the evening had been one of the best for a long time. It was particularly noticeable that the paper by Mr. Robison had resulted in much additional information being received from another source. The vote of thanks was carried with acclamation

Library Digitised Collections Author/s: Grove, Harry Ernest Title: Notes on the test of a butt-weld in a large steel joist Date: 1928 Persistent Link: http://hdl.handle.net/11343/24696 File Description: Notes on the test of a butt-weld in a large steel joist